Nature-Tech, LLC v. Hartford Fire Insurance Company et al
Filing
58
MEMORANDUM OPINION. Signed by Judge Deborah K. Chasanow on 11/21/2022. (sat, Chambers)
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 1 of 16
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MARYLAND
:
NATURE-TECH, LLC
:
v.
:
Civil Action No. DKC 19-2053
:
HARTFORD FIRE INSURANCE
COMPANY, ET AL.
:
MEMORANDUM OPINION
On July 12, 2019, Plaintiff Nature-Tech, LLC (“Nature-Tech”)
commenced
this
action,
which
stems
from
a
heavily
litigated
construction project, asserting a single breach of payment bond
claim against Defendants Capitol Woodwork, LLC (“Capitol”) and
Hartford Fire Insurance Company (“Hartford”).
held on September 28 and September 29, 2022.
A bench trial was
After carefully
considering the parties’ exhibits, the testimony of the witnesses,
the
pretrial
submissions
and
post-trial briefs,
and
the
oral
arguments of counsel, this court now issues findings of fact and
conclusions of law pursuant to Fed.R.Civ.P. 52(a). For the reasons
articulated below, judgment will be entered in favor of Defendants
Capitol and Hartford.
I.
Background
This case involves work done as part of the construction of
a hotel and transition space at the Maryland Live! Casino in
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 2 of 16
Hanover, Maryland (“the Project”). 1
The casino owner, PPE Casino
Resorts Maryland LLC (“the Owner”), hired Tutor Perini Building
Corporation (“Tutor Perini”) as the general contractor for the
Project—neither
lawsuit.
the
Owner
nor
Tutor
(PTX 1 at 1; ECF No. 1). 2
Perini
is
party
to
this
Tutor Perini hired Capitol,
also known as Mortensen Woodwork, to furnish and install millwork
for the Project.
(PTX 1).
Capitol and Hartford executed a payment
bond to guarantee payment for Capitol’s labor and materials.
2).
(PTX
The payment bond states that Capitol and Hartford
jointly and severally, bind themselves . . . to the
Contractor [Tutor Perini] . . . to pay for labor,
materials[,] and equipment used or reasonably required
and furnished for use in the performance of the
Subcontract [between Tutor Perini and Capitol], which is
incorporated in this bond by reference and pursuant to
which this bond is issued.
Capitol
hired
Nature-Tech
to
fabricate
millwork
for
the
Project, and the two companies entered into a Master Subcontract
Agreement (“the Agreement”).
(PTX 3).
Article 12.5 of the
Agreement provides that Nature-Tech, as the Subcontractor, would
submit applications for payment to Capitol, the Contractor, and
the “Contractor shall pay ninety (90%) percent of the amount of
A detailed factual background is also set out in a prior
opinion.
(ECF No. 33); Nature-Tech, LLC v. Hartford Fire Ins.
Co., No. 19-cv-2053-DKC, 2022 WL 899417, at *1-4 (D.Md. Mar. 28,
2022).
1
“PTX” refers to exhibits offered by Nature-Tech at trial,
and “DTX” refers to exhibits offered by Capitol and Hartford.
2
2
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 3 of 16
the Application, withholding ten (10%) percent retainage (the
‘Retainage’) from each Application.”
(PTX 3 at ¶ 12.5).
Article
12.8, titled “Conditions Precedent,” provides:
Retainage and/or the Final Application payment shall be
paid to Subcontractor only after; (a) the Work
(including
any
punch-list
work)
is
completed
satisfactorily and accepted by Owner and Contractor;
. . . and (e) all disputes, claims, liens, causes of
action, and/or lawsuits which are related in any way to
this Agreement or to Subcontractor’s performance of the
Work are resolved.
(PTX 3 at ¶ 12.8).
While construction on the Project was underway, a dispute
arose between Capitol and Tutor Perini related to delays in the
construction schedule.
