O&G Industries, Inc. v. University of Massachusetts Building Authority et al

Filing 93

Judge Rya W. Zobel: ORDER entered denying 71 Motion for Partial Summary Judgment (Urso, Lisa)

Download PDF
UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS CIVIL ACTION NO. 11-12032-RWZ O&G INDUSTRIES, INC. v. UNIVERSITY OF MASSACHUSETTS BUILDING AUTHORITY and R.G. VANDERWEIL & COMPANY, INC. ORDER January 30, 2014 ZOBEL, D.J. This action arises out of the construction of a central heating plant on the University of Massachusetts-Amherst campus. The construction manager, O&G Industries, Inc. (“O&G”), sued the project’s owner, the University of Massachusetts Building Authority (“UMBA”), for breach of contract, unjust enrichment, quantum meruit, and negligent misrepresentation. UMBA now seeks partial summary judgment on Count III of the complaint, in which O&G alleges breach of contract due to UMBA’s failure to pay for “added commissioning costs, extended general conditions, and other costs.” Docket # 1 at 5. UMBA argues that O&G’s claim for “extended general conditions” beyond the project’s contractual completion deadline is precluded by a “no damages for delay” provision in the parties’ contract. UMBA also contends that because it already made payments to O&G for extended general conditions covering March 2008 to April 2009 pursuant to bilaterally executed change orders, any additional claim for general conditions for that 14-month period is barred by the doctrine of accord and satisfaction. Finally, UMBA asserts that O&G’s claim for general conditions is a “total cost claim” which must fail because O&G itself is responsible for a portion of the costs.1 In response, O&G disputes that its extended general conditions costs constitute “delay damages,” challenges the enforceability of the “no damages for delay” provision, claims UMBA waived the provision through its conduct, argues that the executed change orders were merely placeholders and were open to further negotiation, and denies that it is bringing a total cost claim. After oral argument and consideration of the parties’ papers, I find that these arguments involve disputed issues of material fact regarding the contours of the extended general conditions costs claimed by O&G and the parties’ conduct with respect to delay, waiver, and the payment of change orders. As such, O&G’s claim for extended general conditions cannot be resolved at this stage. UMBA’s motion for partial summary judgment as to Count III (extended general conditions) (Docket # 71) is DENIED. /s/Rya W. Zobel RYA W. ZOBEL UNITED STATES DISTRICT JUDGE January 30, 2014 DATE 1 Under the total cost method of proving and computing damages, “the contractor’s bid is subtracted from the total costs incurred in performing the contract.” Tecom, Inc. v. U.S., 86 Fed. Cl. 437, 455-56 (Fed. Cir. 2009). This approach is disfavored and “may be used only when a plaintiff can demonstrate that: (1) it is impractical to prove the actual losses; (2) the bid was reasonable; (3) the actual costs were reasonable; and (4) the plaintiff is not responsible for the additional costs.” Id. 2

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?