Judge Indira Talwani: ORDER entered. MEMORANDUM AND ORDER DENYING 90 MOTION to Strike 81 Notice of Filing Consent to Sue, 83 Notice of Filing Consent to Sue by Cumberland Farms, Inc.(DaSilva, Carolina)
Case 1:15-cv-13955-IT Document 155 Filed 08/14/17 Page 1 of 5
UNITED STATES DISTRICT COURT
DISTRICT OF MASSACHUSETTS
DIANNE BUCCERI, JANET CHARAK, *
LISA SANDERS, and PETER STAFFORD, *
on behalf of themselves and all others
*
similarly situated,
*
*
Plaintiffs,
*
*
v.
*
*
CUMBERLAND FARMS, INC.
*
*
Defendant.
*
Civil Action No. 15-cv-13955-IT
MEMORANDUM & ORDER
August 14, 2017
TALWANI, D.J.
Pending before this court is Defendant Cumberland Farms, Inc.’s (“Cumberland Farms”)
Motion to Strike Untimely Consent to Join Forms [“Motion to Strike”] [#90]. That motion seeks
to strike the Consent to Join forms filed on behalf of two opt-in plaintiffs, Derek Clement
(“Clement”) and Rakesh Vadehra (“Vadehra”). For the reasons that follow, the motion is
DENIED.
I.
Factual Background
On June 2, 2016, and upon stipulation of the parties, the court conditionally certified for
notice purposes a collective action pursuant to § 216(b) of the Fair Labor Standards Act
(“FLSA”), consisting of individuals who were employed by Cumberland Farms as Store
Managers at certain Cumberland Farms stores for any period during the three years prior to June
2, 2016, and who elected to opt-in. Order Regarding 216(b) Notice [#41]. The court ordered that
such individuals would have 60 days from the date of the mailing of Notice of the action to
Case 1:15-cv-13955-IT Document 155 Filed 08/14/17 Page 2 of 5
return a Consent to Join Form (“consent” or “opt-in” form). Id. In order to meet the deadline,
opt-in forms had to be filed, postmarked, or actually received by that date. Id. The Claims
Administrator sent notice to the individuals on July 7, 2016, and as a result, the individuals were
required to postmark their consent forms by September 6, 2016.1 Def.’s Mem. Law Supp. Mot.
Strike Untimely Consent to Join Forms [“Mem. Supp. Mot. Strike”] 2 [#91]; Mot. Strike, Ex. A
[#90-3]. On August 5, 2016, the Claims Administrator sent a postcard reminder to all such
individuals. Mem. Supp. Mot. Strike 2 [#91].
Plaintiffs filed over 100 consent forms. Clement’s consent form, filed on September 20,
2016, is dated September 1, 2016. Pls.’ Notice of Filing Consent to Join Form(s) Under the Fair
Labor Standards Act, 29 U.S.C. § 216(b), at 5 [#81]. The parties dispute the date of the
postmark. Pls.’ Mem. Law Opp’n Def.’s Mot. Strike Untimely Consent to Join Forms [“Pls.’
Opp’n”] [#94]; Mot. Strike Ex. C [#90-5]. Vadehra’s consent form, filed on September 23,
2016, is dated September 8, 2016, and postmarked September 12, 2016. Pls.’ Notice of Filing
Consent to Join Form(s) Under the Fair Labor Standards Act, 29 U.S.C. § 216(b), at 4 [#83];
Mot. Strike, Ex. D [#90-6]. No consent forms have been filed since September 23, 2016. On
November 1, 2016, Defendant moved to strike Clement’s and Vadehra’s consent forms as
untimely.2
II.
Discussion
A. Legal Standard
Collective actions under the FLSA are “fundamentally different” from class actions
1
Because the original deadline to postmark, September 5, 2016, was Labor Day, the parties
agreed to extend the deadline by one day to September 6, 2016. Mot. Strike, Ex. A [#90-3].
2
Defendant also moved to strike a third consent form as untimely. Unopposed Mot. Strike
Consent to Join Form Executed by Mark Anthony Turner [#89]. The court granted that motion as
unopposed. See Elec. Order [#93].
2
Case 1:15-cv-13955-IT Document 155 Filed 08/14/17 Page 3 of 5
under Federal Rule of Civil Procedure 23. Genesis Healthcare Corp. v. Symczyk, 569 U.S. 66,
133 S. Ct. 1523, 1529, 185 L. Ed. 2d 636 (2013) (citing Hoffmann–La Roche Inc. v. Sperling,
493 U.S. 165, 177-78 (1989) (Scalia, J., dissenting)).
[A] putative class acquires an independent legal status once it is certified
under Rule 23. Under the FLSA, by contrast, “conditional certification” does
not produce a class with an independent legal status, or join additional parties
to the action. The sole consequence of conditional certification is the sending
of court-approved written notice to employees, see Hoffmann–La Roche Inc.,
supra, at 171–172 . . . , who in turn become parties to a collective action only
by filing written consent with the court, § 216(b).
