Angus Chemical Co v. Glendora Plantation Inc
Filing
86
RULING re 40 MOTION for Partial Summary Judgment filed by Angus Chemical Co, and 50 MOTION for Summary Judgment filed by Glendora Plantation Inc. Signed by Judge Robert G James on 11/20/13. (crt,DickersonSld, D)
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF LOUISIANA
MONROE DIVISION
ANGUS CHEMICAL COMPANY
CIVIL ACTION NO. 12-1656
VERSUS
JUDGE ROBERT G. JAMES
GLENDORA PLANTATION, INC.
MAG. JUDGE KAREN L. HAYES
RULING
Pending before the Court are a Motion for Partial Summary Judgment [Doc. No. 40] filed
by Plaintiff Angus Chemical Company (“Angus”) and a Motion for Partial Summary Judgment
[Doc. No. 50] filed by Defendant and Plaintiff in Counter Claim Glendora Plantation, Inc.
(“Glendora). For the following reasons, Angus’ motion is GRANTED, and Glendora’s motion is
DENIED.
I.
FACTS AND PROCEDURAL HISTORY
Angus owns an 80-acre facility in Sterlington, Louisiana, where the plant produces 40
nitroparaffin products. A byproduct of the production process is wastewater containing
formaldehyde and acetone. The wastewater is removed from the plant via an underground
pipeline, which carries it three and one-half miles away to a wastewater treatment plant.
The three and one-half mile stretch is owned by others. Therefore, in 1978, Angus’
predecessor-in-interest, IMC Chemical Group, Inc. (“IMC”), obtained rights of way or servitudes
from the landowners for the pipeline. In a March 28, 1978 “Right of Way Easement Option”
(“Option”), two landowners, George P. Smelser and Mary Tilford Smelser (“the Smelsers”)
granted IMC and its successors and assigns “an option to acquire a right of way and easement
with the right to construct, maintain, inspect, operate, protect, alter, repair, replace and change the
size of a pipeline.” [Doc. No. 23-4]. The pipeline was to be constructed “along a route to be
selected by [IMC] . . . after which a copy of the line location plat [was to be] furnished to [the
Smelsers] . . . and a copy . . . attached to this agreement and become a part thereof.” Id. The
Option provided a legal description of the Smelsers’ property in Ouachita Parish and a drawing
was attached to the Option to “more clearly show[]” the property. [Doc. No. 40, Exh. A, pp. 995,
998-1001]. The drawing identified a “proposed” pipeline route with a 10" pipeline.
On August 31, 1978, IMC exercised the option, paying the Smelsers $13,365.00 for the
right of way. Thereafter, the Option “automatically [became] an indefensible right of way
agreement without further action being necessary, and all of the rights, title and privileges granted
. . . thereafter be[came] vested in [IMC], its successors and assign[s].” [Doc. No. 40, Exh. A, p.
996].
In 1979, a 12" pipeline was constructed within the designated thirty-foot width,1 but
portions of the pipeline on the Smelser property lay outside the route identified on the drawing
attached to the Option.
The right of way has continued to be recognized by the successors to the original grantors
and grantee. Angus succeeded to IMC’s rights, and the Smelsers sold their land to Glendora,
subject to the right of way.
There have been leaks from the more than 30-year-old pipeline in 2007, 2010, and 2011.
Because of the leaks and the involvement of the LDEQ, Angus decided to put in a new 16"
pipeline made of high density poleythylene, but leaving the old 12" pipeline plugged and
1
The right of way was to be fifty feet in width during construction, but reverted to “a
permanent width of thirty (30) feet, measuring fifteen (15) feet on either side of the center line of
the right of way.” [Doc. No. 40, Exh. A, p. 995].
2
abandoned. Angus also placed two fiber optic cables parallel to the 16" pipeline, as well as a
tracer wire on top of the pipeline.
Some time after November 30, 2011, Angus tried to obtain permission from the affected
landowners to abandon the 12" pipeline. All but Glendora agreed. In a January 27, 2012 letter,
Angus made an offer to pay $237,000.00 to Glendora for authorization, but Glendora refused.
