Al Jazeera International v. Dow Lohnes PLLC et al
Filing
106
MEMORANDUM OPINION. Signed by Judge Deborah K. Chasanow on 12/21/2016. (sat, Chambers)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MARYLAND
:
AL JAZEERA INTERNATIONAL
:
v.
:
Civil Action No. DKC 13-2769
:
DOW LOHNES PLLC, et al.
:
MEMORANDUM OPINION
Presently pending and ready for resolution in this attorney
malpractice
case
is
Defendants
Dow
Lohnes
(“Defendants”).
briefed,
and
necessary.
a
(ECF
the
motion
PLLC
No.
court
for
and
91).
now
summary
The
rules,
Local Rule 105.6.
judgment
Leslie
H.
issues
no
by
Wiesenfelder
have
hearing
filed
been
being
fully
deemed
For the following reasons, the
motion for summary judgment will be granted in part and denied
in part.
I.
Background1
A.
This
The Facts of the Underlying Litigation
attorney
representation
malpractice
of
Plaintiff
case
Al
stems
from
Jazeera
Defendants’
International
(“Plaintiff”) in a contract dispute with Winmar, Inc.
In 2005,
Plaintiff entered into a construction contract with Winmar, Inc.
to build a television studio and offices in Washington, D.C.
(the “Contract”).
1
(ECF No. 99, at 7).
Janson Design Group (the
Unless otherwise noted, the facts outlined here are
undisputed or construed in the light most favorable to
Plaintiff, the nonmoving party.
“Architect”) was the architect for the project.
(Id.).
The
Contract established a payment process under which Winmar would
submit periodic invoices (“Payment Applications”) for review by
the
Architect
as
Plaintiff’s
agent;
if
the
Architect
was
satisfied, it would certify these Payment Applications to be
paid by Plaintiff.
(Id. at 8).
Between October and December 2005, Winmar submitted four
Payment
Applications
totaling
certified all four of them.
$1,838,140,
(Id.).
and
the
Architect
Concerned that Winmar had
not completed all of the work for which it was seeking payment,
Plaintiff
paid
$474,677.
only
one
at
9).
(Id.
of
the
Winmar
invoices,
sent
in
the
Plaintiff
a
amount
of
notice
of
default on December 22, asserting that it was in breach of the
Contract
and
remaining
directing
certified
it
to
cure
amounts.
the
breach
(Id.).
by
paying
Defendants
the
advised
Plaintiff that even if Winmar had not completed the appropriate
amount of work, the contract language was such that non-payment
could be considered a breach by a reviewing court.
(Id. at 9-
10).
engaged
Given
the
billing
dispute,
Plaintiff
construction manager to review the state of the project.
No.
50
¶
22).
Plaintiff,
and,
payments.
He
concluded
consequently,
that
Winmar
Plaintiff
had
made
a
(ECF
overbilled
no
further
(Id.).
On January 5, 2006, the Architect sent a letter to Winmar,
rescinding
its
certification
for
2
the
three
unpaid
invoices,
declaring that the certifications had been made in error and
were withdrawn on account of “a number of discrepancies in the .
. . Application documents, as well as the lack of appropriate
(ECF No. 99, at 10).2
supporting documentation.”
The Architect
asked Winmar for additional documents supporting the invoices,
which Winmar refused to provide.
(Id. at 10-11).
then terminated the Contract for convenience.
Plaintiff
(Id.
at 12).
Plaintiff soon after sent a letter to Winmar and the Architect
pursuant
to
disputes.
177
the
Contract’s
process
for
resolving
billing
Winmar, Inc. v. Al Jazeera Int’l, 741 F.Supp.2d 165,
(D.D.C.
Plaintiff’s
2010).
The
letter
calculations,
approximately $200,000.
it
stated
had
that,
according
to
Winmar
by
overpaid
Id.
Meanwhile, apparently in response to Plaintiff’s attempt to
confirm
the
Plaintiff’s
status
bank,
of
Qatar
the
single
National
payment
Bank
it
(“QNB”),
transferred the $474,677 payment a second time.
had
made,
erroneously
Id. at 176.
Instead of returning the money to QNB, Winmar construed this as
a payment for one of the other certified Payment Applications
and returned the difference between the payment and Application
amount, an extra $119,380, directly to Plaintiff.
Id. at 177.
Plaintiff evidently considered this payment to be a response to
its
$200,000
2
demand,
so,
at
that
point
in
March
of
2006,
The Architect later rescinded certification for the fourth
Payment Application, the one that Plaintiff had already paid.
(ECF No. 99, at 11).
3
Plaintiff
believed
it
was
owed
roughly
$80,000.
Given
the
amount in dispute, Plaintiff decided that it would not make
economic
amount.
sense
to
file
suit
against
Winmar
to
recover
that
(ECF No. 99, at 27).