Genesis Healthcare Corp., 133 S. Ct. at 1530. Clement and Vadehra having now filed written
consents, the court must consider whether to allow their claims to proceed together with the other
plaintiffs, or to sever the claims and require them to proceed separately.
The FLSA provides no explicit standard by which a court should consider whether to
allow plaintiffs to join a particular action after a court-imposed deadline for the filing of consents
has passed. Ruggles v. Wellpoint, Inc., 687 F. Supp. 2d. 30, 37 (N.D.N.Y. 2009). Courts use
various factors to guide their decision on this question, such as: (1) “whether “good cause” exists
for the late submissions;” (2) whether the defendant would be prejudiced by acceptance of late
submissions; (3) the length of delay; (4) judicial economy; and (5) the FLSA’s remedial purpose.
See, e.g., id. (observing that the caselaw on this question is “wide-ranging”).
Defendant has articulated no prejudice it would suffer should the court accept the late
consent forms. Nor is such prejudice likely, given that the action is not considered to be
commenced as to late-filed claims until the written consent was filed, 29 U.S.C. § 256, so no
stale claims will arise, and the consents were filed in any event before discovery commenced.
Additionally, the delay is minimal. Vadehra postmarked the consent form just six days after the
deadline. And even accepting as true that Clement’s consent form was postmarked on
3
Case 1:15-cv-13955-IT Document 155 Filed 08/14/17 Page 4 of 5
September 10, 2016,3 that represents only a four-day delay. The remedial purposes of the FLSA
also counsel in favor of acceptance. As other courts have recognized, “with respect to the
FLSA, [a] generous reading, in favor of those whom [C]ongress intended to benefit from the
law, is also appropriate when considering issues of time limits and deadlines.” Ruggles, 687 F.
Supp. 2d at 38 (internal quotation marks and citation omitted).
Plaintiffs’ efficiency argument also supports allowing the late-filed consents. If Clement
and Vadehra are not permitted to proceed in this action, their severed claims could still be
asserted in a separate action. Courts have been wary of accepting this efficiency argument
wholesale, because such acceptance could “give Plaintiffs carte blanche to file additional
consent forms in the future.” Ruggles, 687 F. Supp. 2d at 38; see also Morangelli v. Chemed
Corp., 275 F.R.D. 99, 122 (E.D.N.Y. 2011) (expressing concern that “plaintiffs’ well-worn
efficiency argument” was “becoming the carte blanche to file additional consent forms”); Flood
v. Carlson Restaurants, Inc., 14 Civ. 2740 (AT)(GWG), 2016 WL 3221146, at *8 (S.D.N.Y. June
7, 2016) (same). Here, however, no new consent forms have been filed over ten months, and
there is no evidence that Plaintiffs will file additional late consent forms. And unlike in
Morangelli and Flood, the court has not previously extended the opt-in period. The economies to
be gained from accepting two late forms thus outweigh the concern that floodgates will open.
Plaintiffs have not articulated any reason for the late submissions. Where all of the other
factors weigh in Plaintiffs’ favor, courts have found that the absence of a showing of good cause
is not dispositive. See Ruggles, 687 F. Supp. 2d at 37 (“Although Plaintiffs have offered no
good cause for their failure to timely file these consent forms, all of the other factors weigh in
3
As noted above, Plaintiffs argue that because the “postmark date is unclear,” the fact that he
signed and dated the consent form prior to the deadline “support[s] the argument that his consent
was mailed before the deadline.” Pls.’ Opp’n 2 [#94].
4
Case 1:15-cv-13955-IT Document 155 Filed 08/14/17 Page 5 of 5
their favor.”); Saunders v. Getchell Agency, Inc., 1:13-cv-00244-JDL, 2014 WL 12539643, at
*11 n.17 (D. Me. Dec. 12, 2014) (“Defendants are not prejudiced by the joinder of the
individuals identified in Plaintiffs’ Motion to File Opt-In Consent Forms. The tardiness of the
individuals’ filings is not excessive, judicial economy is not negatively impacted, and the
remedial purpose of the FLSA is served by permitting the late opt-ins. These factors support
granting the motion even in the absence of a showing of good cause for the late submissions.”).
Because here all other factors counsel in favor of accepting the two late consent forms, this
court finds that the consent forms should be allowed.
III.
Conclusion
For the foregoing reasons, Defendant’s Motion to Strike [#90] is DENIED.
IT IS SO ORDERED.
Date: August 14, 2017
/s/ Indira Talwani
United States District Judge