On June 14, 2012, Angus filed the instant Complaint, seeking a declaratory judgment that
Angus has a valid servitude, that per the servitude it may abandon the 12" pipeline once a new
pipeline is in place, that it may lay the pipeline, cables, and tracer wire (as set forth above), that
the servitude will be fifty feet in width during construction and thirty feet in width thereafter
(fifteen feet on either side of the center line of the original pipeline), and that it has right of ingress
and egress. Alternatively, Angus prayed for a declaratory judgment that it obtained the servitude
via acquisitive prescription.
In early August 2012, Angus’ construction manager, Ronnie Sharp (“Sharp”), solicited a
quote to determine the cost of delaying the construction of the 16" pipeline across Glendora’s
property. He was told the delay would cost approximately $40,000 on a project with an overall
cost of $3,000,000. However, Sharp did not delay construction.
On August 13, 2012, Glendora filed an answer and counterclaim. Glendora alleges that in
December 2011, it was shown a survey plat with the proposed right of way which showed that the
existing pipeline is located in a different place than shown on the drawing attached to the 1978
option. Glendora also argues that Angus has no right to install additional lines or fiber optic
cables adjacent to the new pipeline, nor does it have the right to abandon the existing pipeline.
Glendora prays for a declaratory judgment on this issue and also seeks damages for the trespass,
3
as well as damages for agricultural losses, soil degradation, cleanup costs, and remediation as a
result of the December 11, 2011 pipeline rupture and wasterwater spill. Finally, Glendora seeks
an order compelling Angus to remove that portion of the pipeline located in a different area from
the drawing attached to the 1978 Option.
Even though this lawsuit was pending, Angus installed the 16" pipeline on Glendora’s
property on or about August 17, 2012, along with two fiber optic cables running parallel to the
16" pipeline and a tracer wire located on top of the pipeline. Between October 3 and November
12, 2012, Angus cleaned, plugged and abandoned the old 12" pipeline.
On October 25, 2012, Glendora amended its counterclaim to allege that Angus violated the
right of way by conducting construction outside the thirty foot right of way and by using the right
of way for two pipelines. Glendora also alleged that Angus’s action constituted a bad faith
trespass. Glendora seeks damages for land leveling, ditching, the substitution of lesser quality
topsoil, and road damage.
II.
LAW AND ANALYSIS
A.
Standard of Review
Under Federal Rule of Civil Procedure 56, summary judgment “should be rendered if the
pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no
genuine issue as to any material fact and that the movant is entitled to judgment as a matter of
law.” FED. R. CIV. P. 56(c)(2). The moving party bears the initial burden of informing the court
of the basis for its motion by identifying portions of the record which highlight the absence of
genuine issues of material fact. Topalian v. Ehrmann, 954 F.2d 1125, 1132 (5th Cir. 1992). A
fact is “material” if proof of its existence or nonexistence would affect the outcome of the lawsuit
4
under applicable law in the case. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A
dispute about a material fact is “genuine” if the evidence is such that a reasonable fact finder
could render a verdict for the nonmoving party. Id.
If the moving party can meet the initial burden, the burden then shifts to the nonmoving
party to establish the existence of a genuine issue of material fact for trial. Norman v. Apache
Corp., 19 F.3d 1017, 1023 (5th Cir. 1994). The nonmoving party must show more than “some
metaphysical doubt as to the material facts.” Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio
Corp., 475 U.S. 574, 586 (1986). In evaluating the evidence tendered by the parties, the Court
must accept the evidence of the nonmovant as credible and draw all justifiable inferences in its
favor. Anderson, 477 U.S. at 255.
B.
Cross Motions for Partial Summary Judgment
Angus moves the Court for summary judgment on the following claims and/or issues: (1)
that Angus has a valid and enforceable servitude through the property of Glendora; (2) that the
right-of-way agreement is a personal servitude of rights of use; (3) that Angus is not a trespasser2;
(4) that Glendora is not entitled to recovery of Angus’ profits; and (4) that Angus’ installation of
the fiber optic cables and tracer wires was within the bounds of the right-of-way agreement and
the accessory rights afforded the owner of a right of use.