On July 24, 2006, QNB filed suit against Winmar in the
United States District Court for the District of Columbia to
recover the $474,677 duplicate payment.
(Id. at 13).
Winmar
then filed a third-party complaint against Plaintiff, alleging
that Plaintiff had breached the Contract by not making payments
pursuant to the Architect’s certifications.
Defendants
to
represent
it
and
filed
a
Plaintiff retained
counterclaim
against
Winmar, denying any liability and asserting that Plaintiff had
overpaid
Winmar
pursuant
to
provisions of the Contract.
prior
to
the
time
the
termination
for
convenience
In its answer, Winmar alleged that,
Plaintiff
terminated
the
Contract
for
convenience, Plaintiff had materially breached the Contract and,
therefore,
invoice
Winmar
certified
was
by
entitled
the
to
the
Architect,
full
more
amount
than
$1.7
of
every
million.
Winmar, 741 F.Supp.2d at 177-78.
B.
The Instant Malpractice Claims
Plaintiff
substantial
now
issue
certification,
but
alleges
regarding
that
that
the
Winmar’s
accuracy
Defendants
failed
suit
raised
of
the
to
investigate
a
Architect’s
the
Architect’s role in the events, including whether the Architect
breached its duty of care.
(ECF No. 50 ¶ 29).
4
It argues that
Defendants’ failure to investigate the Architect left Plaintiff
with no factual defense to Winmar’s principal claim: i.e., that
the
certifications
were
Plaintiff owed Winmar.
raised
the
prima
facie
(Id. ¶ 31).
certifications
at
evidence
of
the
amount
Consequently, when Winmar
trial,
Defendants
rebuttal, leaving Plaintiff greatly exposed.
offered
no
(Id. ¶ 34).
On September 29, 2010, Judge Gladys Kessler of the United
States District Court for the District of Columbia issued a
memorandum
opinion
and
order,
granting
Winmar and against Plaintiff.
judgment
in
favor
of
Winmar, 741 F.Supp.2d at 196.
The court found that “Al Jazeera offered no evidence at trial
showing how the Architect arrived at the decision to certify the
Payment Applications. . . .
In the absence of any evidence from
Al Jazeera that the Architect neglected its duties under the
Contract in making the certification decisions, the certified
Payment
Applications
are
the
most
reliable
evidence
of
services performed by Winmar in the periods covered.”
182-183.
Id. at
Judge Kessler gave little weight to the subsequent
rescissions,
Architect’s]
supporting
the
which
were
conclusion
based
that
documentation,”
valid under the Contract.
a
“in
Winmar
large
is
required
justification
Id. at 182.
part
she
on
to
found
[the
provide
was
not
She also stated that she
“has never been able to understand why neither party ever called
the Architect to testify.”
Id. at 182 n.17.
Judgment was
granted in favor of Winmar for a total of $1,472,625.50.
5
Id. at
196.
Although Plaintiff appealed the judgment to the United
States Court of Appeals for the District of Columbia Circuit, it
decided to settle the dispute for $2,000,000 while that appeal
was pending rather than run the risk of an unfavorable outcome
on appeal.3
On September 19, 2013, Plaintiff filed a complaint in this
court
for
(ECF
No.
legal
1).4
malpractice,
Plaintiff
citing
alleges
diversity
that
jurisdiction.
Defendants,
as
its
attorneys during the Winmar litigation, owed it a duty of care
to conduct a thorough and competent investigation of the facts
and circumstances surrounding Plaintiff’s dispute with Winmar
and to exercise sound and reasonable judgment in planning and
executing
a
defense
to
Winmar’s
claims
against
Plaintiff.
According to Plaintiff, Defendants breached this duty by failing
to depose the Architect or calling the Architect as a witness at
trial.
Plaintiff contends that but for Defendants’ failure to
depose or call the Architect as a witness, Plaintiff would have
prevailed
in
the
Winmar
litigation.
In
the
alternative,
Plaintiff maintains that Defendants breached the duty of care by
3
Beyond the $1.4 million judgment, Plaintiff was also
separately assessed attorneys’ fees; post-judgment interest was
also accruing while the appeal was pending.
Plaintiff
represents that it was facing a final judgment of more than
$3,000,000 if the appeal was unsuccessful.
4
Plaintiff is a corporation organized under the laws of
Qatar with its principal place of business in Qatar. Defendants
are residents of the District of Columbia and Maryland.
The
amount in controversy exceeds $75,000.
6
failing to advise Plaintiff to file suit against the Architect
or
to
join
the
Architect
as
a
defendant
in
the
Winmar
litigation.
After the court denied Defendants’ motion to dismiss (ECF
No. 15), the parties engaged in discovery.
Defendants submitted
the instant motion for summary judgment on April 16, 2016.
No.
91).
Plaintiff
responded
(ECF
No.
99),
and
(ECF
Defendants
replied (ECF No. 102).
