Ariosa & Company LLC v. All State Construction, Inc. et al
Filing
18
MEMORANDUM OPINION. Signed by Chief Judge Deborah K. Chasanow on 6/12/14. (sat, Chambers)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MARYLAND
:
United States of America for
the use and benefit of ARIOSA & :
COMPANY, LLC
:
v.
:
Civil Action No. DKC 13-3560
:
ALL STATE CONSTRUCTION, INC.,
et al.
:
MEMORANDUM OPINION
Presently pending and ready for resolution in this case
arising under the Miller Act is a motion to dismiss filed by
Defendant SEI Group, Inc. (“SEI”).
(ECF No. 7).
The relevant
issues have been briefed and the court now rules pursuant to
Local Rule 105.6, no hearing being deemed necessary.
For the
reasons that follow, the motion will be denied.
I.
Background
A.
Factual Background
The following facts are set forth in the complaint.
No. 1).
(ECF
On or about October 22, 2012, SEI entered into a
contract with the United States government for the construction
of a “Helium Recovery Plant” in Gaithersburg, Maryland (“the
project”).
(Id. at ¶ 14).
As required under the Miller Act,
SEI furnished performance and payment bonds to the government
naming
Defendant
The
Guarantee
Company
of
North
America
USA
(“Guarantee”) as the surety on the project.1
The payment bond
provided that SEI and Guarantee were “jointly and severally”
liable for the penal sum of the bond.
(ECF No. 1-8, at 3).
SEI subcontracted with Defendant All State Construction,
Inc.
(“All
subcontract
State”),
with
which,
Plaintiff
in
turn,
Ariosa
&
entered
Company,
into
LLC,
a
“for
subthe
performance of work and the furnishing of labor and materials
for completion of the installation of [a] mechanical component
(ECF No. 1 ¶ 9).2
structure” of the project.
According to the
complaint, Plaintiff fulfilled its obligations under the subsubcontract,
extras
and
“provid[ing]
change
all
orders,
.
labor
.
.
and
in
materials,
a
safe,
workmanlike manner . . . at substantial expense.”
10).
including
careful
and
(Id. at ¶
At some point, however, “[t]he project was stopped as a
1
The complaint names the surety as “The Guaranty Company of
North America USA,” but the attached bonds indicate the proper
name is “The Guarantee Company of North America USA.” (ECF No.
1-8, at 2).
Performance bonds required under the Miller Act
“protect the government if the contractor fail[s] to complete a
contract,” while payment bonds “protect ‘all persons supplying
labor and material in carrying out the work provided for in the
contract.’” In re ESA Environmental Specialists, Inc., 709 F.3d
388, 391 n. 1 (4th Cir. 2013) (quoting 40 U.S.C. § 3131(b)).
2
Civil actions brought under the Miller Act must be brought
“in the name of the United States for the use of the person
bringing the action.”
40 U.S.C. § 3133(b)(3)(A).
The actual
plaintiff in this case is, therefore, the United States of
America for the use and benefit of Ariosa & Company, LLC. For
ease of exposition, the court refers to Ariosa as Plaintiff
throughout.
2
result of [SEI’s] attempts to supply equipment not compliant
with
the
specifications
required
by
the
United
States
government, namely a helium liquefier and associated equipment
manufactured within the United States.”
(Id. at ¶ 17).
result,
costs
which
Plaintiff
included
materials”
it
subcontract.
“incurred
“heating,
had
substantial
cooling,
purchased
(Id. at ¶ 19).
in
and
and
related
accordance
As a
expenses,”
equipment
with
the
and
sub-
Plaintiff asserts that it has “not
been paid the monies due and owing for its performance” and that
there
is
“a
contractual
balance
due
of
$72,326.00,
plus
additional demobilization costs, lost profits, other damages and
expenses totaling $65,280.00, for a total amount of loss of
$137,515.00.”
B.
(Id. at ¶ 20).
Procedural Background
Plaintiff
commenced
this
action
on
November
25,
2013,
bringing separate counts against All State, SEI, Guarantee, and
CNA Surety, d/b/a Western Surety Company – the surety on bonds
furnished by All State – asserting jurisdiction under the Miller
Act, 40 U.S.C. §§ 3131 et seq., and seeking a judgment against
all
defendants
in
the
amount
attorneys’ fees and costs[.]”
of
“$137,515.00
plus
(ECF No. 1 ¶ 12).
interest,
On February
28, 2014, SEI filed the pending motion to dismiss the second
count of the complaint, the sole count against it, pursuant to
Fed.R.Civ.P. 12(b)(6).
(ECF No. 7).
3
Plaintiff filed a response
in opposition on March 21 (ECF No. 15) and SEI filed a reply on
April 7 (ECF No. 16).