In its opposition to Angus’ motion, Glendora concedes that Angus has a valid and
enforceable servitude and that the right-of-way agreement creates a personal servitude of rights of
2
To reach this conclusion, Angus argues that the Court should find, as a matter of law,
that the right of way through which both pipelines travel was defined by the as-built location and
that the abandonment of the 12" pipeline neither breaches the Right-of-Way Agreement nor
constitutes a trespass. [Doc. No. 40, pp. 11-19].
5
use. The Court agrees, and, to this extent, Angus’ Motion for Partial Summary Judgment is
GRANTED.
However, Glendora otherwise opposes Angus’ Motion for Partial Summary Judgment and
moves the Court to (1) find that Angus did not have authority under the right-of-way agreement to
abandon the original 12" pipeline in place, (2) find that Angus did not have authority to construct
and operate the additional 16" pipeline and fiber optic cables with the 12" pipeline in place, (3)
declare that Angus is a trespasser on Glendora’s property; (4) declare that Angus’ trespass is in
bad faith; and (5) dismiss Angus’ request for a declaratory judgment.
Given the overlapping nature of the parties’ remaining claims, the Court will consider the
motions together.
1.
Right-of-Way Agreement
The parties agree that the Right-of-Way Agreement between IMC and the Smelsers, to
which the parties in this litigation have succeeded, conveyed a personal servitude of right of use.
See LA. CIV. CODE ART. 639 (“The personal servitude of right of use confers in favor of a person a
specified use of an estate less than full enjoyment.”); see also LA. CIV. CODE ART. 642 (“A right of
use includes the rights contemplated or necessary to enjoyment at the time of its creation as well
as rights that may later become necessary, provided that a greater burden is not imposed on the
property unless otherwise stipulated in the title.”). The Right-of-Way Agreement3 is a contract,
and the Court, sitting in diversity, must apply Louisiana law on the interpretation of contracts.
Interpretation of a contract is the determination of the common intent of the parties.” LA.
3
Although the language of the servitude is set forth in the Option, the Court hereinafter
refers to the Right-of-Way Agreement to differentiate the time after the Option was exercised.
6
CIV. CODE ART. 2045. “When the words of a contract are clear and explicit and lead to no absurd
consequences, no further interpretation may be made in search of the parties’ intent.” LA. CIV.
CODE ART. 2046. “The words of a contract must be given their generally prevailing meaning.”
LA. CIV. CODE ART. 2047. Where words or provisions in the contract are susceptible to more
than one meaning, the meaning given must be that which renders the contract effective and best
reflects the object of its makers. LA. CIV. CODE ARTS. 2048, 2049. However, if the meaning of
the words or provisions are doubtful, interpretation must be made “in light of the nature of the
contract, equity, usages4, the conduct of the parties before and after the formation of the contract,
and of other contracts of a like nature between the same parties.” LA. CIV. CODE ART. 2053.
The determination of whether the terms of a contract are clear or ambiguous is a question
of law. See Hendrick v. Patterson, 47,668 (La. App. 2d Cir. 2013), 109 So.3d 475. “Moreover,
when a contract can be construed from the four corners of the instrument without looking to
extrinsic evidence, the question of contractual interpretation is answered as a matter of law and
summary judgment is appropriate.” Ritter v. Commonwealth Land Title Ins. Co., 2013 WL
4080914 at *3 (La. App. 1 Cir. 2013) (citing Sims v. Mulhearn Funeral Home, Inc., 07–0054, pp.
9–10 (La. 5/22/07), 956 So.2d 583, 590).
The Right-of-Way Agreement provides in pertinent part:
George P. Smelser and Mary Tilford Smelser. . . Grantor . . . does hereby grant,
bargain, sell and convey unto IMC CHEMICAL GROUP, INC., . . .as Grantee, an
option to acquire a right of way and easement with the right to construct, maintain,
inspect, operate, protect, alter, repair, replace and change the size of a pipeline for
4
In Kenner Industries, Inc. v. Sewell Plastics, Inc., 451 So.2d 557, 560 (La. 1984), the
Louisiana Supreme Court found that, “(t)he customs of the industry may be considered when
construing ambiguous contracts . . . . Any deviation from industry custom should have been
expressly stated in the agreement.”