This dispute, among other issues, is being
litigated as part of a lawsuit that is presently pending in
Maryland state court. See PPE Casino Resorts Maryland LLC v. Tutor
Perini Building Corp., No. C-02-CV-19-002049 (Anne Arundel Cnty.
Circuit Court 2019).
Capitol, Hartford, Tutor Perini, and the
Owner are among the parties involved in that litigation, but
Nature-Tech is not.
On July 31, 2018, Capitol advised Nature-Tech that it was
“demobilizing the installation team” at the construction site
while it tried to work out its dispute with Tutor Perini and that
“[n]o deliveries [were] to be scheduled to the jobsite” unless
specifically
requested
by
Capitol.
(PTX
47).
Nature-Tech
continued to fabricate millwork but did not ship it, per Capitol’s
3
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 4 of 16
request.
(PTX 50).
On August 23, 2018, Tutor Perini issued to
Capitol a 48-hour “Notice to Cure,” and on August 30, 2018, Tutor
Perini declared Capitol in default and terminated it for failure
to cure.
(PTX 8, 51).
At the time of Capitol’s termination, Nature-Tech had not yet
completed all outstanding purchase orders with Capitol.
Tutor
Perini notified Nature-Tech of its intent for Nature-Tech to
complete that work through new contracts with Tutor Perini.
53).
(PTX
It later issued Nature-Tech purchase orders for shipments
and millwork.
(DTX 49-52).
However, Tutor Perini advised Nature-
Tech to seek payment from Hartford for certain items that were
included in purchase orders from Capitol prior to the termination.
(DTX 22).
Nature-Tech
completed
and
requested
shipped,
payment
millwork
retainage, and Capitol refused.
from
in
Capitol
progress,
for
and
millwork
outstanding
Nature-Tech submitted a claim
against the payment bond for $473,961.70 in unpaid billings.
23).
(DTX
Hartford reviewed Nature-Tech’s claim and analyzed thirty-
two items that Tutor Perini and Nature-Tech had identified as
outstanding
as
of
Capitol’s contract.
August
30,
2018,
the
termination
date
of
Hartford determined that Capitol was not
responsible for twelve of the items, so it deducted $140,629.13
from the claim amount.
It also determined that Capitol was
entitled to keep $135,603.18 as retainage.
4
The remaining amount
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 5 of 16
that Hartford determined was due to Nature-Tech was $197,729.39.
$157,280.56 had already been paid, and Hartford released the
remaining $40,448.83 to Nature-Tech.
(DTX 24).
Nature-Tech has conceded that Capitol was not responsible for
some of the twelve items, but it has maintained that it is entitled
to payment from the payment bond for five items, worth $66,827.25,
as well as $127,855.46 of the retainage. 3
The five items are:
1)
“Foot rail for main bar,” shipped 2/5/19: $7,350.00
2)
“Series #104 Prefunction entrance
shipped 1/16/19: $25,364.00
3)
“Series #9 Coat Check and surrounding wood veneer wall
panels,” shipped 2/5/19: $18,936.00
4)
“Taller Base molding for in Ballroom,” shipped 9/1/18:
$6,342.25
5)
“Ballroom Doors 180 A, B, C, D, E, G, & H,” shipped
9/24/18: $8,835.00 4
(DTX 46).
door
surrounds,”
In a May 9, 2019, email to a Vice President of Tutor
Perini, a Nature-Tech Senior Project Manager listed those items
and described them as “items that were shipped to the job site
AFTER Capitol was terminated from the project,” adding that they
were “all items that were ordered by Capitol, but we were told to
At trial, Nature-Tech provided a revised retainage amount,
which excluded retainage that had been drawn from items for which
Nature-Tech had billed but not completed.
3
Hartford’s report lists the amount it withheld for the
Ballroom Doors as $8,335.00. (DTX 23 at 9, 11). It is unclear
whether the difference in digits is a typographical error or
reflective of a disagreement in calculations.
