Sunshine Construction & Maintenance of Myrtle Beach, LLC v. Cannatelli Builders, Inc.
Filing
10
ORDER & REASONS. It is ORDERED that Plaintiff's 6 Motion to Remand is DENIED. Signed by Judge Carl Barbier. (gec)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
SUNSHINE CONSTRUCTION &
MAINTENANCE OF MYRTLE
BEACH, LLC
CIVIL ACTION
VERSUS
NO: 17-1431
CANNATELLI BUILDERS,
INC.
SECTION: “J”(5)
ORDER & REASONS
Before the Court is a Motion to Remand to State Court (R.
Doc. 6) filed by Plaintiff, Sunshine Construction & Maintenance of
Myrtle Beach, LLC (“Sunshine”), and an opposition (R. Doc. 8)
thereto
filed
by
Defendant,
Cannatelli
Builders,
Inc.
(“Cannatelli”). Having considered the motion and legal memoranda,
the record, and the applicable law, the Court finds that the motion
should be DENIED.
FACTS AND PROCEDURAL BACKGROUND
This case arises from the construction of a Burger King
restaurant in Amite, Louisiana (“Burger King project”). Dunaway
Food Services 1 (“Dunaway”) contracted with Cannatelli to renovate
the Burger King restaurant. Sunshine was then hired to perform all
or part of the renovation for approximately $230,000 and hired
subcontractors to help renovate the Burger King. Sunshine alleges
1
It appears that Dunaway is the owner of the Burger King or the manager of the
Burger King project. See (R. Docs. 6, 8.)
that
when
it
hired
these
subcontractors
it
was
acting
as
Cannatelli’s mandatary. Many of these subcontractors and other
suppliers have not been paid for the work they performed. As a
result, they have filed liens on the Burger King project and have
asserted claims against Cannatelli and Dunaway. In light of these
liens and claims, Cannatelli alleges that Dunaway has withheld
several payments it owes Cannatelli. Sunshine also alleges that
Cannatelli has failed to pay it for much of the work it performed
on the Burger King project, and that Cannatelli is responsible for
paying the unpaid subcontractors. Cannatelli argues that it has
paid
Sunshine
approximately
$214,000,
despite
the
fact
that
Sunshine failed to complete all of its work. Cannatelli further
argues
that
Sunshine
is
responsible
for
paying
the
unpaid
subcontractors and suppliers for the Burger King project.
On December 10, 2016, Sunshine submitted a demand letter to
Cannatelli stating that Cannatelli owes Sunshine approximately
$90,000. (R. Doc. 8-2.) On December 22, 2016, Sunshine submitted
another
demand
letter
requesting
Cannatelli
“to
compensate
Sunshine in the sum of $141,124.64 which constitutes the remainder
of the balance due Sunshine for all of its project expenses
including all sums due and owing to any and all [subcontractors].”
(R. Doc. 8-3, at 5.) On January 4, 2017, Sunshine filed suit in
the
Twenty-First
Judicial
District
Court
for
the
Parish
of
Tangipahoa, Louisiana against Cannatelli seeking a declaratory
2
judgment recognizing Sunshine as Cannatelli’s mandatary as to any
and all contracts, obligations, or other matters which arose from
the
Burger
King
project,
and
terminating
that
relationship
retroactively as of January 4, 2017. (R. Doc. 1-1, at 6.) On
February 2, 2017, Cannatelli removed that action to this Court on
the basis of diversity jurisdiction. (R. Doc. 1.) On April 4, 2017,
Sunshine filed the present motion to remand. In short, Sunshine
concedes that complete diversity exists between the parties, but
argues that the amount in controversy does not exceed $75,000. (R.
Doc. 6-1.) In response, Cannatelli argues that the demand letters
sent by Sunshine prove that the amount in controversy exceeds the
$75,000 diversity jurisdiction threshold. (R. Doc. 8.) Sunshine’s
motion is now before the Court on the briefs and without oral
argument.
LEGAL STANDARD
A defendant may remove to federal court “any civil action
brought in a State court of which the district courts of the United
States have original jurisdiction.” 28 U.S.C. § 1441(a). “A federal
district court has subject matter jurisdiction over a state claim
when the amount in controversy is met and there is complete
diversity of citizenship between the parties.” Mumfrey v. CVS
Pharmacy, Inc., 719 F.3d 392, 397 (5th Cir. 2013) (citing 28 U.S.C.
§ 1332(a)). The amount in controversy required by § 1332(a) is
currently $75,000. Id. The Court considers the jurisdictional
3
facts that support removal as of the time of removal. Gebbia v.