7
the transportation of liquids, gases, solids in either singular or mixed form or any
other substances which can be transported through pipelines, together with all
incidental equipment and appurtenances, either above or below ground, including
but not limited to filtering devices, valves, meters, drips, and other necessary and
convenient installations, on, over, under, across and through the following
described property, along a route to be selected by the Grantee, after which a copy
of the line location plat will be furnished to Grantor and a copy will be attached to
this agreement become and a part hereof. It is understood that the right of way will
be fifty (50) feet in width for the purposes of construction and upon completion
thereof, said right of way shall revert to a permanent width of thirty (30) feet,
measuring fifteen (15) feet on either side of the center line of the right of way. The
property subject to this agreement is situated in Ouachita Parish, Louisiana, and
described as follows, to-wit:
Lands of Grantor in Sections 46, 42 and 43, Township 19 North,
Range 4 East and Sections 37 and 38, Township 19 North Range 3
East as is more clearly shown on Grantee’s drawing attached hereto
and made a part hereof.
together with the right of ingress and egress over and across the land described
above for any and all purposes necessary to the exercise of the rights herein granted
.....
[Doc. No. 40, Exh. A].
1.
Construction of 1979 Pipeline
As an initial matter, Glendora argues, in part, that Angus is a trespasser because a portion
of the pipeline falls outside the boundary of the thirty-foot right of way “as shown on the drawing
attached to the Option.” [Doc. Nos. 7 & 14]. Angus does not dispute the fact that a portion of the
pipeline falls outside the boundary depicted in the drawing, but points out that the drawing
showed only a “proposed 10" pipeline” and that the language of the Right-of-Way Agreement
permitted its predecessor to construct a pipeline “through the . . . described property, along a
route to be selected by [IMC].” [Doc. No. 40, Exh. A]. The final as-built 12" pipeline was within
the Smelsers’ property, along a route selected by IMC and to which the Smelsers and their
8
successor made no objection for more than thirty years.
Under Louisiana law, a civil trespass is the “unlawful invasion of the property of
possession of another.” Boudreaux v. Palquemines Parish Gov’t, 22 So.2d 1117, 118 (La. App.
4th Cir. 2009). If the 1979 construction of the pipeline was permitted under the Right-of-Way
Agreement, however, Angus’ predecessor, IMC, could not have unlawfully invaded the Smelsers’
land.
Having reviewed the terms of the Right-of-Way Agreement, the Court finds that it clearly
and unambiguously permitted IMC to construct the original pipeline in 1979 along a route it
selected within the legal property description of the Smelsers’ land. The fact that IMC then failed
to provide a copy of the final line location plat to the Smelsers or attach a copy to the Right-ofWay Agreement is of no moment to IMC’s right to construct the pipeline along its selected route.5
Thus, the Court finds that Glendora cannot establish a breach of contract or a trespass on this
basis.6 To this extent, Angus’ Motion for Partial Summary Judgment is GRANTED, and
5
Glendora urges the Court to reject Angus’ argument that the drawing was attached as a
further description of the property and was likely the “first modern depiction of the property.”
Glendora contends that any depiction of the pipeline would have been pointless if the drawing
was meant only to describe the property, and Angus is merely speculating as to the reason it is
attached. However, if the route were established, it would also have been pointless to label it
“proposed,” and Glendora disregards the reality that routes, even if established, sometimes have
to be changed once construction begins.
6
Even if the proposed route had been somehow binding, the Court finds that the pipeline’s
location outside that route is properly viewed as a breach of contract. Although not raised by the
parties and not necessary to the Court’s determination, a breach of contract claim brought more
than thirty years after the construction of the pipeline is well outside the prescriptive period. The
Court is aware of Glendora’s argument that it could not have known where the pipeline was
located until 2007, but this argument clearly discounts the fact that the Smelsers certainly could
have and should have known where a pipeline was placed on their property at the time it was
constructed.
9
Glendora’s Motion for Partial Summary Judgment is DENIED.
2.
Construction of 16" Pipeline and Abandonment of 12"Pipeline
Next, the Court must consider Angus’ 2012 construction of the 16" pipeline. It is
undisputed that the Right-of-Way Agreement permitted Angus to replace the 12" pipeline with the
16" pipeline. However, the parties dispute whether Angus had the contractual authority under the
Right-of-Way Agreement to construct and operate the additional 16" pipeline, while abandoning
the 12" pipeline in place within the thirty-foot right of way.