4
5
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 6 of 16
ship by Tutor Perini so that the project could continue to move
towards completion.” 5
The Nature-Tech employee went on to state
that “these items need to be added to you[r] claim against Capitol
and the[n] we would receive compensation from Tutor Perini.”
The
Vice President of Tutor Perini responded that he understood that
Hartford refused to pay for those items and said, “We are including
[them] in our claim.”
(DTX 46).
Nature-Tech filed the instant lawsuit to recover the portion
of its claim against the payment bond for which it argues Hartford
improperly
denied
payment.
Capitol
asserted
a
counterclaim
against Nature-Tech for breach of contract, 6 but Capitol declined
to pursue its counterclaim at trial.
Nature-Tech on that claim.
are
whether
Nature-Tech
Judgment will be entered for
The only issues that remain unresolved
is
entitled
to
payment
for
the
five
outstanding items and whether Nature-Tech is entitled to immediate
payment of the retainage.
This court took the matter under
advisement after the trial concluded, and the parties submitted
The email listed a sixth item, but Nature-Tech has since
conceded that it does not have evidence that it is entitled to
payment for that item.
5
Capitol also initially asserted a counterclaim for tortious
interference. This court granted Nature-Tech’s motion for summary
judgment on both counterclaims but subsequently granted Capitol’s
motion to reconsider as to the breach of contract counterclaim.
See Nature-Tech, LLC v. Hartford Fire Ins. Co., No. 19-cv-2053DKC, 2022 WL 899417 (D.Md. Mar. 28, 2022); Nature-Tech, LLC v.
Hartford Fire Ins. Co., No. 19-cv-2053-DKC, 2022 WL 2065875 (D.Md.
June 8, 2022).
6
6
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 7 of 16
post-trial briefs.
(ECF Nos. 55-57).
For the reasons set forth
below, this court concludes that Nature-Tech has not met its burden
to prove by a preponderance of the evidence that it is presently
entitled to any additional payment from Hartford and Capitol.
II.
Findings of Fact and Conclusions of Law
A.
Five Outstanding Items
Nature-Tech’s claim is for breach of a payment bond, brought
against Capitol as principal and Hartford as surety of the payment
bond.
Nature-Tech has the burden to prove that it is entitled to
payment under the payment bond for the disputed items.
In a
suretyship, “[t]he bond is the measure of the surety’s obligation,”
Atl. Contracting & Material Co. v. Ulico Cas. Co., 380 Md. 285,
300 (2004), and it “is to be construed in connection with the
contract whose performance it secures[] in determining the right
of laborers or materialmen to recover thereon.”
Lange v. Bd. of
Educ. ex rel. I.B.M. Corp., 183 Md. 255, 261 (1944); see also Gen.
Builders Supply Co. v. MacArthur, 228 Md. 320, 326 (1962)(“[I]t is
clear that the liability of the surety is measured by the contract
of the principal.”). Surety bonds “must be construed in accordance
with our traditional rules of objective contract interpretation.” 7
Atl. Contracting & Material Co., 380 Md. at 300.
The terms of the
As noted in a previous opinion, Maryland law applies to the
payment bond claim. See Nature-Tech, LLC v. Hartford Fire Ins.
Co., No. 19-cv-2053-DKC, 2022 WL 899417, at *5 (D.Md. Mar. 28,
2022).
7
7
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 8 of 16
bond “must be interpreted in context[] and given their ordinary
and
usual
meaning,”
but
when
“a
coverage
issue
depends
upon
language of the policy which is ambiguous, we will resolve that
ambiguity in favor of the insured.” Id. at 301 (internal quotation
marks omitted).
Hartford denied payment for four of the five items because
the items were not fully fabricated before the termination of
Capitol’s contract with Tutor Perini.
(DTX 23 at 6-7, 9-10).