Wal-Mart Stores, Inc., 233 F.3d 880, 883 (5th Cir. 2000). Because
removal raises significant federalism concerns, any doubt about
the propriety of removal must be resolved in favor of remand. Gasch
v. Hartford Accident & Indem. Co., 491 F.3d 278, 281-82 (5th Cir.
2007).
When the petition is silent on the exact amount of claimed
damages, the removing party bears the burden of proving “by a
preponderance of the evidence that the amount in controversy
exceeds $75,000.” Grant v. Chevron Phillips Chem. Co., 309 F.3d
864, 868 (5th Cir. 2002) (citing Manguno v. Prudential Prop. &
Cas. Ins. Co., 276 F.3d 720, 723 (5th Cir. 2002)). The removing
party can satisfy this burden either: “(1) by demonstrating that
it is ‘facially apparent’ from the petition that the claim likely
exceeds $75,000 or (2) by setting forth the facts in controversy—
preferably in the removal petition, but sometimes by affidavit—
that support a finding of the requisite amount.” Id. (quoting Allen
v. R & H Oil & Gas Co., 63 F.3d 1326, 1335 (5th Cir. 1995)).
“Removal,
however,
cannot
be
based
simply
upon
conclusory
allegations.” Allen, 63 F.3d at 1335. If the removing party can
establish by a preponderance of the evidence that the amount in
controversy exceeds the requisite amount, “[t]he plaintiff can
defeat
diversity
jurisdiction
only
by
showing
to
a
‘legal
certainty’ that the amount in controversy does not exceed $75,000.”
4
Grant, 309 F.3d at 869 (citing De Aguilar v. Boeing Co., 47 F.3d
1404, 1412 (5th Cir. 1995)). It is well settled that this is not
a burden-shifting exercise; rather, the “plaintiff must make all
information known at the time he files the complaint.” Id.
DISCUSSION
The
parties
do
not
dispute
that
complete
diversity
of
citizenship exists. See (R. Doc. 6-1, at 4; R. Doc. 8, at 4.)
Consequently, the only issue before the Court is whether Cannatelli
has satisfied its burden of proving that the amount in controversy
exceeds
the
$75,000
threshold
necessary
for
diversity
jurisdiction. The amount in controversy is not facially apparent.
Sunshine seeks declaratory and monetary relief, but Sunshine filed
suit in state court in Louisiana, and Louisiana’s procedural rules
generally do not permit plaintiffs to plead a specific amount of
money damages. Harris v. Winn-Dixie Store No. 1430, No. 16-17697,
2017 WL 511228, at *2 (E.D. La. Feb. 8, 2017) (citing Hammel v.
State Farm Fire & Cas. Co., No. 06-7470, 2007 WL 519280, at *1
(E.D. La. Feb. 14, 2007)). Therefore, the Court must determine
whether Cannatelli has submitted sufficient facts in controversy
to establish that the jurisdictional amount is met from Sunshine’s
perspective. La. Indep. Pharmas. Ass’n v. Catamaran Corp., No. 14598, 2015 WL 1922599, at *6 (M.D. La. Apr. 27, 2015)
Sunshine contends that it only seeks to be recognized as
Cannatelli’s mandatary, for such mandatary-principal relationship
5
to be terminated retroactively, and for Cannatelli to be obligated
to honor any and all obligations which Sunshine entered on behalf
of Cannatelli. (R. Doc. 6-1, at 5-6.) Sunshine concedes it sent
demand letters for sums in excess of $75,000, but argues that if
it is recognized as Cannatelli’s mandatary, the sum which would
flow to Sunshine would be less than $75,000, because Cannatelli
would
be
held
liable
for
all
sums
owed
to
the
unpaid
subcontractors. Cannatelli argues that Sunshine has affirmatively
asserted claims for money damages in excess of $75,000, and even
if Sunshine does not seek monetary damages, Sunshine’s requested
declaratory relief would alleviate Sunshine of its obligation to
pay over $130,000 to the subcontractors. (R. Doc. 8, at 5.)
Cannatelli argues that regardless of the relief requested, the
amount in controversy in this case exceeds $75,000, and Sunshine’s
motion should be denied Id.