Angus contends that its right to “replace” the 12" pipeline with the 16" pipeline,
encompassed the right to abandon the 12" pipeline in place and that the Right-of-Way Agreement
neither gave it the right to nor required the removal of the 12" pipeline.
Glendora argues that the term “replace” required Angus to remove the old pipeline.
Instead, Angus admittedly left the 12" pipeline in place and temporarily capped it, so that the 12"
pipeline can serve as a backup. By doing so, Glendora contends Angus has committed a bad faith
trespass on its land. Glendora further contends that Angus has also committed a bad faith trespass
because the Right-of-Way Agreement only permitted the maintenance and operation of one
pipeline, but Angus is now maintaining and/or operating two pipelines.
The clear and unambiguous language of the Right-of-Way Agreement permits Angus to
“replace” the 12" pipeline. The Right-of-Way Agreement does not define “replace” and does not
contain any provisions relating to either the removal of a replaced pipeline or the abandonment of
that pipeline in place. The Court must give the term “replace” its generally prevailing meaning.
In that regard, both parties have cited to dictionary definitions of “replace.” Glendora cites The
American Heritage Dictionary of the English Language (5th ed.), which defines “replace” as “1.
10
To put back into a former position or place: replaced the sofa after vacuuming; 2. To take the
place of or fill the role of: Jets have largely replaced propeller planes; 3. To provide a substitute
for (something broken or unsatisfactory, for example: to replace a spark plug; replace a team’s
coach.” [Doc. No. 55, p.11]. Glendora argues that “[w]hen a light bulb is replaced in a single bulb
lamp, the old light bulb is not left in the socket. Likewise, when a pipeline is replaced pursuant to
a clear and unambiguous single pipeline right, the pipeline to be replaced cannot be abandoned on
the ground.” Id.
On the other hand, Angus argues that Glendora has ignored the “glaring omission” from
the Right-of-Way Agreement, which is “the obligation to ‘remove’ a pipeline.” [Doc. No. 59, p.
4]. Moreover, Angus argues that in “common usage,” the term “replace” is more akin to
“‘substitute,’ and while a substitution may occasionally involve a removal, such a requirement is
neither common usage nor inherent in the term. . . .” Id. at p. 5. Angus cites to Merriam-Webster,
which defines “replace” as
1: to restore to a former place or position ‹replace cards in a file›
2: to take the place of especially as a substitute or successor
3: to put something new in the place of ‹replace a worn carpet›
MERRIAM-WEBSTER’S ONLINE DICTIONARY (2013 ed.). Angus admits that some of the examples
in various dictionary definitions presuppose that an item will be removed before its replacement is
substituted. However, Angus argues that removal is not “inherent in the definition of replace,”
but is instead “incumbent in the nature of the thing being replaced.” [Doc. No. 59, p. 5].
Expounding on the examples accompanying the definitions both parties have cited, Angus points
out that home buyers who take up worn carpet may find hardwood floors underneath, so it was
clear that the hardwood was not removed before being “replaced” with the new flooring, carpet.
11
Similarly, jets may have “largely replaced” propeller planes, but propeller planes have not be
removed from airports; instead, this replacement speaks to the greater use of jet engines, rather
than propeller engines, in commercial planes. Finally, as a final “illustration” that “‘remove’ is
not part and parcel of the right to ‘replace,’” Angus cites Terrebonne Par. Sch. Bd. v. Columbia
Gulf Transmission Co., 290 F.3d 303 (5th Cir. 2002), where the defendant was granted “‘a
servitude, right of way and easement to construct, lay, maintain, operate, alter, repair, remove,
change the size of, and replace a pipeline and appurtenances thereof . . . . .’” [Doc. No. 59, p. 6
(quoting 290 F.3d at 308) (emphasis added)].
In this case, the Court finds that, applying the generally prevailing meaning, the term
“replace” does not require Angus to remove the 12" pipeline which is no longer in operation.