It
is Hartford and Capitol’s position that anything fabricated after
Capitol’s termination was not covered by the payment bond because
the payment bond only covered work performed under Capitol’s
contract with Tutor Perini.
should
pay
for
any
items
Nature-Tech contends that Capitol
Nature-Tech
fabricated
pursuant
purchase orders that Capitol issued prior to termination.
payment
bond’s
terms
better
support
Hartford
and
to
The
Capitol’s
position.
The payment bond was issued “pursuant to” the contract between
Capitol and Tutor Perini and binds Capitol and Hartford to pay for
items “used or reasonably required and furnished for use in the
performance of” that contract.
(PTX 2).
The bond’s purpose was
to indemnify Tutor Perini from claims under its contract with
Capitol.
(PTX 1 at 6).
Anything fabricated after the termination
of the contract between Tutor Perini and Capitol was not “for use
8
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 9 of 16
in the performance of” that contract because that contract was no
longer in effect.
Evidence suggesting that Tutor Perini arranged for NatureTech to fabricate items directly for Tutor Perini after Capitol’s
termination supports this conclusion and undermines Nature-Tech’s
position that the items were fabricated for Capitol’s contract.
In an August 31, 2018, email to the CEO of Nature-Tech advising
him that Capitol’s contract had been terminated, Tutor Perini’s
Executive Vice President stated that Tutor Perini’s contract with
Capitol
“permits
[Tutor
Perini]
to
complete
[Capitol’s]
work
through others if they are found in default and/or are terminated.”
The
email
advised
Nature-Tech
that
Tutor
Perini
would
be
“contacting [Nature-Tech] shortly to arrange for immediate jobsite
delivery of completed millwork items[,] including those currently
in fabrication upon completion,” and that it would be “issuing
[Nature-Tech] a purchase order for all remaining items needed to
complete the work currently under [Capitol’s] contract.”
(PTX
53).
Capitol and Hartford introduced into evidence a document on
Tutor
Perini
letterhead,
dated
“As-of
08/30/18”
and
titled
“Balance of Millwork Items for NT [Nature-Tech] to Fabricate &
TPBC [Tutor Perini] to Install After [Capitol’s] Termination,”
that appears to include each of the five disputed items.
15).
(DTX
The Executive Vice President of Nature-Tech testified at
9
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 10 of 16
trial that this document was generated as part of the process in
which
Nature-Tech
worked
with
Tutor
outstanding millwork for the project.
Perini
to
complete
the
There was also an email
exchange, dated January 10, 2019, between employees of Tutor Perini
and Nature-Tech regarding outstanding millwork items that were
received or would soon be received by Tutor Perini’s “millwork
installation crew and carpenter foreman”; the email specifically
mentioned the foot rail as having been fabricated and in transit
to the job site. (PTX 55).
Nature-Tech has not presented evidence
that contradicts a reading of these documents as indicative that
at least some of the items were fabricated under the direction of
Tutor Perini, not Capitol.
The record does not support a conclusion that the items
shipped
several
months
after
Capitol’s
August
30,
2018,
termination were fabricated for use in the performance of the
Capitol-Tutor Perini contract.
The parties have represented that
the foot rail was not shipped until February 2019, the “Series
#104 Prefunction entrance door surrounds” were not shipped until
January 2019, and the “Series #9 Coat Check and surrounding wood
veneer wall panels” were not shipped until February 2019. (DTX
23).
At trial, Capitol’s corporate representative testified that
items that were delivered four or five months after the termination
date were clearly fabricated outside the purview of Capitol’s
contract.
Nature-Tech did not present any alternative explanation
10
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 11 of 16
for the several-month delay in shipment for items supposedly
fabricated in the performance of Capitol’s terminated contract.
Nature-Tech has not met its burden to prove that it is entitled to
payment for those three items from the payment bond.
The ballroom doors were shipped on September 24, 2018, which
is closer to the termination date.
that
Nature-Tech
completed
However, Hartford determined
fabrication
for
this
termination per the request from [Tutor Perini].”
item
“after
(DTX 23 at 9).
