FEDERAL ENERGY REGULATORY COMMISSION v. SILKMAN et al
Filing
155
ORDER ON MOTIONS FOR SUMMARY JUDGMENT denying 133 Motion for Summary Judgment; granting 134 Motion for Partial Summary Judgment By JUDGE JOHN A. WOODCOCK, JR. (CCS)
UNITED STATES DISTRICT COURT
DISTRICT OF MAINE
FEDERAL ENERGY REGULATORY )
COMMISSION,
)
)
Petitioner,
)
)
v.
)
)
RICHARD SILKMAN, et al.,
)
)
Respondents.
)
1:16-cv-00205-JAW
ORDER ON MOTIONS FOR SUMMARY JUDGMENT
An energy consulting company and its employee and managing member
challenge FERC’s assessment of civil penalties against them for violating FERC’s
anti-manipulation rule, alleging that the action brought in this Court by FERC is
time-barred under the general statute of limitations, 28 U.S.C. § 2462.
FERC
maintains in a countervailing motion for summary judgment that its civil action was
timely filed.
First, the Court concludes that the Respondents did not waive their statute of
limitations argument. Next, the Court concludes that FERC’s disgorgement order is
not subject to a separate accrual date for purposes of the statute of limitations.
Finally, the Court rejects the Respondents’ argument that Gabelli v. SEC, 568 U.S.
442 (2013) and Kokesh v. SEC, 137 S. Ct. 1635 (2017) eclipsed United States v. Meyer,
808 F.2d 912 (1st Cir. 1987). Based on Meyer, which the Court views as binding, the
Court concludes that the FERC enforcement action is not time-barred.
I.
BACKGROUND
A.
Procedural History
1.
Proceedings in the District of Massachusetts
On December 2, 2013, the Federal Energy Regulatory Commission (FERC, the
Commission) filed a petition in the District of Massachusetts for an order affirming
its assessment orders.
Pet. for Order Affirming FERC’s Aug. 29, 2013 Orders
Assessing Civil Penalties Against Richard Silkman and Competitive Energy Services,
LLC (ECF No. 1) (FERC Pet.). On December 19, 2013, the Respondents filed a motion
to dismiss, Resp’ts’ Mot. to Dismiss (ECF No. 8), and a motion to transfer to the
District of Maine. Resp’ts’ Mot. to Transfer (ECF No. 9). On January 9, 2014, FERC
filed oppositions to the motion to dismiss, FERC’s Opp’n to Resp’ts’ Mot. to Dismiss
(ECF No. 18), and the motion to transfer. FERC’s Opp’n to Resp’ts’ Mot. to Transfer
(ECF No. 19). On July 18, 2014, Judge Woodlock heard arguments on the motion to
dismiss and supplemental briefs on procedure, as well as additional arguments
regarding transfer to the District of Maine. Elec. Clerk’s Notes (ECF No. 43); Tr. of
Mot. Hr’g (ECF No. 44).
The case was effectively stayed pending resolution of related issues in the
United States Supreme Court 1 and the United States Bankruptcy Court for the
On June 4, 2014, the Respondents moved for judgment on the pleadings, arguing that FERC
did not have jurisdiction over demand response programs such as the one at issue in this case. Resp’ts’
Mot. for J. on the Pleadings at 1–2 (ECF No. 35) (citing Elec. Power Supply Ass’n v. FERC, 753 F.3d
216 (D.C. Cir. 2014)). However, in FERC v. Electric Power Supply Ass’n, 136 S. Ct. 760 (2016), the
Supreme Court held that FERC does have jurisdiction over demand response programs. Accordingly,
the Respondents withdrew their motion for judgment on the pleadings. Resp’ts’ Suppl. Br. (ECF No.
60).
1
2
District of Maine. 2 By April 5, 2016, both matters were resolved, and the proceedings
continued. On April 11, 2016, Judge Woodlock denied the Respondents’ motion to
dismiss, FERC v. Silkman, No. 13-13054-DPW, 2016 U.S. Dist. LEXIS 48409 (D.
Mass. April 11, 2016) (ECF No. 65) (Order on Mot. to Dismiss), and transferred the
cases to the District of Maine. FERC v. Silkman, 177 F. Supp. 3d 683 (D. Mass. 2016)
(ECF No. 66) (Silkman I).
2.
Proceedings in the District of Maine
On April 21, 2016, following transfer to the District of Maine, the Respondents
answered FERC’s petition.
Resp’ts’ Answer (ECF No. 72).
That same day, the
Respondents filed a motion requesting a scheduling conference and an order
assigning the case to the complex track. Defs.’ Mot. for Scheduling Order and Conf.
(ECF No. 73).
On June 3, 2016, the Court held a scheduling conference. Minute Entry (ECF
No. 84); Tr. of Proceedings (ECF No. 85). At the scheduling conference, the parties
presented arguments concerning the procedures that should govern the Court’s de
novo review of the Commission’s assessment orders. Tr. of Proceedings at 2:24–49:18.
The Court ordered additional briefing from both parties. Id. at 46:6–48:7. On January
26, 2017, the Court issued an order regarding the procedures applicable to FERC’s
petition and assigned the case to the complex track. Order Regarding Procedures
Another FERC petition was also pending before Judge Woodlock in a related case, FERC v.
Lincoln Paper and Tissue, LLC, No. 1:13-cv-13056-DPW. On September 28, 2015, Lincoln Paper filed
for bankruptcy. As a result, Judge Woodlock stayed the proceedings in both Lincoln and Silkman. On
April 5, 2016, the District of Maine Bankruptcy Court ruled that the automatic bankruptcy stay did
not apply to FERC’s district court litigation against Lincoln Paper. In re Lincoln Paper & Tissue, LLC,
No. 15:10715, 2016 Bankr. LEXIS 3501 (U.S. Bankr. D. Me. Apr. 5, 2016). Accordingly, Judge
Woodlock allowed the proceedings in both cases to continue. Silkman I, 177 F. Supp. 3d at 701.
2
3
Applicable to Pet. for Order Affirming Assessment of Civil Penalties (ECF No. 95).
On February 15, 2017, the parties appeared telephonically for a conference of
counsel before this Judge, and the Court issued an order staying the case pending a
settlement conference. A settlement conference was held before Magistrate Judge
Rich on March 31, 2017, but settlement was not achieved. Min. Entry (ECF No. 104).
On February 28, 2018, the Respondents filed a Motion for Summary Judgment
(ECF No. 133) (Resp’ts’ Mot.) along with an accompanying Statement of Fact (ECF
No. 136) (DSMF). FERC responded in opposition on March 30, 2018, FERC’s Resp.
in Opp. to Mot. for Summ. J. (ECF No. 140) (Pl.’s Opp’n), and filed a response to the
Respondents’ statement of fact with a statement of additional facts that same day.
FERC’s Resp. to Statement of Fact with Statement of Additional Facts (ECF No. 141)
(PRDSMF; PSAMF). On April 20, 2018, the Respondents replied to FERC’s additional
statement of fact and responded to FERC’s requests to strike made in response to the
Respondents’ statement of fact. Defs.’ Reply to Resp. to Mot. for Summ. J. (ECF No.
143) (Resp’ts’ Reply); Defs.’ Reply Statement of Material Fact (ECF No. 144)
(DRPSAMF).
Meanwhile, on February 28, 2018, FERC filed a cross-motion for partial
summary judgment on the issue of the statute of limitations. Mot. for Partial Summ.
J. regarding Statute of Limitations (ECF No. 134) (Pl.’s Mot.). The Respondents
responded in opposition on March 30, 2018. Defs.’ Resp. in Opp’n to Mot. for Partial
Summ. J. (ECF No. 138) (Resp’ts’ Opp’n). FERC replied on April 20, 2018. Reply to
Resp. to Mot. for Partial Summ. J. (ECF No. 145) (Pl.’s Reply).
4
On September 25, 2018, FERC filed an unopposed motion for leave to file
supplemental authority. Mot. for Leave to File Notice of Supple. Information (ECF
No. 152). The Court granted the motion on November 7, 2018. Order Granting Mot.
for Leave to File Notice of Supple. Information (ECF No. 153). On November 8, 2018,
FERC filed as supplemental authority a copy of the Fourth Circuit Court of Appeals’
order granting interlocutory appeal in Federal Energy Regulatory Commission v.
Powhatan Energy Fund., LLC, 286 F. Supp. 3d 751, 754 (E.D. Va. 2017).
B.
The Parties and Relevant Entities
FERC is an administrative agency of the United States, organized and existing
pursuant to the Federal Power Act (FPA), 16 U.S.C. §§ 791a et seq. FERC Pet. ¶ 13.
FERC’s Office of Enforcement (Enforcement) “initiates and executes investigations of
possible violations of the Commission’s rules, orders, and regulations relating to
energy market structures, activities, and participants. Office of Enforcement (OE),
FERC, https://www.ferc.gov/about/offices/oe.asp (last visited December 18, 2017).
Based on its investigations, Enforcement may submit reports to the Commission
recommending that the Commission institute administrative proceedings. FERC’s
Opp’n to Resp’ts’ Br. Concerning Disc. (ECF No. 88) (FERC’s Disc. Resp.) at 4. Once
the Commission authorizes an administrative proceeding, Enforcement’s role shifts
from investigator to litigator, and a “wall” goes up between the Commission and its
Enforcement arm to prevent ex parte communication. Id.
ISO-New England (ISO-NE) is an independent, non-profit organization that
works to ensure the day-to-day reliable operation of New England’s bulk electric
5
energy generation and transmission system by overseeing the fair administration of
the region’s wholesale energy markets. FERC Pet. ¶ 2. FERC regulates the markets
that ISO-NE administers. Id.
Respondent Competitive Energy Services (CES) is a limited liability company
organized under the laws of Maine with its principal place of business in Portland,
Maine.
Id. ¶ 15.
It provides energy consulting and other services to clients
throughout North America. Id. ¶ 35. Respondent Richard Silkman resides in Maine
and is an employee and managing member of CES. Id. ¶ 14.
II.
STATEMENT OF FACTS 3
A.
Statement
Judgment
of
Facts:
Respondents’
Motion
for
Summary
FERC alleges that the Respondents’ wrongdoing occurred “from July 2007
until February 2008.” DSMF ¶ 1; PRDSMF ¶ 1. On December 2, 2013, FERC filed a
Petition for an Order Affirming the Federal Energy Regulatory Commission’s August
29, 2013 Orders Assessing Civil Penalties Against Richard Silkman and Competitive
Where, as here, the parties file cross-motions for summary judgment, the Court must evaluate
each motion independently and “determine ‘whether either of the parties deserves judgment as a
matter of law on facts that are not disputed.’” Matusevich v. Middlesex Mut. Assurance Co., 782 F.3d
56, 59 (1st Cir. 2015) (quoting Barnes v. Fleet Nat’l Bank, N.A., 370 F.3d 164, 170 (1st Cir. 2004)). For
cross-motions for summary judgment, the standard of review is applied to each motion separately.
Libertarian Party of N.H. v. Gardner, 759 F. Supp. 2d 215, 212 (D.N.H. 2010), aff’d, 638 F.3d 6 (1st
Cir. 2011). Thus, in accordance with “the conventional summary judgment praxis,” with regard to the
Respondents’ motion for summary judgment and its supporting facts, the Court recounts the facts in
the light most hospitable to the Respondents’ case theories consistent with record support. Gillen v.
Fallon Ambulance Serv., Inc., 283 F.3d 11, 17 (1st Cir. 2002). In compliance with obligation, the Court
recites supported facts as true even if FERC disputes them. Id. Likewise, with the Petitioner’s crossmotion for partial summary judgment and supporting facts, the Court recounts the facts in the light
most hospitable to FERC’s case theories consistent with record support and recites supported facts as
true even if the Respondents dispute them. Id.
3
6
Energy Services, LLC. 4 DSMF ¶ 2; PRDSMF ¶ 2. The petition was filed at least five
years, ten months, and two days after the wrongdoing ceased. 5 DSMF ¶ 3; PRDSMF
¶ 3.
Enforcement began an inquiry in February 2008 following a telephone call
from the ISO-NE market monitoring unit regarding certain market participants’
conduct relating to their participation in the ISO-NE Day Ahead Load Response
Program (DALRP). In March 2008, after receiving a written referral from ISO-NE,
Enforcement commenced a non-public investigation pursuant to Part 1b of the
Commission’s regulations (18 C.F.R. Part 1b) to determine whether certain market
participants had engaged in fraudulent conduct in their participation in the DALRP.
In November 2009, Enforcement commenced an investigation of Dr. Silkman
4
The Respondents’ paragraph 2 states “FERC filed its complaint in federal court in this matter
on December 2, 2013.” DSMF ¶ 2. The Petitioner interposes a qualified response, stating that FERC
filed a petition, not a complaint. PRDSMF ¶ 2. The Court adjusted the Petitioner’s statement to
reflect the Petitioner’s qualification.
5
The Respondents’ paragraph 3 states “The Court may take judicial notice that the federal court
complaint was filed at least five years, 10 months, and 2 days, after the allegedly wrongdoing ceased.”
DSMF ¶ 3. The Petitioner interposes a qualified response, arguing that the Respondents’ paragraph
3 should be stricken because this fact is not material or relevant to the issue on summary judgment.
PRDSMF ¶ 3 (citing United States v. Meyer, 808 F.2d 912 (1st Cir. 1987); Silkman I, 177 F. Supp. 3d
at 68; United States v. Worldwide Indus. Enters., Inc., 220 F. Supp. 3d 335 (E.D.N.Y. 2016)). FERC
puts forth the same request to strike in response to seventy-four of the ninety-three statements of fact
of the Respondents without attempting to explain why the specific statement of fact is irrelevant or
immaterial. Resp’ts’ Reply to Additional Statement of Fact and FERC’s Reqs. to Strike (ECF No. 143)
(Resp’ts’ Reply). See PRDSMF. Requests to strike are disfavored in summary judgment motions. D.
ME. LOC. R. 56(e) (“Motions to strike statements of material fact are not allowed. If a party contends
that an individual statement of fact should not be considered by the court, the party may include as
part of the response that the statement of fact ‘should be stricken’ with a brief statement of the
reason(s) and the authority or record citation in support”); Randall v. Potter, 366 F. Supp. 2d 120, 121
(D. Me. 2005) (“Although the motion to strike remains available for the extraordinary case, this is one
weapon in the strategic arsenal that is more effective when used sparingly”). The Court is decidedly
unenthusiastic about repetitive, pro forma requests to strike filed in motions for summary judgment
and will not address each request individually.
The Petitioner further argues that without prejudice to the determination of its request to
strike, FERC denies that it filed a complaint, but admits that it filed a petition, and admits to the date
stated by the Respondents. PRDSMF ¶ 3. The Court adjusts the Respondents’ paragraph 3 to reflect
the date the Petitioner cited.
7
individually, pursuant to Part 1b of the Commission’s regulations for Dr. Silkman’s
conduct related to the DALRP, as memorialized in a November 4, 2009 letter sent to
Dr. Silkman’s counsel. 6 DSMF ¶ 4; PRDSMF ¶ 4.
1.
Roles of FERC Enforcement and the Commission
Enforcement staff, in their role as the Commission staff tasked with
investigating potential violations of the FPA and the Commission’s regulations,
communicated with the Commission and certain members of its advisory staff during
the investigation of the Respondents.
The Commission initiated adversarial
adjudicatory proceedings on July 17, 2012 when it issued Orders to Show Cause and
Notice of Proposed Penalty (“Proposed Penalty Orders”) to each Respondent. Under
FERC’s Separation of Functions Rule (18 C.F.R. § 385.2202), a “wall” went up
between agency decisional staff — the Commissioners and the staff that may advise
them — and the Enforcement staff serving a prosecutorial role in the proceedings. In
accordance with the Commission’s rule regarding ex parte communications (18 C.F.R.
§ 385.2202), a prohibition on ex parte communications between decisional staff and
Enforcement prosecutorial staff also went into effect at that time. Pursuant to the
Commission’s Separation of Functions Rule and ex parte rule, following issuance of
the Proposed Penalty Orders, the Commission issued a notice in each proceeding on
The Respondents’ paragraph 4 states, “FERC’s Office of Enforcement . . . began its
investigation of Defendants in February 2008.” See Compl. ¶ 52 (ECF No. 1). The Petitioner denies
the Respondents’ paragraph 4, offering a more detailed timeline of the inquiry, non-public
investigation, and subsequent public information. PRDSMF ¶ 4. Though the Court does not view the
Petitioner’s paragraph 4 as directly contradicting the Respondents’ paragraph 4, the Court includes
the Petitioner’s paragraph 4 as it provides detail and context.
6
8
July 26, 2012 identifying decisional and non-decisional staff. 7 DSMF ¶ 5; PRDSMF
¶ 5.
Over the course of the investigation of the Respondents, Enforcement
communicated in writing and orally with the FERC Commissioners and their staff
concerning the investigation outside the presence of the Respondents and their
counsel. 8
DSMF ¶ 6; PRDSMF ¶ 6.
During the investigation, Enforcement
considered FERC and the FERC Commissioners to be their client.
PRDSMF ¶ 7.
DSMF ¶ 7;
Enforcement’s communications with the FERC Commissioners and
their staff concerning the investigation of the Respondents have not been disclosed to
the Respondents. 9 DSMF ¶ 8; PRDSMF ¶ 8.
The Respondents’ paragraph 5 states “FERC Enforcement did not set up any form of a ‘Chinese
wall’ with any other entity within FERC, including the FERC Commissioners and their staff, after it
began its investigation.” DSMF, Attach. 1., FERC Dep. (ECF No. 136-1) at 79-80 (FERC Dep.). The
Petitioner clarifies the Respondents’ paragraph 5 in a series of qualifications and denials regarding
the communication procedure at various stages of the FERC investigation and adjudication process.
PRDSMF ¶ 5. The Court included the Petitioner’s clarifications but declines to include the
Respondents’ denials as to the various implications of the Respondents’ statements.
8
The Petitioner denies what it views as the implications of the Respondents’ paragraph 6.
PRDSMF ¶ 6. The Court does not view these implications as facts but as argument and declines to
include them.
9
The Petitioner denies the Respondents’ paragraph 8, stating that “communications between
Enforcement staff and the Commission during an investigation under Part 1b of the Commission’s
regulations are properly characterized as “ex parte” because “[t]here are no parties, as that term is
used in adjudicative proceedings, in an investigation.” See PSMF (ECF No. 135); Decl. of Att’y Demetra
Anas (ECF No. 137) (Anas Decl.), and 18 C.F.R. § 1b.11 (2008)). The Court agrees with the Petitioner
that the term “ex parte” could be misleading in this context, and the Court removed the phrase from
the Respondents’ paragraph 8.
The Petitioner objects to the inclusion of the Brann Declaration as inadmissible under Federal
Rules of Civil Procedure 56(c)(2) and (c)(4), arguing first that the Declaration is an “impermissible
attempt to offer in the guise of ‘fact’ an opinion as to the ultimate issue presented to the court.” See
PRDSMF ¶ 9 (citing DSMF (ECF No. 136), Attach. 3, Brann Decl. (ECF No. 136-3) (Brann Decl.)). The
Petitioner cites Lamarche v. Metropolitan Life Insurance Company in support of its contention. 236
F. Supp. 2d 34, 42 n.9 (D. Me. 2002). The Court is aware of the distinction between fact and argument,
and, as FERC has pointed out, an attorney representing a party may not present an argument as fact
with the intention of forcing the Court to accept a contested legal argument as a proffered fact. The
Court will enforce the distinction.
Second, the Petitioner argues that the Brann Declaration should be excluded because Attorney
Brann did not disclose himself as a fact witness. PRDSMF ¶ 9. The Court views the Brann Declaration
7
9
2.
Notice and Disclosure to the Respondents
In this litigation, FERC disclosed the identities of people with “relevant
knowledge” who had been interviewed as part of the investigation, and who had not
been disclosed to the Respondents prior to the time FERC issued the Orders
Assessing Penalties. 10 DSMF ¶ 87; PRDSMF ¶ 87. FERC also disclosed documents
that it claims were part of the administrative record which had not been disclosed to
the Respondents prior to the time FERC issued the Orders Assessing Penalties. 11
as a vehicle for presenting uncontested facts to the Court for the purposes of the motion. His statement
in paragraph 4, for example, that he was never permitted to conduct any discovery on behalf of the
Respondents, is presumably a statement of uncontested fact, which involves the conduct of the
litigation based on Attorney Brann’s role as counsel for the Respondents, not as a witness to the facts
underlying the dispute. Either Attorney Brann was or was not allowed to engage in discovery on
behalf of his clients. If the Petitioner contends that Attorney Brann’s assertion is erroneous,
Respondent would have an undoubted right to contest those asserted facts. But it appears that the
Petitioner is contending not that the Attorney Brann statement is false, only that he may not make it.
The alternative would be for Attorney Brann to file a request for admission, which-if truePetitioner would have to admit. If Attorney Brann had moved to be allowed to file a request for
admission, the Court would likely have granted it. See FED. R. CIV. P. 56(d). In this sense, Attorney
Brann’s sworn declaration is simply another way of placing uncontested facts before the Court for
purposes of the motion. Indeed, as Respondents point out, when Petitioner thought it advantageous
to place facts underlying the process before the Court, it supported its facts with an attorney affidavit,
an irony Respondents did not hesitate to point out. PSAFM ¶ 2; DRSAMF ¶ 2 (“Proving that irony is
no stranger to the law, FERC’s sole support for this allegation is a declaration from counsel, Demetra
Anas, as to the procedure employed in the investigation”). The Court overrules the Petitioner’s
objection and denies Petitioner’s request to be allowed to depose Attorney Brann.
Third, the Petitioner argues that the Brann Declaration attempts to offer “facts” for summary
judgment not found in the Respondent’s Statement of Material Facts. The Court will not consider a
statement in the Brann Declaration but not in the Respondents’ Statement of Material Facts.
10
The Respondents’ paragraph 87 states: “In this litigation, FERC disclosed the identities of
people with ‘relevant knowledge’ who had been interviewed as part of the investigation, and who had
not been disclosed to the Respondents prior to the time FERC issued the Orders Assessing Penalties.”
DSMF ¶ 87. The Petitioner denies the statement as unsupported by the cited record, because the only
cited support for the statement is paragraph 37 of the Brann Declaration, which refers only to the fact
that FERC had interviewed individuals from Constellation and ISO-NE who were unfamiliar to
Attorney Brann. Brann Decl. ¶ 37. The Court finds that cited record supports the Respondents’
paragraph 87.
The Petitioner also denies the Respondents’ paragraph 87 based on the argument that the
Respondents interacted with the individuals FERC interviewed, and therefore the Respondents were
aware of their identities. The Court views this denial as non-responsive to the Respondent’s statement
and overrules the denial.
11
The Petitioner denies the Respondents’ paragraph 88 as “mischaracterizing the Notice of
Filing of the Administrative Record” because the Notice of Filing contained not only the contents of
10
DSMF ¶ 88; PRDSMF ¶ 88. FERC disclosed additional documents that appear to
have been obtained as part of the investigation which had not been disclosed to the
Respondents prior to the time FERC issued the Orders Assessing Penalties and which
were not included in what FERC claims were part of the administrative record. 12
DSMF ¶ 89; PRDSMF ¶ 89.
a.
Depositions
Under FERC’s regulations, the Respondents were not notified in advance of
depositions conducted by Enforcement during its investigation, other than the
deposition of Dr. Silkman. 13 DSMF ¶ 9; PRDSMF ¶ 9. Other than the deposition of
Dr. Silkman, the Respondents and their counsel were also not allowed to attend the
depositions conducted by Enforcement during its investigation, pursuant to FERC’s
regulations. The Commission’s regulations require the sequestration of witnesses
during testimony taken in an investigation, and all information and documents
received during an investigation, as well as the existence of an investigation, is
treated as confidential, non-public information. Disclosure of information during an
investigation is permitted only at the Commission’s direction or authorization, or as
is otherwise required to be disclosed. 14 DSMF ¶ 10; PRDSMF ¶ 10.
the administrative record, but also additional materials “for the convenience of the Court and the
Parties.” PRDSMF ¶ 88 (citing Notice of Submission of Administrative R. (ECF No. 26) (Notice of
Administrative R). The Court views the Petitioner’s denial as not directly responsive to the
Respondents’ statement and overrules it.
12
The Petitioner admits the Respondents’ paragraph 89, but “denies the suggestion . . . that such
documents were improperly not included in the administrative record.” PRDSMF ¶ 89. The Court
overrules the denial because a denial of an inference is not a fact. See infra note 57.
13
The Court finds the Respondents’ paragraph 9 adequately supported by the record citation and
overrules the Petitioner’s denial.
