Prime Steel Erecting, Inc v. Williams Building Company, Inc. et al
Filing
57
Judge Mark L. Wolf: ORDER entered. MEMORANDUM AND ORDER. (Bartlett, Timothy)
UNITED STATES DISTRICT COURT
DISTRICT OF MASSACHUSETTS
UNITED STATES OF AMERICA,
flulblo PRIME STEEL ERECTING,
INC. ,
Plaintiff,
v.
)
)
)
)
)
C.A. No. 13-CV-11920-MLW
)
)
WILLIAMS BUILDING COMPANY,
INC. ,
and
INTERNATIONAL FIDELITY
INSURANCE COMPANY,
Defendants.
)
)
)
)
)
)
MEMORANDUM AND ORDER
WOLF, D.J.
September 29, 2015
On August 9, 2013, Prime Steel Erecting, Inc.
a
complaint
("Williams")
("IFIC").
against
and
the
Williams
International
Building
Fidelity
("Prime") filed
Company,
Insurance
Inc.
Company
Prime alleged that Williams and IFIC owed Prime payment
for work on a federal construction project.
On October 4, 2013,
Williams filed its first motion to stay the proceedings pending
mediation
and
complaint
against
Inc.
("VHB")
arbitration.
two
Williams
subcontractors,
and Unistress Corporation
also
filed
Vanasse
a
third-party
Hangen
("Unistress")
Brustlin,
related to
the same construction project.
The parties have since filed many
counterclaims and crossclaims.
On April 10, 2014, Prime stipulated
to dismissal of its original complaint.
However, Williams's third-
party complaint, the counterclaims and crossclaims concerning it,
and
Unistress's
fourth-party
complaint
against
IFIC
remain
pending.
On April 25, 2014, Williams moved either to dismiss for lack
of subject matter jurisdiction or to stay the litigation pending
arbitration.
For the reasons explained below, Williams's motion
to stay pending arbitration is being allowed.
Williams's motion
to dismiss for lack of subject matter jurisdiction is being denied
without prejudice subject to possible refiling after arbitration.
1.
BACKGROUND
A.
Factual Allegations
The undisputed facts include the following.
out
of
a
federal
neighborhood
government
of
hired
construction
Boston,
project
as
the
construction of a parking garage.
relevant
subcontractors,
subcontracted with Prime.
Williams
as
required by
in
the
In
2011,
Massachusetts.
Williams
VHB
This case arises
prime
Jamaica
the
contractor
Plain
federal
for
the
Williams contracted with two
and
Unistress.
Unistress
IFIC provided surety bonds on behalf of
federal
law.
The
project
ran behind
schedule and over budget, leading to disputes among the parties.
In its third-party complaint, Williams alleged the following.
Williams hired VHB to "perform layout services for the project,"
but VHB "failed to properly perform its surveying duties, resulting
in the foundation for the new garage being located closer to the
2
existing garage" than had been specified in project plans.
No.
17 at
~~16-17.
In its answer, VHB denied these allegations.
~~16-17.
Docket No. 24 at
Williams
Docket
further
alleged that
its
contract with Unistress
required Unistress to "perform measurements at the Project site
before
fabricating
the
precast
concrete
Unistress did not perform these measurements.
~~31-32.
panels,"
Docket No.
but
17 at
After learning that the foundation had been laid closer
to the old garage than planned,
Unistress failed to "modify the
panels in its shop prior to transporting them to the Proj ect site."
Id. at
As a result, Unistress "engaged Prime to perform
~~33-35.
additional services for which it, Unistress, has failed and refused
to pay Prime."
~36.
Id.
In its answer, Unistress "admits that it
was informed at some point that the foundation for the new garage
was located closer to the existing garage" than planned, but denied
the other allegations.
In
its
complaint,
Prime
pursuant to its contract,
and steel at
performed
the
"Extra
alleged
the
following.
Prime,
installed concrete precast components
Docket
job site.
&
~~31-36.
Docket No. 34 at
Corrective
Work"
No.
1
at
including
~8.
Prime also
"making
j obsi te
adjustments to material and site preparations provided by Williams
and/or Unistress," as well as "many other fixes, repairs, and field
adjustments."
Id.
at
~10.
This additional work was not in the
3
original contract, but Williams and Unistress requested that Prime
perform this work.
Id.
at lJrlJrll-12.
Prime was not compensated
either for its contracted-for work or for the additional work, and
its complaint sought $171,328.82 plus attorneys'
Id.
at
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?