United States of America for the Use and Benefit of James Communication, Inc. et al v. LACO Electric, Inc. et al
Filing
47
MEMORANDUM OPINION. Signed by Judge Deborah K. Chasanow on 3/27/2015. (sat, Chambers)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MARYLAND
:
UNITED STATES OF AMERICA FOR THE
USE AND BENEFIT OF JAMES
:
COMMUNICATION, INC., et al.
:
v.
:
Civil Action No. DKC 14-0946
:
LACO ELECTRIC, INC., et al.
:
MEMORANDUM OPINION
Presently pending and ready for resolution in this breach
of contract dispute is an unopposed motion for partial summary
judgment
filed
by
(“Plaintiff” or “JCI”).
Plaintiff
James
(ECF No. 25).
hearing being deemed necessary.
Communication,
Inc.
The court now rules, no
Local Rule 105.6.
For the
following reasons, Plaintiff’s motion will be granted, but the
request
for
prejudgment
interest
will
be
denied
without
prejudice to renewal.
I.
Background
Defendant John C. Grimberg Co., Inc. (“Grimberg”) entered
into a contract with the United States Army Corps of Engineers
regarding the design and construction of an Emergency Services
Center located in Fort Detrick, Maryland.
(ECF No. 23 ¶ 13).
Grimberg then entered into a subcontract with Defendant LACO,
Electric, Inc. (“LACO”) for the purchase and installation of
certain electrical and telecommunication systems for the Fort
Detrick
project.
contracted
with
(Id.
¶
Plaintiff
15).
to
On
January
provide
the
systems for the Fort Detrick Project.
17,
2011,
LACO
telecommunications
Under the terms of the
purchase order (“FTD Purchase Order”), LACO was required to pay
Plaintiff $194,969.48 for materials and services in providing
the
telecommunications
system
for
the
(See ECF No. 25-1, purchase order).
obligations
under
the
purchase
Fort
Detrick
Plaintiff performed its
order
on
May
25,
2013,
invoiced LACO throughout the performance of its work.
25-2 ¶¶ 7-8).
and
(ECF No.
Plaintiff asserts that it demanded payment from
LACO and Grimberg in June 2013.
that
Project.
Plaintiff
perform
On June 8, 2013, LACO requested
additional
work
on
the
Fort
Detrick
Project, and agreed to pay Plaintiff $1,000 for the extra work
(“FTD Change orders”).
(See ECF No. 25-2 ¶ 10; ECF No. 11 ¶¶
22-23, LACO’s answer).
Plaintiff performed the additional work
and again demanded payment from LACO and Grimberg for the FTD
Purchase Order and the FTD Change Orders.
On March 26, 2014, Plaintiff filed the instant complaint,
naming as defendants LACO, Grimberg, and Hartford, among others.
(See ECF No. 1).
The complaint asserts seven causes of action,
although Plaintiff has since voluntarily dismissed two counts of
the complaint.
(See ECF No. 9).
On August 11, 2014, Plaintiff
moved for partial summary judgment only as to the breach of
2
contract
claim
complaint.
against
Defendant
(See ECF No. 25).
LACO
in
count
two
of
the
LACO did not oppose the motion.
On March 26, 2015, Plaintiff filed a supplement to its motion
for partial summary judgment.
II.
(ECF No. 46).
Standard of Review
It is well established that a motion for summary judgment
will be granted only if there exists no genuine issue as to any
material fact and the moving party is entitled to judgment as a
matter
of
law.
See
Fed.R.Civ.P.
56(f);
Celotex
Corp.
v.
Catrett, 477 U.S. 317, 322 (1986); Emmett v. Johnson, 532 F.3d
291, 297 (4th Cir. 2008).
In other words, if there clearly exist
factual issues “that properly can be resolved only by a finder
of fact because they may reasonably be resolved in favor of
either party,” summary judgment is inappropriate.
Anderson v.