14
The Petitioner offers the following qualification to the Respondents’ paragraph 10:
11
The Respondents and their counsel were not given copies of the depositions
conducted by Enforcement (other than the deposition of Dr. Silkman) until after their
depositions had been taken—sometimes over a year later—and then only after
Respondents’ counsel pressed Enforcement to provide such copies. 15 DSMF ¶ 11;
PRDSMF ¶ 11.
Under FERC’s regulations, deponents and their counsel in the
investigation were instructed by Enforcement not to give copies of their deposition
transcripts to the Respondents or their counsel; deponents and their counsel were
instructed regarding the testimony of witnesses in accordance with the requirements
of section 1b.16 of the Commission’s regulations, requiring sequestration of
witnesses. 16 DSMF ¶ 12; PRDSMF ¶ 12.
In this litigation concerning events that occurred in 2007 and 2008, fact
witnesses repeatedly testified in their 2017 depositions that they did not remember
or did not recall in response to over forty questions asked during their depositions,
Under the Commission’s regulations, Respondents were not entitled to attend the
taking of testimony from third party witnesses. The Commission’s regulations
require the sequestration of witnesses during testimony taken in an investigation,
and all information and documents received during an investigation, as well as the
existence of an investigation, is treated as confidential, non-public information.
Disclosure of information during an investigation is permitted only at the
Commission’s direction or authorization, or as is otherwise required to be disclosed.
PRDSMF ¶ 10. The Court included the Petitioner’s qualification as it provides detail and context to
the Respondents’ statement.
15
The Petitioner admits the Respondents’ paragraph 11 in part, but also interposes the same
qualification to the Respondents’ paragraph 11 as it put forth in response to paragraph 10. As the
Court has already included the qualification with regard to paragraph 10, it declines to repeat it in
paragraph 11.
16
The Petitioner interposes, in part, the same qualified response to the Respondents’ paragraph
12 as it put forth in its qualification to paragraph 10 and paragraph 11. As the Court already included
the qualification in paragraph 10, it declines to repeat it in paragraph 12. The Petitioner further
states in its qualified response: “Deponents and their counsel in the investigation were instructed
regarding the testimony of witnesses in accordance with the requirements of section 1b.16 of the
Commission’s regulations, requiring sequestration of witnesses.” PRDSMF ¶ 12. The Court has
included the Petitioner’s qualification because it adds relevant context to Respondents’ paragraph 12.
12
and for several witnesses, for over eighty questions asked during their depositions,
although some witnesses’ lack of memory was resolved by follow-up questions or the
use of exhibits to refresh their recollections. 17 DSMF ¶ 90; PRDSMF ¶ 90.
Enforcement requested Dr. Silkman to come to Washington, D.C. for his twoday deposition in February 2009. 18 DSMF ¶ 13; PRDSMF ¶ 13. At the conclusion of
Dr. Silkman’s deposition on February 27, 2009, Enforcement instructed Dr. Silkman
not to share a copy of his deposition transcript with anyone else, including Mark
Isaacson, who was a member and managing partner of CES during the relevant
period; Enforcement also instructed Dr. Silkman that if he felt the need to share the
transcript with anyone else, to contact Enforcement and they would discuss it. 19
The Petitioner admits “that the witnesses identified in the Peters Declaration claimed to not
recall answers to some of the questions asked during their depositions” but “denies the suggestion . . .
that the number of times witnesses claimed a lack of recall accurately reflects an equal number of
unresolved answers or that each claimed lack of memory was due solely to the passage of time.”
PRDSMF ¶ 90. The Petitioner then demonstrates testimony surrounding each example of a witness
failing to remember offered by the Respondents, which shows that in each case, refreshing the
witness’s recollection resulted in the witness’s ability to recall the answer to the question. Id.
The Court finds that the Respondents’ paragraph 90 may be misleading in the light of the
surrounding testimony, which provides additional context, and the Court amends the Respondents’
paragraph 90 accordingly.
18
The Petitioner argues that the Respondents’ paragraph 13 is improper as it cites the Brann
Declaration. The Court concludes that the Brann Declaration is proper record evidence for the
assertion in paragraph 13. See supra n.9.
The Petitioner also denies the statement, arguing that the FERC Enforcement staff did not
issue a subpoena, but merely “requested” Dr. Silkman’s appearance. PRDSMF ¶ 13. The Petitioner
also maintains that Dr. Silkman never asked FERC to pay his travel expenses. Id. (citing PDSMF ¶
2; Aff. of Att’y Demetra Anas ¶ 13 (ECF No. 142) (Anas Resp. Aff.). The dispute is factual, and as the
Court is required to view the facts in the light most favorable to the non-movant, the Court accepts
the Petitioner’s denial as a qualification and amends the statement.
19
The Petitioner interposes a two-part qualification to the Respondents’ paragraph 14, first
noting that the FERC regulations require the sequestration of witnesses and second, stating that
FERC Enforcement told Dr. Silkman that the transcript was not to be shared, but if Dr. Silkman felt
the need to share it, he should contact FERC Enforcement to discuss it. PRDSMF ¶ 14. The Court
included the Petitioner’s initial qualification with regard to paragraph 12 and declines to include it
here. The Court also finds that the Respondents’ statement may be misleading without including the
second part of the Petitioner’s qualification and has amended the Respondents’ paragraph 14
accordingly.
17
13
DSMF ¶ 14; PRDSMF ¶ 14. Dr. Silkman was instructed by Enforcement not to share
the questions or answers that were given during the deposition with anyone else;
Enforcement issued these instructions to Dr. Silkman in accordance with applicable
regulations, 18 C.F.R. § 1b.12, 1b.16. 20 DSMF ¶ 15; PRDSMF ¶ 15. In accordance
with applicable regulations, Enforcement also instructed him not to disclose
questions or answers that were given in the course of the deposition to anyone from
Rumford Paper Company (Rumford). 21 DSMF ¶ 16; PRDSMF ¶ 16.
b.
Document Requests
Enforcement does not have to obtain approval from a FERC administrative law
judge or any other independent entity or decisionmaker concerning the scope of data
requests or its investigation.
DSMF ¶ 21; PRDSMF ¶ 21.
Despite numerous
requests, in accordance with the confidentiality provisions in the Commission’s
regulations, Enforcement did not provide the Respondents all the information it
obtained during its investigation from Rumford, Constellation NewEnergy, Inc.
(Constellation), and ISO-NE. DSMF ¶ 22; PRDSMF ¶ 22. However, during the
investigation, Enforcement staff provided the Respondents with copies of all
materials Enforcement staff cited in the preliminary findings letters to CES and Dr.
The Petitioner interposes a qualified response, arguing again that Dr. Silkman was instructed
according to the FERC regulations regarding the sequestration of witnesses. PRDSMF ¶ 15. The
Court amended paragraph 15 to reflect that this qualification applies as well to paragraph 15.
21
The Petitioner denies the Respondents’ paragraph 16, arguing that the cited record does not
support the statement, but instead states that Silkman “was instructed by FERC Enforcement not to
communicate with anyone from Rumford, or to provide them with any information” and that he was
told that the regulations “require you not to disclose the questions or answers that were given during
the course of this deposition.” PRDSMF ¶ 16 (citing Anas Resp. Aff., Attach. 4, Ex. Dep. Test. Tr. Of
Richard Silkman (ECF No. 136-4) at 430:2-10. The Court accepts the Petitioner’s qualification and
amends the Respondents’ paragraph 16 to reflect the cited record. The Court also added the
Petitioner’s qualification that Enforcement’s instructions to Dr. Silkman were pursuant to regulation.
20
14
Silkman except publicly-available information already in the Respondents’
possession.
Id.
During the investigation, Enforcement staff provided the
Respondents with all potentially exculpatory information regarding the Respondents
in its investigative files.
Id.
On July 17, 2012, the date of issuance of the
Commission’s Proposed Penalty Orders, Enforcement provided CES and Dr. Silkman
copies of all documents cited in the Enforcement Staff Reports attached to the
Proposed Penalty Orders except those documents already in Respondents’ possession
or publicly available. 22 Id.
Pursuant to FERC regulations, Enforcement did not give the Respondents
advance or contemporaneous notice of any document requests or interrogatories
(“data requests”) that Enforcement served upon third parties during the
investigation. 23 DSMF ¶ 17; PRDSMF ¶ 17. However, Dr. Silkman and CES entered
into a joint defense agreement with Rumford Paper Company (Rumford) and drafted
responses for Rumford to Enforcement data requests. Id. The Respondents were not
The Petitioner admits the Respondents’ paragraph 22 but then appears to interpose
qualifications. The Court treats the Petitioner’s response as a qualification and amends Respondents’
paragraph 22 to include the detail and context the Petitioner offered. The Petitioner otherwise denies
the Respondents’ paragraph 22 as unsupported by the cited record, presumably because of its earlier
argument that the Brann Declaration is inadmissible. The Court overrules the denial. See supra note
9.
23
The Petitioner interposes a qualified response to the Respondents’ paragraph 17, noting that
the lack of advance or contemporaneous notice given to the Respondents of document requests or
interrogatories served by FERC Enforcement on third parties was pursuant to FERC regulations
because the Respondents were the subjects of the investigation. PRDSMF ¶ 17. The Court amended
the Respondents’ paragraph 17 accordingly.
The Petitioner also states that “CES entered into a joint defense agreement with Rumford
Paper Company effective March 19, 2018, and Silkman and CES drafted responses for Rumford to
data requests served by Enforcement staff on Rumford during the investigation.” Id. Viewing the
facts in the light most favorable to the Petitioner, the Court included its assertion that the
Respondents had access to discovery Enforcement served on Rumford and assisted Rumford in
preparing responses.
22
15
entitled to object to data requests served by Enforcement upon third parties during
the investigation. DSMF ¶ 18; PRDSMF ¶ 18. According to FERC regulations,
Enforcement did not give the Respondents contemporaneous notice of third party
responses to any data requests served by Enforcement upon third parties during the
investigation. 24 DSMF ¶ 19; PRDSMF ¶ 19. However, Dr. Silkman and CES entered
into a joint defense agreement with Rumford Paper Company (Rumford) and drafted
responses for Rumford to Enforcement data requests. Id. Enforcement determined
what data requests to submit as part of its investigation, determined when the
responses were due in the first instance, which could be in as little as one week,
determined whether to grant enlargements of time, and determined whether the
responses were adequate. 25 DSMF ¶ 20; PRDSMF ¶ 20.
c.
Preliminary Findings
On November 23, 2009, Enforcement provided CES with a 32-page letter,
which included 179 footnotes, titled “Preliminary Findings Letter,” and initially gave
CES three weeks to respond, which Enforcement later extended to January 8, 2010. 26
The Petitioner interposes a qualified response, putting forth the same arguments as it did in
response to the Respondents’ paragraph 18. PRDSMF ¶ 19. The Court amended the Respondents’
paragraph 19 to reflect the context that the Petitioner acted in accordance with FERC regulations. For
the same reason set forth above, the Court amended Respondents’ paragraph 19 with regard to a joint
defense agreement. See supra note 18.
25
The Petitioner denies the Respondents’ paragraph 20 in part, arguing that the statement is
unsupported by the record citation in part, but it is unclear which part it denies, since it also admits
each clause of Respondents’ paragraph 20. The Court finds that the Respondents’ paragraph 20 is
supported by their record citation, and the denial is overruled. The Petitioner also argues that the
Brann Declaration is improper and should be stricken. The Court denies the request to strike. See
supra note 9. The Court amended Respondents’ paragraph 20 to clarify that Petitioner’s deadline
determinations were done in the first instance and were subject to Enforcement’s enlargement.
26
The Petitioner denies the Respondents’ paragraph 23, noting that a letter titled “Preliminary
Findings Letter” was dated November 23, 2009, not November 21, 2009. PRDSMF ¶ 23; DSMF,
Attach. 8, FERC Dep. Ex. 19 (ECF No. 136-8). The Court amended Respondents’ paragraph 23 to
reflect the date of November 23, 2009, as demonstrated by FERC Exhibit 18.
24
16
DSMF ¶ 23; PRDSMF ¶ 23. Prior to the time that CES was directed to respond to
Enforcement’s preliminary findings and analysis, Enforcement did not provide all the
materials obtained in its investigation but claimed it had provided the materials that
it had relied upon in making its preliminary findings and analysis. 27 DSMF ¶ 24;
PRDSMF ¶ 24.
Enforcement staff agreed to provide all documents referenced in
Enforcement staff’s November 23, 2009 Preliminary Findings Letter to CES that
were not either (a) publicly available or (b) already within Respondents’ possession.” 28
DMSF ¶ 25; PRDSMF ¶ 25.
On January 8, 2010, CES provided its response to the preliminary findings and
conclusions in a thirty page, single-spaced letter, asserting that Enforcement had not
The Petitioner further denies the Respondents’ use of quotation marks around the word
“preliminary” to the extent that it suggests that the conclusions of Enforcement staff were not
preliminary, which the Petitioner argues is not supported by record evidence. PRDSMF ¶ 23. The
Court accepts the denial and removed the quotation marks from “preliminary” in the Respondents’
paragraph 23 and in subsequent paragraphs to which the Petitioner has made the same objection.
The Petitioner further states that it admits the remainder of Respondents’ paragraph 23, but
then puts forth a qualification, stating that “Enforcement staff later provided CES with additional
time, until January 8, 2010, for CES to respond to the letter.” PRDSMF ¶ 23. To ensure that the
Respondents’ statement is not misleading, the Court amended the statement to include the Petitioner’s
qualification.
27
In response to the Respondents’ paragraph 24, the Petitioner “denies the statement that
Enforcement staff ‘claimed’ to have ‘provided the materials it “relied upon” in its ‘preliminary’ findings
and analysis because Enforcement staff in fact agreed to provide, and provided, all such materials that
it had not provided.” PRDSMF ¶ 24. The Court views the Respondents’ use of the word “claim” in
their statement in a manner consistent with Petitioner’s position, namely reflective of the fact that the
Petitioner stated that it had provided all materials it relied upon in its preliminary findings and
analysis. The Court, therefore, overrules the Petitioner’s denial.
The Petitioner further denies the Respondents’ statement because of quotation marks around
the word “preliminary.” The Court removed the punctuation. See supra note 26.
28
The Petitioner admits the Respondents’ paragraph 25 in part but denies the statement that
“Enforcement agreed to disclose some, but not all of the cited materials, provided that they were not
shared with Defendants’ co-counsel or anyone at CES other than Dr. Silkman.” DSMF ¶ 25, citing
Brann Decl. ¶¶ 13-14. The Petitioner argues that “Enforcement staff agreed to provide all documents
referenced in Enforcement staff’s November 23, 2009 Preliminary Findings Letter to CES that were
not either (a) publicly available or (b) already within Respondents’ possession.” PRDSMF ¶ 25. The
Court views the dispute as factual and is required to view the facts in the light most favorable to the
non-moving party. The Court accepts the Petitioner’s denial and amends the statement accordingly.
17
provided exculpatory evidence in its possession, including copies of depositions that
Enforcement had taken outside the presence of the Respondents and counsel, and
that Enforcement had seriously misstated the factual record in order to reach its
preliminary findings and conclusions. 29 DSMF ¶ 26; PRDSMF ¶ 26.
On April 19, 2010, Enforcement provided its preliminary findings and analyses
concerning Dr. Silkman in a twenty-nine-page letter with 176 footnotes, and initially
gave Mr. Silkman two weeks to respond. DSMF ¶ 27; PRDSMF ¶ 27. Enforcement
staff later extended the response date an additional seventeen days, until May 20,
2010. 30 Id. Enforcement’s preliminary findings and analyses concerning Dr. Silkman
were virtually identical to Enforcement’s preliminary findings and analyses
concerning CES and did not directly respond to any factual or legal argument in the
thirty-page response CES previously submitted. 31
DSMF ¶ 28; PRDSMF ¶ 28.
The Petitioner admits the Respondents’ paragraph 26 in part but interposes a qualified
response to the Respondents’ statement regarding the word-count of the CES letter, stating that it is
unaware of the word-count of the document since it was not sent to the Petitioner in its original Word
format. PRDSMF ¶ 26. Even though the Court wonders about whether the actual number of words
in a thirty-page letter is worth quibbling about, the Court is required to view contested facts in the
light most favorable to the Petitioner and for purposes of this recitation, it excludes the asserted wordcount.
The Petitioner further denies the Respondents’ statement because of quotation marks around
the word “preliminary.” The Court removed the punctuation. See supra note 26.
30
The Petitioner admits the Respondents’ paragraph 27 in part, but interposes a qualification,
stating: “The letter was substantively similar to the Petitionary Findings Letter that Enforcement
staff sent to CES via its counsel in November 2009, and to which counsel had responded via a 30-page
letter. Enforcement staff later extended the response date by an additional 17 days, until May 20,
2010.” PRDSMF ¶ 27. The Court views the first sentence of the Petitioner’s qualification as not
directly related to the Respondents’ statement and declines to include it. The Court amended the
Respondents’ paragraph 27 to include the second sentence of the Petitioner’s qualification to ensure
that the statement is not misleading.
31
The Petitioner interposes a qualified response to the Respondents’ paragraph 28, admitting
that its “preliminary findings with respect to Silkman were substantively similar to its preliminary
findings with respect to CES, because Silkman was CES’s managing member and took the lead on its
behalf on planning and perpetuating fraud in the DALRP, thereby resulting in similar facts underlying
the respective roles of Silkman and CES in the fraud.” PRDSMF ¶ 28 (citing Anas Decl; Anas Decl.,
Attach. 40, Order Assessing Civil Penalty Against CES (ECF No. 137-40) (Order Assessing Civil
29
18
FERC’s corporate designee was not aware of any substantive fact or substantive
conclusion that was changed in light of the thirty-page response CES previously
submitted. 32 DSMF ¶ 29; PRDSMF ¶ 29. FERC’s corporate designee was not aware
of any substantive conclusion of Enforcement’s preliminary findings and analyses
concerning Dr. Silkman that was changed in light of the thirty-page response CES
previously submitted. 33 DSMF ¶ 30; PRDSMF ¶ 30.
On April 26, 2010, Enforcement informed Respondents for the first time that
Rumford’s “enrolling participant,” Constellation, had changed its response to a data
request concerning a meeting between Constellation and Respondents. DSMF ¶ 31;
PRDSMF ¶ 31. Constellation had changed its answer from an answer that had
originally been exculpatory for the Respondents to an answer now inculpatory, which
attempted to deflect responsibility from Constellation to the Respondents. 34 DSMF
Penalty Against CES); Anas Decl., Attach 41, Order Assessing Civil Penalty Against Richard Silkman
(ECF No. 137-41) (Order Assessing Civil Penalty Against Silkman). The Court finds that the record
citation does not adequately support the Petitioner’s conclusion and declines to include the
qualification.
The Petitioner further denies the Respondents’ statement because of quotation marks around
the word “preliminary.” The Court removed the punctuation. See supra note 26.
32
The Respondents’ paragraph 29 states “FERC’s corporate designee was not aware of any
factual assertion in FERC Enforcement’s “preliminary” findings and analyses concerning Dr. Silkman
that was changed in light of the 30-page response previously submitted by CES.” DSMF ¶ 29 (citing
FERC Dep. 171-72). The Petitioner offers a qualified response, clarifying what was stated during the
FERC 30(b)(6)’s testimony. The Court finds that the Petitioner’s qualification accurately reflects what
was stated during the deposition and amends the Respondents’ paragraph 29.
The Petitioner further denies the Respondents’ statement because of quotation marks around
the word “preliminary.” The Court removed the punctuation. See supra note 26.
33
The Petitioner denies the Respondents’ statement because of quotation marks around the word
“preliminary.” The Court removed the punctuation. See supra note 26.
34
The Respondents’ paragraph 32 states: “In the view of Defendant’s counsel, this information
should have been disclosed much earlier because Constellation had changed its answer 180 degrees
from an answer that originally had been exculpatory for Respondents to an answer that was now
inculpatory, which attempted to deflect responsibility from Constellation to Respondents, and that the
original Constellation data response eviscerated FERC Enforcement’s theory of this case.” DSMF ¶
32 (citing Brann Decl. ¶ 20).
19
¶ 32; PRDSMF ¶ 32.
On April 29, 2010, Enforcement proposed to disclose what it deemed to be
additional relevant depositions, affidavits, and data responses of Constellation to Dr.
Silkman and Mark Isaacson of CES, and to Respondents’ counsel, provided that they
agreed not to disclose the information to anyone else. 35 DSMF ¶ 33; PRDSMF ¶ 33.
On May 20, 2010, Dr. Silkman responded to Enforcement’s preliminary findings and
analyses concerning Dr. Silkman in a thirty-four-page, single-spaced letter. DSMF ¶
34; PRDSMF ¶ 34.
d.
Settlement Negotiations
In May 2010, pursuant to Commission regulations, Enforcement had a closed
meeting with a quorum of the FERC Commissioners outside the presence of the
Respondents and their counsel in which Enforcement’s investigation of the
Respondents was discussed. 36 DSMF ¶ 35; PRDSMF ¶ 35. On November 15, 2010,
The Petitioner denies the Respondents’ paragraph 32, stating that “the statements and
assertions of ‘fact’ in the Brann Declaration and in Respondents’ SMF ¶ 32 as unsupported by
admissible record evidence.” The Court agrees with the Petitioner that portions of the Respondents’
paragraph 32 put forth legal arguments in the guise of statements of fact. Also, the views of
Respondents’ counsel about the timing of disclosure are not material to the undisputed facts
undergirding the resolution of this motion. The Court grants the Petitioner’s denial and removes the
impermissible legal argument from the Respondents’ paragraph 32.
35
The Petitioner interposes a qualification to the Respondents’ paragraph 33, reciting the
contents of the April 29, 2010 letter Enforcement staff sent to defense counsel. PRDSMF ¶ 33. The
Court does not find the majority of the Petitioner’s extensive qualification to conform with Local Rule
56(b), which requires that “[e]ach fact asserted in the statement shall be simply and directly stated”,
nor is it necessary to provide context to the Respondents’ paragraph 33. The Petitioner further states
that “Respondents’ counsel could have asked that other signatories be added to the letter.” PRDSMF
¶ 33. This statement is not supported by the cited record, and the Court declines to amend the
Respondents’ paragraph 33 to include it.
36
The Petitioner interposes a qualified response to the Respondents’ paragraph 35, stating: “The
testimony of the FERC 30(b)(6) witness cited as support for Respondents’ SMF ¶35 was that: (a) closed
meetings occur pursuant to the Commission’s regulations and those regulations define what
constitutes a closed meeting (see 18 C.F.R. § 375.201); (b) a number of enforcement investigations were
discussed during the May 2010 closed meeting, including Enforcement’s various DALRP
investigations; and (c) the CES and Silkman investigations were among the topics discussed.”
20
Enforcement served additional data requests on CES, initially giving CES two weeks
to respond. 37 DSMF ¶ 36; PRDSMF ¶ 36. Other than considering Dr. Silkman’s
response to the data requests and sending a new data request, FERC’s corporate
designee was either not aware of or unable to reveal anything else that Enforcement
did as part of its investigation between May and November 2010 without violating
attorney-client privilege. 38 DSMF ¶ 37; PRDSMF ¶ 37. Whether to do anything
during that period, as well as during the entire investigation, was up to Enforcement.
DSMF ¶ 38; PRDSMF ¶ 38.
Between November 2010 and March 2013, i.e., both before and after FERC
issued its Orders to Show Cause in July 2012, Enforcement communicated with
FERC Commissioners and their staff outside the presence of the Respondents or their
counsel concerning a possible settlement with Rumford regarding Rumford’s
participation in the DALRP. 39 DSMF ¶ 39; PRDSMF ¶ 39. In this action, FERC
PRDSMF ¶ 35. The Court amended the Respondents’ paragraph 35 to include the portions of the
Petitioner’s qualifications necessary for context.
37
The Petitioner interposes a qualified response to the Respondents’ paragraph 36, first noting
that the date that the second set of data requests was served on CES was November 15, 2010, not
November 20, 2010. PRDSMF ¶ 36. The remainder of the qualification is not directly responsive to
the Respondents’ paragraph 36, and the Court declines to include it.
38
The Petitioner denies the Respondents’ paragraph 37 as unsupported by the cited record,
noting that the FERC witness “was instructed by counsel not to answer the question in any way that
violates privilege,” and noting that the witness stated, in response to the question, “between the time
Dr. Silkman responded one thing Enforcement staff was doing was considering the response of Dr.
Silkman; and the other thing that I know they did is sent this data request.” PRDSMF ¶ 37 (citing
Anas Aff., Attach. 1, Ex. Dep. Test. Tr. of Jeremy Medovoy, October 18, 2017 (ECF No. 137-1)). The
Court amended the Respondents’ paragraph 37 accordingly.