II.
Standard of Review
A motion for summary judgment will be granted only if there
exists no genuine dispute as to any material fact and the moving
party
is
entitled
to
judgment
as
a
matter
of
law.
See
Fed.R.Civ.P. 56(a); Celotex Corp. v. Catrett, 477 U.S. 317, 322
(1986);
Anderson
v.
Liberty
Lobby,
Inc.,
477
U.S.
242,
250
(1986); Emmett v. Johnson, 532 F.3d 291, 297 (4th Cir. 2008).
A
dispute about a material fact is genuine “if the evidence is
such
that
a
nonmoving
reasonable
party.”
jury
Liberty
could
return
a
verdict
Lobby,
477
U.S.
at
for
249.
the
In
undertaking this inquiry, a court must view the facts and the
reasonable
inferences
drawn
therefrom
“in
the
light
most
favorable to the party opposing the motion,” Matsushita Elec.
Indus.
Co.
(quoting
v.
United
Zenith
States
Radio
Corp.,
v.
Diebold,
475
U.S.
Inc.,
574,
369
587
U.S.
(1986)
654,
655
(1962)); see also EEOC v. Navy Fed. Credit Union, 424 F.3d 397,
405 (4th Cir. 2005), but a “party cannot create a genuine dispute
7
of
material
fact
inferences.”
through
mere
speculation
or
compilation
of
Shin v. Shalala, 166 F.Supp.2d 373, 375 (D.Md.
2001) (citation omitted).
To prevail on a motion for summary judgment, the moving
party generally bears the burden of showing that there is no
genuine dispute as to any material fact.
No genuine dispute of
material fact exists, however, if the nonmoving party fails to
make a sufficient showing on an essential element of his case as
to which he or she would have the burden of proof.
U.S.
at
322–23.
nonmoving
party
Therefore,
has
the
on
those
burden
issues
of
proof,
Celotex, 477
on
it
which
is
the
his
responsibility to confront the summary judgment motion with an
“affidavit
or
other
evidentiary
showing”
there is a genuine issue for trial.
demonstrating
that
See Ross v. Early, 899
F.Supp.2d 415, 420 (D.Md. 2012), aff’d, 746 F.3d 546 (4th Cir.
2014).
III. Analysis
To succeed on a legal malpractice claim under District of
Columbia law, a plaintiff must show that: (1) the defendant was
employed as the plaintiff’s attorney; (2) the defendant breached
a reasonable duty; and (3) that breach resulted in, and was the
proximate cause of, the plaintiff’s loss or damages.
Martin v.
Ross, 6 A.3d 860, 862 (D.C. 2010) (citing Niosi v. Aiello, 69
8
A.2d 57, 60 (D.C. 1949)).5
“Unless a party has a good cause of
action against the party proposed to be sued, the first party
loses nothing by the conduct of his attorney even though the
latter were guilty of gross negligence.”
Niosi, 69, A.2d at 60.
“[I]f, notwithstanding the negligence, the client had no cause
of action or meritorious defense as the case may be; or [] if
conduct of an attorney with respect to litigation results in no
damage to his client[,] the attorney is not liable.”
Id.
A.
Defendants’ Failure to Depose or Call the Architect as
a Witness
Defendants
begin
by
arguing
that
they
are
entitled
to
summary judgment under Plaintiff’s theory of liability based on
their failure to interview, depose, or call the Architect as a
witness because evidence shows that the alleged failure was not
the proximate cause of Plaintiff’s injuries.
In an attorney
malpractice case, the plaintiff must show that the outcome of
the underlying suit would have been more favorable absent the
alleged
negligence
by
the
attorney.
F.Supp.2d 1, 4 (D.D.C. 2011).
Hickey
v.
Scott,
796
“[I]n most cases, the existence
of proximate cause is a question of fact for the jury, and only
if it is absolutely clear that the defendant’s negligence could
not have been a proximate cause of the harm asserted by the
plaintiff is it a question of law.”
Smith v. Hope Village,
Inc., 481 F.Supp.2d 172, 185 (D.D.C. 2007); see also Hickey, 796
5
As discussed in the court’s previous memorandum opinion on
Defendants’ motion to dismiss, substantive District of Columbia
law applies to the claims in this case. (ECF No. 15, at 7 n.4).
9
F.Supp.2d
at
4
(“Causation
is
normally
a
question
of
fact
Tsai,
the
reserved for the jury.”).
Having
now
taken
the
deposition
of
Mr.
representative of the Architect who certified the payments on
the Winmar project, Defendants contend that his testimony would
merely have supported Judge Kessler’s finding that the certified
Payment Applications were the most reliable and best evidence of
the amount of work that Winmar had performed at the time.
(ECF
No.
Tsai
91,
at
indicating
24).
that
Applications
for
They
his
point
regular
clients
to
testimony
routine
included
“on
in
from
certifying
site
Mr.