At trial, Capitol’s corporate representative testified that there
were no drawings or field dimensions approved as of August 30,
2018, for the ballroom doors, which he said indicated that NatureTech could not have fabricated them until after the termination.
A
document
sent
from
a
Tutor
Perini
employee
to
Nature-Tech
employees, dated August 27, 2018, and titled “Items-Status Log,”
lists the ballroom doors with a note: “Need updated drawings.”
(DTX 20). Nature-Tech has not contradicted that version of events,
nor
has
it
presented
evidence
that
the
fabricated before Capitol’s termination.
ballroom
doors
were
Nature-Tech has not met
its burden to prove that the ballroom doors were covered by the
payment bond.
The fifth item—the “Taller Base molding for in Ballroom”—
requires a different analysis because the parties have agreed that
it was shipped on September 1, 2018, and Capitol has conceded that
this item was probably fabricated before the termination. However,
11
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 12 of 16
Hartford only denied payment for some of the amount Nature-Tech
requested for this item.
(DTX 23 at 10).
Hartford determined
that this item was billed at $25,369 for 1,600 linear feet of
molding, but the delivery ticket showed that only 1,200 linear
feet of molding was delivered.
Therefore, Hartford reduced the
contract value by one quarter and paid all but $6,342.25 for that
item.
has
Nature-Tech now requests the remaining $6,342.25, but it
produced
no
evidence
that
the
full
1,600
was
delivered.
Therefore, Nature-Tech has not met its burden to prove that it is
entitled to additional payment for this item.
B.
Retainage
Nature-Tech
also
seeks
withheld as retainage.
immediate
payment
of
the
amount
Pursuant to its contract with Nature-Tech,
Capitol withheld 10% of each payment to Nature-Tech as retainage.
This money is covered by the payment bond because the work to which
it pertains was done “for use in the performance of” the CapitolTutor Perini contract.
The question is whether Nature-Tech is
presently entitled to payment of that retainage.
The answer turns on the terms of the Agreement between Capitol
and Nature-Tech, which provides that retainage shall be paid to
Nature-Tech “only after” certain conditions are met, including
that
“all
disputes,
claims,
liens,
causes
of
action,
and/or
lawsuits which are related in any way to this Agreement or to
[Nature-Tech’s] performance of the Work are resolved.”
12
(PTX 3 at
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 13 of 16
¶
12.8).
Under
this
provision,
which
is
titled
“Conditions
Precedent,” each condition must be met before Nature-Tech is
entitled to payment.
See Duff v. Trenton Beverage Co., 73 A.2d
578, 604 (N.J. 1950) (“Generally, no liability can arise on a
promise subject to a condition precedent until the condition is
met.”); 8 see also Assoc. Mech. Corp., Inc. v. Martin K. Eby Constr.
Co., 67 F.Supp.2d 1375, 1379 (M.D.Ga. 1999) (determining that
language identical to the clause at issue in the present case was
a “condition precedent” for payment to a subcontractor).
Nature-
Tech bears the burden of proving that the conditions precedent
have been satisfied.
See Thomas Orr Trucking & Forwarding Co. v.
Metro. Sur. Co., 73 A. 541, 543 (N.J. 1909) (“It cannot be doubted
that,
where
there
is
an
allegation
by
the
defendant
of
nonperformance of the special conditions precedent, the general
performance of which has been asserted by the plaintiff . . . ,
the burden of proof remains with the plaintiff to show performance
as at common law.”); see also 5A Wright & Miller, Fed. Prac. &
Proc. Civ. § 1304 (4th ed.). 9
Pursuant to Article 16.1 of the Agreement, the Agreement is
subject to New Jersey law. (PTX 3 at ¶ 16.1).
8
Although the parties dispute who bears the burden of proving
the satisfaction of the condition precedent at issue here, neither
party questions whether the satisfaction or lack thereof was
properly pleaded in the complaint and answers. See 5A Wright &
Miller, Fed. Prac. & Proc. Civ. § 1304 (4th ed.). However, even
assuming the burden of proof is on the Defendants here, they have
met that burden for the same reasons discussed.