39
The Petitioner admits the Respondents’ paragraph 39 but denies the statement with regard to
several potential implications. First, the Petitioner denies the implication “that these communications
should have been prohibited by a wall or characterized as ‘ex parte’ because ‘there are no parties. . . in
an investigation.” PRDSMF ¶ 39. The Petitioner also denies the suggestion that “communications
between. . . Commissioners or their advisory staff and Enforcement staff regarding investigative
matters are inappropriate prior to the commencement or an adjudicatory adversarial proceeding . . .
because prior to the commencement of an . . . order to show cause proceeding, Enforcement staff, in its
role as Commission staff tasked with investigating potential violations of the FPA and the
21
withheld the communications between Enforcement and FERC Commissioners and
their staff outside the presence of the Respondents or their counsel concerning a
possible settlement with Rumford between November 2010 and March 2013 on the
grounds of attorney-client privilege, among other reasons. DSMF ¶ 40; PRDSMF ¶
40.
FERC produced to the Respondents a privilege log describing those
communications pursuant to Magistrate Judge Nivison’s September 8, 2017 Order on
Discovery Issues (ECF No. 117). 40 Id. The same lawyers from Enforcement who
communicated between November 2010 and March 2013 with the FERC
Commissioners and their staff outside the presence of the Respondents or their
counsel concerning a possible settlement with Rumford were conducting the
investigation of the Respondents. DSMF ¶ 41; PRDSMF ¶ 41.
In February 2011, Enforcement made a settlement proposal orally to
Respondents’ counsel at a meeting in Washington, D.C. DSMF ¶ 42; PRDSMF ¶ 42.
On March 11, 2011, the Respondents requested seven categories of material not
Commission’s regulations, are permitted under the Commission’s regulations to communicate with the
Commission and certain of its advisory staff during an investigation.” Id. The Petitioner also “denies
the implication that Enforcement staff engaged in prohibited ex parte communications with the
Commission regarding a potential settlement with Rumford after formal adjudicatory proceedings
involving Rumford” began. Id.
The Court has not read, and will not read, any of the implications outlined by the Petitioner
with regard to the Respondents’ paragraph 39. The Petitioner further notes that on September 6,
2012, Enforcement staff . . . obtained a written waiver from Rumford of the protections afforded under
the Separation of Function Rule. . . and the ex parte rule. . . to consult with the Commission . . . for
purposes of exploring potential settlement. . .” Id. The Court does not view this statement as directly
responsive to the Respondents’ statement because it concerns Rumford and Rumford’s defense counsel,
not the Respondents’ or Respondents’ counsel.
40
The Petitioner admits the Respondents’ paragraph 40, but then denies certain implications
from the facts it admitted. PRDSMF ¶ 40. The Court includes the Petitioner’s qualification regarding
the production of a privilege log regarding these communications as it provides context to the
Respondents’ statement. The Petitioner also denies any implication made by the Respondents’
regarding ex parte or improper communications, which the Court notes.
22
previously disclosed in order to respond to Enforcement’s settlement proposal,
including a deposition of Rumford’s expert; all communications with and data
provided by Constellation; all communications with and data provided by ISO-NE;
all other information considered, evaluated, or relied upon by FERC to assess the
claims against the Respondents; and the methodology behind its settlement proposal.
DSMF ¶ 43; PRDSMF ¶ 43. On March 31, 2011, Enforcement responded to the
Respondents’ request, declining to produce such additional information because it
“does not believe that further disclosures of non-public investigative information are
warranted,” DSMF, Attach 1., FERC Dep. Ex. 18, (ECF No. 136-16), given the
Commission’s disclosure policies, the fact that the Commission already provided CES
and Dr. Silkman copies of all documents the Commission relied upon for their
preliminary conclusions, and that the Commission had already provided CES and Dr.
Silkman all potentially exculpatory material consistent with longstanding
Commission practice. DSMF ¶ 44; PRDSMF ¶ 44. Additionally, in a letter sent to
Respondents’ counsel on May 9, 2011, Enforcement staff provided a detailed
explanation of its calculation of the proposed penalties against CES and Dr. Silkman
that formed the basis of its settlement proposal. 41 Id. Enforcement determines
whether to provide information in the possession of Enforcement staff to the subject
of an investigation based on the law, the Commission’s regulations, policy statements,
and statutes governing the confidentiality of information gathered during
The Petitioner interposes a qualified response to the Respondents’ paragraph 44, detailing
additional reasons it stated in its response to the Respondents’ request for additional material to assist
them in settlement calculations. PRDSMF ¶ 44. To ensure that the Respondents’ paragraph 44 is
placed within context, the Court amended the statement to include the Petitioner’s qualifications.
41
23
investigations. 42 DSMF ¶ 45; PRDSMF ¶ 45.
On April 26, 2011, the Respondents submitted an eight-page response to
FERC’s oral settlement proposal. DSMF ¶ 46; PRDSMF ¶ 46. On May 9, 2011,
Enforcement rejected the Respondents’ settlement proposal, did not make a counterproposal, and initially gave the Respondents two days to submit a revised settlement
proposal. DSMF ¶ 47; PRDSMF ¶ 47. On May 9, 2011, Enforcement staff sent an
email and attached letter to Respondents’ counsel, which stated “[w]e carefully
considered your response, but disagree with your analysis,” and provided an
explanation of the Commission’s Penalty Guidelines and Enforcement’s calculations
of the proposed penalties articulated during the February 2011 settlement
conference. 43 Id. The Respondents’ counsel stated in an email to Enforcement staff
on May 9, 2011 that he would be meeting with his clients on May 11, and that he
anticipated getting back to Enforcement staff on May 12. Id. Enforcement staff
responded by email and agreed to delay any further action until after the close of
business on May 12, 2011. Id. On May 12, 2011, the Respondents responded to
Enforcement’s settlement letter but did not make a revised settlement proposal or
The Respondents’ paragraph 45 states “In determining whether to provide information in the
possession of FERC Enforcement that the subject of an investigation claims to need, it is up to FERC
Enforcement whether or not to turn over that information, subject to any FERC regulation or other
statute that prohibits disclosure.” DSMF ¶ 45. The Petitioner interposes a qualified response,
clarifying that FERC Enforcement’s decision to disclose “is based on the law, the Commission’s
regulations and Policy Statement on Disclosure of Exculpatory Materials, 129 FERC ¶ 61,248 (2009),
and statutes governing the confidentiality of information gathered during investigations.” PRDSMF
¶ 45. The Court amended the Respondents’ paragraph 45 to include the additional sources FERC
Enforcement uses to determine whether to disclose information.
43
In its response to Respondents’ paragraph 47, the Petitioner clarified the circumstances under
which it rejected the Respondents’ counteroffer and under which the deadline for a further response
from the Petitioner was due. PRDSMF ¶ 47. The Court included these additional details to provide
context.
42
24
accept Enforcement’s prior unchanged settlement demand. DSMF ¶ 48; PRDSMF ¶
48. On May 13, 2011, Enforcement responded to the Respondents’ settlement letter,
stating: “[i]t appears at this time that we will be unable to reach a settlement
regarding this matter.” 44
DSMF ¶ 49; PRDSMF ¶ 49.
In the same letter,
Enforcement informed the Respondents that their “preliminary conclusions have not
materially changed” and it intended to recommend that FERC issue Orders to Show
Cause but allowed the Respondents to submit a response to Enforcement. DSMF ¶
51; PRDSMF ¶ 51.
On June 27, 2011, CES and Dr. Silkman submitted a joint seventy-nine-page
response to Enforcement’s 1b.19 Letters. DSMF ¶ 52; PRDSMF ¶ 52. As required
by 18 C.F.R. § 1b.19, Enforcement submitted the Respondents’ response to the
Commission together with Enforcement staff’s report and recommendation that the
Commission initiate adversarial on-the-record order-to-show-cause proceedings
against the Respondents. In their 1b.19 response, which Enforcement staff provided
to the Commission, the Respondents restated the settlement positions they asserted
in the April 26, 2011 letter. 45 DSMF ¶ 50; PRDSMF ¶ 50.
The Petitioner interposes a qualified response to Respondents’ paragraph, stating several
other statements contained in FERC’s response letter. The Court does not find that these statements
are proper qualifications, but instead are an attempt to reframe the Respondents’ statement with more
detail than is necessary under Local Rule 56(b). See supra note 30.
45
The Respondents’ paragraph 50 states: “There is no entry on FERC’s privilege log that
indicates that FERC Enforcement ever conveyed the Defendants’ settlement proposal, or Defendants’
communications concerning settlement, to the FERC Commissioners or their staff. DSMF ¶ 50, citing
FERC Dep.; DSMF, Attach. 4, Dep. Test, Tr. of Richard Silkman, February 27, 2009 (ECF No. 136-4)
(Silkman Dep.). The Petitioner denies the Respondents’ paragraph 50 as unsupported by the cited
record material.
The Court finds that the record citation does not support the Respondents’ paragraph 50 and
affirms the Petitioner’s denial. In denying the Respondents’ paragraph 50, the Petitioner notes that
the Respondents’ 79-page response to FERC Enforcement’s May 13, 2011 letters, which restated the
Respondents’ settlement positions asserted in the April 26, 2011 letter, were shared with the
44
25
e.
Orders to Show Cause
On February 16, 2012, Enforcement submitted drafts of FERC’s Orders to
Show Cause and Enforcement’s Reports concerning the Respondents to FERC
Chairman Wellinghoff’s Chief of Staff, which have been withheld in this litigation on
the grounds of attorney-client privilege, among other reasons. 46
DSMF ¶ 53;
PRDSMF ¶ 53. Enforcement did not provide its reports to the Respondents when
Enforcement submitted them to the FERC Commissioners and did not disclose what
specific evidence it provided the FERC Commissioners. DSMF ¶ 54; PRDSMF ¶ 54.
There is no entry on FERC’s privilege log that indicates that when Enforcement
submitted the draft Orders to Show Cause and Enforcement’s Reports concerning the
Respondents to the FERC Commissioners and their staff, but Enforcement conveyed
to the FERC Commissioners or their staff the Respondents’ seventy-nine-page
response concerning Enforcement’s intention to recommend that FERC issue Orders
to Show Cause. 47 DSMF ¶ 55; PRDSMF ¶ 55.
Between February 16, 2012, when Enforcement submitted drafts of FERC’s
Commission as required by 18 C.F.R. §1b.19. PRDSMF ¶ 50. The Court included this statement for
context.
46
The Petitioner interposes a qualified response to the Respondents’ paragraph 53, noting that
“draft orders to show cause and Enforcement’s Staff Reports were submitted by Enforcement staff to
Chairman Wellinghoff’s Chief of Staff, not to the Commission.” PRDSMF ¶ 53 (citing Silkman Dep. at
16). The Court accepts the qualification and amended the Respondents’ paragraph 53.
47
The Respondents’ paragraph 55 states “[t]here is no entry on FERC’s privilege log that
indicates that when FERC Enforcement submitted the draft Orders to Show Cause and FERC
Enforcement’s Reports concerning the Respondents to the FERC Commissioners and their staff, it also
conveyed to the FERC Commissioners or their staff Defendants’ 79-page response concerning FERC
Enforcement’s intention to ‘recommend’ that FERC issue Orders to Show Cause.” DSMF ¶ 55. The
Petitioner admits the Respondents’ statement but denies “the implication that the absence of an entry
on a log of email communications means that Enforcement did not provide Respondents’ 1b.19
response to the commission.” PRDSMF ¶ 55. The Court included this fact offered by the Petitioner to
provide further context to the Respondents’ paragraph 55.
26
Orders to Show Cause and Enforcement’s Reports concerning the Respondents to the
Chairman Wellinghoff’s Chief of Staff, and July 17, 2012, when FERC issued the
Orders to Show Cause and Reports, there were written communications between
Enforcement and the Commission and the FERC Office of the Secretary outside the
presence of the Respondents and their counsel that have been withheld in this
litigation on the grounds of attorney-client privilege, among other reasons. 48 DSMF
¶ 56; PRDSMF ¶ 56. The FERC corporate designee was instructed not to answer
whether he knew if the FERC Commissioners made any changes to the draft Orders
or Reports submitted by Enforcement to them. 49 DSMF ¶ 57; PRDSMF ¶ 57.
On July 17, 2012, FERC issued a four-page Order to Show Cause against Dr.
Silkman, which attached Enforcement’s thirty-one-page report that “describes the
background of [Enforcement’s] investigation, findings and analysis, and proposed
sanctions.” DSMF ¶ 58; PRDSMF ¶ 58. FERC initially gave the Respondents thirty
days to respond to the Order to Show Cause, and to “elect (a) administrative hearing
before an ALJ at the Commission [‘Option 1’] or (b) if the Commission finds a
violation, an immediate penalty assessment by the Commission which a United
States district court is authorized to review de novo [‘Option 2’].” Id. On the same
The Petitioner denies the Respondents’ paragraph 56 on two bases: (1) That the reports were
submitted to Chairman Wellinghoff’s Chief of Staff, not to the Commission, and (2) that the record
does not support that there were eighteen written communications between FERC Enforcement and
the Commission. PRDSMF ¶ 56. The Court affirms the Petitioner’s denial and amended the
Respondents’ paragraph 56 to reflect the content of the cited record.
49
The Respondents’ paragraph 57 states: “The FERC Corporate Designee was instructed not to
answer whether the FERC Commissioners made any changes to the draft Orders or Reports submitted
by FERC Enforcement to them.” DSMF ¶ 57. The Petitioner denies the Respondents’ statement as
unsupported by the cited record, stating that the FERC designee was asked “Do you know if the
commission made any changes to the draft that was submitted by enforcement staff?” PRDSMF ¶57.
The Court affirms the denial and amends the Respondents’ paragraph 57 accordingly.
48
27
day, FERC issued a four-page Order to Show Cause against CES, which attached
Enforcement’s
thirty-one-page
Report
that
“describes
the
background
of
[Enforcement’s] investigation, findings and analysis, and proposed sanctions.” DSMF
¶ 59; PRDSMF ¶ 59.
FERC initially gave the Respondents thirty days to respond to the Orders to
Show Cause, and to “elect (a) administrative hearing before an ALJ at the
Commission [‘Option 1’] or (b) if the Commission finds a violation, an immediate
penalty assessment by the Commission which a United States district court is
authorized to review de novo [‘Option 2’]. DSMF ¶ 59; PRDSMF ¶ 59. Neither FERC
nor Enforcement ever made statements to the Respondents concerning the two
options other than what was contained in the Orders to Show Cause. DSMF ¶ 60;
PRDSMF ¶ 60. In other words, neither FERC nor Enforcement ever stated to the
Respondents that they could only get discovery or a hearing if they selected Option 1,
or that Option 2 was an “informal adjudication,” an “administrative penalty
assessment process,” or a “show cause proceeding” being conducted by FERC. Id.
At the same time, the statutes and regulations applying to contested on-therecord show cause proceedings are publicly available and were available to the
Respondents. Id. The Proposed Penalty Orders expressly stated that Respondents
could “elect (a) an administrative hearing before an ALJ at the Commission or (b) if
the Commission finds a violation, an immediate penalty assessment by the
Commission which a United States district court is authorized to review de novo.” Id.
That a proceeding before the Commission would be different than a proceeding before
28
an ALJ is apparent both from the language of the Proposed Penalty Orders issued to
Respondents on July 17, 2012 (“if the Commission finds a violation, an immediate
penalty assessment” by a Commission “order assessing a penalty”) and the governing
statute, which provides for a “prompt assessment” by Commission “order” if a
violation is found without mention of discovery or a live hearing. 50 Id.
On July 27, 2012, Enforcement provided the Respondents with additional
information “specifically referenced” in Enforcement’s Report and Recommendation
to FERC that had not been previously provided to the Respondents. DSMF ¶ 61;
PRDSMF ¶ 61. That same day, the Respondents filed a written election of option
two—to have an immediate penalty assessment by FERC if it found a violation—
which a district court could then review de novo. DSMF ¶ 62; PRDSMF ¶ 62.
On September 14, 2012, the Respondents submitted their written response to
the Orders to Show Cause. 51 DSMF ¶ 63; PRDSMF ¶ 63. On November 13, 2012,
Enforcement filed a reply with FERC to the Respondents’ response to the Orders to
Show Cause, the last filing before FERC issued the Orders Assessing Penalties. 52
The Petitioner denies the Respondents’ paragraph 60, arguing that the statement is
unsupported by admissible record evidence and is contradicted by other admissible record evidence.
PRDSMF ¶ 60. The Court finds that the Respondents’ citation to the Brann Declaration supports its
statement. See supra note 9. The Court includes the relevant supplemental information offered by
the Petitioner, because the dispute is factual in nature, and the Court must view the facts in the light
most favorable to the non-movant.
51
The Petitioner admits the Respondents’ paragraph 63 but denies that Exhibit 40, the record
citation offered by the Respondents, supports the statement, and instead points to Exhibit 39 for
support. PRDSMF ¶ 63 (citing Order Assessing Civil Penalty Against CES; Order Assessing Civil
Penalty Against Richard Silkman). The Court, after reviewing the two exhibits as well as the
testimony of the FERC designee, finds that the Respondents’ statement is supported by Exhibit 39,
not Exhibit 40.
52
The Petitioner admits the Respondents’ paragraph 64 but denies that Exhibit 41, the record
citation offered by the Respondents, supports the statement, and instead points to Exhibit 40 for
support. PRDSMF ¶ 64. The Court, after reviewing the two exhibits as well as the testimony of the
FERC designee, finds that the Respondents’ statement is supported by Exhibit 40.
50
29
DSMF ¶ 64; PRDSMF ¶ 64. On November 14, 2012, Enforcement provided the
Respondents with additional information “specifically referenced” in Enforcement’s
Reply that had not been previously provided to the Respondents.
DSMF ¶ 65;
PRDSMF ¶ 65.
Other than these written submissions, there were no communications to or
from FERC and the Respondents after FERC issued the Orders to Show Cause until
FERC issued its Orders Assessing Penalties. DSMF ¶ 66; PRDSMF ¶ 66. Other than
making its written declaration of Option 2 and submitting a written response to the
Orders to Show Cause, the Respondents did not participate in any proceeding after
FERC issued the Orders to Show Cause. 53 DSMF ¶ 67; PRDSMF ¶ 67. After FERC
issued Orders to Show Cause, the Respondents were not automatically entitled to
obtain or conduct discovery; however, the Respondents could have made a request for
discovery to the Commission via motion, pursuant to the Commission’s Rules of
Practice and Procedure, 18. C.F.R. Part 385. 54 DSMF ¶ 68; PRDSMF ¶ 68. During
the investigation and the Order to Show Cause Proceedings, the Respondents did not
take any depositions, although defense counsel was permitted to ask questions of Dr.
The Petitioner admits the Respondents paragraph 67 but “denies that the Commission’s
proceedings are “alleged” proceedings because, under the Commission’s regulations, issuance of a
Proposed Penalty Order commences a ‘contested on-the-record proceeding’ known as a “show cause
proceeding,” subject to the Commission’s Rules of Practice and Procedure.” PRDSMF ¶ 67. The Court
affirms the Petitioner’s denial and removes the word “alleged” from the Respondents’ paragraph 67,
as it is not supported by the record, and is argument, not fact.
54
The Petitioner denies the Respondents’ paragraph 68, stating: “[u]nder the Commission’s
regulations, the Respondents could have made a request for discovery to the Commission via motion.”
PRDSMF ¶ 68. The Petitioner “further specifically denies that Respondents ‘were not permitted’ to
obtain or conduct any discovery after the Proposed Penalty Issues were issued because Respondents
did not make any request via motion. . ..” Id. This is a factual dispute between the parties, and the
Court must view the evidence in the light most favorable to the non-movant. The Court, therefore,
amended the Respondents’ paragraph 68 to conform to its obligation to view contested facts in the
light most favorable to the Petitioner.
53
30
Silkman when Enforcement took his deposition. 55 DSMF ¶ 84; PRDSMF ¶ 84. FERC
and Enforcement did not conduct additional fact-finding after FERC issued the
Orders to Show Cause. 56 DSMF ¶ 69; PRDSMF ¶ 69. Subsequently, the Commission
conducted additional fact-finding after FERC issued Orders to Show Cause cited by
FERC in the Orders Assessing Penalties. 57 Id. There was no live hearing, as opposed
to a paper hearing, conducted before the FERC Commissioners or a decisionmaker
who in the Respondents’ view was neutral and impartial either before or after FERC
issued Orders to Show Cause concerning the merits of the allegations against the
Respondents. 58 DSMF ¶ 70; PRDSMF ¶ 70. The Respondents were not permitted to
The Petitioner admits that the Respondents did not take any depositions during the
investigation or the order-to-show-cause proceedings but denies that the Respondents did not take any
depositions during this litigation, and states that defense counsel “deposed multiple witnesses during
discovery in this litigation.” PRDSMF ¶ 84 (citing FERC Dep; DSMF, Attach. 25, Alley Dep. (ECF No.
136-25); DSMF, Attach. 26, Butte Dep. (ECF No. 136-26); DSMF, Attach. 27, Fuller Dep. (ECF No. 13627)). The Court amended the Respondents’ paragraph 84 to clarify the period during which the
Respondents did not take depositions.
56
The Respondents’ paragraph 69 states in part that “[t]he Defendants are not aware of any
additional fact-finding conducted by FERC Enforcement or FERC after FERC issued the Orders to
Show Cause.” DSMF ¶ 69. The Petitioner admitted this assertion, PRDSMF ¶ 69, so the Court
amended it from one of the Respondents’ belief to one of fact.
57
In Respondents’ paragraph 69, the Respondents also stated that “Defendants are not aware
of any additional fact-finding conducted by them (namely Enforcement or FERC) after FERC issued
Orders to Show Cause that was cited by FERC in the Orders Assessing Penalties.” DSMF ¶ 69. The
Petitioner denies, however, that the Respondents were not aware that “the Commission engaged in
fact finding after the Commission issued the Proposed Penalty Orders because the Commission’s
August 29, 2013 Assessment Orders reflect that the Commission made findings of fact based on the
record evidence presented to it by the parties in their written submissions during the on-the-record
adjudicatory show cause proceedings.” Id. The Court views the dispute as factual in nature and is
required to view the evidence in the light most favorable to the Respondents. The Petitioner’s denial
of the Respondents’ paragraph 69 is affirmed and the statement is amended accordingly. The Court
altered the statement from one that describes what the Respondents knew or did not know to one of
fact.
58
The Petitioner “admits that the Respondents did not receive a live hearing (as opposed to a
paper hearing) during the adjudicative order-to show-cause proceedings” but denies “that there was
no hearing before a ‘neutral impartial decision-maker’” as unsupported by the cited record. PRDSMF
¶ 70. The Court altered the Respondents’ paragraph 70 to include the reference to paper hearing
because it is required to view contested facts in the light most favorable to the nonmovant. The Court
amended the Respondents’ paragraph 70 to acknowledge that whether the decisionmaker was neutral
and impartial is a contested conclusion, and the Court altered paragraph 70 to confirm that the
Respondents’ position is that the decisionmaker was neither neutral nor impartial.
55
31
meet ex parte with the FERC Commissioners and their staff concerning the merits of
the claims asserted against Respondents after the commencement of the order-toshow-cause proceedings as the Commission’s regulations prohibit any party to a
contested on-the-record proceeding, including an order-to-show-cause proceeding,
from engaging in ex parte contacts with the Commission. 59 DSMF ¶ 71; PRDSMF ¶
71.
In their written submissions, the Respondents could only cite evidence from
the investigation that had been developed by Enforcement to prosecute the case
against the Respondents and that had been disclosed by Enforcement, and could only
cite answers to deposition questions asked by Enforcement outside the presence of
the Respondents or their counsel or witnesses who had incentive to deflect
responsibility from themselves to the Respondents. 60 DSMF ¶ 72; PRDSMF ¶ 72. 61
f.
Orders Assessing Penalties
The Petitioner denies that the Respondents were not permitted to meet with the FERC
Commissioners and their staff at any time, “because no regulation prohibited Respondents from
making a written request during the Enforcement investigation . . ..” PRDSMF ¶ 71. The Petitioner
also denies the statement “as to the time period covered by the adjudicatory order-to-show-cause
proceedings” but does not offer specific record support for this denial. Id. The Petitioner further states
that FERC regulations “prohibit any party to a contested on-the-record proceeding . . . from engaging
in ex parte contacts with the commission”, and that FERC regulations allow “a party to a contestedon-the-record proceeding . . . to file a motion for relief to toe Commission at any time during the
proceeding.” Id. The Court views the dispute over the Respondents’ paragraph 71 as factual and
must view the facts in the light most favorable to the Respondents. The Petitioner’s denial is affirmed,
and the Respondents’ statement is accordingly amended.