Although the term “replace” could, in some cases, imply a corresponding duty to remove, the
Court agrees with Angus that the appropriate definition in this case is to “substitute.” Angus
substituted one operating pipeline (the 12" pipeline) with another (the 16" pipeline), but a
substitution does not require the removal of the non-operating pipeline. This definition of
“replace,” as applied, renders the contract effective and reflects the object of the makers to allow
the chemical company to operate one pipeline through the property to dispose of wastewater at its
wastewater facility. Further, such a definition is consistent with the apparent practice of others
holding servitudes on Glendora when, as Angus points out, old pipe not belonging to Angus or its
predecessor had to be removed during the installation of the 16" pipeline.7
7
Glendora relies heavily on testimony and emails of Angus employees and contractors to
support its argument that abandonment of the 12" pipeline was not permitted by the Right-ofWay Agreement. However, the Court has concluded that the language of the Right-of-Way
Agreement was clear, and, thus, parol evidence is irrelevant to the Court’s legal determination.
12
However, even if Angus had the general right to abandon the old pipeline in place, the
Court must also consider Glendora’s argument that Angus is now operating and/or maintaining
two pipelines, instead of “a pipeline” as contemplated by the Right-of-Way Agreement. In
support of its argument, Glendora cites testimony from Angus’ site leader, Ernest Green
(“Green”), that the 12" pipeline was a possible backup to the 16" pipeline, which is consistent
with the work order prepared by the contractor. Green testified that use of the 12" pipeline as
backup constituted having two pipelines in “operation” at once. The project manager for the 16"
pipeline construction, M.A. Shah (“Shah”), testified consistently that the 12" pipeline was a
backup for the 16"pipeline. Further, at the least, Glendora points to Green’s testimony that Angus
has to “maintain” the 12" pipeline as a backup.
Angus responds that the use of the term “a pipeline” in the Right-of-Way Agreement does
not limit the number of pipelines on the property, “only the one upon which [Angus] may act” in
operating, maintaining, inspecting, protecting, altering, repairing, and changing the size. [Doc.
No. 59, p. 11]. Contrary to Glendora’s contentions, Angus asserts that there are not two pipelines
being operated and maintained because only the 16" pipeline is operational.
The Court finds that Angus is not operating or maintaining two pipelines based on the
abandonment of the 12" pipeline or based on its possible use as a backup for the operational 16"
pipeline. It is undisputed that wastewater from Angus flows through only one pipeline–the 16"
pipeline–, and it is further undisputed that the 12" pipeline was cleaned and capped. Thus, Angus
is not operating two pipelines. Speculation or conjecture that Angus might remove the caps and
use the 12" pipeline in the future does not render Angus currently in breach of the Right-of-Way
Agreement or result in the commission of a trespass.
13
Moreover, while Green answered “yes,” to the question that Angus has a duty to
“maintain” the 12" pipeline, his testimony is irrelevant to the Court’s legal determination. The
Court must again apply the generally prevailing meaning of the term at issue. Merriam-Webster
defines “maintain” as follows:
1: to keep in an existing state (as of repair, efficiency, or validity) : preserve from
failure or decline
2: to sustain against opposition or danger : uphold and defend
3: to continue or persevere in : carry on, keep up
4a: to support or provide for
b: sustain
5: to affirm in or as if in argument : assert
See Merriam-Webster, http://www.merriam-webster.com/, last visited November 18, 2013. The
applicable definition in this case is to “preserve from failure or decline,” but, other than Green’s
irrelevant and conclusory opinion, there is no indication Angus has in fact done anything to
preserve the 12" pipeline from failure or decline by abandoning and capping it. The undisputed
facts show that this 1979 pipeline was leaking, which is why it was replaced and capped.
Therefore, the Court finds that Angus is not operating or maintaining two pipelines in breach of
the Right-of-Way Agreement, nor is it engaged in a bad faith trespass of Glendora’s property
based on these arguments. Angus’ Motion for Partial Summary Judgment is GRANTED,8 and
8
Angus moved for summary judgment on the basis that its installation of 16" pipeline and
abandonment of the 12" pipeline did not constitute a trespass because they were permitted under
the Right-of-Way Agreement. Although Angus did not specifically move for summary judgment
on Glendora’s claim that Angus is “maintaining” two pipelines, the Court finds it appropriate to
grant summary judgment to Angus and deny Glendora’s motion for summary judgment, having
concluded that Angus is neither operating nor maintaining two pipelines in contravention of the
Right-of-Way Agreement.