Payment
observations”
and
“walk[ing] around the site to see that the work has been done”
and
that
he
“signed
[the
certifications]
believing
that
the
numbers [that Winmar was claiming was due] were correct.” (ECF
No. 91-11, at 2-4).
According to Defendants, calling Mr. Tsai
as a witness only “would have cemented” Judge Kessler’s opinion
about
the
reliability
of
the
certified
Payment
Applications.
(ECF No. 91, at 25).
Plaintiff does not mention Defendants’ failure to depose or
call the Architect as a witness in the causation section of its
opposition to the motion.
to
elsewhere
in
its
The only piece of evidence it points
papers
that
might
refute
Defendants’
causation arguments is that Dennis Janson, the owner of the
Architect, testified that “upon further investigation of those
payments, actually going down to the job site, looking at it
10
again the issue came up that what they were asking for was not
consistent with the state of the project.”
10).
(ECF No. 99-27, at
As Defendants note, however, Mr. Janson later stated that
the
Payment
Applications
were
incomplete,
not
necessarily
incorrect, and that he had “no idea” whether documentation would
have shown that certification was appropriate or not.
(ECF Nos.
102, at 9; 91-25, at 13-14).
None
of
this
testimony
would
have
“rebutt[ed]
the
presumption of the certified Payment Applications’ accuracy by
presenting
evidence
that
they
were
prepared
incorrectly,”
as
Judge Kessler said Plaintiff would have needed to do to change
the outcome of the case.
added).
Mr.
Tsai’s
Winmar, 741 F.Supp.2d at 182 (emphasis
testimony
would
have
supported
the
reliability of the certifications, and Mr. Janson’s testimony
would merely have restated the Architect’s ambiguous assertion
that the Payment Applications were not valid – something the
Architect’s
reasonable
rescissions
jury
could
had
find
already
that
the
expressed.
combined
Thus,
testimony
no
from
these two representatives of the Architect would have altered
Judge
Kessler’s
analysis
of
the
case
in
Plaintiff’s
favor.
Defendants’ decisions not to depose the Architect and not to
call the Architect as a witness, even if negligent, did not
cause
Plaintiff’s
losses.
Defendants’
judgment will therefore be granted in part.
11
motion
for
summary
B.
Defendants’ Failure to Advise Plaintiff to Sue the
Architect
Defendants next argue that Plaintiff cannot survive summary
judgment on its alternate theory that they should have advised
it
to
sue
theory
of
the
Architect.
malpractice,
a
Unlike
claim
Plaintiff’s
based
on
trial
failure
conduct
to
advise
Plaintiff to sue is not dependent on the outcome of the Winmar
case.
Rather, to show malpractice for failure to advise it to
sue, Plaintiff must demonstrate that it had a viable cause of
action and that Defendants did not advise pursuing that cause of
action.
Macktal v. Garde, 111 F.Supp.2d 18, 21 (D.D.C. 2000);
Niosi, 69 A.2d at 60.
This requires the court to evaluate the
viability of the unpursued claim, “the so-called ‘case within
the case[,]’ to determine if it was a good cause of action.”
Macktal, 111 F.Supp.2d at 21.
On Defendants’ instant summary
judgment motion, then, Plaintiff must show some evidence that it
had a viable claim against the Architect.
1.
The Case Within the Case
“The elements of an action for professional negligence are
the
same
plaintiff
as
those
bears
of
the
an
ordinary
burden
of
negligence
presenting
action.
evidence
‘The
which
establishes the applicable standard of care, demonstrates that
this
standard
has
been
violated,
and
develops
a
causal
relationship between the violation and the harm complained of.’”
O'Neil
v.
Bergan,
452
A.2d
337,
341
(D.C.
1982)
(quoting
Morrison v. MacaNamara, 407 A.2d 555, 560 (D.C. 1979)).
12
In a
negligence action against the Architect, then, Plaintiff would
have had to show: (1) that the Architect owed it a duty of care;
(2) that the Architect breached that duty when it certified the
Payment Applications; and (3) that the certification was the
proximate
cause
of
an
injury
or
damages
to
Plaintiff.
The
contractual relationship between the Architect and the Plaintiff
clearly imposed a duty of care, but the parties dispute the
other two elements of Plaintiff’s putative claim.
a.
The Architect’s Breach
Plaintiff alleges that the Architect breached its duty of
care by certifying the Payment Applications even though they did
not
accurately
completed.
reflect
the
amount
(ECF No. 50 ¶ 18).
of
work
that
had
been
It has produced expert testimony
from another architect who stated in his report that “Winmar in
fact did not complete the work it claimed to have completed at
the time that it issued the payment applications,” and that the
“Architect’s
certification
of
the
payment
applications
under
these circumstances breached the duty of care the Architect owed
to [Plaintiff]]” (ECF No. 99-85, at 4).
witness’s
testimony
therefore
meets
Plaintiff’s expert
Plaintiff’s
burden
with
regard to the breach element of a potential claim.