60
The Petitioner denies the Respondents’ paragraph 72 “because no rules of evidence governed
the order-to-show-cause proceedings” and “because the Commission’s Rules of Practice and Procedure
governing adjudicatory proceedings before the Commission . . . specifically provide that a Respondents’
answer must include ‘documents that support the facts in the answer in possession of, or otherwise
attainable by Respondents, including, but not limited to, contracts and affidavits.” PRDSMF ¶ 72
(citing 18 C.F.R. § 385.215(c)(4)(2012)). The Petitioner further notes that the Respondents never made
a request via motion for discovery during the proceedings. PRDSMF ¶ 72. The Court views the
Petitioner’s denial as not directly responsive to the Respondents’ statement. The denial is overruled.
61
The Respondents’ paragraph 73 states “Defendants perceived that they received less process
after FERC issued its Orders to Show Cause than they received before that time.” DSMF ¶ 73. The
59
32
On August 29, 2013, FERC issued Orders Assessing Penalties against the
Respondents. DSMF ¶ 74; PRDSMF ¶ 74.
FERC had control over its docket and
could decide how long to take to issue a decision, and thus it was within its control
whether to take over a year from July 17, 2012, when FERC issued the Orders to
Show Cause, until August 29, 2013, when FERC issued the Orders Assessing
Penalties. DSMF ¶ 75; PRDSMF ¶ 75.
During that period, the Respondents and
Enforcement each moved for an enlargement of time of approximately thirty days,
and each extension was granted by the Commission. 62 Id. Other than requesting
and receiving additional time to respond to Enforcement’s Preliminary Findings and
Proposed Penalty Orders, the Respondents did not have any control or input over
when FERC issued its Orders Assessing Penalties, or when FERC issued its earlier
Orders to Show Cause, or when Enforcement issued its earlier preliminary findings
and conclusions, or when Enforcement recommended to FERC that it issue its Orders
to Show Cause. 63 DSMF ¶ 76; PRDSMF ¶ 76.
Petitioner denies the Respondents’ paragraph 73 “because Petitioner has no way to know what
Respondents’ ‘perceived’ . . .” and because defense counsel states in his declaration what he perceived,
not what the Respondents perceived. PRDSMF ¶ 73. What the Defendants or their lawyer perceived
about the extent of due process afforded them at varying times is neither material nor relevant to the
legal issues before the Court. Although due process is flexible, it cannot turn on the perceptions of the
litigants or their attorneys, but on what is legally required. Whether the Respondents in fact received
more or less due process during various phases is a question of fact, not of perception. The Court
declines to include the Respondents’ paragraph 73.
62
The Petitioner interposes a qualified response to the Respondents’ paragraph 75, noting that
both FERC Enforcement and the Respondents filed motions for enlargement of time during this period.
To ensure that the Respondents’ statement is not misleading, the Court amended it to include the
Petitioner’s qualification in part. The Petitioner also details other considerations of the Commission’s
workload in its qualification, which the Court views as not directly responsive to the Respondents’
paragraph 75 and the Court declines to include.
63
In response to the Respondents’ paragraph 76, the Petitioner interposes a qualification, stating
that the Respondents “requested and received additional time to respond to Enforcement’s Preliminary
Findings and requested and received additional time to respond to the Commission’s Proposed Penalty
Orders . . .” PRDSMF ¶ 76. The Court amended the Respondents’ paragraph 76 to include the
qualification.
33
Enforcement did not provide the Respondents with all the information it
obtained as part of its investigation of the Respondents before FERC issued the
Orders Assessing Penalties. 64 DSMF ¶ 77; PRDSMF ¶ 77. Although the Respondents
could have requested discovery, the Respondents did not have the right to conduct
discovery at any point prior to the time FERC issued the Orders Assessing
Penalties. 65 DSMF ¶ 78; PRDSMF ¶ 78. Although the Respondents could have
requested discovery, the Respondents also did not have the right to serve document
requests on FERC or to compel Enforcement to disclose what it had obtained as part
of its investigation at any time before FERC issued the Orders Assessing Penalties.66
DSMF ¶ 79; PRDSMF ¶ 79. Both before and after FERC issued its Orders to Show
Cause, the Respondents did not serve any interrogatories on FERC. 67 DSMF ¶ 80;
PRDSMF ¶ 80.
Although the Respondents could have requested discovery, the
Respondents did not have the right to serve interrogatories on FERC at any time
The Petitioner admits the Respondents’ paragraph 77 “but denies the suggestion that
Petitioner did not provide relevant or material information to Respondents at all relevant times.”
PRDSMF ¶ 77. The Petitioner’s qualification is not factual but argument about proper inferences from
the facts. The Court declines to include it.
65
The Petitioner admits the Respondents’ paragraph 78 in part but “denies the suggestion that
Respondents could not have requested such discovery, as the Commission’s Rules of Practice and
Procedure permit parties to contested . . . proceedings . . . to file motions for relief to the Commission
at any time during the proceedings. . .” PRDSMF ¶ 78. To make the record accurate, the Court
included the Petitioner’s statement that the Respondents could have requested discovery, even though
the Respondents correctly state that they did not have the right to discovery.
66
In response to the Respondents’ paragraph 79, the Petitioner “denies the suggestion that the
Respondents’ could not have requested such discovery.” PRDSMF ¶ 79. As with paragraph 78, to
make the record accurate, the Court amended the Respondents’ paragraph 79 to reflect that they could
have requested discovery, even though they did not have the right to discovery.
67
In response to the Respondents’ paragraph 80, the Petitioner “denies the suggestion” that the
Respondents’ could not have requested such discovery. PRDSMF ¶ 80. The Court just clarified that
the Respondents could have requested discovery. DSMF ¶¶ 78-79; PRDSMF ¶¶ 78-79. The only
asserted fact here is that the Respondents did not actually serve any interrogatories on Petitioner.
The Court overrules the Petitioner’s qualified response.
64
34
before FERC issued the Orders Assessing Penalties. 68 DSMF ¶ 81; PRDSMF ¶ 81.
Although the Respondents could have requested discovery, they did not have the right
to serve third party subpoenas at any time before FERC issued the Orders Assessing
Penalties. 69 DSMF ¶ 82; PRDSMF ¶ 82. Although the Respondents could have
requested discovery, the Respondents did not have the right to compel the production
or preservation of any documents from any third parties at any time before FERC
issued the Orders Assessing Penalties. 70
DSMF ¶ 83; PRDSMF ¶ 83.
The
Respondents did not have the right to notice testimony of any third-party witness at
any time before FERC issued the Orders Assessing Penalties. 71
PRDSMF ¶ 85.
DSMF ¶ 85;
Although the Respondents could have requested discovery, the
Respondents did not have the right to compel testimony or an interview with any
third-party witness before FERC issued the Orders Assessing Penalties. 72 DSMF ¶
The Petitioner puts forth the same response to the Respondents’ paragraph 81 as it does to the
Respondents’ paragraphs 78 and 79. For the reasons stated above, the Court amends the Respondents’
paragraph 81 to reflect the fact that they could have requested discovery but did not have a right to
discovery. See supra note 66-67.
69
See supra note 66-67.
70
See supra note 66-67.
71
The Petitioner denies the Respondents’ paragraph 85 as unsupported by the cited record
materials, because it argues that the Brann Declaration is inadmissible, and that Petitioner’s response
to RFA ¶ 51, cited in support of the Respondents’ statement, states that the Respondents “did not have
the right to notice or take testimony of any witness during Enforcement’s investigation under Part 1b
of the Commission’s regulations, and that the Commission’s regulations do not provide discovery as a
matter of right during order-to-show-cause proceedings.” PRDSMF ¶ 85 (citing DSMF, Attach. 2,
FERC FRA Resp. (ECF No. 136-2)).
The Court finds the Respondents’ paragraph 85 adequately supported by the cited record and
overrules the Petitioner’s denial. See supra note 9. Unlike the Petitioner’s other responses, here the
Petitioner does not claim that the Respondents could have requested permission to notice the
testimony of third party witnesses. PRDSMF ¶ 85. Instead it states that the Respondents do not cite
any statutes or regulations that would have prohibited them from doing so. The Court overrules the
Petitioner’s denial because Respondents’ paragraph 85 is adequately supported by the record and the
Petitioner’s denial is not.
72
The Petitioner admits that “the Commission’s regulations do not provide discovery as a matter
of right during order-to-show-cause proceedings . . . but denies the suggestion that Respondents could
not have requested such discovery . . . as the Commission’s Rules of Practice and Procedure permit
68
35
86; PRDSMF ¶ 86.
In or around February 2009, Enforcement staff requested the testimony of Dr.
Richard Silkman in its investigations of certain DALRP participants. PSAMF ¶ 2;
DRPSAMF ¶ 2. Enforcement staff could have compelled Dr. Silkman’s testimony
only after (a) receiving the Commission’s authorization to convert its investigation to
formal status under 18 C.F.R. § 1b.5, (b) issuing a subpoena for Dr. Silkman’s
testimony, and (c) if Dr. Silkman refused to comply with the subpoena, successfully
seeking to have the subpoena enforced by a federal judge, 18 C.F.R. § 1b.15, none of
which FERC Enforcement staff did in this instance. Id. The Commission was neither
asked to pay, nor paid, Dr. Silkman’s travel expenses in appearing to testify. Id.
FERC Enforcement set the location for the deposition in Washington, D.C., rather
than Maine, and then informed Dr. Silkman’s counsel on several occasions that the
Defendants’ “cooperation” would be taken into account in determining how to
proceed. 73 Id.
The Respondents produced in discovery in this litigation a joint defense
agreement entered into between CES and Rumford effective March 19, 2009,
concerning FERC’s investigation of Rumford’s participation in the ISO-NE DALRP.
PSAMF ¶ 3; DRPSAMF ¶ 3.
Dr. Silkman provided draft answers to Rumford or its counsel to data requests
parties . . . to file motions for relief . . .” PRDSMF ¶ 86. Consistent with its prior rulings, the Court
amends the Respondents’ paragraph 86. See supra note 66-67.
73
The Respondents interpose a qualified response to the Petitioner’s paragraph 2, providing
further details surrounding Dr. Silkman’s deposition. The Court amended the Petitioner’s statement
to include this additional context.
36
served on Rumford by Enforcement staff during Enforcement’s investigation of
Rumford’s participation in the DALRP. 74 PSAMF ¶ 4; DRPSAMF ¶ 4.
Although the Respondents question whether the so-called preliminary findings
were in fact preliminary, Enforcement staff sent a Preliminary Findings Letter to
CES on November 23, 2009, explaining Enforcement’s preliminary conclusion that
CES had committed fraud in violation of the Commission’s Anti-Manipulation Rule,
as well as the factual and legal bases for this conclusion. 75 PSAMF ¶ 5; DRPSAMF
¶ 5. In the letter, Enforcement staff initially asked for a response within three weeks
from the date of the letter.
Id.
Enforcement staff subsequently provided CES
additional time, until January 8, 2012, to respond to the November 23, 2009
Preliminary Findings Letter to CES. Id.
Again, although the Respondents question whether the so-called preliminary
findings were in fact preliminary, Enforcement staff sent a Preliminary Findings
Letter to Dr. Silkman on April 19, 2010, explaining Enforcement’s preliminary
conclusion that Dr. Silkman had committed fraud in violation of the Commission’s
Anti-Manipulation Rule, as well as the factual and legal bases for this conclusion.
PSAMF ¶ 6; DRPSAMF ¶ 6. In the letter, Enforcement staff initially asked for a
response by May 3, 2010. Enforcement staff subsequently provided Dr. Silkman with
additional time, until May 20, 2010, to respond to the April 19, 2010 Preliminary
The Respondents pose a qualification to the Petitioner’s statement, stating that Dr. Silkman
responded to some, but not all, of the data requests, but they fail to provide a record citation. The
Court declines to include the qualification.
75
The Respondents admit that Petitioner labeled the letter a Preliminary Findings Letter, but
they deny that the findings were in fact preliminary. PSAMF ¶ 5; DRPSAMF ¶ 5. The Court qualified
the Petitioner’s additional paragraph 5 to reflect the Respondents’ skepticism.
74
37
Findings Letter to Dr. Silkman. Id.
As stated in the May 2008 Policy Statement on Enforcement, the purpose of
preliminary findings issued by Enforcement staff is to allow the subject of an
investigation to understand Enforcement staff’s position and to provide an
opportunity for the subject to respond with argument or evidence if it believes
Enforcement staff’s position is incorrect, thereby allowing Enforcement staff to
change its position before reaching its final conclusions should they be persuaded by
the subject’s response. 76 PSAMF ¶ 7; DRPSAMF ¶ 7.
On April 29, 2010, Enforcement staff sent Respondents’ counsel a letter that
was later countersigned by the Respondents and their counsel, which, in part, stated:
(a) “Staff believes that disclosure of certain documents will facilitate CES’s
understating of the investigation and Constellation NewEnergy, Inc.’s (CNE)
purported knowledge of Rumford’s baseline period generation curtailment,” (b)
“However, all of the information was obtained as part of a non-public investigation
and the information is confidential in nature under section 1b.9 of the Commission’s
regulations. 18 C.F.R. § 1b.9 (2009),” (c), “CNE also believes that the information
includes non-public and confidential commercial information,” (d) “Nevertheless,
Enforcement has obtained permission from CNE and counsel to Ms. Amy Richard,
Mr. Peter Kelly-Detwiler, and Mr. Bruce McLeish to release relevant portions of all
The Respondents interpose a qualification, reciting verbatim the entire Revised Policy
Statement on Enforcement (ECF No. 137-6). DRPSAMF ¶ 7. The Petitioner’s statement provides an
accurate summary of the Policy Statement, and the Respondents have not explained why any word
differences between Petitioner’s additional paragraph 7 and the quoted Policy Statement matter. The
Court declines to accept the Respondents’ qualification and deems Petitioner’s additional paragraph 7
admitted.
76
38
deposition transcripts and affidavits of CNE employees as well as other narrative
data request responses from CNE involving CNE’s knowledge of Rumford’s
operations, subject to the restrictions in this letter,” and (e),
In order to maintain the non-public nature of this investigation and the
materials obtained as part of the investigation, we will require CES to agree
that these documents, and this letter, will be used only by the CES attorneys
working on this matter, and, for purposes of review, shown only to fellow
signatories to the attachment.
PSAMF ¶ 8; DRPSAMF ¶ 8. The letter contained signature lines for Dr. Silkman,
Mark Isaacson, Attorney Brann, and any Brann & Isaacson attorneys or employees
working on the matter.
Id.
Respondents’ counsel could have asked that other
signatories be added to the letter. Id. The letter stated that both the documents and
the letter “will be used only by the CES attorneys working on this matter,” and that
“[a]t no time shall CES or the other signatories to the attachment permit further
dissemination of these documents, including to any other subject of the investigation.
Id. The letter only came after the Respondents specifically requested that principals
of CES and co-counsel be permitted to see the materials FERC had initially forbidden
them to see. 77 Id.
On November 15, 2010, Enforcement staff served a second set of data requests
on CES via counsel for CES. The second set of data requests consisted of five request
items and asked for a response by November 29, 2010. PSAMF ¶ 9; DRPSAMF ¶ 9.
CES, through counsel, provided a four-page written response to the second set of data
request on November 29, 2010. Id. In addition, certain attachments to the response
The Respondents interpose a qualified response to the Petitioner’s statement of additional
material fact ¶ 8, which the Court included to supply additional context to the April 29, 2010 letter.
77
39
were sent on disk and received by Enforcement staff on December 1, 2010. Id.
The Commission issued an Order to Show Cause and Notice of Proposed
Penalty to Rumford on July 17, 2012 and commenced a proceeding against Rumford. 78
PSAMF ¶ 10; DRPSAMF ¶ 10. In accordance with the Commission’s Separation of
Function Rule, 18 C.F.R. § 385.2202, and the Commission’s ex parte rule, 18 C.F.R. §
385.2201, following issuance of the Order to Show Cause and Notice of Proposed
Penalty to Rumford, the Commission issued a notice in the docketed proceeding on
July 26, 2012 identifying decisional and non-decisional staff.
PSAMF ¶ 11;
DRPSAMF ¶ 11.
On September 6, 2012, Enforcement staff who participated in the investigation
of Rumford and received a settlement offer from Rumford obtained a written waiver
from Rumford of the provisions of 18 C.F.R. § 385.2202 and 18 C.F.R. § 385.2201 to
consult with the Commission and Commission decisional staff for purposes of
exploring potential settlement with Rumford. 79
PSAMF ¶ 12; DRPSAMF ¶ 12.
Enforcement staff neither asked for or received waivers from Respondents to engage
in what Respondents view as ex parte discussions with the FERC Commissioners
regarding Rumford’s DALRP participation, an issue that the Respondents view as
being at the heart of the pending claims against them. Id.
In response to the Petitioner’s statement of additional material fact ¶ 10, the Respondents
interpose a qualification, noting that “[t]he referenced exhibit does not refer to a ‘docketed show cause
proceeding’ or even a ‘show cause proceeding.” DRPSAMF ¶ 10. The Court agrees that the phrase is
not included in the record citation and omits it from the Petitioner’s statement.
79
The Respondents interpose a qualified response to the Petitioner’s statement of additional
material fact ¶ 12, noting that “[w]hether or not FERC Enforcement received a waiver from Rumford,
it neither asked for nor received any such waiver from CES or Silkman to continue to engage in ex
parte discussions with the FERC Commissioner’s regarding Rumford’s DALRP participation.”
DRPSAMF ¶ 12. The Court amended Petitioner’s additional paragraph 12 to reflect this fact.
78
40
Although Respondents believe otherwise, consistent with the Commission’s
Policy Statement on Disclosure of Exculpatory Materials, 129 FERC ¶ 61,248 (2009),
Enforcement staff provides subjects of Enforcement investigations under Part 1b of
the Commission’s regulations with all potentially exculpatory materials obtained
during Enforcement’s investigation. 80 PSAMF ¶ 13; DRPSAMF ¶ 13.
Enforcement staff submitted to the Commission in paper form Enforcement’s
Staff Report and Recommendations together with Respondents’ joint seventy-ninepage written response provided by Respondents to Enforcement staff pursuant to 18
C.F.R. § 1b.19. 81 PSAMF ¶ 14; DRPSAMF ¶ 14.
B.
Statement of Facts: FERC’s Partial Motion for Summary
Judgment
1.
Organization, Powers, and Rulemaking Authority
The Commission is an administrative agency of the United States, organized
and existing as an independent, bipartisan Commission. PSMF ¶ 1; DRPSMF ¶ 1.
A majority of the Commission determines its actions, with three members of the
Commission constituting a quorum for the transaction of business. 82 PSMF ¶ 2;
The Respondents deny the Petitioner’s statement of additional material fact paragraph 13,
citing other statements of material fact. The Court noted the Respondents’ skepticism but is required
to view contested facts in the light most favorable to the nonmovant.
81
The Respondents request to strike the Petitioner’s additional statement of material fact
because its only cited record support is Attorney Anas’ declaration. The Court resolved this dispute
and will not strike the affidavit or the Petitioner’s statement of additional fact ¶ 14. See supra note 9.
With regard to the Respondents’ qualification, the Court considers the dispute an issue of fact, and
must view disputed facts in the light most favorable to the non-moving party. The Court, therefore,
declines to include the Respondents’ qualification.
82
The Respondents interpose a qualification to the Petitioner’s statement, noting that the
“characterization that the Commission ‘acts through orders’ is not supported by the record citations.”
DRPSMF ¶ 2. The cited record states that “Actions of the Commission shall be determined by a
majority vote of the members present.” Anas Decl., Attach. 45, Exhibit 42 U.S.C. § 7171 (2016) (ECF
No. 137-45). The Court changed the Petitioner’s statement to track the cited statutory language.
80
41
DRPSMF ¶ 2. The Federal Power Act (FPA) §§ 307 et seq. authorizes the Commission
to conduct investigations. PSMF ¶ 3; DRPSMF ¶ 3. Section 307(a) provides that
“[t]he Commission may permit any person, electric utility, transmitting utility, or
other entity to file with it a statement in writing under oath or otherwise, as it shall
determine, as to any or all facts and circumstances concerning a matter which may
be the subject of investigation.” PSMF ¶ 4; DRPSMF ¶ 4. FPA § 307(b) provides that:
For the purpose of any investigation or any other proceeding under this
Act, any member of the Commission, or any officer designated by it, is
empowered to administer oaths and affirmations, subpoena witnesses,
compel their attendance, take evidence, and require the production of
any books, papers, correspondence, memoranda, contracts, agreements,
or other records which the Commission finds relevant or material to the
inquiry.
PSMF ¶ 5; DRPSMF ¶ 5. Section 308 authorizes the Commission to conduct hearings
but does not require the Commission to do so, and no hearing was conducted in this
case. 83 PSMF ¶ 6; DRPSMF ¶ 6.
Congress described the Commission’s authority:
In carrying out any of its functions, the Commission shall have the
powers authorized by the law under which such function is exercised to
hold hearings, sign and issue subpoenas, and receive evidence at any
place in the United States it may designate The Commission may, by
one or more of its members or by such agents as it may designate,
conduct any hearing or other injury necessary or appropriate to its
functions, except that nothing in this subsection shall be deemed to
supersede the provisions of section 556 of title 5 relating to hearing
examiners.
42 U.S.C. §7171(g) (2012). PSMF ¶ 7; DRPSMF ¶ 7.
Petitioner’s paragraph 6 merely states: “FPA § 308 authorizes the Commission to conduct
hearings.” PSMF ¶ 6. The Respondents interpose a qualified response to the Petitioner’s paragraph
6, noting that “[w]hile FPA § 308 authorizes the Commission to conduct hearings, it does not require
the Commission to conduct hearings, and no hearing was conducted in this case.” DRPSMF ¶ 6. The
Court included the qualification to provide context for this case.
83
42
FPA § 308(b) requires that:
All hearings, investigations, and proceedings under this Act shall be
governed by rules of practice and procedure to be adopted by the
Commission, and in the conduct thereof the technical rules of evidence
need not be applied. No informality in any hearing, investigation, or
proceeding or in any manner of taking testimony shall invalidate any
order, decision, rule, or regulation issued under the authority of this
chapter. 84
16 U.S.C. § 825g(b) (2012). PSMF ¶ 8; DRPSMF ¶ 8.
FPA § 309 further grants the Commission:
The power to perform any and all acts, and to prescribe, issue, make,
amend, and rescind such orders, rules, and regulations as it may find
necessary or appropriate to carry out the provisions of this chapter.
Among other things, such rules and regulations may define accounting,
technical, and trade terms used in this Act; and may prescribe the form
or forms of all statements, declarations, applications, and reports to be
filed with the Commission, the information they contain, and the time
within which they shall be filed. Unless a different date is specified
therein, rules and regulations of the Commission shall be effective thirty
days after publication in the manner which the Commission shall
prescribe. Orders of the Commission shall be effective on the date and
in the manner which the Commission shall prescribe. 85
16 U.S.C. § 825h (2012). PSMF ¶ 9; DRPSMF ¶ 9.
Congress provided the Commission with the authority to establish rules and
procedures:
The Commission is authorized to establish such procedural and
administrative rules as are necessary to the exercise of its functions.
Until changed by the Commission, any procedural and administrative
rules applicable to particular functions over which the Commission has
The Respondents interpose a qualified response to the Petitioner’s paragraph 8, noting that
the record citation uses the term “chapter” instead of “Act.” See Anas Aff., Attach. 47, Exhibit 17
U.S.C. § 825g (ECF No. 137-47). The Court amended the Petitioner’s paragraph 8 accordingly.
85
The Respondents interpose the same qualified response to the Petitioner’s paragraph 9 as they
did to paragraph 8, noting that the record citation uses the term “chapter” instead of “Act.” See Anas
Aff., Attach. 47, Exhibit 17 U.S.C. § 825g (ECF No. 137-47). The Court amended the Petitioner’s
paragraph 9 accordingly.
84
43
jurisdiction shall continue in effect with respect to such particular
functions.
42 U.S.C. § 7171. PSMF ¶ 10; DRPSMF ¶ 10. The Commission codified Rules
Relating to Investigations at 18 C.F.R. Part 1b and Rules of Practice and Procedure
at 18 C.F.R. Part 385. PSMF ¶ 11; DRPSMF ¶ 11.
2.
Civil Penalty Authority
FPA § 316A authorizes the Commission to levy civil penalties for violations of
Part II of the Act—which includes the prohibition of energy market manipulation, §
222, 16 U.S.C. § 824v(a)—or “of any rule or order thereunder.” 16 U.S.C. § 825o-1
(2012). 86 PSMF ¶ 12; DRPSMF ¶ 12. The FPA requires that the Commission assess
such penalties, after “notice and opportunity for public hearing, in accordance with
the same provisions as are applicable under section 823b(d) in the case of civil
penalties assessed under section 823b.” 87 PSMF ¶ 13; DRPSMF ¶ 13. FPA § 31(d)
sets out two applicable provisions, or paths that the proceeding can take at the
election of the respondent: (1) the “default” procedure enunciated in § 31(d)(2), under
which the Commission shall provide a hearing before an ALJ, or (2) an alternative
process under § 31(d)(3), whereby the Commission shall assess a penalty, and then
institute an action in the appropriate U.S. district court for an order of affirmance,
during which resulting proceeding the district court is able to review de novo the law
The Respondents again interpose a qualified response noting that the record citation uses the
term “chapter” instead of “Act”. Again, the Court made the change.
