Sugar Bay Club & Resort Corporation v. Agency Project Management, LLC et al
Filing
52
ORDER AND REASONS regarding 48 MOTION for Reconsideration. Accordingly, IT IS HEREBY ORDERED that GEES's Motion for Reconsideration (Rec. Doc. 48 ) is GRANTED IN PART. Defendant CRSC shall file into the record proof of pre-litigation notic e to APM, as specified in the Master Contract, no later than October 11, 2024. Failure to supply such notification proof will lead to the denial of CRSC's Motion for Summary Judgment (Rec. Doc. 39 ) and the grant of Sugar Bay's Motion f or Partial Summary Judgment (Rec. Doc. 32 ) without further notice. IT IS FURTHER ORDERED that GEES and Sugar Bay's Motion for Pretrial Conference (Rec. Doc. 33 ) is DENIED without prejudice. Signed by Judge Carl J Barbier on 9/26/24. (cg)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
SUGAR BAY CLUB & RESORT
CORP.
CIVIL ACTION
VERSUS
NO: 23-5480
AGENCY PROJECT
MANAGEMENT, LLC ET AL.
SECTION: “J”(5)
ORDER AND REASONS
Before the Court is Intervenor Green Earth Engineering Services,
Corporation’s Motion for Reconsideration (Rec. Doc. 48), which Plaintiff Sugar Bay
Club and Resort Corp. joins in support (Rec. Doc. 49). Defendant CRSC, LLC has filed
an opposition (Rec. Doc. 50). Having considered the motions and legal memoranda,
the record, and the applicable law, the Court finds that Intervenor Green Earth
Engineering Services, Corporation’s motion should be GRANTED IN PART.
FACTS AND PROCEDURAL BACKGROUND
As previously detailed, this matter arises from a dispute between
subcontractors involved in the cleanup after Hurricanes Maria and Irma hit the U.S.
Virgin Islands in 2017. Prime contractor AECOM Caribe, LLP was hired using funds
from the Federal Emergency Management Agency (“FEMA”). Below AECOM were
three layers of subcontractors. AECOM entered into a subcontract with Defendant
CRSC, LLC, which in turn entered into a subcontract with Defendant Agency Project
Management (“APM”). Finally, APM entered into subcontracts with Plaintiff Sugar
1
Bay Club & Resort Corporation and Intervenor Green Earth Engineer Services Corp.
(“GEES”).
Difficulties, however, arose at the third contractual layer. APM allegedly
became insolvent at some point after entering into these agreements. Sugar Bay is
now a judgment creditor of APM, and GEES is the assignee of APM’s accounts
receivable.
Upon receipt of funds from AECOM, and in light of the multiple claimants
owed payment by APM, CRSC began a separate interpleader action in Section B of
this Court. See CRSC, LLC v. Blue Elephant Financing, LLC, et al., No. 22-1315 (E.D.
La.). CRSC received $1,607,272.83 from AECOM owed to APM, but only deposited
$1,366,181,91 of those funds into the registry of the Court for disbursal. CRSC
retained the remaining $241,090.92.
In this action, Sugar Bay and CRSC filed cross-motions for summary
judgment. Sugar Bay argued CRSC illegally retained funds that should have been
disbursed due to the “pay when paid” contract between APM and CRSC. CRSC
countered that it is entitled to withhold these funds necessary for costs and attorney’s
fees and that Sugar Bay had not met the requirements of an oblique action. In
denying Sugar Bay’s motion and granting CRSC’s, this Court determined that (1) the
contract between APM and CRSC incorporated the terms of the Master Contract as
a whole; (2) through the Master Contract, CRSC possessed rights that flowed to it
from AECOM; and (3) CRSC thereby had the right to withhold retainage for
attorney’s fees and costs relating to litigation brought by APM’s vendors and
2
subcontractors. The Court further dismissed Sugar Bay’s oblique action and GEES’s
claims based on assignment of rights because CRSC is not currently indebted to APM.
GEES now requests reconsideration of that Order and Reasons because of an
error of law, namely, that CRSC did not strictly follow the retainage requirements of
the Master Contract. Sugar Bay joins the motion in support. In contrast, CRSC
contends the motion is merely an attempt to relitigate issues previously before the
Court and, thus, should be dismissed.
LEGAL STANDARD
The Federal Rules of Civil Procedure do not expressly allow motions for
reconsideration of an order. Bass v. U.S. Dep’t of Agric., 211 F.3d 959, 962 (5th Cir.
2000). However, the Fifth Circuit has consistently recognized that parties may
challenge a judgment or order under Federal Rules of Civil Procedure 59(e). Southern
Snow Manufacturing Co, Inc. v. SnoWizard Holdings, Inc., 921 F. Supp. 2d 548, 563–
64 (E.D. La. 2013).
Altering or amending a judgment under Rule 59(e) is an “extraordinary
remedy” used “sparingly” by the courts. Templet v. HydroChem Inc., 367 F.3d 473,
479 (5th Cir. 2004). A motion to alter or amend calls into question the correctness of
a judgment and is permitted only in narrow situations, “primarily to correct manifest
errors of law or fact or to present newly discovered evidence.” Id.; see also Schiller v.
Physicians Res. Grp. Inc., 342 F.3d 563, 567 (5th Cir. 2003).