Despite
Sunshine
in
Sunshine’s
characterization
fact
a
seeks
declaratory
of
its
judgment
complaint,
that
it
is
Cannatelli’s mandatary, that Cannatelli, rather than Sunshine, is
responsible for paying the unpaid subcontractors, payment for all
services Sunshine rendered but has not been paid for, and for an
award of attorney’s fees and costs. (R. Doc. 1-1, at 6-7.) “In
actions seeking declaratory or injunctive relief the amount in
controversy
is
measured
by
the
value
of
the
object
of
the
litigation” from the plaintiff’s viewpoint. Catamaran Corp., 2015
6
WL 1922599, at *3 (quoting Leininger v. Leininger, 705 F.2d 727,
729 (5th Cir. 1983)). 2 Sunshine’s December 10, 2016 demand letter
to
Cannatelli
position
specifically
that,
at
this
states
time,
that
“[i]t
[Cannatelli]
is
owes
Sunshine’s
the
sum
of
$90,478.84 to Sunshine for services rendered pursuant to the
original
contractual
consideration
of
amount
either
the
provided
revised
by
CBI
contract
and
amount
without
or
any
additional sums owed. . . . Please note that this sum is due and
owing. Further, please note that it is Sunshine’s position that
the sums owed to any and all subcontractors who have not been paid
in full is to be paid from this sum. . . .” (R. Doc. 8-2, at 3.)
The letter goes on to state that Sunshine’s subcontractors have
not been paid an additional $132,887.73. 3 Id. Sunshine’s December
22, 2016 demand letter provides, in relevant part, “please accept
this as a FORMAL DEMAND LETTER demanding [Cannatelli] to compensate
Sunshine in the sum of $141,124.64 which constitutes the remainder
of the balance due Sunshine for all of its project expenses
including all sums due and owing to any and all [subcontractors].”
(R. Doc. 8-3, at 5.) These demand letters were sent shortly before
Sunshine filed suit, the demand letters are several pages and
2
In Leininger the court also stated that “the amount in controversy in an
action for declaratory or injunctive relief, is the value of the right to be
protected or the extent of the injury to be prevented.” Catamaran, 2015 WL
1922599, at *3 n.1 (citing Leininger, 705 F.2d at 729).
3 The letter states, “In addition to the foregoing, it is my appreciation that
the . . . sum presently owed to the [subcontractors] totals $132,887.73.” (R.
Doc. 8-2, at 3.) Thus, the demand letter makes clear that Sunshine seeks at
least $90,000 in addition to $132,887.73 for the unpaid subcontractors.
7
detail Sunshine’s position as to why it believes it is owed the
sums demanded, and Sunshine has not argued in its motion to remand
that the settlement demand was inflated or did not honestly assess
its damages. Accordingly, these pre-petition settlement demands
are “relevant evidence of the amount in controversy at the time of
removal.” See Creppel v. Fred’s Stores of Tenn., Inc., No. 13-734,
2013 WL 3490927, at *3-4 (E.D. La. July 10, 2013) 4 (citing Carver
v. Wal-Mart Stores, Inc., No. 08-42, 2008 WL 2050987 (M.D. La. May
13, 2008); Fairchild v. State Farm Mut. Auto. Ins. Co., 907 F.
Supp. 969, 970-71 (M.D. La. 1995)). The “object” of this litigation
from Sunshine’s viewpoint is the amount of money allegedly owed to
the unpaid subcontractors and additional sums of money it is
allegedly owed for services rendered. Regardless of whether the
Court
determines
that
Sunshine
was
or
was
not
Cannatelli’s
mandatary, the “value” of the object of this litigation is, by
Sunshine’s own admission, at least $90,478.84 and potentially in
excess of $141,124.64. Both of these sums obviously exceed the
$75,000
threshold
to
satisfy
28
U.S.C.
§
1332.
Therefore,
Sunshine’s motion to remand must be denied. Removal of this action
from state court was proper because there is complete diversity of
4
In Creppel, this Court determined that other district courts within the Fifth
Circuit have considered pre-petition demand letters as evidence of the amount
in controversy at the time of removal. Further, “the Fifth Circuit has generally
stated that a defendant may prove by a preponderance of the evidence that the
amount in controversy exceeds $75,000 based on ‘summary judgment type evidence’
of facts in controversy that support a finding of the requisite amount.”
Creppel, 2013 WL 3490927, at *3 (citing Manguno v. Prudential Prop. & Cas. Ins.
Co., 276 F.3d 720, 723 (5th Cir. 2002)).
8
citizenship between the parties, and the amount in controversy at
the time of removal was in excess of $75,000.
CONCLUSION
Accordingly,
IT IS HEREBY ORDERED that Plaintiff’s Motion to Remand (R.
Doc. 6) is DENIED.
New Orleans, Louisiana this 2nd day of May, 2017.
CARL J. BARBIER
UNITED STATES DISTRICT JUDGE
9
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?