87
The Respondents interpose a qualification to the Petitioner’s paragraph 13, noting that the
record citation references section 823b(d), not section 31. The Court agrees that the Respondents’
qualification is correct and amended the statement accordingly.
86
44
and facts involved. 88 16 U.S.C. § 823b(d)(1) (2012). PSMF ¶ 14; DRPSMF ¶ 14.
Regardless of whether a respondent elects the procedures under § 31(d)(2) or under §
31(d)(3), the Commission is required by statute to assess a penalty “by order.” 16
U.S.C. §§ 823b(d)(2)(A) & 823b(d)(3)(A). PSMF ¶ 15; DRPSMF ¶ 15.
When assessing and imposing penalties, the Commission must consider and
apply statutorily-prescribed criteria, namely, “the seriousness of the violation and the
efforts of such person to remedy the violation in a timely manner.” 89 PSMF ¶ 16
(quoting 16 U.S.C. § 825o-1(b)(2012)); DRPSMF ¶ 16. If a civil penalty has not been
paid within 60 calendar days after an order assessing the civil penalty has been made
under § 31(d)(3)(A), “the Commission shall institute an action in the appropriate
district court of the United States for an order affirming the assessment of the civil
penalty. The court shall have authority to review de novo the law and the facts
involved, and shall have jurisdiction to enter a judgment enforcing, modifying, and
enforcing as so modified, or setting aside in whole or in [p]art such assessment.” 90
PSMF ¶ 17 (quoting 16 U.S.C. § 823b(d)(3)(B)); DRPSMF ¶ 17. Pursuant to the FPA,
this Court has authority to “review de novo the law and the facts involved and . . .
The Respondents interpose a qualified response to the Petitioner’s paragraph 14, replacing the
phrase “an alternative process under FPA section 31(d)(3) that affirmatively foregoes the ALJ hearing”
with a more accurate description of the record citation. DRPSMF ¶ 14. The Court finds the language
in Petitioner’s paragraph 14 to be unsupported by its record citation and amended the statement to
include the Respondents’ qualification.
89
The Respondents interpose a qualification to the Petitioner’s paragraph 16, stating that
“[a]lthough the cited statute requires FERC to consider such statutorily-prescribed criteria,
Defendants dispute that FERC actually did so.” DRPSAMF ¶ 16. The Respondents offer no record
support for this contention, and the Court declines to include the qualification.
90
The Respondents offer a qualification to the Petitioner’s paragraph 17, providing the
remainder of the relevant provision. DRPSAMF ¶ 17. The Court declines to include as the Petitioner’s
paragraph 18 includes the remainder of the provision.
88
45
jurisdiction to enter a judgment enforcing, modifying, and enforcing as so modified,
or setting aside in whole or in [p]art, such assessment.” Id. PSMF ¶ 18 (quoting 16
U.S.C. § 823b(d)(3)(B)(2012)); DRPSMF ¶ 18.
3.
Commission Regulations Regarding Investigations
The Commission’s rules relating to investigations are set forth in Part 1b of
the Commission’s regulations.
PSMF ¶ 19; DRPSMF ¶ 19.
Enforcement is
authorized to initiate and conduct investigations relating to any matter subject to the
Commission’s jurisdiction. PSMF ¶ 20 (citing 18 C.F.R. § 1b.3 (2008) & 18 C.F.R. §
375.311 (2008)); DRPSMF ¶ 20.
Section 1b.7 of the Commission’s regulations
provides:
Where it appears that there has been or may be a violation of any of the
provisions of the acts administered by the Commission or the rules,
opinions or orders thereunder, the Commission may institute
administrative proceedings, initiate injunctive proceedings in the
courts, refer matters, where appropriate, to the other governmental
authorities, or take other appropriate action.
PSMF ¶ 21 (quoting 18 C.F.R. § 1b.7 (2012)); DRPSMF ¶ 21. All information and
documents received during an investigation, as well as the existence of an
investigation, are treated by regulation as non-public and confidential, “except to the
extent that (a) the Commission directs or authorizes the public disclosure of the
investigation; (b) the information or documents are made a matter of public record
during the course of an adjudicatory proceeding; or (c) disclosure is required by the
Freedom of Information Act, 5 U.S.C. 552.” PSMF ¶ 22 (quoting 18 C.F.R. § 1b.9
(2008)); DRPSMF ¶ 22.
The Commission’s regulations provide: “There are no parties, as that term is
46
used in adjudicative proceedings, in an investigation under this part and no person
may intervene or participate as a matter of right in any investigation under this part.”
PSMF ¶ 23 (quoting 18 C.F.R. § 1b.11 (2008)); DRPSMF ¶ 23. Section 1b.16 of the
Commission’s regulations addresses the rights of witnesses during an investigation.
Id.
This section provides that a witness or subject of an investigation may be
accompanied, represented, and advised by counsel.
Id.
However, 18 C.F.R.
§1b.16(c)(4) states:
The Investigating Officer shall take all necessary action to regulate the
course of the proceeding to avoid delay and prevent or restrain
obstructionist or contumacious conduct or contemptuous language. Such
officer may report to the Commission any instances where an attorney
or representative has refused to comply with his directions, or has
engaged in obstructionist or contumacious conduct or has used
contemptuous language in the course of the proceeding. The
Commission may thereupon take such further action as the
circumstances may warrant, including suspension or disbarment of
counsel from further appearance or practice before it, in accordance with
§ 385.2101 of this chapter, or exclusion from further participation in the
particular investigation.
18 C.F.R. § 1b.16 also requires the sequestration of witnesses during an investigation.
It further states that “[n]o witness or the counsel accompanying any such witness
shall be permitted to be present during the examination of any other witness called
in such proceeding.” 91 PSMF ¶ 24; DRPSMF ¶ 24.
The Commission’s regulations provide that “[a]ny person may, at any time
during the course of an investigation, submit documents, statements of facts or
The Respondents interpose a qualified response to the Petitioner’s paragraph 24, noting
limitations on the right of a witness to have counsel present set forth in the regulation cited by the
Petitioners. DRPSMF ¶ 24. The Court included the additional language of the regulation to provide
additional detail on FERC’s procedures regarding the right to counsel.
91
47
memoranda of law for the purpose of explaining said person’s position or furnishing
evidence which said person considers relevant regarding the matters under
investigation.” PSMF ¶ 25; DRPSMF ¶ 25. The Commission noted in a May 2008
Policy Statement on Enforcement that the Commission’s regulations allow the
subject of an investigation to submit, in writing, any information or evidence directly
to the Commissioners themselves at any time during the investigation. PSMF ¶ 26;
DRPSMF ¶ 26. Neither the policy statement nor the rule regarding investigations
places a page limit on such submissions nor requires any rules of evidence to apply.
Id.
If Enforcement preliminarily concludes that a subject committed a violation,
Enforcement’s practice pursuant to official Commission policy is to inform the subject
of its preliminary conclusions, including both the relevant facts and legal theories,
explain the evidence on which it relied, and invite the subject to respond. 92 PSMF ¶
27; DRPSMF ¶ 27. If Enforcement determines to recommend to the Commission that
an entity be made the subject of a proceedings governed by part 385 of this chapter,
or that an entity be made a defendant in a civil action to be brought by the
Commission, Enforcement shall, unless extraordinary circumstances make prompt
Commission review necessary in order to prevent detriment to the public interest or
irreparable harm, notify the entity that Enforcement intends to make such a
The Respondents interpose a qualification to the Petitioner’s paragraph 27, highlighting the
following additional language of the Revised Policy Statement on Enforcement, 123 FERC ¶ 61,156 at
P 32 (2008): “If staff reaches the conclusion that a violation occurred that warrants sanctions, staff
shares with the subject of the investigation its views, including both the relevant facts and legal
theories.” DRPSMF ¶ 27. The Court amended the Petitioner’s paragraph 27 to include the language
of the Policy Statement not already paraphrased in the Petitioner’s statement.
92
48
recommendation. 93
PSMF ¶ 28; DRPSMF ¶ 28.
As provided by § 1b.19, an
enforcement subject may submit its own statement to Enforcement, in the form of a
non-public response to the 1b.19 Letter, which “may consist of a statement of fact,
argument, and/or memorandum of law, with such supporting documentation as the
entity chooses.” PSAMF ¶ 29 (quoting 18 C.F.R. § 1b.19 (2011)); DRPSAMF ¶ 29.
Enforcement is required to submit the subject’s statement, if timely made, to the
Commission together with Enforcement’s recommendation. Id. Such statements
from Enforcement subjects have no page limits and are subject to no rules of
evidence. 94 Id.
4.
Commission Regulations Regarding Proceedings
Sections 201 through 218 of Part 385 apply, inter alia, to any “pleading” or
“order to show cause.” 18 C.F.R. § 385.201. PSMF ¶ 30; DRPSMF ¶ 30. Under the
Commission’s regulations, issuance of an Order to Show Cause commences a
contested on-the-record proceeding, known as a “show cause proceeding,” which is
The Petitioner’s paragraph 28 states: “If Enforcement and the subject are unable to reach a
settlement, Enforcement will provide the subject, pursuant to 18 C.F.R. § 1b.19, with a notice (“1b.19
Letter”) of its intent to recommend to the Commission that the Commission initiate contested on-therecord show cause proceedings pursuant to the Commission’s rules for hearings set forth in 18 C.F.R.
§ Part 385.” PSAMF ¶ 28 (citing 18 C.F.R. § 1b.19 (2011)).
The Respondents deny the Petitioner’s paragraph 28, stating that “The referenced citation
merely refers to providing notice if the ‘investigating officer’ intends ‘to recommend to the Commission
that an entity be made the subject of a proceeding governed by part 385 of this chapter,’ which, in turn,
is a regulation governing ex parte communications when an order to show cause has issued. The
referenced citation does not refer to ‘contested on-the-record show cause proceedings.’”
Rather than become enmeshed in the parties’ semantic arguments, the Court quoted the exact
language of 18 C.F.R. § 1b.19 in place of the parties’ disputed paraphrasing.
93
The Respondents interpose a qualified response to the Petitioner’s paragraph 29, arguing that
“[a]lthough Enforcement is required to submit the subject’s statement to the Commission, together
with Enforcement’s recommendation, there is no reference to such submission on FERC’s privilege log
provided in this litigation.” The Respondents’ qualification is not directly responsive to the Petitioner’s
paragraph 28 and the Court declines to include the qualification.
94
49
subject to the Commission’s Rules of Practice and Procedure. 95 PSMF ¶ 31; DRPSMF
¶ 31. The Commission’s regulations provide that the statement of matters set forth
in an order to show cause “is tentative and sets forth issues to be considered by the
Commission.” PSMF ¶ 32 (citing 18 C.F.R. § 385.209(b)(2012)); DRPSMF ¶ 32.
Upon the initiation of a show cause proceeding, the Commission’s Separation
of Functions Rule requires that “no officer, employee, or agent assigned to work upon
The Petitioner’s paragraph 31 reads: “Under the Commission’s regulations, issuance of an
Order to Show Cause and Notice of Proposed Penalty (‘Proposed Penalty Order’) commences a
‘contested on-the-record proceeding,’ known as a ‘show cause proceeding,’ which is subject to the
Commission’s Rules of Practice and Procedure (18 C.F.R. Part 385).” PSAMF ¶ 31.
In support of this paragraph, the Petitioner cites Attorney Anas’ February 28, 2018 sworn
declaration at paragraph 12 and the attached exhibit CCC, which in turn attached 18 C.F.R. §§
385.201-385.218 (2012). Id. The Petitioner says that § 385.209(a)(2) authorizes the Commission to
initiate “a proceeding . . . by issuing an order to show cause.” Id. Citing exhibit DDD, which in turn
attached 18 C.F.R. §§ 385.2201, the Petitioner says the regulations define “any proceeding initiated
by the Commission on its own motion . . . or any proceeding arising from an investigation under part
1b of this chapter beginning from the time the Commission initiates a proceeding governed by part
385 of this chapter” as a “contested on-the-record proceeding.” Id. DRPSAMF ¶ 29. Section
385.2201(c)(1)(i) defines “contested on-the-record” proceeding to mean (with an exception), “any
proceeding before the Commission to which there is a right to intervene and in which an intervenor
disputes any material issue, any proceeding initiated pursuant to rule 206 by the filing of a complaint
with the Commission, any proceeding initiated by the Commission on its own motion or in response to
a filing, or any proceeding arising from an investigation under part 1b of this chapter beginning from
the time the Commission initiates a proceeding governed by part 385 of this chapter.” Anas Decl.
Attach. 56 (18 C.F.R. § 385.2201).
The Respondents interpose a qualification to the Petitioner’s paragraph 31, stating that “[t]he
referenced regulations do not use the phrase ‘show cause proceeding’ or ‘proposed penalty order.’ The
Respondents go on to say that although Part 385 uses the phrase ‘contested on-the-record proceeding,’
that is only contained in the section pertaining to ‘Rules governing off-the-record communications. .
..’” DRPSMF ¶ 31.
95
The Court understands that the Respondents’ qualification is a means to drive home its point
about the alleged inadequacy of the FERC process, but in the context of statements of material fact, it
is hyper-technical at best. Section 385.209(a)(2) states that “[t]he Commission may initiate a
proceeding against a person by issuing an order to show cause.” It would hardly come as a surprise
that such a proceeding would be known as a “show cause proceeding.” Section 385.2201(c)(1)(i)’s
definition of a “contested ‘on-the record’” proceeding expressly includes “any proceeding arising from
an investigation under part 1b of this chapter beginning from the time the Commission initiates a
proceeding governed by part 385 of this chapter.” Nor would it come as a surprise that the
Commission’s order to show cause letter that it issued under part 1b would be known as a proposed
penalty order.
The Court overrules the Respondents’ objections to Petitioner’s paragraph 31.
50
the proceeding or to assist in the trial thereof, in that or any factually related
proceeding, shall participate or advise as to the findings, conclusion or decision,
except as a witness or counsel in public proceedings.” 96 PSMF ¶ 33 (18 C.F.R. §
3985.2202 (2012)); DRPSMF ¶ 33. Upon the initiation of a show cause proceeding,
the Commission’s ex parte rule prohibits any off-the-record communications between
(i) Commissioners and the staff that may advise them (decisional staff) and (ii)
Enforcement prosecutorial staff involved in the investigation or show cause
proceeding. PSMF ¶ 34 (citing 18 C.F.R. § 385.2201(c)(1)(i) (2012)); DRPSMF ¶ 34.
However, the rule does not on its face preclude Enforcement from communicating
with the Commission regarding related matters, which, in this case, included the
settlement negotiations with Rumford concerning its participation in the DALRP,
which is the subject of this action. 97
Id.
Nor does the rule prohibit ex parte
The Respondents interpose a qualified response to the Petitioner’s paragraph 33, noting that
the language “order-to-show-cause proceeding” is not in the regulation cited by the Petitioner.
DRPSMF ¶ 33. The Petitioner states that the cited regulation applies to “any proceeding arising from
an investigation under part 1b of this chapter beginning from the time the Commission initiates a
proceeding governed by part 385 of this chapter.” Id. The Petitioner has also noted that a “show cause
proceeding” is subject to the Commission’s Rules of Practice and Procedure, 18 C.F.R. Part 385.
DRPSMF ¶ 31. The Court overrules the Respondents’ qualified response. See supra note 95.
97
The Respondents interpose the same qualification to the Petitioner’s paragraph 34 as they did
to the Petitioner’s paragraph 33. The Court declines to include the qualification. See supra note 95.
The Respondents further argue that the referenced regulation does not “preclude Enforcement
from continuing to engage in ex parte communications with the Commission concerning any related
matters, which, in this case, included the settlement negotiations with the company that Defendants
advised, Rumford, concerning its participation in the program that is the very subject of this
litigation.” DRPSMF ¶ 34. The Respondents’ position skirts making a legal, not factual argument
about the correct meaning of the regulation. Rather than adopt Respondents’ language, the Court has
stated the undeniable, namely that the regulation does not on its face restrict Enforcement from
communicating the status of such settlement negotiations with the Commission. The regulation does
not address whether Commission practice forbids or allows such communication.
The Respondents also contend that the referenced regulation “does not seem to prohibit ex
parte communications, as long as they are put ‘on the record,’ and it does not prohibit FERC from
making the record ‘non-public.’ Id. (citing Fed. Energy Regulatory Comm'n v. Barclays Bank PLC, 247
F. Supp. 3d 1118, 1137 n.38 (E.D. Cal. 2017)). Despite some misgivings because the issue seems to be
more one of law than fact, the Court included this further qualification because the authority for the
96
51
communications, so long as they are put “on the record,” or prohibit FERC from
making the record “non-public.” Id.
A person who is ordered to show cause is required under the Commission’s
regulations to submit a formal answer. 98
PSMF ¶ 35; DRPSMF ¶ 35.
The
Commission’s regulations require that an answer “[a]dmit or deny, specifically and
in detail, each material allegation” and “[s]et forth every defense relied on” “to the
extent practicable.” 99 PSMF ¶ 36; DRPSMF ¶ 36. The failure to submit an answer
can give rise to a default judgment or summary disposition. PSMF ¶ 37; DRPSMF ¶
37. An answer must also include “documents that support the facts in the answer in
possession of, or otherwise attainable by, the respondent, including, but not limited
to, contracts and affidavits.” PSMF ¶ 38; DRPSMF ¶ 38. Under the Commission’s
Rules of Practice and Procedure, a party to a contested on-the-record proceeding may
file a motion for relief to the Commission at any time during the proceeding. 100 PSMF
¶ 39; DRPSMF ¶ 39.
district court’s conclusion is a regulation and the parties have been presenting the meaning of
regulations through their statements of fact. See Barclays Bank, 247 F. Supp. 3d at 1137 n.38 (citing
18 C.F.R. § 375.205(a)(10)).
98
The Respondents interpose a qualified response to the Petitioner’s paragraph 35, stating that
“the referenced regulation does not refer to a ‘formal’ answer.” DRPSMF ¶ 35. Again, the Respondents’
quibble is hyper-technical. Section 385.209(c) says that “[a] person who is ordered to show cause must
answer in accordance with Rule 213.” A fair reading of Rule 213 is that an answer is a responsive
pleading. See 18 C.F.R. § 385.213(a)(1-4). Like Federal Rule of Civil Procedure 12(a)(1)(A), the
apparent objective of § 385.209(c) is to require the responding party to file a formal response and the
failure to do so, as Respondents later acknowledge, could subject the responding party to default. See
PSMF ¶ 37; DRPSAMF ¶ 37. The Court rejects the Respondents’ qualified response.
99
The Respondents interpose a qualification to the Petitioner’s paragraph 36, noting that the
regulation’s requirements of the Respondents are “to the extent practicable.” DRPSMF ¶ 36. The
Court included the qualification.
100
The Respondents interpose a qualified response to the Petitioner’s paragraph 39, noting that
the referenced regulation “does not refer to a ‘contested-on-the-record proceeding.’” DRPSMF ¶ 39
(citing § 385.201). Section 385.201, however, refers to “any . . . order to show cause.” However, as
noted earlier, the order to show cause may lead to a “contested on-the-record” proceeding. See supra
note 95. The Court rejects the Respondents’ qualified response.
52
5.
Enforcement’s Investigation of Respondents
Following a referral from ISO-NE’s market monitoring unit, in March 2008,
Enforcement commenced a non-public investigation pursuant to Part 1b of the
Commission’s regulations to determine whether certain market participants had
engaged in fraudulent conduct in their participation in ISO-NE’s DALRP. 101 PSMF
¶ 40; DRPSMF ¶ 40. Enforcement notified CES by letter dated August 1, 2009 that
it commenced a non-public investigation of CES pursuant to Part 1b of the
Commission’s regulations concerning CES’s conduct related to the DALRP. PSMF ¶
41; DRPSMF ¶ 41. On February 26 and 27, 2009, Enforcement took investigative
testimony of Dr. Richard Silkman as a witness in the investigation. PSMF ¶ 42;
DRPSMF ¶ 42.
In November 2009, Enforcement commenced an investigation of Dr. Silkman,
individually, pursuant to Part 1b of the Commission’s regulations of Dr. Silkman’s
conduct related to the DALRP, as memorialized in a November 4, 2009 letter sent to
Dr. Silkman’s counsel. 102 PSMF ¶ 43; DRPSMF ¶ 43. After CES and Dr. Silkman
were identified as subjects of the investigation, Enforcement served data requests
The Respondents interpose a qualified response to the Petitioner’s paragraph 40, citing the
Complaint as stating that FERC began its investigation of the Respondents in February 2008.
DRPSMF ¶ 40. The Respondents also state that “the referenced referral did not refer to Defendants.”
Id. The Petitioner’s record citation supports its statement, which references “certain market
participants,” not the Respondents. PRSMF ¶ 40 (citing FERC Test. 67:22-68:9, 77:6-9. The Court
rejects the Respondents’ qualified response.
102
In response to the Petitioner’s paragraph 43, the Respondents offer a qualification, noting that
the Complaint states that FERC began its investigation of the Respondents in February 2008.
DRPSMF ¶ 43. The testimony cited by the Petitioner indicates that FERC first commenced an
investigation of CES, and then later, in November of 2009, “commence[d] an investigation or include[d]
Dr. Silkman in its DALRP investigations.” FERC Test. 158:7-13. The Court, therefore, rejects the
Respondents’ qualified response.
101
53
(the equivalent of interrogatories, requests for admission, and requests for production
of documents) on CES and Dr. Silkman. PSMF ¶ 44; DRPSMF ¶ 44.
On November 23, 2009, Enforcement staff sent CES a Preliminary Findings
Letter explaining Enforcement’s preliminary conclusion that CES had committed
fraud in violation of the Commission’s Anti-Manipulation Rule, 16 U.S.C. § 824v and
18 C.F.R. § 1c.2 (Anti-Manipulation Rule), as well as the factual and legal bases for
this conclusion. 103 PSMF ¶ 45; DRPSMF ¶ 45. On December 1, 2009, Enforcement
staff sent CES copies of the documents cited in the Preliminary Findings Letter to
CES except publicly-available information and information already in the possession
of CES. 104 PSMF ¶ 46; DRPSMF ¶ 46.
On January 8, 2010, CES submitted a response to the Preliminary Findings
Letter to CES. PSMF ¶ 47; DPRSMF ¶ 47. CES was not required to comply with
any page limit nor any rules of evidence in drafting this response. Id. The response
was thirty pages, single-spaced. Id.
The Respondents admit the conclusion of Enforcement but deny the accuracy of the conclusion.
DRPSMF ¶ 45. The Court does not accept Petitioner’s paragraph 45 for its truth, and it overrules the
Respondents’ denial.
104
The Respondents interpose a qualified response to the Petitioner’s paragraph 46:
103
Enforcement staff sent CES copies of the documents bates stamped as CNE0023813,
ISO-NE generated load profiles and five-minute data for Rumford Paper Company; the
document bates stamped as RUM0000926-946; and Rumford Data Responses 35, 36,
36(d), and 36(e). Additionally, Enforcement contacted ACE-Federal Reporters, Inc.
and authorized it to release the transcript of the deposition of Bruce McLeish to CES
upon its request.
PSMF ¶ 46. The exhibit cited by the Petitioners, a letter to Attorney Brann from Nicole Brisker, states
“OE has provided, via electronic mail, the documents referenced in those letters . . .” and lists the
documents provided. The Court omitted the word “all” from the Petitioner’s statement, as that word
is not used in the record citation. The Court finds, however, that it is not necessary to list the
documents provided because sufficient detail is provided in the Petitioner’s paragraph 46.
54
On April 19, 2012, Enforcement staff sent Dr. Silkman a Preliminary Findings
Letter explaining Enforcement’s preliminary conclusion that Dr. Silkman had
committed fraud in violation of the Anti-Manipulation Rule, as well as the factual
and legal bases for this conclusion. 105 PSMF ¶ 48; DRPSMF ¶ 48. At the time
Enforcement staff sent Dr. Silkman the Preliminary Findings Letter, Dr. Silkman’s
counsel possessed all non-public materials cited in the Preliminary Findings Letter,
the same materials as those cited in the Preliminary Findings Letter to CES and
provided to Dr. Silkman’s counsel on December 1, 2009, with the exception of the
testimony transcript of witness Amy Richard; the Richard transcript was provided
eleven days later along with other investigatory documentation.