Courts have noted that motions to reconsider or amend a final or partial
judgment are “not the proper vehicle for rehashing evidence, legal theories, or
3
arguments that could have been offered or raised before entry of judgment.” Templet,
367 F.3d at 478–79; SnoWizard, 921 F. Supp. 2d at 565. Also, such motions should
not be used to “re-litigate prior matters that . . . simply have been resolved to the
movant’s dissatisfaction.” See Voisin v. Tetra Techs., Inc., No. 08-1302, 2010 WL
3943522, at *2 (E.D. La. Oct. 6, 2010). Thus, to prevail on a motion under Rule 59(e),
the movant must clearly establish at least one of four factors: (1) the motion is
necessary to correct a manifest error of law, (2) the movant presents newly discovered
or previously unavailable evidence, (3) the motion is necessary in order to prevent
manifest injustice, or (4) the motion is justified by an intervening change in
controlling law. SnoWizard, 921 F. Supp. 2d at 565; Schiller, 342 F.3d at 567; Ross v.
Marshall, 426 F.3d 745, 763 (5th Cir. 2005).
DISCUSSION
For purposes of its reconsideration, GEES accepts the subcontract between
CRSC and APM fully incorporates the terms of the Master Contract. On that basis,
however, GEES asserts its error of law. GEES avers three errors in CRSC’s retainage
of funds: (1) its failure to provide timely notice of the reason for the fund’s
withholding; (2) its retainage of 15% of funds, rather than the contractually agreedupon 5%; and (3) its retainage of funds more than sixty days after work completion
without a pending warranty claim. Within its argument, however, GEES admits
some of these points were previously briefed before the Court. (See Rec. Doc. 48-1 at
4–5 (discussing the notice requirement, “Plaintiff, Sugar Bay, raised this very issue
in its reply”)). Sugar Bay also previously alleged CRSC was withholding 15% of funds
4
it was obliged to pay to APM. (See Rec. Doc. 11 at 2–3 ¶ 20; Rec. Doc. 32 at 2; Rec.
Doc. 41 at 4).
A previously unaddressed notice issue is presented here. In the previous
resolution, this Court noted not merely the retainage language of the Master
Contract, but also broader terms within the “Payment” section:
The Master Contract between AECOM and CRSC does allow AECOM
to withhold payment for numerous reasons including for “claims or liens
chargeable to Subcontractor, . . . monies paid by AECOM on behalf of or
for the benefit of Subcontractor, . . . and any costs or liability AECOM
has incurred or may incur for which Subcontractor may be responsible
under any other agreement between the parties.”
(Rec. Doc. 46 at 8 (quoting Rec. Doc. 38-3 at 7 (Master Contract))). These terms,
incorporated within the subcontract, are sufficient to justify CRSC’s current
withholding of funds due to ongoing costs incurred and pending final payment.
However, the Master Contract also required written notice for the withholding
of payments, “specifying (i) the amount withheld; (ii) the basis for the withholding;
and (iii) remedial actions to be taken by Subcontractor to receive payment of withheld
amounts, have the right to withhold payment or assess backcharges, in whole or in
part, otherwise due Subcontractor . . . .” (Rec. Doc. 38-3 at 7). Unlike the authorities
cited by GEES, the Master Contract does not evidence any time limit for the
presentation of this type of notice. See Hartford Cas. Ins. Co. v. MDI Const., L.L.C.,
No. 10-4369, 2012 WL 4970210, at *1–2 (E.D. La. Oct. 17, 2012) (twenty-one days
after the occurrence of the event); Env’t, Safety & Health Consulting Servs. v. Crest
Energy Partners, L.P., No. 13-5747, 2015 WL 2452458, at *1 (E.D. La. May 21, 2015)
(fifteen days after invoice date).
5
Nonetheless, another defined aspect of the notice demands scrutiny. Even
without a firm deadline requirement for withholding notice, the Master Contract does
specify what kinds of notice are acceptable:
All notices to be given by either party to the other shall be in writing
and shall be served by (i) personal delivery, (ii) a nationally recognized
overnight courier, (iii) sent by fax or telecopy (provided proof of receipt
is received by the sender), or (iv) by depositing such notice in the United
States mail, certified, return receipt requested, postage prepaid,
addressed and delivered to the party to receive the notice at the
addresses set forth herein or at such other address as may be indicated
by one party to the other party by written notice.
(Rec. Doc. 38-3 at 13). In its motion for summary judgment, CRSC has not supplied
proof of the notice it sent to APM for the withholding of payment. As is clear from the
definitional section, filings within this action cannot be so construed to supply notice.
As the law between the parties, unambiguous contractual provisions must be
complied with. See La. Civil Code Art. 2046.
CONCLUSION
Accordingly, IT IS HEREBY ORDERED that GEES’s Motion for
Reconsideration (Rec. Doc. 48) is GRANTED IN PART. Defendant CRSC shall file
into the record proof of pre-litigation notice to APM, as specified in the Master
Contract, no later than October 11, 2024. Failure to supply such notification proof
will lead to the denial of CRSC’s Motion for Summary Judgment (Rec. Doc. 39) and
the grant of Sugar Bay’s Motion for Partial Summary Judgment (Rec. Doc. 32)
without further notice.
6
IT IS FURTHER ORDERED that GEES and Sugar Bay’s Motion for Pretrial
Conference (Rec. Doc. 33) is DENIED without prejudice.
New Orleans, Louisiana, this 26th day of September, 2024.
____________________________________
CARL J. BARBIER
UNITED STATES DISTRICT JUDGE
7
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?