Liberty Lobby, Inc., 477 U.S. 242, 250 (1986); see also JKC
Holding Co., LLC v. Washington Sports Ventures, Inc., 264 F.3d
459, 465 (4th Cir. 2001).
When ruling on a motion for summary judgment, the court
must construe the facts alleged in the light most favorable to
the party opposing the motion.
See Scott v. Harris, 550 U.S.
372, 377 (2007); Emmett, 532 F.3d at 297.
A party who bears the
burden of proof on a particular claim must factually support
each element of his or her claim.
323.
Celotex Corp., 477 U.S. at
“[A] complete failure of proof concerning an essential
3
element . . . necessarily renders all other facts immaterial.”
Id.
Thus, on those issues on which the nonmoving party will
have the burden of proof, it is his or her responsibility to
confront the motion for summary judgment with an affidavit or
other
similar
evidence
in
genuine issue for trial.
order
to
show
the
existence
of
See Anderson, 477 U.S. at 254.
a
“A
mere scintilla of proof, however, will not suffice to prevent
summary judgment.”
2003).
There
Peters v. Jenney, 327 F.3d 307, 314 (4th Cir.
must
be
“sufficient
evidence
favoring
the
nonmoving party for a jury to return a verdict for that party.”
Anderson,
477
U.S.
at
249.
“If
the
evidence
is
merely
colorable, or is not significantly probative, summary judgment
may be granted.”
Id. at 249-50 (citations omitted).
Where, as here, the nonmoving party fails to respond, the
court may not automatically grant the requested relief.
Fed.R.Civ.P. 56(e)(2).
See
Rather, it must “review the motion, even
if unopposed, and determine from what it has before it whether
the moving party is entitled to summary judgment as a matter of
law.”
Custer v. Pan American Life Ins. Co., 12 F.3d 410, 416
(4th Cir. 1993).
III. Analysis
Plaintiff
moves
for
partial
summary
breach of contract claim against LACO.
for
breach
of
contract,
a
plaintiff
4
judgment
as
to
the
“To prevail in an action
must
prove
that
the
defendant owed the plaintiff a contractual obligation and that
the
defendant
North
breached
America,
LLC
v.
that
obligation.”
Manhattan
Jaguar
Imported
Land
Cars,
Rover
Inc.,
738
F.Supp.2d 640, 649 (D.Md. 2010) (citing Taylor v. NationsBank,
N.A., 365 Md. 166, 175 (2001)).
Here, it is undisputed that
Plaintiff and LACO executed a purchase order in the amount of
$194,969.48.
answer).
entitled
(ECF
No.
25-1
&
ECF
No.
11
¶¶
22-23,
LACO’s
There also is no dispute that the FTD Purchase Order
Plaintiff
to
payment
for
work
performed.
In
its
answer, LACO states that it is without knowledge to admit or
deny whether it failed to pay Plaintiff pursuant to the FTD
Purchase Order; it also adds, however, that “Grimberg failed to
pay LACO for Plaintiff’s materials or services provided.”
No. 11 ¶ 45).
conditions
(ECF
Nothing in the FTD Purchase Order, however,
payment
to
Plaintiff
on
receiving
payment
Grimberg, and LACO does not argue as much in its answer.
from
In its
March 26, 2015 supplemental submission to the court, Plaintiff
indicates that Grimberg paid Plaintiff $100,000 on February 5,
2015.
(ECF No. 46, at 1).
Thus, Plaintiff represents that
“[t]he principal amount of Plaintiff’s claim is reduced from
$194,969.48
to
$94,969.48
to
account
received [on] February 5, 2015.”1
for
(Id.).
a
$100,000
credit
Plaintiff has shown
that it is entitled to judgment in the amount of $94,969.48.
1
In its complaint and motion for partial summary judgment,
5
In the March 26, 2015 supplemental submission, Plaintiff
also requests prejudgment interest.
It states:
The amount of prejudgment interest Plaintiff
requests is $20,266.83.