PSMF ¶ 49;
DRPSMF ¶ 49.
On April 30, 2010, Enforcement staff provided counsel for the Respondents,
Peter Brann, with the testimony transcript of Amy Richard and additional, nonpublic information related to Enforcement’s investigation of the activities of CES and
Dr. Silkman in the DALRP. 106 PSMF ¶ 50; DRPSMF ¶ 50.
On May 20, 2010, Dr.
Silkman submitted a response to the Preliminary Findings Letter to Silkman. PSMF
¶ 51; DRPSMF ¶ 51. Dr. Silkman was not required to comply with any page limit
nor any rules of evidence in drafting this response. Id. The response was thirty-four
The Respondents admit the conclusion of Enforcement but deny the accuracy of the conclusion.
DRPSMF ¶ 48. The Court does not accept paragraph 48 for its truth, and it overrules the denial.
106
The Respondents interpose a qualified response to the Petitioner’s paragraph 50, stating that
Enforcement staff provided “certain non-public materials related to” Enforcement’s investigation of
CES and Dr. Silkman. DRPSMF ¶ 50. The Court agrees that the Petitioner’s assertion that
Enforcement provided “information that Staff believed might assist his understanding of the matter,
as well as documents that may be relevant to CES and Silkman’s defenses” is not supported by the
record. PRSMF ¶ 50. The Court adjusted the statement to reflect the language in the cited record.
105
55
pages, single-spaced. Id.
After Enforcement obtained authority to initiate settlement discussions, the
Commission issued Notices of Alleged Violation to the Respondents on January 25,
2011. PSMF ¶ 52; DRPSMF ¶ 52. The Notices of Alleged Violation were issued
pursuant to Commission practice memorialized in an Order Authorizing Secretary to
Issue Staff’s Preliminary Notice of Violation. 107 Id.
As provided by the Commission’s procedures, Enforcement Staff engaged in
settlement discussions with CES and Dr. Silkman in 2011. PSMF ¶ 53; DRPSMF ¶
53. In February, Enforcement made an oral settlement proposal to CES and Dr.
Silkman at a meeting in Washington D.C. Id. CES and Dr. Silkman requested
additional, previously undisclosed information to evaluate the proposal, but the
request was denied, and they provided a response in April. Id. In May, FERC
rejected the Respondents’ responsive proposal, and asked the Respondents to submit
a revised proposal. Id. The Defendants responded but declined to submit a revised
proposal. 108 Id.
On May 13, 2011, Enforcement staff sent 1b.19 Letters to CES and Dr.
The Respondents put forth a qualification to the Petitioner’s paragraph 52, arguing that
“although the Notices were issued pursuant to the cited Order, the Order announced a change in policy,
it is not accurate to refer to it as memorializing “Commission practice.” DRPSAMF ¶ 52. The Court
finds that the Order Authorizing Secretary to Issue Staff’s Preliminary Notice of Violations did
memorialize Commission practice in announcing a change of policy, and the Court declines to include
the qualification. Anas Decl., Attach 7., Ex. Order Authorizing Secretary to Issue Staff’s Preliminary
Not. of Violations (ECF No. 137-7).
108
Petitioner’s paragraph 53 refers generally to Enforcement engaging in settlement discussions
with CES and Dr. Silkman until May 2011. PSMF ¶ 54.
The Respondents interpose a qualified response to the Petitioner’s paragraph 53, detailing the
settlement negotiations. DRPSMF ¶ 53. The Court amended the Petitioner’s statement to include
these details.
107
56
Silkman. PSMF ¶ 54; DRPSMF ¶ 54.
Enforcement explained in the 1b.19 Letters
that its final conclusions after considering the Respondents’ responses to the
Preliminary Findings Letters were not materially different than its preliminary
conclusions, that it intended to recommend that the Commission issue an Order to
Show Cause why Dr. Silkman “should not be made the subject of a public proceeding
for enforcement of 18 C.F.R. § 1c.2 (2011) and pay a civil penalty,” and that it invited
each Respondent to “submit a non-public response to this notice” by a date specified
therein. 109 Id. On June 27, 2011, CES and Dr. Silkman submitted a joint seventynine-page response to Enforcement’s 1b.19 Letters. CES and Dr. Silkman were not
required to comply with any page limit nor any rules of evidence in drafting this
response. PSMF ¶ 55; DRPSMF ¶ 55.
Having concluded that CES and Dr. Silkman engaged in fraudulent behavior
in violation of the Anti-Manipulation Rule, Enforcement prepared reports and
recommendations (OE Staff Reports) to the Commission recommending that the
Commission initiate proceedings under 18 C.F.R. § 385.209 by issuing Proposed
Penalty Orders to each Respondent. As required by 18 C.F.R § 1b.19, Enforcement
submitted the OE Staff Reports to the Commission along with the Respondents’ joint
seventy-nine-page response to the 1b.19 Letters. 110
PSMF ¶ 56; DRPSMF ¶ 56.
The Respondents interpose a qualification to the Petitioner’s paragraph 54, noting that the
Letters stated that Enforcement would “recommend that the Commission ‘issue an Order to Show
Cause why [CES/Silkman] should not be made the subject of a public proceeding for enforcement of 18
C.F.R. §1c.2(2011) and pay a civil penalty.” DRPSMF ¶ 54. The Court agrees that the 1b.19 Letters
reflect the language the Respondents quoted and amended the Petitioner’s statement accordingly.
110
In response to the Petitioner’s paragraph 56, the Respondents interpose a qualification, noting
that the phrase “adversarial on-the-record proceedings” does not appear in the cited material.
DRPSMF ¶ 56. The Court disagrees. In support of paragraph 56, Petitioner cited 18 C.F.R. § 385.209.
Section 385.209 authorizes the Commission to “initiate a proceeding against a person by issuing an
109
57
6.
Show Cause Proceedings Before the Commission
On July 17, 2012, the Commission initiated adversarial on-the-record
proceedings under 18 C.F.R § 385.209 by issuing Proposed Penalty Orders under
Docket Nos. IN12-12-000 (CES) and IN12-13-000 (Dr. Silkman). 111 PSMF ¶ 57;
DRPSMF ¶ 57. On July 17, 2012, CES and Dr. Silkman were provided copies of
information specifically referenced in the OE Staff Reports attached to the Proposed
Penalty Orders. PSMF ¶ 58; DRPSMF ¶ 58. CES and Dr. Silkman were not provided
with documents already in their possession or publicly available. 112 Id.
In accordance with the Commission’s Separation of Function Rule, 18 C.F.R. §
385.2202, and the Commission’s ex parte rule, 18 C.F.R. § 385.2201, following
issuance of the Proposed Penalty Orders, the Commission issued a notice in each
order to show cause.” In the Court’s view, a proceeding against a person is an adversarial proceeding.
Also, the Court previously discussed its conclusion that the Commission proceeding on an order to
show cause is a contested on-the-record proceeding. See supra fn 95 (citing 385.2201(c)(1)(i)’s
definition of a “contested on-the record proceeding”). If there is a difference between a contested onthe-record proceeding and an adversarial on-the-record proceeding, it is too subtle to be meaningful in
the context of this dispositive motion. The Court overrules the Respondents’ qualified response.
The Respondents also note that “there is no indication on the privilege log that Enforcement
submitted the Defendants’ 79-page response to the 1b.19 Letters to FERC. Id. The record material
cited by the Petitioner, namely the sworn declaration of Attorney Anas, provides a sufficient basis for
the Petitioner’s statement. The Court rejects the second part of the Respondents’ qualification.
111
The Respondents interpose a qualification to the Petitioner’s paragraph 57, stating that
“[n]either the Commission’s Rules of Practice and Procedure nor the referenced orders refer to
“proposed penalty orders.” DRPSMF ¶ 57. The orders are titled “Orders to Show Cause and Notice of
Proposed Penalty Orders.” PSMF ¶ 57 (citing Anas Aff., Attach. 24, Proposed Penalty Order issued to
CES (ECF No. 137-24) (CES Proposed Penalty Order); id., Attach. 25, Proposed Penalty Order Issued
to Silkman, ECF No. 137-45) (Silkman Proposed Penalty Order). The Court declines to include the
Respondents’ qualification. In addition, the Petitioner is using the abbreviation the Respondents
themselves use in DSMF ¶ 5. The Court will not address this qualification again as it is repeated in
several of the Respondents’ responses.
112
The Respondents interpose a qualified response to the Petitioner’s paragraph 58, noting that
the cited letters state that “Enforcement provided Respondents with what it claimed was ‘information
specifically referenced’ in the OE Staff Reports.” DRPSMF ¶ 58 (citing Anas Aff., Attach. 20, Ex. Letter
from Gabriel Sterling to Mr. Brann, July 17, 2012 (ECF No. 137-20); id., Attach. 21, Ex. Letter from
Gabriel Sterling to Mr. Brann, July 17, 2012 (ECF No. 137-21). The Court agrees that the Petitioner’s
statement “all documents cited in the OE Staff Reports” is not supported by the record, and the Court
amended the statement to include the language in the letters referenced.
58
proceeding on July 26, 2012 identifying decisional and non-decisional staff. 113
114
PSMF ¶ 59; DRPSMF ¶ 59. The Proposed Penalty Orders provided a summary of
Enforcement’s allegations against CES and Dr. Silkman and attached the OE Staff
Reports. PSMF ¶ 61; DRPSMF ¶ 61. The OE Staff Reports attached to the Proposed
Penalty Orders alleged that the fraudulent conduct by CES and Dr. Silkman occurred
from July 2007 through early February 2008. 115 PSMF ¶ 62; DRPSMF ¶ 62.
Pursuant to the Commission’s Rules of Practice and Procedure, the Proposed
Penalty Orders directed CES/Dr. Silkman each to file an answer with the
Commission showing cause (i) why it/he should not be found to have violated the AntiManipulation Rule and (ii) why it/he should not be assessed the proposed penalties.
PSMF ¶ 63; DRPSMF ¶ 63. In accordance with the Commission’s Rules of Practice
and Procedure, the Proposed Penalty Orders directed that the answers provide “a
clear and concise statement regarding any disputed factual issues and any law upon
which [it/he] relies. PSMF ¶ 64; DRPSMF ¶ 64. The Commission further ordered
that, “[i]n any answer, Respondent should address any matter, legal, factual or
The Respondents offer a qualified response to the Petitioner’s paragraph 59, stating that the
cited materials do not refer to “proposed penalty orders.” DRPSMF ¶ 59 (citing Anas Aff., Attach. 26,
Ex. Notice of Designation of Commission Staff as Non-Decisional issued in Docket No. IN12-12000,
July 26, 2012 (ECF No. 137-26); id., Attach. 27, Ex. Notice of Designation of Commission Staff as NonDecisional issued in Docket No. IN12-13-000 (Richard Silkman), July 26, 2012 (ECF No. 137-27). The
Court declines to include the qualification. See supra note 111.
114
The Petitioner’s paragraph 60 states, “The Proposed Penalty Orders provided the statutorilyrequired notice of proposed penalties under FPA §§31(d)(1), 16 U.S.C. § 823b(d)(1), and 316A(b), 16
U.S.C.§ 825o-1.” PSMF ¶ 60. The Respondents interpose a qualified response, arguing that “[w]hether
the notices complied with the referenced statutes is a legal and not factual question.” DRPSMF ¶ 60.
The Court agrees with the Respondents and has not included the Petitioner’s paragraph 60 in this
statement of facts.
115
The Respondents admit “that the OE staff reports make those allegations” but “den[y] that the
allegations were correct.” DRPSMF ¶ 62. The Petitioner’s paragraph 61 is clearly framed as an
allegation, not a fact. The Court overrules the denial.
113
59
procedural, that [it/he] would urge in the Commission’s consideration of this matter.”
PSMF ¶ 65; DRPSMF ¶ 65. As required by the Commission’s Rules of Practice and
Procedure, the Proposed Penalty Orders directed that each answer, “to the extent
practicable, admit or deny, specifically and in detail, each material allegation
contained in the OE Staff Report and “set forth every defense relied upon.” 116 PSMF
¶ 66; DRPSMF ¶ 66.
The Proposed Penalty Orders provided notice to the Respondents, as required
by FPA § 31(d)(1), 16 U.S.C. § 823b(d)(1), that they had the option under the FPA to
choose between either (a) an administrative hearing before an ALJ at the Commission
prior to the assessment of a penalty under § 31(d)(2), § 823b(d)(2) or (b), an
assessment by the Commission under § 31(d)(3), § 823b(d)(3) “if the Commission finds
a violation.” 117 PSMF ¶ 67; DRPSMF ¶ 67.
On July 27, 2012, CES and Dr. Silkman filed an unopposed motion for an
enlargement of time seeking an extension under September 14, 2012, to respond to
the Orders to Show Cause, in which each Respondent also elected the procedures of
§ 31(d)(3).” 118 PSMF ¶ 68; DRPSMF ¶ 68. On August 13, 2012, the Commission
The Respondents interpose a qualification to the Petitioner’s paragraph 66, noting that the
Proposed Penalty Orders include the phrase “to the extent practicable.” DRPSMF ¶ 66 (citing CES
Proposed Penalty Order; Silkman Proposed Penalty Order). The Court included the phrase in the
Petitioner’s paragraph 65 to ensure the statement is complete and not misleading.
117
The Respondents interpose a qualified response to the Petitioner’s paragraph 67, reciting a
longer passage from the Proposed Penalty Order. The Court does not find that the Petitioner’s
statement would benefit from the inclusion of such details, as the Respondents have not stated what
they find Petitioner’s paragraph 67 to be misleading or lacking context. The Court declines to include
the qualification.
118
The Petitioner’s paragraph 68 states that the motion for an enlargement of time was filed by
CES and Dr. Silkman “to respond to the allegations in the OE Staff Reports attached to the Proposed
Penalty Orders. . .” PSAMF ¶ 68. The Respondents interpose a qualification, stating that the request
for enlargement of time “was sought to respond to the Orders to Show Cause.” DRPSAMF ¶ 68 (citing
Anas Aff., Attach. 28, Ex. CES and Silkman’s Notice of Extension of Time issued in Docket No. IN12116
60
issued a Notice of Extension of Time in each proceeding, allowing CES and Dr.
Silkman until September 14, 2012, to respond to the allegations in the OE Staff
Reports. PSMF ¶ 69; DRPSMF ¶ 69. On September 14, 2012, CES and Dr. Silkman
filed a joint ninety-eight-page answer, including attachments, in opposition to
Enforcement’s allegations and the proposed penalties, arguing that the evidence
gathered during Enforcement’s investigation did not support a finding that they
committed fraud. PSMF ¶ 70; DRPSMF ¶ 70. This filing was not subject to any page
limit or any rules of evidence. 119 Id.
The CES/Dr. Silkman Answer did not assert a defense based on the statute of
limitations. 120 PSMF ¶ 71; DRPSMF ¶ 71. Neither during the investigation nor
during either show cause proceeding, did CES or Dr. Silkman assert a statute of
limitations defense in a filing submitted to the Commission. PSMF ¶ 72; DRPSMF ¶
72. CES and Dr. Silkman did not file any amended pleading or motion pursuant to
18 C.F.R. § 385.212 at any time during the pendency of the show cause proceedings
12-000 (CES) and IN12-13-000 (Richard Silkman), ECF No. 137-28. Although the Court is unclear
why the difference is significant, the Court agrees that the record citation references an enlargement
of time to respond to the Orders to Show Cause and amended the Petitioner’s statement accordingly.
119
The Respondents interpose a qualification to the Petitioner’s paragraph 70, stating that the
answer, inclusive of attachments, totaled 98 pages. DRPSMF ¶ 70. The Court included the
qualification.
120
The Respondents respond to the Petitioner’s paragraph 71 with a two-part qualification, noting
that the Answer is only required to assert legal defenses “to the extent practicable.” DRPSMF ¶ 71
(citing 18 C.F.R. § 385.213(c)(2)(ii)). As the Court incorporated this qualification into the Petitioner’s
paragraph 66, it declines to repeat it here.
The Respondents also argue that “[t]he statute of limitations had not expired at the time the
Answer was filed. The statute of limitations applies only to “an action, suit, or proceeding for the
enforcement of any civil fine, penalty, or forfeiture, 28 U.S.C.§ 2462, none of which applies to FERC’s
procedures in this matter.” DRPSMF ¶ 71. The Court considers this part of the qualification as not
directly responsive to the Petitioner’s statement and combining legal argument and fact, as evidenced
by the lack of record support put forth by the Respondents. The Court declines to include the second
portion of the Respondents’ qualification to paragraph 71 and declines to include the same
qualification in response to subsequent statements.
61
seeking relief based on the statute of limitations. PSMF ¶ 73; DRPSMF ¶ 73.
On September 21, 2012, pursuant to the Commission’s Rules of Practice and
Procedure, Enforcement litigation staff filed an unopposed motion for extension of
time requesting that it be granted an additional thirty days, until November 13, 2012,
to file its reply to the CES/Dr. Silkman Answer in each proceeding. PSMF ¶ 74;
DRPSMF ¶ 74. On September 26, 2012, the Commission issued a Notice of Extension
of Time in each proceeding allowing Enforcement litigation staff until November 13,
2012 to file its reply in each proceeding. PSMF ¶ 75; DRPSMF ¶ 75. On November
13, 2012, Enforcement litigation staff filed a reply in each proceeding explaining why
Respondents’ evidence and arguments did not rebut Enforcement’s evidence. PSMF
¶ 76; DRPSMF ¶ 76.
On August 29, 2013, the Commission issued separate Orders Assessing Civil
Penalties (Assessment Orders) Against CES and Silkman. PSMF ¶ 77; DRPSMF ¶
77. The Assessment Orders are each more than forty pages in length, and contain
sections setting forth the Commission’s “Findings of Fact,” “Determination of
Violation,” and “Civil Penalty Determination.” PSMF ¶ 78; DRPSMF ¶ 78. The
Assessment Orders set forth the Commission’s evaluation of the legal and factual
defenses raised by CES and Dr. Silkman in the Answer, the allegations in the OE
Staff Reports, and other evidence in the record, such as Dr. Silkman’s investigative
testimony and Dr. Silkman’s data responses. 121 PSMF ¶ 79; DRPSMF ¶ 79.
Among other things, the Assessment Orders show that the Commission found
The Respondents interpose a qualified response to the Petitioner’s paragraph 78, stating “[i]t
is unclear what “record” is intended by this statement. The Court rejects the qualification.
121
62
that Dr. Silkman, as a representative of CES, devised and implemented a scheme to
inflate Rumford paper mill’s baseline during initial baseline measurement for
participation in the DALRP and thereby obtain payment for electricity load
reductions that were not actually provided and were never intended to be provided.
PSMF ¶ 80; DRPSMF ¶ 80. 122 The Assessment Orders reflect the Commission’s
further finding that CES and Dr. Silkman’s scheme constituted a fraudulent scheme
or artifice in violation of the Anti-Manipulation Rule. Id. The Assessment Orders
reflect the Commission’s further finding that CES and Dr. Silkman’s scheme
constituted a fraudulent scheme or artifice in violation of the Anti-Manipulation
Rule.
PSMF ¶ 81; DRPSMF ¶ 81.
The Assessment Orders also reflect the
Commission’s finding that CES and Dr. Silkman acted with scienter. PSMF ¶ 82;
DRPSMF ¶ 82. The Assessment Orders imposed a $7,500,000 civil penalty against
CES and a $1,250,000 civil penalty against Dr. Silkman. Id. The Assessment against
CES also ordered CES to pay disgorgement of $166,841.13, plus interest. PSMF ¶
83; DRPSMF ¶ 83.
In assessing and imposing civil penalties for the violations, the FPA required
the Commission to consider and apply the following statutory criteria: “the
seriousness of the violation and the efforts of such person to remedy the violation in
a timely manner.” PSMF ¶ 84 (quoting 16 U.S.C. § 825o-1(b)); DRPSMF ¶ 84. With
respect to CES, the Assessment Order states that the Commission considered and
The Respondents admit that the Commission found such facts but deny the accuracy of the
statement. The Court overrules the denial and overrules subsequent denials to the extent they are
not based on a record citation.
122
63
applied these statutory criteria and Penalty Guidelines applicable to organizations
that it has adopted to shape its application of the statutorily-prescribed criteria.
PSMF ¶ 85; DRPSMF ¶ 85. With respect to Dr. Silkman, who, as a natural person,
is not subject to the Commission’s Penalty Guidelines, the Assessment Order states
that the Commission considered and applied the statutory criteria, and evaluated five
factors it had previously articulated and applied in assessing penalties against
individuals to shape the statutorily-required criteria: (1) the seriousness of the
offense; (2) commitment to compliance; (3) self-reporting; (4) cooperation; and (5)
reliance on Enforcement staff guidance. PSMF ¶ 86; DRPSMF ¶ 86.
The Commission’s Assessment Orders reflect that the Commission found the
civil penalties to be statutorily authorized under the FPA and appropriate in these
cases. PSMF ¶ 87; DRPSMF ¶ 87. With respect to CES, the Commission concluded,
“[b]ased on the foregoing factors, the pleadings in this case and the OE Staff Report,
the Commission finds that a civil penalty of $7,500,000 and disgorgement of $166,841,
plus interest, is fair and reasonable under the circumstances.” PSMF ¶ 88; DRPSMF
¶ 88. With respect to Dr. Silkman, the Commission concluded, “[b]ased on the
foregoing factors, the pleadings in this case and the OE Staff Report, the Commission
finds that there is a need to deter the fraudulent conduct at issue and that a civil
penalty of $1,250,000 is fair and reasonable under the circumstances.” PSMF ¶ 89;
DRPSMF ¶ 89.
On March 22, 2013, the Commission entered an Order Approving Stipulation
and Consent Agreement, which approved a stipulation and consent agreement
64
between Enforcement and Rumford that resolved Enforcement’s investigation into
whether Rumford engaged in fraudulent conduct in violation of the AntiManipulation Rule in its participation in the DALRP. PSMF ¶ 90; DRPSMF ¶ 90.
The Order reflects that Rumford agreed to a disgorgement of $2,836,419.08 and a
$10,000,000 civil penalty. PSMF ¶ 91; DRPSMF ¶ 91. The Order reflects that
Rumford agreed to satisfy the disgorgement and civil penalty obligations by a
payment of $3,036,419.08, and, given the fact that Rumford was in bankruptcy,
Enforcement agreed that this payment was acceptable satisfaction of Rumford’s
disgorgement and civil penalty obligations.
PSMF ¶ 92; DRPSMF ¶ 92.
The
Commission’s Order directed Rumford to pay an amount of $2,836,419.08 (the
amount of the disgorgement) from the settlement payment to ISO-NE within ten
business days of the effective date of the agreement, and further directed ISO-NE “to
allocate the $2,836,419.08 pro rata to network load [rate payers] during the
applicable period.” 123 PSMF ¶ 93; DRPSMF ¶ 93.
Section 307(n) does not provide any reciprocal right or ability for the subjects
of a Commission investigation to “subpoena witnesses, compel their attendance, take
evidence, and require the production of any books, papers, correspondence,
memoranda, contracts, agreements, or other records.” DSAMF ¶ 1 (quoting 16 U.S.C.
§ 825(b)); PRDSAMF ¶ 1. However, under the Commission’s Rules of Practice and
Procedure, a party to a show cause proceeding may file a motion for relief with the
The Respondents interpose the following qualification to the Petitioner’s paragraph 93: “[t]he
effective date of the Agreement was subject to, inter alia, approval of the Agreement and authorization
of the Bankruptcy Court.” DRPSMF ¶ 93. The Court finds the qualification non-responsive to the
Petitioner’s statement and declines to include it.
123
65
Commission at any time during the proceeding.” 124 DSAMF ¶ 1; PRDSAMF ¶ 1.
Section 1b.16, concerning the rights of witnesses, does not prohibit witnesses or
counsel from speaking with other persons or counsel outside the examination, but
requires the sequestration of witnesses during testimony taken in an investigation.
DSAMF ¶ 2; PRDSAMF ¶ 2.
Other Commission regulations provide that all
information and documents received during an investigation and the existence of the
investigation are treated as confidential, non-public information. Id. Disclosure of
information during an investigation is permitted only at the Commission’s direction
or authorization, or as is otherwise required to be disclosed. 125 Id.
Following his deposition, Dr. Silkman was instructed by FERC Enforcement
not to communicate with his business partner, Mark Isaacson, with Rumford
personnel, or anyone else regarding the questions or answers from his deposition nor
to share a copy of his deposition transcript. DSAMF ¶ 3; PRDSAMF ¶ 3. Enforcement
staff informed Dr. Silkman that if he felt the need to share information regarding the
contents of the deposition to anyone else, he should contact Enforcement staff and
The Petitioner admits the contents of DSAMF ¶ 1, but “otherwise denies” the statement
“because respondents to an order-to-show-cause proceeding who were the subjects of an enforcement
investigation have the ability to request discovery via motion under the . . . FPA.” Even though
Petitioner’s denial would be properly framed as a qualification, the Court has interpreted the denial
as a qualification, and incorporated its contents into the Respondents’ additional material fact
paragraph 1.