II.
Standard of Review
The purpose of a motion to dismiss under Rule 12(b)(6) is
to test the sufficiency of the complaint.
Charlottesville,
464
F.3d
480,
483
Presley v. City of
(4th
Cir.
2006).
A
plaintiff’s complaint need only satisfy the standard of Rule
8(a), which requires a “short and plain statement of the claim
showing that the pleader is entitled to relief.”
8(a)(2).
Fed.R.Civ.P
“Rule 8(a)(2) still requires a ‘showing,’ rather than
a blanket assertion, of entitlement to relief.”
v. Twombly, 550 U.S. 544, 555 n. 3 (2007).
Bell Atl. Corp.
That showing must
consist of more than a “formulaic recitation of the elements of
a cause of action” or “naked assertion[s] devoid of further
factual enhancement.”
Ashcroft v. Iqbal, 556 U.S. 662, 678
(2009) (internal quotation marks omitted).
At this stage, the court must consider all well-pleaded
allegations in a complaint as true, Albright v. Oliver, 510 U.S.
266, 268 (1994), and must construe all factual allegations in
the
light
most
favorable
to
the
plaintiff,
see
Harrison
v.
Westinghouse Savannah River Co., 176 F.3d 776, 783 (4th Cir.
1999) (citing Mylan Labs., Inc. v. Matkari, 7 F.3d 1130, 1134
(4th
Cir.
1993)).
The
court
unsupported legal allegations.
need
not,
however,
accept
Revene v. Charles Cnty. Comm’rs,
4
882 F.2d 870, 873 (4th Cir. 1989).
Nor must it agree with legal
conclusions couched as factual allegations, Ashcroft v. Iqbal,
556 U.S. 662 (2009), or conclusory factual allegations devoid of
any reference to actual events, United Black Firefighters v.
Hirst,
604
F.2d
844
(4th
Cir.
1979);
see
also
Giacomelli, 588 F.3d 186, 193 (4th Cir. 2009).
Francis
v.
“[W]here the
well-pleaded facts do not permit the court to infer more than
the mere possibility of misconduct, the complaint has alleged,
but it has not ‘show[n] . . . that the pleader is entitled to
relief.’”
8(a)(2)).
Iqbal,
556
U.S.
at
679
(quoting
Fed.R.Civ.P.
Thus, “[d]etermining whether a complaint states a
plausible claim for relief will . . . be a context-specific task
that
requires
the
reviewing
experience and common sense.”
court
to
draw
on
its
judicial
Id.
III. Analysis
The Miller Act requires a general contractor on a federal
construction project of more than $100,000 to furnish, inter
alia,
a
payment
bond
“for
the
protection
of
all
persons
supplying labor and materials in carrying out the work provided
for in the contract.”
40 U.S.C. § 3131(b)(2).
“The Act further
provides that any person who furnishes labor or materials for
such a bonded project and has not been paid may sue on the bond
for the amount due,” but recovery is limited “to first- and
second-tier subcontractors.”
Datastaff Technology Group, Inc.
5
v. Centex Const. Co., Inc., 528 F.Supp.2d 587, 592-93 (E.D.Va.
2007) (citing 40 U.S.C. § 3133).
Pursuant to § 3133(b)(2), a
second-tier subcontractor is required to provide written notice
to the general contractor within ninety days of the date it last
performed the labor or supplied the materials that form the
basis of its Miller Act claim.
To state a claim under the Miller Act, the plaintiff must
set forth facts showing that “(1) it has furnished labor or
material in carrying out work provided for in a contract for
which a payment bond is furnished[;] . . . and (2) it has not
been paid in full within 90 days.”
U.S. ex rel. Tenn. Valley
Marble Holding Co. v. Grunley Constr., 433 F.Supp.2d 104, 114
(D.D.C.
2006)
statute
is
construed
those
to
whose
(internal
“highly
remedial
“effectuate
labor
citation
and
the
in
and
marks
nature”
Congressional
materials
go
into
omitted).
and
is
intent
public
The
liberally
to
protect
projects.”
Clifford F. MacEvoy, Co. v. U.S. for Use & Benefit of Calvin
Tomkins Co., 322 U.S. 102, 107 (1944).
SEI argues that dismissal is warranted because it “does not
have any contractual obligations to Plaintiff by virtue of the
contract by and between All State and Plaintiff.”
at 4).
(ECF No. 7-1,
In other words, SEI suggests that it could only be
liable under the Miller Act if it were in direct contractual
privity
with
Plaintiff.