Plaintiff seeks
[]
on
the
recovery
of
6%
interest[2]
principal of $194,969.48 from June 7, 2013
(the date of the bond claim to Hartford) to
February 5, 2015 (the date of Grimberg’s
$100,000 payment), 608 days, at a per diem
rate
of
$32.049777,
for
a
total
of
$19,486.26.
Plaintiff also seeks recovery
of 6% interest on the principal of $94,
969.48 from February 5, 2015 (the date of
Grimberg’s $100,000.00 payment) to March 26,
2015, 50 days, at a per diem rate of
$15.611421, for a total of $780.57.
(ECF No. 46, at 1).
“[I]nterest is allowable as a matter of
right for a breach of contract to pay when the amount due has
been liquidated, ascertained, or agreed to.”
United States v.
State of W.Va., 764 F.2d 1028, 1031 (4th Cir. 1985); Wood Prods.,
Inc. v. CMI Corp., 651 F.Supp. 641, 653 (D.Md. 1986).
Here, the
record is insufficient to grant prejudgment interest.
complaint,
$194,969.48
Plaintiff
with
sought
judgment
pre-judgment
in
interest,
the
In the
amount
without
of
any
specification as to when the breach of contract claim accrued as
Plaintiff indicated that it agreed to perform additional work on
the Fort Detrick Project for $1,000. Plaintiff appears to have
abandoned any claim for the additional $1,000, as it seeks
judgment
in
the
amount
of
$94,969.48
(plus
prejudgment
interest).
2
In Maryland, the legal rate of interest is six percent per
annum.
Mitchell v. Kentmorr Harbour Marina, No. WMN-19-0337,
2011 WL 5826674, at *5 (D.Md. Nov. 17, 2011) (citing Md. Const.
art. III, § 57).
6
to
LACO.
Moreover,
Plaintiff
did
not
request
pre-judgment
interest in its motion for partial summary judgment.
No. 25).
(See ECF
The affidavit in support of the motion for partial
summary judgment is devoid of any facts from which it can be
determined when the breach of contract occurred, let alone that
it occurred on June 7, 2013 as Plaintiff now suggests in its
supplemental
submission.
The
complaint
only
indicates
that
Plaintiff demanded payment from LACO via email on June 7, 2013
for the materials and services provided pursuant to the FTD
Purchase Order, but this does not conclusively establish that
the obligation to pay became due then.
In
fact,
the
complaint
indicates
(See ECF No. 1 ¶ 21).
that
perform additional work on June 8, 2013.
Plaintiff
agreed
to
The reference to June
7, 2013 as the date of the “bond claim to Hartford” in the
supplemental
submission
is
also
unclear
and
does
not
conclusively establish that prejudgment interest should accrue
from
June
7,
2013.
Without
more
information,
prejudgment
interest cannot be fairly awarded.
Plaintiff indicates in its supplemental submission that it
withdraws
its
claim
for
attorneys’
fees
against
LACO,
and
further consents to the dismissal of counts one, three, six, and
seven in the complaint upon entry of judgment in its favor.
Accordingly, Plaintiff’s motion for partial summary judgment as
to Grimberg and Hartford will be denied as moot.
7
Based
judgment
on
as
prejudgment
the
to
foregoing,
the
motion
LACO
will
be
granted,
interest
will
be
denied
for
but
partial
the
without
summary
request
prejudice
for
to
Plaintiff’s right to renew.
IV.
Conclusion
For the foregoing reasons, Plaintiff’s motion for partial
summary judgment as to LACO will be granted, but the prejudgment
request will be denied without prejudice to renewal.
for
partial
summary
judgment
as
to
Defendants
The motion
Grimberg
and
Hartford will be denied as moot, and Counts One, Three, Six, and
Seven will be dismissed.
A separate order will follow.
/s/
DEBORAH K. CHASANOW
United States District Judge
8
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?