125
Respondents’ additional statement of material fact paragraph 2 stated: “Section 1b16,
concerning the ‘Rights of witnesses,’ does not prohibit witnesses or counsel from speaking with other
persons or counsel outside the examination.” DSAMF ¶ 2.
The Petitioner interposes a qualification, noting additional regulations regarding
sequestration of witnesses and confidentiality of information and documents during an investigation.
PRDSAMF ¶ 2. The Court included the qualification to provide additional context to the Respondents’
statement and to make sure the paragraph is complete and not misleading.
124
66
they would discuss it. 126 Id.
FERC Enforcement also instructed other deponents in the investigation not to
share copies of their deposition transcripts with the Respondents or their counsel. 127
DSAMF ¶ 4; PRDSAMF ¶ 4. Under the Commission’s regulations, Respondents were
not entitled to attend the taking of testimony from third party witnesses when
Enforcement was engaged in investigative fact-finding or to receive copies of their
testimony. Id. The Commission’s regulations require the sequestration of witnesses
during testimony taken in an investigation, and all information and documents
received during an investigation, as well as the existence of an investigation, is
treated as confidential, non-public information. Id. Disclosure of information during
an investigation is permitted only at the Commission’s direction or authorization, or
as is otherwise required to be disclosed. Id. Deponents and their counsel in the
investigation were instructed regarding the testimony of witnesses in accordance
with the requirements of §§ 1b.12 and 1b.16 of the Commission’s regulations,
requiring sequestration of witnesses during testimony, and in accordance with the
Commission’s regulations regarding confidentiality of investigations. Id.
Respondents’ additional statement of material fact paragraph 3 is reflected verbatim in the
preceding sentence.
In response, the Petitioner interposes a qualified response, stating the Commission’s
regulations regarding sequestration of witnesses. DSAMF ¶ 3. The Court declines to include this
portion of the qualification as it has already included similar facts regarding regulations in DSAMF
paragraph 2. However, the Petitioners also put forth the qualification that if Dr. Silkman felt the need
to share the deposition with anyone else, he should contact Enforcement staff for discussion.
PRDSAMF ¶ 3. The Court included this qualification to ensure the Respondents’ additional material
fact paragraph 3 is complete and not misleading.
127
The Petitioner interposes a qualified response to the Respondents’ additional material fact
paragraph 4, setting forth the regulations and Commission practice behind the Respondents’
statement. PRDSAMF ¶ 4. The Court included these Commission regulations and practices regarding
other deponents to be complete and to avoid being misleading.
126
67
Although the Commission’s Revised Policy Statement on Enforcement allows
written submissions, the Commission’s Revised Policy Statement on Enforcement
prohibits any oral communications to the Commissioners or their assistants from any
person concerning an ongoing staff investigation as to which such person is the
subject. 128 DSAMF ¶ 5; PRDSAMF ¶ 5. The Commission’s Revised Policy Statement
on Enforcement does not prohibit oral communications to the Commissioners or their
assistants from a staff member concerning an ongoing staff investigation. DSAMF ¶
6; PRDSAMF ¶ 6. The Commission’s Statement of Administrative Policy Regarding
the Process for Assessing Civil Penalties does not require a hearing or discovery for
entities that choose Option 2 under 16 U.S.C. § 823b(d)(3)(A), but rather only the
“immediate assessment” of the civil penalty.” DSMAF ¶ 7; PRDSAMF ¶ 7. Although
the 2006 Policy Statement does not require discovery, respondents to a show cause
proceeding have the ability to request discovery via motion under the procedural rules
promulgated by the Commission pursuant to its express delegation of authority by
Congress under the FPA. 129 Id.
The Petitioner interposes a qualification to the Respondents’ additional material fact
paragraph 5, reciting the entire paragraph of the Commission’s Revised Policy Statement on
Enforcement cited by the Respondents. PRDSAMF ¶ 5. The Court declines to place in the statement
of material facts the entire statement, but it has summarized the fact that the Revised Policy
Statement allows for written communication in order to be complete and not misleading.
129
The Petitioner sets forth the following qualification to the Respondents’ statement of
additional material fact paragraph 7:
128
The FPA and the Commission’s regulations promulgated pursuant to its
statutory authority under the FPA set forth the statutory requirements and
procedures for assessing civil penalties by order. See, e.g., SUMF (ECF No. 135) ¶¶ 710, 12-17, 30-39. The Commission’s Statement of Administrative Policy Regarding the
Process for Assessing Civil Penalties, 117 FERC ¶ 61,317 (2006) (hereinafter, “2006
Policy Statement”) does not, itself, require anything, and does not supersede any
statutory requirements; rather, the Statement “outlines the basic procedures to be
followed” while “retain[ing] the right to modify these procedures to fit the
68
circumstances presented by specific cases, while still providing process that meets the
applicable statutory criteria.” See Statement of Administrative Policy Regarding the
Process for Assessing Civil Penalties, 117 FERC ¶ 61,317 at P 2 (2006). Even though
the 2006 Policy Statement refers to an “immediate penalty assessment” by the
Commission, the FPA does not use such language and requires that the Commission
“promptly” assess such penalty “by order” after “notice and opportunity for public
hearing, in accordance with the same provisions as are applicable under section
823b(d)” after taking into consideration mandatory statutory factors, namely, “the
seriousness of the violation and the efforts of such person to remedy the violation in a
timely manner.” See SUMF (ECF No. 135) ¶¶ 13-16; D. Anas Decl. (ECF No. 137) ¶ 11,
Exs. WW (16 U.S.C. § 825o-1(b) (2012)) & XX (16 U.S.C. § 823b(d) (2012)). Moreover,
the 2006 Policy Statement articulates that an “immediate penalty assessment by the
Commission” (as opposed to an Initial Decision by an ALJ that will then be considered
by the Commission together with any exceptions filed) involves a procedure by which
the Commission will first determine whether a violation or violations occurred and
then issue an order setting forth its factual findings and assessment of any penalty
determined to be appropriate. See Statement of Administrative Policy Regarding the
Process for Assessing Civil Penalties, 117 FERC ¶ 61,317 at P 5 at 1.b.i (2006)
(“Immediate Penalty Assessment. If the Commission finds a violation, the Commission
will issue an order setting forth the material facts that constitute the violations and
assess any appropriate penalty.”) (bold text in original). Further, although the 2006
Policy Statement does not “require” a hearing, the 2006 Policy Statement notes the
Commission’s use of paper hearings in various circumstances, including the procedure
by which civil penalties are to be assessed under the Natural Gas Act which “draws on
existing processes for the FPA and [Natural Gas Policy Act of 1978] for the
administrative process the Commission generally will follow in assessing civil
penalties under the NGA.” See Statement of Administrative Policy Regarding the
Process for Assessing Civil Penalties, 117 FERC ¶ 61,317 at PP 6-7 (2006). Finally,
although the 2006 Policy Statement does not “require” discovery, respondents to a
show cause proceeding have the ability to request discovery via motion under the
procedural rules promulgated by the Commission pursuant to its express delegation of
authority by Congress under the FPA. 12 Under the Commission’s Rules of Practice
and Procedure codified at 18 C.F.R. Part 385, which apply to show cause proceedings
(see SUMF (ECF No. 135) ¶¶ 11, 30-31; D. Anas Decl. (ECF No. 137) ¶ 12, Ex. CCC
(18 C.F.R. § 385.201 (2012) (Applicability); id. (18 C.F.R. § 385.209(a)(2) (2012)
(authorizing the Commission to initiate “a proceeding . . . by issuing an order to show
cause”)), a party to a show cause proceeding may file a motion for relief with the
Commission at any time during the proceeding. See SUMF (ECF No. 135) ¶ 39; D.
Anas Decl. (ECF No. 137) ¶ 12, Ex. CCC (18 C.F.R. § 385.212 (2012)). The
Commission’s regulations regarding discovery, moreover, expressly state that the
provisions apply “to discovery in proceedings set for hearing under subpart E of this
part [i.e., ALJ hearing], and to such other proceedings as the Commission may order.”
See D. Anas Opp. Decl. (ECF No. 142) ¶ 11, Ex. CC (18 C.F.R. § 385.401 (2012)
(Applicability) (emphasis added)).
PRDSAMF ¶ 7. The Court finds that, in large part, the Petitioner’s qualification adds unnecessary
detail to the Respondents’ statement. However, the Court does find that the statement “although the
2006 Policy Statement does not ‘require’ discovery, respondents to the show cause proceeding have the
ability to request discovery via motion under the procedural rules . . .” should be included as it ensures
the Respondents’ statement is not misleading. The Court declines to incorporate the remainder of the
qualification.
69
III.
POSITIONS OF THE PARTIES
A.
The Respondents’ Motion for Summary Judgment
1.
The Respondents’ Motion
The Respondents contend that the statute of limitations that governs this suit,
28 U.S.C. § 2462, prohibits government action concerning alleged wrongdoing that
occurred more than five years before the government filed suit. Resp’ts’ Mot. at 1-2.
According to the Respondents, “[b]ecause FERC filed suit in federal court more than
five years after the alleged wrongdoing ended,” the instant action is time-barred. Id.
In support, the Respondents rely on Gabelli v. SEC, 568 U.S. 442 (2013) and Kokesh
v. SEC, 137 S. Ct. 1635 (2017). They further argue that FERC is incorrect in its
argument that the First Circuit Court of Appeals decision in United States v. Meyer,
808 F.2d 912 (1st Cir. 1987), controls here, because the Respondents did not receive
an “adjudicatory administrative proceeding” in light of the lack of due process that
FERC afforded them, which the Respondents describe in detail. Resp’ts’ Mot. at 2-7.
To the extent this argument relies on facts, the Respondents submitted those facts in
their accompanying Statement of Material Facts. (ECF No. 136).
According
to
the
Respondents,
because
Congress
did
not
delegate
administrative authority to a specific agent to administer the general federal statute
of limitations, 28 U.S.C. § 2462, the Court owes no Chevron 130 deference to FERC,
and the Supreme Court’s interpretation of the statute controls. Id. at 8. As such, in
Chevron, U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 844 (1984) (“We
have long recognized that considerable weight should be accorded to an executive department’s
construction of a statutory scheme it is entrusted to administer, and the principle of deference to
administrative interpretations”).
130
70
the Respondents’ view, the Supreme Court’s decision that the statute of limitations
in § 2462 began to run when the alleged fraud was committed, not when it was
discovered by the SEC, controls here. Similarly, the Respondents contend that the
Supreme Court ruled in Kokesh that the SEC “could only seek disgorgement under
Section 2462 for alleged fraud that occurred within five years of the date the claim
accrued.” Id. (citing Kokesh, 137 S. Ct. at 1635). The Respondents note that the
Supreme Court’s rulings in Gabelli and Kokesh are particularly applicable to the case
at bar because “FERC’s market manipulation statute and . . . anti-manipulation rule
were specifically patterned on Section 10(b) of the Securities Exchange Act, 15 U.S.C.
§ 78j(b), and SEC’s Rule 10b–5, 17 C.F.R. § 240.10b–5.” Id. at 9.
The Respondents argue that Gabelli and Kokesh overruled Meyer, which the
Respondents’ characterize as holding that “the government had five years under
Section 2462 to commence an ‘adjudicative administrative proceeding’ . . . and then
after that proceeding ended, the government had another five years under Section
2462 to file suit in federal court to enforce the judgment awarded in the proceeding.”
Id. at 9-10. The Respondents ask that the Court “agree with the Barclays court and
conclude that Meyer is no longer good law in light of Gabelli.” Id. (citing FERC v.
Barclays Bank PLC, 105 F. Supp. 3d 1121, 1131 (E.D. Cal. 2015) (Barclays I)).
The Respondents further contend that even if Meyer has not been overruled,
Meyer does not apply to this case because the “Defendants did not receive any of the
hallmarks of an adjudicatory administrative proceeding, and FERC’s long wind-up
should be considered as nothing more than a decision to bring suit against
71
Defendants.” Id. at 10-11. The Respondents distinguish Meyer, noting that unlike in
the instant case, the defendant in Meyer was afforded the protections of the
Administrative Procedure Act, and the charges were heard by an administrative law
judge, who issued a decision subject to appeal. Id. (citing Meyer, 808 F.2d at 913,
919).
The Respondents argue that “courts have repeatedly held” that defendants
who select Option 2 under 16 U.S.C. 823b(d)(3) “do not receive any meaningful
process from FERC.” Id. at 12-13 (citing Powhatan, 2017 WL 6629093, at *12; FERC
v. Barclays Bank PLC, 247 F. Supp. 3d 1118, 1121 n.7, 1129 (E.D. Cal. 2017)
(Barclays II).
According to the Respondents, several facts demonstrate the inadequate due
process provided by FERC.
First, what is characterized by FERC as the
“administrative record” did not contain the entire investigative file, but it did contain
documents that had not been disclosed previously to the Respondents. Id. at 14.
Second, the Respondents contend that FERC Enforcement engaged in ex parte
communications concerning the Respondents with FERC Commissioners and their
staff.
Id.
Third, the Respondents claim that “it does not appear that FERC
Enforcement even read Defendants’ response to its allegations.” Id. at 15.
The Respondents also allege that no additional factfinding must occur once a
party elects to proceed under FERC’s Option 2, and that the decision to charge a party
with a proposed penalty is conducted without a neutral arbiter. Id. at 16. The
Respondents claim that they “did not receive any additional process after FERC
issued the Orders to Show Cause.” Id. at 17. According to the Respondents, “. . . once
72
a party elects Option 2, there is no requirement for FERC to conduct any proceeding,
only for FERC to “promptly assess such penalty.” Id. (citing § 823b(3)(A)).
The
Respondents contend that they were not afforded “an adversarial adjudication before
a neutral decision-maker”, which they state is “the very hallmark of our system of
prosecution of criminal and civil offenses.” Id. at 17-18 (citing FERC v. Barclays Bank
PLC, No. 2:13-CV-02093-TLN-DB, 2017 WL 4340258 at *11, 2017 U.S. Dist. LEXIS
161414, at *33 (E.D. Cal. Sept. 29, 2017) (Barclays III)). The Respondents conclude
that the process provided by FERC amounted to a prosecutorial determination, not a
proceeding. Id. at 19.
2.
FERC’s Opposition
FERC responds and asks the Court to deny the Respondents’ motion, arguing
that under the First Circuit’s decision in Meyer, which controls, “the dispositive factor
for determining whether an administrative assessment proceeding meets the
requirements of 18 U.S.C. § 2462 is whether ‘assessment of administrative penalty is
a statutory prerequisite to the bringing of an action judicially to enforce such
penalty.’” Pl.’s Opp’n at 1 (citing Meyer, 808 F.2d at 922). According to FERC, it
could only bring an action in district court seeking an order affirming the assessment
of the civil penalty against the Respondents when they failed to pay; therefore, the
case “falls squarely within Meyer and the requirements of § 2462.” Id. Finally, FERC
argues that the Commission’s adjudication constituted a proceeding that met the first
statute of limitations under Meyer. Id.
FERC avers that Meyer “was not silently overruled” as the Respondents state,
73
by Gabelli and Kokesh, and that Meyer remains “longstanding precedent in the First
Circuit that represents the view of a majority of courts; only the Fifth Circuit has
adopted a different approach.” Id. at 3-4 (citing SEC v. Mohn, 465 F.3d 647 (6th Cir.
2006); United States v. Godbout-Bandal, 232 F.3d 637 (8th Cir. 2000); 3M Co. v.
Browner, 17 F.3d 1453 (D.C. Cir. 1994); U. S. Dep’t of Labor v. Old Ben Coal Co., 676
F.2d 259 (7th Cir. 1982); United States v. Worldwide Indus. Enters., Inc., 220 F. Supp.
3d 335, 340 (E.D.N.Y. 2016)); United States v. Sacks, Case No. C10- 534RAJ, 2011
WL 6883740 (W.D. Wash. Dec. 28, 2011); United States v. Great Am. Veal, Inc., 998
F. Supp. 416 (D.N.J. 1998); Atl. States Legal Found. v. Al Tech Specialty Steel Corp.,
635 F. Supp. 284 (N.D.N.Y. 1986); In re Donohoo, 243 B.R. 139 (Bankr. M.D. Fla.
1999). FERC agrees that in Gabelli, the Supreme Court held that “the statute of
limitations in Section 2462 began to run when the alleged fraud was committed, not
when the Securities and Exchange Commission (SEC) discovered the fraud.” Id. at 4
(citing Resp’t’s Mot. at 8-9). But FERC distinguishes Gabelli from Meyer because
Gabelli “does not consider a statute requiring an agency to assess a penalty through
an administrative process as a prerequisite to filing in district court . . . and fails to
address Meyer at all.” Id. at 4. FERC also notes that “Judge Woodlock considered
and squarely rejected their reliance on Gabelli . . . [because] the fraud discovery rule
does not extend to SEC actions for civil penalties.” Id. (citing Silkman I, 177 F. Supp.
3d at 699 (citing Gabelli, 568 U.S. 442 at 1219)).
FERC similarly rejects the
contention that Kokesh supports the Respondents’ position, arguing that “[b]ecause
there were no prior administrative proceedings at issue in Kokesh, the Court had no
74
occasion to address the issue presented here and in Meyer regarding the applicability
of the statute of limitations where an administrative proceeding is a condition
precedent to filing suit in district court.” Id. (citing Kokesh, 137 S. Ct. at 1635).
FERC disputes the Respondents’ argument that “the details of a particular
adversarial agency proceeding” is “the key factor under Meyer and its progeny . . .”
Id. at 7-8, instead contending that “ it is beyond dispute under the plain language of
§ 2462, FPA § 31(d), and the weight of case law, that the process leading to the
assessment of such an order is a ‘proceeding’ under Meyer.” Id. at 8. FERC cites
Worldwide Industrial Enterprises, Incorporated, 220 F. Supp. 3d 335, 344 (E.D.N.Y.
2016) as “rejecting [the] claim that the nature of the administrative proceeding
determines if § 2462 has been met” under Meyer. Id. at 9.
FERC maintains that, under the Administrative Procedure Act — which
defines “‘adjudication’ as ‘agency process for the formulation of an order” — the show
cause proceeding “was an agency adjudication and not a mere decision to prosecute,”
and does not violate due process principles, as the Respondents contend. Id. at 11-12
(citing 5 U.S.C. §§ 551(12); 551(7)).
According to FERC, “[u]nder enduring
administrative law principles, agency processes ending in an ‘order’ are both
‘adjudications’ and ‘proceedings.’”
Id.
Moreover, FERC contends that the
“Respondents do not cite any case law in support of the proposition that these
arguments are relevant to the statute of limitations issue.” Id. at 12 (citing Resp’ts’
Mot. at 13-15).
With respect to the contention that FERC did not provide due process, FERC
75
states that the Respondents were provided notice and an opportunity to be heard, as
required by the FPA and its regulations. Id. at 12-14. FERC further avers that “due
process does not require that Respondents receive a live hearing” and notes that the
“Respondents would have received a live hearing before an ALJ had they allowed the
show cause proceeding to proceed on the default path; they, however, affirmatively
chose to waive that hearing in favor of a penalty assessment by the Commission.” Id.
at 14.
Finally, FERC argues that the Court should not follow FERC v. Barclays Bank
PLC because:
Barclays was not governed by Meyer, is inconsistent with the weight of
case law, misstates the nature of the Commission’s penalty assessment
proceedings, does not mention respondents’ right to challenge
Enforcement staff’s allegations during such proceedings, misconstrues
the cases on which it relies, denies the Commissioner’s role as neutral
decision-makers, and was based on an incomplete record.”
Id. at 15-16 (citing Barclays III).
3.
Respondents’ Reply
In reply, the Respondents argue that FERC’s reliance on Meyer is “misplaced”,
reiterating its position that Meyer was founded in the fact that the defendant in that
case received an adjudicatory administrative proceeding.
Resp’ts’ Reply at 1. The
Respondents also highlight that “the Meyer court distinguished the prosecutorial
determinations made by the FTC and CPSC, which were subject to the five-year
limitation of 28 U.S.C. § 2462.” Id. at 2. The Respondents also dispute FERC’s
contention that the SEC proceedings in Gabelli differ from the procedures in this
case. Id.
76
B.
FERC’s Motion for Partial Summary Judgment
1.
FERC’s Motion
FERC filed a separate motion for partial summary judgment on the statute of
limitations issue. Although in different form, FERC advances several of the same
arguments it did in response to the Respondents’ motion for summary judgment. See
Pl.’s Mot at 1-3; Resp’ts’ Mot. In addition, FERC asks that its summary judgment be
granted on two bases. FERC first contends that because the portion of the penalty
assessed against the Respondents is based on disgorgement under its remedial
authority, it is not subject to the statute of limitations under § 2462. Pl.’s Mot. at 1718, n.90. Second, it argues that if the Court accepts the Respondents’ position on the
statute of limitations, “then Respondents waived this defense by not raising it during
the Commission’s adjudication.”
Id. at 2-3.
According to FERC, “Respondents’
statute of limitations defense . . . ripened . . . during the Commission’s show cause
proceeding, but Respondents failed to raise it at that time as they were required to
by (a) the Commission’s regulations, (b) the Proposed Penalty Orders, and (c) case
law.” Id. at 19-20. FERC further contends that “statutes of limitations, when sought
to be applied against the government, are to be strictly construed in favor of the
government.” Id. at 10 (citing Badaracco v. Comm’r of Internal Revenue, 464 U.S.
386, 391 (1984); U.S. v. Commonwealth Energy Sys. and Subsidiary Cos., 235 F.3d
11, 13-14 (1st Cir. 2000)).
2.
Respondents’ Opposition
The Respondents oppose FERC’s motion.
77
Resp’ts’ Opp’n at 1.
First, the
Respondents disagree with the Petitioner’s contention that the statute of limitations
does not apply in disgorgement actions. Id. They reiterate the arguments set forth
in their motion for summary judgment, as well as the supporting case law. See
Resp’ts’ Mot. The Respondents contend that “none of the cited regulations purported
to provide Defendants with adjudicatory, show cause, administrative, contested, onthe-record, or adversarial proceedings. . .. Calling something an adjudicatory, show
cause administrative, contested, on-the-record, or adversarial proceeding does not
make it so.” Id. at 13-14. Finally, the Respondents argue that the Court does not
have jurisdiction to order disgorgement, because FERC cites only dicta in support of
their position. Id. at 16. Additionally, according to the Respondents, “FERC does not
cite any authority that this Court has subject matter jurisdiction to order
disgorgement. In its petition, FERC does not cite 16 U.S.C. § 823h at all, and only
claims subject matter jurisdiction under 16 U.S.C. § 823b(d)(3)(B),” which does not
reference disgorgement. Id. (citing FERC Pet. ¶ 16).
3.
FERC’s Reply
FERC filed a reply to the Respondents’ opposition, reiterating its previous
argument that Meyer controls, and refuting the Respondents’ claim that its
administrative action violated due process. See generally Pl’s Reply at 1-7.
IV.
LEGAL STANDARD
Summary judgment is appropriate “if the movant shows that there is no
genuine dispute as to any material fact and the movant is entitled to judgment as a
matter of law.” FED. R. CIV. P. 56(a). A fact is “material” if it “has the potential to
78
change the outcome of the suit.” Tropigas de Puerto Rico, Inc. v. Certain Underwriters
at Lloyd’s of London, 637 F.3d 53, 56 (1st Cir. 2011) (quoting Borges ex rel. S.M.B.W.
v. Serrano-Isern, 605 F.3d 1, 5 (1st Cir. 2010)). A dispute is “genuine” if “a reasonable
jury could resolve the point in favor of the nonmoving party.” Id. (quoting McCarthy
v. Nw. Airlines, Inc., 56 F.3d 313, 315 (1st Cir. 1995)).
Once this evidence is supplied by the moving party, the nonmovant must
“produce ‘specific facts, in suitable evidentiary form, to . . . establish the presence of
a trialworthy issue.’” Triangle Trading Co., Inc. v. Robroy Indus., Inc., 200 F.3d 1, 2
(1st Cir. 1999) (quoting Morris v. Gov’t Dev. Bank of P.R., 27 F.3d 746, 748 (1st Cir.
1994)).