Defendants make two arguments that attack the viability of
the underlying claim on the element of the Architect’s breach of
duty.
First,
Defendants
aver
that
Judge
Kessler’s
opinion
collaterally estops Plaintiff from disputing the validity of the
13
certifications.
to
blame
for
Defendants assert that, so long as they are not
Plaintiff’s
failure
in
the
Winmar
litigation,
Plaintiff is “bound by the factual conclusion made by Judge
Kessler that the certified Payment Applications were reliable
and
the
Winmar.”
best
evidence
of
the
amount
(ECF No. 91, at 49).
of
work
performed
by
Collateral estoppel bars a
subsequent court from revisiting the “determination of an issue
of fact or law when (1) the issue is actually litigated and (2)
determined by a valid, final judgment on the merits; (3) after a
full and fair opportunity for litigation by the parties or their
privies;
(4)
under
circumstances
essential to the judgment.”
where
the
determination
was
Modiri v. 1342 Restaurant Group,
Inc., 904 A.2d 391, 394 (D.C. 2006).
Defendants acknowledge, as the court pointed out in its
memorandum opinion on Defendants’ motion to dismiss, that use of
collateral estoppel would be unfair if “an unfavorable judicial
decision allegedly wrought by their legal malpractice can be
used as a shield against a legal malpractice claim.”
15, at 11).
(ECF No.
Because the evidence now shows that their trial
conduct was not the cause of the unfavorable decision below,
however,
they
now
contend
that
the
court’s
findings
that
certifications were reliable means that Plaintiff cannot dispute
that the Architect was not acting negligently when it made them.
(ECF No. 102, at 24).
14
Although
Judge
Kessler’s
opinion
refers
to
the
certifications as “reliable and accurate evidence of the work
completed,” her analysis demonstrates that she was evaluating
the certifications relative to the other evidence in front of
her and in the absence of facts about the Architect’s process.
As this court found in its prior opinion, “Judge Kessler only
presumed
that
the
Architect’s
(ECF No. 15, at 10).
certifications
were
credible.”
She determined that the certified payment
applications were the best evidence presented to that court but
made no determination as to whether the certifications were made
with reasonable care.
Nor was she in any position to do so
without ever hearing from the Architect; as her opinion noted,
she
found
it
perplexing
that
neither
party
ever
called
the
Architect as a witness.
Winmar, 741 F.Supp.2d at 182 n.17.
Judge
that
Kessler
determined
the
certifications
were
valid
under the Contract despite the Architect’s rescissions, with the
caveat that Plaintiff “offered no evidence at trial showing how
the Architect arrived at the decision to certify the Payment
Applications.”
that
Plaintiff
See id. at 182.
might
have
She specifically pointed out
rebutted
the
accuracy
of
the
certifications “by presenting evidence that they were prepared
incorrectly,” but that it failed to do so.
Id.
Had Plaintiff
filed a claim in the suit against the Architect, the parties
might have presented evidence – like that of Plaintiff’s expert
witness here - rebutting Judge Kessler’s assumption that “if
15
there was any bias in the Architect’s decision to certify the
Payment Applications, . . . it would have been in [Plaintiff’s]
favor.”
Id. at 181.
Judge Kessler’s opinion thus does not
preclude consideration of Plaintiff’s evidence on the issue of
“how the Architect arrived at the decision to certify.”
Second, Defendants contend that finding the Architect to
have
breached
its
duty
would
be
logically
inconsistent
with
Judge Kessler’s holdings that the certified Payment Applications
were the best evidence.
of
Defendants’
This argument is simply a reformulation
collateral
estoppel
argument.
Because
the
parties did not present Judge Kessler with any evidence as to
the
Architect’s
certification
certifications
at
sufficient
create
to
face
a
process,
value.
dispute
she
accepted
Plaintiff’s
of
fact
over
those
evidence
is
whether
the
Architect breached its duty of care.
b.
Proximate Cause and The Architect’s Rescissions
As noted above, proximate cause is typically a question for
the jury and should only be determined on summary judgment where
“it is absolutely clear.”
Smith v. Hope Village, Inc., 481
F.Supp.2d 172, 185 (D.D.C. 2007).
Architect’s
breach
was
distinguishable, injuries.
the
Plaintiff contends that the
cause
of
two
related,
but
First, the Architect’s certification
established a debt that Plaintiff was obligated to pay to Winmar
under the Contract.
According to Plaintiff, the work certified
in the Payment Applications was not completed, and therefore the
16
Architect’s negligent certification put them in the untenable
position of paying Winmar money it had not earned or breaching
its contract by not making payments that had been certified.6
Plaintiff argues that its ensuing breach of contract caused the
Winmar case, and, therefore, the Architect is liable for all
costs connected to the litigation.