9
13
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 14 of 16
Capitol and Hartford contend that a condition precedent to
payment
of
the
retainage
has
not
been
satisfied
because
the
litigation presently pending in Maryland state court is related to
Nature-Tech’s
thereunder.
contract
with
Capitol
and
the
work
performed
Nature-Tech argues that because Nature-Tech is not a
party to the lawsuit, and Capitol has not proven that deficiencies
in Nature-Tech’s work are the basis for the claims against it, the
lawsuit is not “related in any way” to Nature-Tech or its work.
Nature-Tech’s reading of this provision is too narrow.
A
plain reading of “related in any way” is that it has a broad reach,
including disputes or lawsuits that involve the Agreement or
Nature-Tech’s work on the Project in any way.
Cf. United States
v. Gonzales, 520 U.S. 1, 5 (1997) (“Read naturally, the word ‘any’
has an expansive meaning[.]”); E. Coast Repair & Fabrication, LLC
v. United States ex rel. Dep’t of Navy, 16 F.4th 87, 89, 91 (4th
Cir. 2021) (interpreting a release from liability for “any and all
[claims] arising out of or in any way relating to” a contract as
“broad”).
Nature-Tech argues that the lawsuit could be unrelated
to its work because “Capitol’s contractual scope of work on the
Maryland Live! Project far exceeded simply supplying the millwork;
it involved preparing shop drawings and the labor to install all
of the millwork.”
(ECF No. 56).
But the shop drawings Nature-
Tech used to fabricate the millwork and the labor used to install
14
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 15 of 16
the
millwork
Nature-Tech
fabricated
are
clearly
“related”
to
Nature-Tech’s work.
Capitol has provided a list of the backcharges that Tutor
Perini has asserted against Capitol, (DTX 8), and it identified at
trial through the testimony of its corporate representative that
$629,576 relate to the Agreement and Nature-Tech’s performance of
work under the Agreement.
Nature-Tech responds that Capitol and
Hartford have not proven that the backcharges are “valid” or
“establish[ed]
vaguely
any
alleged
Nature-Tech.”
causal
connection
backcharges
and
any
(ECF No. 56 at 5).
between
specific
Tutor
Perini’s
deficiencies
by
But the Agreement does not
require that claims be valid in order to justify withholding of
retainage—it merely requires that claims exist and that they be
unresolved.
And a causal connection is not required—the claims in
the lawsuit must merely be “related” to Nature-Tech’s work “in any
way,” and that is clearly the case.
Even if, as Nature-Tech asserts, all of Tutor-Perini’s claims
against
Capitol
pertain
solely
to
Capitol’s
deficiencies
in
performing its obligations under its contract with Tutor Perini,
it is inconceivable that they could all be completely unrelated to
Nature-Tech’s
performance
under
the
Agreement.
Nature-Tech
attempts to give examples of Capitol’s failures that are unrelated
to Nature-Tech’s performance, such as “prepar[ing] shop drawings
containing errors and missing information, delaying the start of
15
Case 1:19-cv-02053-DKC Document 58 Filed 11/21/22 Page 16 of 16
fabrication[, and] fail[ing] to prepare shop drawings for a large
portion of its contracted scope of work.”
(ECF No. 56 at 5).
But
those are all related in some way to Nature-Tech’s performance—
they all impacted Nature-Tech’s ability to fabricate the millwork
in a timely way as required by Tutor Perini, regardless of who was
at fault for those delays.
Therefore, until the litigation is
resolved, Capitol is entitled under the Agreement to continue
withholding retainage.
III. Conclusion
For the foregoing reasons, judgment will be entered in favor
of Defendants Capitol and Hartford. A separate order will follow.
/s/
DEBORAH K. CHASANOW
United States District Judge
16
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?