In other words, the nonmoving party must “present ‘enough competent
evidence’ to enable a factfinder to decide in its favor on the disputed claims.” Carroll
v. Xerox Corp., 294 F.3d 231, 237 (1st Cir. 2002) (quoting Goldman v. First Nat’l Bank
of Bos., 985 F.2d 1113, 1116 (1st Cir. 1993)). The Court then “views the facts and
draws all reasonable inferences in favor of the nonmoving party.”
Ophthalmic
Surgeons, Ltd. v. Paychex, Inc., 632 F.3d 31, 35 (1st Cir. 2011). However, the Court
“afford[s] no evidentiary weight to ‘conclusory allegations, empty rhetoric,
unsupported speculation, or evidence which, in the aggregate, is less than
significantly probative.’” Tropigas, 637 F.3d at 56 (quoting Rogan v. City of Boston,
267 F.3d 24, 27 (1st Cir. 2001)); accord Sutliffe v. Epping Sch. Dist., 584 F.3d 314,
325 (1st Cir. 2009).
Where, as here, the parties have filed cross-motions for summary judgment,
the court must evaluate each motion independently and “determine whether either
79
of the parties deserves judgment as a matter of law on facts that are not disputed.”
Matusevich v. Middlesex Mut. Assurance Co., 782 F.3d 56, 59 (1st Cir. 2015) (citing
Barnes v. Fleet Nat'l Bank, N.A., 370 F.3d 164, 170 (1st Cir. 2004)). As such, for crossmotions for summary judgment, the standard of review is applied to each motion
separately. Gardner, 759 F. Supp. 2d at 221. The presence of cross-motions for
summary judgment “neither dilutes nor distorts” the summary judgment standard.
Mandel v. Bos. Phoenix, Inc., 456 F.3d 198, 205 (1st Cir. 2006).
V.
DISCUSSION
There are two threshold issues. First, FERC asserts that the Respondents
waived their statute of limitations defense, contending that the Respondents should
have raised this defense by February 2013, six months before the Commission issued
its August 29, 2013 Assessment Orders. Pl.’s Mot. at 19-20; Pl.’s Reply at 6. Judge
Woodlock squarely addressed this issue in his April 11, 2016 order on the motion to
dismiss. Silkman I, 177 F. Supp. 3d at 697. Judge Woodlock wrote:
FERC’s theory produces an absurd result; it would require that a statute
of limitations defense be raised before it had ripened. Fortunately,
FERC’s procedural rules avoid such an absurdity by requiring only that
a Respondent set forth the defenses relied upon “to the extent
practicable.” 18 C.F.R. § 385.213(c)(2). Requiring a Respondent to
anticipate and raise defenses that might only have merit at some future
date and which are dependent upon various contingencies — some of
which are controlled by the agency itself — is not “practicable.”
Respondents were not required to raise their statute of limitations
defense during the administrative proceeding, in advance of the
expiration of the statute of limitations, in order to now raise the issue.
Id. The Court agrees with Judge Woodlock and concludes that the Respondents did
not waive their statute of limitations defense by failing to raise it during the FERC
80
proceeding.
Second, in response to FERC’s contention that the portion of the penalty
assessed against the Respondents based on disgorgement falls under its remedial
authority, and therefore is not subject to the statute of limitations under § 2462, Pl.’s
Mot. at 17-18, n.90, the Respondents contend that “FERC does not cite any authority
that this Court has subject matter jurisdiction to order disgorgement.” Resp’ts’ Mot.
at 16. The Supreme Court in Kokesh held that “SEC disgorgement constitutes a
penalty within the meaning of § 2462,” based on the fact that “SEC disgorgement is
imposed by the courts as a consequence for violating public laws” and “for punitive
purposes” and is “often not compensatory.” 137 S. Ct. 1635, 1643 (2017). The Court
concludes that the Kokesh holding with regard to SEC penalties applies with equal
force to FERC penalties. As such, the entire penalties assessed by FERC, including
disgorgement, are subject to the statute of limitations under § 2462.
The myriad factual and legal disputes among the parties boil down to one issue:
whether the five-year statute of limitations for the enforcement of civil penalties, 28
U.S.C. § 2462, as applied to the civil penalties FERC assessed against the
Respondents, accrued at the time the Respondents committed the alleged violation or
at the time FERC assessed the penalty. This issue hinges upon whether the First
Circuit’s decision in Meyer is superseded or, in the alternative, distinguishable, as the
Respondents contend.
A.
Preliminary Discussion
1.
Statutory Language of 16 U.S.C. § 823b(d)
81
FERC is authorized to assess civil penalties for violations of the FPA “after
notice and an opportunity for public hearing.” 16 U.S.C. § 823b(c). Before FERC may
issue “an order assessing a civil penalty against any person,” the FPA requires the
Commission to “inform such person of his opportunity to elect” one of two procedural
paths. Id. § 823b(d)(1). The default option (Option 1) is set forth in § 823b(d)(2).
Under Option 1, an adjudication is required before FERC assesses a penalty:
[The Commission] shall assess the penalty, by order, after a
determination of violation has been made on the record after an
opportunity for an agency hearing ... before an administrative law judge
. . .. Such assessment order shall include the administrative law judge's
findings and the basis for such assessment. Any person against whom a
penalty is assessed under this paragraph may ... institute an action in
the United States court of appeals for the appropriate judicial circuit for
judicial review of such order . . .. The court shall have jurisdiction to
enter a judgment affirming, modifying, or setting aside in whole or in
[p]art, the order of [the Commission], or the court may remand the
proceeding to [the Commission] for such further action as the court may
direct.
Id. § 823b(d)(2)(A)–(B).
Here, the Respondents chose to proceed under § 823b(d)(3) (Option 2). Under
Option 2:
[The Commission] shall promptly assess such penalty, by order[.] . . . If
the civil penalty has not been paid within 60 calendar days . . . [the
Commission] shall institute an action in the appropriate district court
of the United States for an order affirming the assessment of the civil
penalty. The court shall have authority to review de novo the law and
the facts involved, and shall have jurisdiction to enter a judgment
enforcing, modifying, and enforcing as so modified, or setting aside in
whole or in [p]art such assessment.
Id. § 823b(d)(3)(A)–(B). As noted by the Court in its Order Regarding Procedures
Applicable to Petition for Order Affirming Assessment of Civil Penalties (ECF No.
82
95), § 823b(d)(3) “does not dictate the procedures the Commission should use to assess
the civil penalties.” Silkman, 233 F. Supp. 3d at 219. “The only statutory directive
is promptness.” Id. “There is nothing in the language of the statute that requires the
Commission to provide the targeted parties any procedural protections, such as
access to discovery, a hearing, or the ability to confront evidence.” Id.
2.
The Statutory Period under 28 U.S.C. § 2462
The parties agree that as FERC has not prescribed a time limit within which
an administrative claim to impose a civil penalty or an action to enforce such a
penalty; therefore, the general statute of limitations under § 2462 applies. Section
2462 states that “an action, suit, or proceeding for the enforcement of any civil fine,
penalty, or forfeiture, pecuniary or otherwise, shall not be entertained unless
commenced within five years from the date when the claim first accrued.” The correct
interpretation of the phrase “when the claim first accrued” is disputed by the parties.
The Court turns to relevant caselaw.
3.
United States v. Meyer
In Meyer, the First Circuit addressed when the statute of limitations under §
2462 accrues. Meyer arose under circumstances similar to the instant case: the
United States Department of Commerce charged Robert Meyer with “furnishing
boycott information to Saudi Arabia on three separate occasions . . . and failing to
report receipt of a request for boycott-related information to the United States
Department of Commerce. . ..” in violation of regulations under the Export
Administration Act (EAA). 808 F.2d at 913. On July 21, 1981, the Department of
83
Commerce “initiated administrative enforcement proceedings against Meyer by
issuing a ‘charging letter’ pursuant to 15 C.F.R. § 388.4(a).” Id. On July 22, the
administrative law judge assigned to the matter issued an initial decision, finding
that Mr. Meyer violated the regulations and imposing a civil penalty of $5,000. Id.
When Mr. Meyer refused to pay the sanctions, “on December 31, 1985—more than
five years after the infractions themselves occurred, but within five years of the
assessment of the penalty—the Department brought an enforcement suit in the
United States District Court for the District of Massachusetts. Id. The district court
relied on the Fifth Circuit’s opinion in United States v. Core Laboratories, Inc., 759
F.2d 480 (5th Cir. 1985), in dismissing the action as time-barred under 28 U.S.C. §
2462. Id. The First Circuit reversed, holding that Ҥ 2462 affords an additional fiveyear period following final administrative assessment of a civil penalty during which
the government may sue to enforce the action.” Id. at 914.
In reaching its decision, the First Circuit first analyzed the plain language of
the statute. It stated that “the standard definition of the concept of accrual is to the
effect that ‘[a] cause of action “accrues” when a suit may be maintained thereon.’”
Id. According the Meyer Court, the language of the statute requires that the
government “refrain from initiating a civil suit until the appropriate administrative
authority has imposed a sanction which the respondent has thereafter refused to
satisfy.” Id. In other words, the claim for the enforcement of a civil penalty cannot
accrue until the civil penalty has assessed. Id. (“In the case at bar, it is abundantly
clear that no suit to recover a civil penalty can be mounted under the EAA unless
84
and until the penalty has first been assessed administratively”). The First Circuit
disagreed with the Fifth Circuit’s approach, which relied heavily on interpretation
of the Legislature’s intent behind the statute. Id. at 915 (“Where, as here, the
language of a statute seems clear and unambiguous, courts should be extremely
hesitant to search for ways to interpose their own notions of Congress’s intent”)
(citing Yates v. United States, 354 U.S. 298, 305 (1957), Browder v. United States,
312 U.S. 335, 338 (1941)).
The Meyer Court also reviewed caselaw “which produces abundant support
for such a commonsense construction of 28 U.S.C. § 2462,” noting:
Outside of the Fifth Circuit, no court has ever held that, in a case where
an antecedent administrative judgment is a statutory prerequisite to the
maintenance of a civil enforcement action, the limitations period on a
recovery suit runs from the date of the underlying violation as opposed
to the date on which the penalty was administratively imposed.
Id. at 916. The First Circuit quoted Lins v. United States, 688 F.2d 784, 786 (Ct. Cl.
1982) as stating that “if disputes are subject to mandatory administrative
proceedings [before judicial action may be taken], then the claim does not accrue until
their conclusion.” Id. The First Circuit also examined Crown Coat Front Company
v. United States, 386 U.S. 503 (1967), in which the Supreme Court held that the right
to resort to the courts in a similar statutory scheme occurred “only upon the making
of that administrative determination.” Id. at 916-17 (discussing Crown Coat Front,
386 U.S. at 511-12).
Under this rationale, the First Circuit observed that the
Supreme Court held that the plaintiff’s action in the courts was not time-barred
under the relevant statute of limitations despite that the action was brought “more
85
than six years after the occurrence of the events underlying his contract claim, but
less than six years from the issuance of a final administrative decision on that claim.”
Id. at 917.
The Meyer Court also considered the “golden rule of statutory interpretation
that ‘legislation should be interpreted to avoid . . . unreasonable results whenever
possible’” to support its holding. Id. at 919 (citing Am. Tobacco Co. v. Patterson, 456
U.S. 63, 71 (1982)). “The concern that 28 U.S.C § 2462 could pluck an enforcement
suit from the vine before it had even ripened enough to be brought is by no means
theoretical.” Id. The First Circuit observed that following the Department’s issuance
of a charging letter, “the timing of the case is largely beyond the Department’s
control” due to the requirements of the Administrative Procedure Act and its
regulations “designed to ensure procedural fairness,” as well as the respondents’ right
to appeal. Id.
The First Circuit distinguished other cases relied on by the Fifth Circuit in
light of fundamental procedural differences. Most of the cases the Fifth Circuit cited
did not involve “the necessity for allowing an administrative proceeding to run its
course as a precondition to the commencement of the suit.” Id. at 920. Another group
of cases the Fifth Circuit cited in Core “involved situations where prosecutorial
determinations, rather than adjudicatory administrative proceedings, constituted the
precondition to the suit.” Id. (citing United States v. Athlone Induss., Inc., 746 F.2d
977 (3d Cir. 1984); United States v. Advance Mach. Co., 547 F. Supp. 1085 (D. Minn.
1982); F.T.C. v. Lukens Steel Co., 454 F. Supp. 1182 (D. D. C. 1978)). The Meyer Court
86
distinguished these cases that concerned decisions to bring suit, reasoning that
because they fall entirely within the control of the government, if the statute of
limitations were to run, the government agency “would only have its own indecision
to blame.” Id.
4.
Gabelli v. SEC and Kokesh v. SEC
The Respondents contend that the United States Supreme Court’s decisions in
Gabelli and Kokesh overruled Meyer.
In Respondents’ view, under the Gabelli
interpretation of § 2462, the claims accrued at the time of the violation. Resp’t’s Mot.
at 8. The statute of limitations governing the action in Gabelli, as in this case, is the
general statute of limitations that governs many penalty provisions throughout the
U.S. Code, 28 U.S.C. § 2462. 568 U.S. at 444. The SEC sought civil penalties against
the petitioners in an action in district court, and the petitioners moved to dismiss,
arguing that the action was time-barred under § 2462. Id. at 446. The district court
dismissed the claim. Id. at 446-47. The Second Circuit reversed under the SEC’s
argument that “because the underlying violations sounded in fraud, the ‘discovery
rule’ applied, meaning that the statute of limitations did not begin to run until the
SEC discovered or reasonably could have discovered the fraud.” Id. at 447. The
Supreme Court granted certiorari and reversed the Second Circuit, holding that “the
fraud discovery rule has not been extended to Government enforcement actions for
civil penalties.” Id. In Kokesh, the Supreme Court cited Gabelli as support for the
proposition that “the 5-year statute of limitations set forth in 28 U.S.C. § 2462 applies
when the [S.E.C.] seeks monetary penalties.” 137 S. Ct. at 1640. The Kokesh Court
87
held that § 2462 applies to claims for disgorgement in an SEC enforcement action,
and “any claim for disgorgement . . . must be commenced within five years of the date
the claim accrued.” Id. at 1645.
B.
Analysis
The Respondents first contend that Meyer is no longer good law following the
Supreme Court’s decisions in Gabelli and Kokesh. The Court disagrees.
“As a general proposition, an argument that the Supreme Court has implicitly
overruled one of its earlier decisions is suspect.” United States v. Symonevich, 688
F.3d 12, 20 (1st Cir. 2012) (citing Agostini v. Felton, 521 U.S. 203, 237 (1997) (“We do
not acknowledge, and we do not hold, that other courts should conclude our more
recent cases have, by implication, overruled an earlier precedent. . ..”)). Furthermore,
“[u]ntil a court of appeals revokes a binding precedent, a district court within the
circuit is hard put to ignore that precedent unless it has unmistakably been cast into
disrepute by supervening authority.” Eulitt ex rel. Eulitt v. Maine, Dep't of Educ.,
386 F.3d 344, 349 (1st Cir. 2004) (citing Sarzen v. Gaughan, 489 F.2d 1076, 1082 (1st
Cir. 1973) (“When a . . . federal court has spoken, stability and stare decisis require
that litigants and other courts take its pronouncement at face value until formally
altered”)).
The issue in Meyer — whether the claim accrues at the time of the violation,
or at the time a claim is brought to enforce a penalty order — was not at issue in
Gabelli or Kokesh. As stated by Judge Woodlock in his order on the Respondents’
motion to dismiss, “Gabelli did not concern a case in which administrative
88
proceedings preceded an action in federal court; there, the SEC sued directly in
court.” Silkman I, 177 F. Supp. 3d at 699. The issue in Gabelli—whether the
discovery rule in fraud actions extends to government enforcement proceedings—is
also unrelated to the issue decided in Meyer. Furthermore, “Meyer sits on one side of
a circuit split, yet the Gabelli court did not purport to address or resolve that split.
Nothing in Gabelli suggests that it is inconsistent or incompatible with Meyer.” Id.
at 700 n.9 (internal citation omitted).
For a district court faced with prior circuit authority to change course, the law
requires that circuit court precedent be “formally altered”, Eulitt, 386 F.3d at 349, or
“unmistakably . . . cast into disrepute by supervening authority.” Sarzen, 489 F.2d at
1082. As the Supreme Court’s decisions in Gabelli and Kokesh address different
issues regarding the application of § 2462 and the First Circuit has not formally
altered Meyer, the Court disagrees with the Respondents’ contention that either
Gabelli and Kokesh superseded Meyer. Libertarian Party of N.H. v. Gardner, 843
F.3d 20, 32-33 (1st Cir. 2016) (“When a . . . federal court has spoken, stability and
stare decisis require that litigants and other courts take its pronouncement at face
value until formally altered”) (quoting Sarzen, 489 F.2d at 1082).
The second argument the Respondents have championed is that even if Meyer
is still good law, it is distinguishable because the process FERC afforded amounted
to a decision to prosecute, in contrast to the adjudicatory administrative proceeding
the FEC afforded the defendants in Meyer, and therefore the FERC process fell
outside the scope of Meyer’s holding regarding § 2462. Meyer states that “where
89
prosecutorial determinations, rather than adjudicatory administrative proceedings,
constituted the precondition to suit . . . the limitations period . . . runs from the time
of the underlying violation rather than from the government’s decision to prosecute
the charge.” 808 F.2d at 920. The First Circuit notes that for the EAA administrative
proceedings at issue in Meyer, a prosecutorial determination would be more akin to
“the Department’s initial issuance of a charging letter” than to “the imposition of a
statutory penalty by an ALJ after notice, discovery, and hearing.” Id.
In support of their contention that FERC provided only a prosecutorial
determination, the Respondents rely on Barclays III from the District Court for the
Eastern District of California, which commented in an order for judgment on the
pleadings that the same FERC process constituted a prosecutorial determination
rather than an adjudicatory administrative proceeding.
Barclays III, 2017 WL
4340258, at *15. On this basis, the Barclays III Court concluded that FERC’s action
to enforce six years after the violation occurred was time-barred. Id. at *13. The
Barclays III Court, in determining whether § 2462 applied to an administrative
proceeding, looked to caselaw to assess whether FERC held a proceeding, within the
meaning of § 2462. Id. at 10-12. Relying on 3M Co. (Minnesota Min. & Mfg.) v.
Browner, 17 F.3d 1453 (D.C. Cir. 1994) and Marshall v. Jerrico, Inc., 446 U.S. 238,
242 (1980), the district court considered factors such as whether a neutral adjudicator
was provided and whether the proceeding was adversarial in nature in its
determination that FERC’s Administrative Penalty Assessment Process did not
constitute a proceeding, but rather a decision to prosecute. Barclays III, 2017 WL
90
4340258, at *11-14.
As a district court within the Ninth Circuit, the Barclays III Court was not
bound, as this Court is, by First Circuit precedent. Nor did the Barclays III Court
rely upon caselaw binding in this circuit in making its determination. 131 By contrast,
this Court must rely on the First Circuit’s teaching in Meyer to decide this issue.
Although Meyer concerned the enforcement of the Department of Commerce’s
administrative action aimed at imposing a civil penalty under the EAA, as opposed
to FERC’s enforcement action for an administrative penalty at issue here, its analysis
of the applicability of § 2462 governs.
The Meyer Court’s holding that “§ 2462 affords an additional five year period
following final administrative assessment of a civil penalty during which the
government may sue to enforce the action”, 808 F. 2d at 914, is based on four key
factors: (1) the clear and unambiguous language of the statute, (2) the balance of the
caselaw, (3) the goal of avoiding a “self-abnegating result,” and (4), the primary
legislative purpose of enacting statutes of limitations: to ensure fairness to
defendants. See generally Meyer, 808 F.2d at 912. The First Circuit’s comparison of
the “mandatory administrative adjudication” at issue in Meyer with the
“prosecutorial decisionmaking” in Athlone Industries, 746 F.2d 997, Advance
The Barclays III Court relies on the Supreme Court’s statement in Marshall v. Jerrico that
“[t]he Due Process Clause entitles a person to an impartial and disinterested tribunal in both civil and
criminal cases,” 446 U.S. at 242, in support of its conclusion that a neutral decision-maker is required
for the Administrative Penalty Assessment Process to constitute a proceeding. Marshall does not
involve the definition of “proceeding” as applied to § 2462 but addressed “whether the statutory
provision requiring that penalties be paid to the agency ‘violates the Due Process Clause of the Fifth
Amendment by creating an impermissible risk of bias in the Act’s enforcement and administration.,’”
Id. (quoting Marshall, 446 U.S. at 239).
131
91
Machine, 547 F. Supp. 1085, Ancorp, 516 F.2d 198, and Lukens Steel, 454 F. Supp.
1182, was not meant to carve out an exclusion to its holding, but to distinguish Meyer
from several of the cases the Fifth Circuit had relied upon in Core, based on the
differences in the types of proceeding they govern. Meyer 808 F.2d at 920. As noted
in Worldwide, “[b]ecause such administrative decisions ‘are not in any sense
adjudicative . . . [but] comprise nothing more or less than decisions to bring suit,’ they
differ[] markedly from the EAA's process for imposing a sanction and thus [are] of
little value on the statute of limitations question.” 220 F. Supp. 3d at 342 (quoting
Meyer, 808 F.2d at 920).
Under this interpretation of Meyer, the Court finds
unpersuasive the Respondents’ effort to distinguish Meyer from this case based on
the alleged procedural inadequacies they suffered.
However, even taking as true the Respondents’ view that the dispositive issue
in Meyer was the nature of the proceeding afforded to the defendants and viewing the
facts in the light most favorable to the Respondents, the Court finds FERC’s
proceeding closer to the adjudication in Meyer than to a prosecutorial determination
or charging letter. 132 The Respondents stress that the procedural safeguards the
The Respondents repeatedly compare the FERC procedure leading to an order assessing
penalties to a prosecutor’s decision leading to a criminal charge, a position the Barclay Court may
accept. See Barclay III, 2017 U.S. Dist. LEXIS 161414, at *35 (“The Administrative Penalty
Assessment Process is tantamount to a decision to prosecute rather than a ‘prosecution’”). From the
Court’s perspective, whether to criminally charge or indict someone is markedly dissimilar to the
FERC process. For example, a grand jury proceeding, unlike a FERC proceeding, is secret, see United
States v. Johnson, 319 U.S. 503, 513 (1943), and individuals who violate the secrecy of a grand jury
may be subject to criminal prosecution under 18 U.S.C. § 1503. See In re Grand Jury Proceedings, 814
F.2d 61, 70 (1st Cir. 1987). Whatever limitations the FERC procedure imposes on individuals like Dr.
Silkman and entities like CES, the FERC process is a different order of magnitude from the process
leading to a grand jury indictment or prosecutorial complaint. Leaving the substantive merits of the
Respondents’ claims aside about the level of due process FERC should have accorded them, the Court
found the Respondents’ analogy to criminal prosecution distracting and unhelpful. As with many
132
92
FERC proceeding offered them did not include full discovery or a live hearing before
an administrative law judge. 133 But this does not transform the FERC proceeding
into a discretionary decision to prosecute. In Silkman I, Judge Woodlock addressed
this same issue and observed that “[e]ven if the FERC proceeding contained “less
formal and . . . fewer of the procedural protections than some adjudications under the
APA — or even the adjudication in Meyer — . . . it was significantly more than a
prosecutorial determination.” Silkman I, 177 F. Supp. 3d at 700. Judge Woodlock
concluded the following in an earlier order in this case, and the Respondents
presented no facts to the contrary on summary judgment:
The Commission made extensive findings of facts and applied the law to
those facts. It did not merely suggest penalties to be sought later; it
ordered Respondents to pay those penalties to the United States
Treasury. . . FERC did more than decide to bring suit. It conducted an
adjudication.
Id. In sum, the Court concludes that pursuant to the First Circuit’s holding in Meyer,
the claim in this case accrued when FERC brought an action in court to enforce the
penalties it assessed against the Respondents; therefore, FERC’s enforcement action
is not time-barred.
VI.
CONCLUSION
The Court DENIES Respondents’ Motion for Summary Judgment (ECF No.
analogies, the legitimacy of the point is lost in significant differences between the case at hand and
the purported example.
133
The Respondents themselves have written that “irony is no stranger to the law.” DRSAMF ¶
2. Here, the fewer procedural protections, in part, were by choice of the Respondents, who opted out
of FERC’s default procedure for the assessment of penalties, which provides “an opportunity for an
agency hearing before an administrative law judge,” in favor of a prompt assessment of penalty with
the opportunity for de novo review of the law and facts involved in FERC’s assessment by the district
court. 16 U.S.C. §§ 823b(d)(2)(A)–(B), 823b(d)(3).
93
133) and GRANTS the Defendants’ Partial Motion for Summary Judgment (ECF No.
134).
SO ORDERED.
/s/ John A. Woodcock, Jr.
JOHN A. WOODCOCK, JR.
UNITED STATES DISTRICT JUDGE
Dated this 4th day of January, 2019
94