Then, the certification by
the Architect was accepted by Judge Kessler as the best evidence
in the Winmar litigation, which Plaintiff argues caused it a
second harm, higher damages than it would have had to pay had
the Payment Applications not been certified.
Plaintiff’s expert
testified that, but for the certifications, Winmar would have
owed Plaintiff money – rather than vice versa - when Plaintiff
terminated the Contract.
(ECF No. 99-85, at 4).
This evidence
is sufficient to create a dispute of fact as to whether the
Architect’s breach was the proximate cause of its damages.
Defendants argue that any negligence by the Architect was
not
the
proximate
cause
of
Plaintiff’s
Architect rescinded the certifications.
Defendants
maintain
that
“even
if
injuries
because
the
(ECF No. 91, at 43-44).
the
certifications
were
improvidently issued in the first place, they could not have
injured Plaintiff[]” because the rescissions would have undone
any harm.
(Id.).
According to Defendants, Judge Kessler erred
by holding that the rescissions were not authorized under the
6
Plaintiff also alleges to have suffered
making the single payment that it did make.
17
an
injury
by
Contract, which they would have proven on appeal had Plaintiff
not settled the suit.
appellate
court
had
See Winmar, 741 F.Supp.2d at 182.
honored
the
rescissions,
If the
they
aver,
Plaintiff would not have suffered any injury.
Defendants have not shown that it is absolutely clear that
the Architect did not cause harm to Plaintiff.
First, even if
Judge Kessler was wrong about the Contract and the rescissions,
Plaintiff has argued that the certifications caused the Winmar
litigation.
Put another way, the litigation, and the costs
accompanying
it,
were
an
injury
caused
by
the
Architect
no
matter its outcome – and, in turn, regardless of Judge Kessler’s
interpretation of the Contract.
As Plaintiff points out, the
rescissions came well after the three day window it had to make
the
payments
or
else
be
Defendants knew well.
rescission
may
have
in
breach
of
the
Contract,
(See ECF No. 99, at 9-10).
been
an
effort
to
“reduce
a
fact
In short,
a
client’s
damages, [but does] not necessarily prove that the [] negligence
did not injure the client.”
Knight v. Furlow, 553 A.2d 1232,
1235 (D.C. 1989).
Moreover, there is also a dispute of fact as to whether
Judge
Kessler
Although
erred
Defendants
in
are
her
interpretation
correct
that
the
of
the
Claims
Contract.
process
articulated in Section 4 of the Contract gives the Architect the
power to demand “a response with supporting data from the other
party” and to “approve the Claim” (ECF No. 91-6, at 20-21),
18
Defendants have not proven that the Architect was responding to
a
Claim
under
the
Contract.
The
Architect
rescinded
its
certification of the payments on January 5, 2006 (ECF No. 9921), more than a month before Plaintiff sent its claim letter to
the
Architect
on
February
24.
(ECF
No.
91-13).7
If
the
Architect rescinded outside of the claims process, it could only
have
done
reasons
so,
for
as
Judge
rescission
Kessler
of
a
also
not
clear
whether
for
previously
one
issued
of
the
valid
certification
(See ECF No. 91-7, at 2-3).8
articulated in Section 9.5.1.
is
held,
a
claim
could
be
made
after
It
the
7
Although Judge Kessler referred to this as a “formal
claim,” there may be some ambiguity even in the letter. Winmar,
741 F.Supp.2d at 177.
The letter references Sections 4.3-4.4,
the Claims sections, and Section 4.2.11 of the Contract, which
gives the Architect power to “decide matters concerning
performance under and requirements of the Contract.” (91-6, at
19).
Plaintiff had already terminated the Contract for
convenience at the time of the letter, which would have
triggered Section 14.4.3’s requirement that Winmar was “entitled
to receive payment for work executed,” which, in turn, might
have required the Architect’s review under 4.2.11 as opposed to
4.3 or 4.4.
8
In a footnote in their reply brief, Defendants also argue
that the rescissions were valid under Section 9.5.1.4, which
permits rescission because of “reasonable evidence that the Work
cannot be completed for the unpaid balance of the Contract Sum.”
(ECF No. 102, at 22).
In the rescission letter, the Architect
made no reference to concerns about completing the project on
budget, but Defendants argue that the Architect’s reference to a
$140,000 overcharge meant that “the Work clearly could not be
completed ‘for the unpaid balance.’”
(Id.)
They offer no
evidence to support this contention other than a vague response
from Plaintiff’s expert that such a discrepancy was “possibly a
basis for rescission” (ECF No. 102-2, at 144 (emphasis added)),
and thus have not shown that there is no material dispute over
whether the rescission was valid under the provisions of Section
9.5.1.
19
termination of the Contract.