14
Glendora’s Motion for Partial Summary Judgment is DENIED.
3.
Installation of Tracer Wire and Fiber Optic Cables
Finally, the parties dispute whether Angus’ installation of tracer wire and two fiber optic
cables was contractually permitted under the Right-of-Way Agreement or constitutes a bad faith
trespass.
Under the language of the Right-of-Way Agreement, Angus is permitted to construct not
only a pipeline, but “all incidental equipment and appurtenances . . . and other necessary and
convenient installations . . .” The undisputed facts show that the tracer wire was installed to allow
Angus to check for leaks in the pipeline, and the fiber optic cables, which are not currently
operable, would permit Angus to control operation of the wastewater treatment facility from its
main control room at the chemical plant.
Applying the clear and unambiguous language of the Right-of-Way Agreement, Angus had
the right to install the tracer wire. In fact, this would appear to the Court to be the very type of
incidental equipment permitted by the right of way, as it allows Angus to detect and locate the 16"
pipeline in the event of future leaks and would, thus, protect Glendora from damage to its
property. Moreover, as Angus points out, Louisiana Civil Code article 642, provides that a “right
of use includes the rights contemplated or necessary to enjoyment at the time of the creation as
well as rights that may later become necessary, provided that a greater burden is not imposed on
the property unless otherwise stipulated in the title.” Although tracer wire was not in use in 1979
when the pipeline was constructed, it is available now, serves to protect both parties, and, located
within the bounds of the servitude, creates no greater burden on the property. Because the Court
finds that Angus was within its authority to install the tracer wire, Angus’ Motion for Partial
15
Summary Judgment on this issue is GRANTED, and Glendora’s Motion for Partial Summary
Judgment is DENIED.
The parties argue more contentiously over the fiber optic cables. Angus asserts that it was
entitled under the Right-of-Way Agreement and Article 642 to install the fiber optic cables to
“monitor, maintain, and protect” the 16" pipeline. [Doc. No. 40, p. 22]. Angus argues that this
technology “enhances the performance and safety of the pipeline and could not have been
specifically addressed since it did not exist in 1979. Glendora asserts that the fiber optic cables
are not “incidental or necessary” as set forth in the Right-of-Way Agreement because the cables
have not been connected. Glendora further asserts that the “primary” purpose of the fiber optic
cables, based on evidence from Angus and its contractors and employees, is “not related to the
wastewater pipeline,” but is intended to allow Angus to operate the wastewater treatment plant
from the plant production control room. [Doc. No. 50, p. 18].
Again applying the plain language of the Right-of-Way Agreement, the Court finds that
Angus had the authority to install the fiber optic cable as “incidental equipment and appurtenances
. . . and other necessary and convenient installations . . . .” Under the broadly worded language of
the Right-of-Way Agreement, this installation is permissible, whether viewed as “incidental” or
“necessary and convenient.” Although the fiber optic cables are not currently connected, they will
give Angus the ability to control the flow and pressure of the wastewater traveling through the 16"
pipeline. These tasks are currently monitored by radio telemetry, but this is newer technology
giving Angus a second way to check flow and pressure. Accordingly, on this issue, Angus’
Motion for Partial Summary Judgment is GRANTED, and Glendora’s Motion for Partial
Summary Judgment is DENIED.
16
III.
CONCLUSION
For the foregoing reasons, Angus’ Motion for Partial Summary Judgment [Doc. No. 40] is
GRANTED. Glendora’s Motion for Partial Summary Judgment [Doc. No. 50] is DENIED. The
Court finds that Angus has a valid and enforceable servitude through the property of Glendora;
that the Right-of-Way Agreement created a personal servitude of rights of use; (3) that Angus had
the authority under the Right-of-Way Agreement to construct the 16" pipe and abandon the
original 12" pipeline in place; and (4) that Angus had the authority under the Right-of-Way
Agreement to install fiber optic cables and tracer wires. In light of the Court’s determinations, the
Court need not reach Glendora’s arguments regarding trespass or trespass in bad faith.
MONROE, LOUISIANA, this 20th day of November, 2013.
17
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?