This
6
argument
is
belied
by
the
statutory
language,
which
expressly
authorizes
“[a]
person
[i.e., Plaintiff] having a direct contractual relationship with
a
subcontractor
[i.e.,
All
State]
but
no
contractual
relationship, express or implied, with the contractor furnishing
the payment bond [i.e., SEI] [to] bring a civil action on the
payment bond on giving written notice to the contractor within
90 days from the date on which the person did or performed the
last of the labor or furnished or supplied the last of the
material for which the claim is made.”
40 U.S.C. § 3133(b)(2).
There appears to be no dispute that Plaintiff is a second-tier
subcontractor; thus, assuming it provided the requisite notice
and filed its claim in a timely manner, it has a right to
recover
labor
and
material
costs
expended
under
the
sub-
subcontract.
Insofar as the statute permits an action to be brought “on
the payment bond,” courts generally agree that a surety may be
sued directly and that a general contractor, such as SEI, is not
an indispensable party.
See United States ex rel. Henderson v.
Nucon Contr. Corp., 49 F.3d 1421, 1423 (9th Cir. 1995) (citing
United States ex rel. Hudson v. Peerless Ins. Co., 374 F.2d 942,
945 (4th Cir. 1967)).
The specific basis of liability as to a
general contractor is somewhat less clear.
Some courts have
simply relied on the fact that “nothing [in the Miller Act]
prevents
a
sub-subcontractor
from
7
also
suing
the
prime
contractor or the subcontractor,” U.S. ex rel. Polied Envtl.
Servs.,
Inc.
v.
Incor
Grp.,
Inc.,
238
F.Supp.2d
456,
460
(D.Conn. 2002); see also U.S. ex rel. Thyssenkrupp Safway, Inc.
v.
Tessa
Structures,
LLC,
No.
1:10cv512
(JCC/JFA),
2011
WL
1627311, at *3 (E.D.Va. Apr. 27, 2011), while others have cited
language in the payment bond establishing that the principal and
surety are jointly and severally liable, see United States ex
rel. Apex Roofing and Insulation, Inc. v. Union Indemnity Ins.
Co., 865 F.2d 1226, 1227 (11th Cir. 1989).
As noted, the payment
bond in this case provides that Guarantee and SEI are jointly
and severally liable for payment of the penal sum.
8, at 3).
(ECF No. 1-
Thus, the record supports that SEI was properly named
as a defendant.
On the other hand, to the extent that Plaintiff sought to
bring a common law tort or third party beneficiary claim, as
suggested
support
in
its
opposition
liability.
To
papers,
state
a
the
claim
complaint
for
does
not
negligence,
the
plaintiff must allege that the defendant owed a duty of care,
see Iodice v. United States, 289 F.3d 270, 281 (4th Cir. 2002)
(“a negligence claim must disclose that each of the elements is
present
in
order
to
be
sufficient”),
asserted in Plaintiff’s complaint.
and
no
such
duty
is
Plaintiff also suggests that
SEI’s conduct amounted to fraud, but a fraud claim is subject to
the heightened pleading standard of Fed.R.Civ.P. 9(b) and the
8
plaintiff must assert that the defendant knowingly made a false
representation of, or concealed, a material fact for the purpose
of
defrauding
it.
See
SpinCycle,
Inc.
v.
Kalender,
186
F.Supp.2d 585, 590 (D.Md. 2002) (quoting Alleco, Inc. v. Harry &
Jeanette Weinberg Foundation, Inc., 340 Md. 176, 195 (1995)).
Plaintiff’s
complaint
does
not
identify
any
alleged
misrepresentation or omission by SEI, let alone set forth facts
supporting a fraudulent intent.
Finally, Plaintiff cannot show
that it was an intended third party beneficiary of the SEI/All
State subcontract.
“To prevail on a third party beneficiary
theory, the [third party] ‘must allege and prove that the intent
of the [parties to the contract] to benefit the [third party]
was
a
direct
purpose
of
the
transaction
or
relationship.”
Fields v. Walpole, Civ. No. DKC 11-100, 2011 WL 2669401, at *4
(D.Md. July 6, 2011) (quoting Flaherty v. Weinberg, 303 Md. 116,
130 (1985)).
Plaintiff does not allege that the SEI entered
into the All State subcontract for its benefit, nor could it do
so under these facts.
liability
under
a
tort
Thus, the complaint does not support
or
third
party
beneficiary
theory.
Because Plaintiff does state a valid claim under the Miller Act,
however, SEI’s motion will be denied.
9
IV.
Conclusion
For the foregoing reasons, the motion to dismiss filed by
SEI Group, Inc. (ECF No. 7), will be denied.
A separate order
will follow.
________/s/_________________
DEBORAH K. CHASANOW
United States District Judge
10
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?