(See, e.g., ECF No. 91-6, at 19
(Section 4.3.3. requiring that the contractor proceed diligently
and the owner continue to make payments during the pendency of a
claim, which at least suggests that claims would be occurring as
part of an ongoing contract)).
If the rescissions were not
based on a claim, Judge Kessler’s opinion not to consider them
valid under the Contract could have been correct.9
Given all of
these disputed facts, Defendants have not shown that they are
entitled to summary judgment in spite of Plaintiff’s evidence of
a claim against the Architect.
2.
Plaintiff’s Instructions Not to Sue
Defendants next argue that, to the degree that Plaintiff
had a case against the Architect, it specifically directed them
not to sue.
They contend that, although it was obvious that
Plaintiff had a potential cause of action against the Architect,
Plaintiff told them not to sue the Architect, presumably because
of
their
ongoing
working
relationship
–
Plaintiff
and
the
Architect were working on numerous projects together worldwide
9
It is also unclear that the certification would not have
done harm, even if Judge Kessler had accepted the rescissions.
Judge Kessler may have simply found the rescissions less
persuasive than the certifications as to the value of the work
done.
Judge Kessler’s opinion was based on two separate
theories of damages, one for breach of contract and one for
restitution for work done.
In an effort to determine how much
work was actually done, then, she might have considered the
certifications
as
evidence
even
if
they
had
not
been
contractually binding, and, in turn, might have given the
precise numeric information in the certifications more weight
than
the
rescissions,
which
were
based
only
on
vague
“discrepancies” and missing documentation.
20
at the time.
(ECF No. 91, at 41).
They point to a declaration
from Gary Napier, the primary on-site coordinator for Plaintiff,
who specifically stated that Plaintiff made the decision not to
sue the Architect and communicated that decision to Defendants.
(Id.).
Plaintiff
disputes
the
veracity
of
this
instruction,
pointing out that Mr. Napier’s declaration does not identify who
exactly
gave
this
instruction
to
individual had authority to do so.
whom,
and
whether
that
(ECF No. 99, at 31-32).
Moreover, it argues that Defendants appear to be relying on
conversations that do not account for the changes in the Winmar
dispute.
It points to testimony from Mr. Napier stating that
the decision he referred to was made at a meeting in June 2006.
(See, e.g., ECF No. 99-9, at 14).
In June 2006, before QNB had
initiated the Winmar litigation, Plaintiff and Defendants had
agreed not to sue the Architect, or Winmar for that matter,
because
they
believed
the
amount
at
stake
was
only
about
$80,000, which was owed to them, and the cost to pursue it might
have been “lost in legal fees.”
13).
(ECF Nos. 99, at 27; 99-9 at
When Winmar’s third party claim against Plaintiff occurred
in November 2006, Plaintiff went from potentially being owed
$80,000, to potentially owing more than $1.7 million.
argues
that
Defendants
had
a
duty
to
reevaluate
options and their legal advice at that time.
27).
Plaintiff
Plaintiff’s
(ECF Nos. 99, at
Defendants attempt to rebut this notion by pointing to a
21
treatise on legal malpractice, which states that the extent of a
duty “derives from the circumstances, being the subject matter
of
the
retention
and
the
parties’
agreement.”
1
Ronald
E.
Mallen & Allision M. Rhodes, Legal Malpractice, § 8:5 (2016).
But as Plaintiff points out, the subject matter of the retention
changed
when
they
went
from
potential
plaintiffs
in
a
suit
against Winmar to defendants in a litigation with much larger
consequences.
re-assess
Defendants’ obligation was not to “continually
whether
a
claim
should
be
brought
against
the
Architect” (ECF No. 102, at 18), but when Plaintiff was sued and
it hired Defendants to defend it against the Winmar suit, they
had a duty to advise Plaintiff on how to mitigate its losses
under the circumstances.
A reasonable jury could find that this
duty would include an obligation to advise Plaintiff that a suit
against the Architect was in its best interest.
Defendants make a last ditch effort to argue that they did
advise Plaintiff to sue by pointing to a statement made to the
mediator in the Winmar litigation in which they noted that “the
Architect failed to perform many of its obligations under the
Contract, . . . [but] no action or claim ha[d] been asserted
against the Architect in connection with the Contract,” which
they say called to Plaintiff’s attention the fact that claims
against the Architect had not been asserted.
6).
(ECF No. 91-30, at
The question is not whether Plaintiff was aware that it
might have had a claim against the Architect, but rather whether
22
Defendants advised Plaintiff to pursue such a claim or discussed
the possibility with them in the way that a reasonable attorney
would.
Ambiguous
addressed
to
third
statements
parties
made
are
in
attachments
insufficient
to
that
show
are
that
Defendants are entitled to summary judgment.10
3.
Statute of Limitations
Finally, Defendants assert that even if Plaintiff had a
valid
claim
against
the
Architect,
their
failure
to
advise
Plaintiff to sue was not the cause of its failure to sue because
Plaintiff hired new counsel within the statute of limitations
period of its claims against the Architect.
Defendants contend
that the three-year statute of limitations had not run when new
counsel began representing Plaintiff in July 2012.
at 56).
(ECF No. 91,
They base this argument on the premise that Plaintiff
“suffered no injury from the Architect’s alleged certification
errors, and thus no legal harm occurred, until Judge Kessler
chose, in preference to all of the other evidence offered at
trial, to rely upon the Architect’s rescinded certifications as
proof of the amount of work that Winmar had completed prior to
the termination for convenience.”
10
(Id. at 55).
According to
Defendants further point to the statement submitted by
Winmar to the mediator, which stated that “if [Plaintiff] had a
problem with their Architect, it would seem as though they might
need to be a party to this action or, at least seek some sort of
redress against the Architect.”
(ECF No. 91-31, at 8).
Although this type of statement seems closer to actual advice
than Defendants’ own statement, it was made by Winmar, an
opposing party, to the mediator, and thus has no bearing on what
Defendants advised Plaintiff to do in this matter.
23
Defendants, then, the limitations period did not begin to run
until, “at the earliest, those findings of fact were made on
September 29, 2010, or, at the latest, upon issuance of final
judgment on March 13, 2012.”
(Id. at 56).
Defendants cite to
Wagner v. Sellinger, 847 A.2d 1151 (D.C. 2004), to support their
contention that a claim does not accrue in a malpractice suit
until the plaintiff had suffered actual injury by losing the
underlying
suit.
There,
the
District
of
Columbia
Court
of
Appeals stated:
If that potential is not realized until
later — if its occurrence depends on “a
contingent or future event” — then the
injury is not sustained until the contingent
or future event occurs. . . . That is to
say, until the lawsuit is resolved (either
by verdict or ruling in court or by
settlement), the injury remains uncertain or
inchoate.
Id. at 1156.
In Wagner, the defendant lawyers represented the
plaintiff in a medical malpractice suit, but were fired during
the suit.
Id. at 1153.
The defendants’ discovery efforts had
apparently been woefully inadequate, but the court held that
“[n]o injury allocable to Sellinger’s apparent negligence could
be ascertained unless and until the Wagners — using competent
counsel to resurrect their medical malpractice claim — failed
nonetheless
to
recover
damages
from
the
medical
defendants.”
Id. at 1153, 1156.
Wagner dictates that Plaintiff here could not have brought
a claim against Defendants until their errors caused injury,
24
which, indeed, depended on the outcome of the case.
It does
not, however, suggest that Plaintiff could not have brought a
potential
against
negligence
the
suit
lawyer
in
against
Wagner
the
came
Architect.
to
fruition
The
claim
during
the
underlying litigation; as the court said, “Typically, therefore,
a potential — not actual — injury has occurred when a client
claims
that
an
attorney
has
mishandled
a
lawsuit
still
in
progress by failing to take appropriate discovery or by making
some other error that, however egregious, does not conclude the
lawsuit.”
Id. at 1156 (emphasis added).
Here, the Architect’s
negligence occurred prior to the lawsuit, and allegedly, was the
cause
of
Winmar’s
suit
against
Plaintiff.
This
case
is
therefore much more like the ones “when an attorney negligently
drafts a document . . . that fails to protect the client’s
interests,” under which, the Wagner court stated, an injury is
realized at the time of the error.
Id. at 1157 n.9.
In cases where the negligence is the alleged cause of the
underlying suit, the District of Columbia courts have clearly
stated that the “attorney’s fees and costs expended as a result
of [the negligent act] constitute legally cognizable damages for
purposes of stating a claim.”
1235
(D.C.
1989).
As
the
Knight v. Furlow, 553 A.2d 1232,
Knight
court
clarified,
where
litigation ensues because of a third party’s negligent act, an
injury
has
occurred,
even
if
the
litigation
is
“ultimately
successful for the client, [if it] could have been avoided by
25
adherence to a proper standard of care.”
Id.
Thus, while
success in the litigation “undoubtedly will reduce a client’s
damages, it will not necessarily prove that the [] negligence
did not injure the client.”
limitations,
then,
Id.
Plaintiff
For the sake of the statute of
would
have
suffered
an
alleged
injury due to the Architect’s negligent certifications when it
began to incur legal fees as a result of Winmar’s third-party
claim against it, which was filed on November 9, 2006.
That
claim was time-barred by Novemeber of 2009, well before new
counsel
took
over,
and
Defendants
cannot
justify
summary
judgment in their favor based on the appointment of new counsel
in 2012.
IV.
Conclusion
For the foregoing reasons, the motion for summary judgment
filed by Defendants will be granted in part and denied in part.
A separate order will follow.
/s/
DEBORAH K. CHASANOW
United States District Judge
26
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?