Callen Manufacturing Corporation v. Nexteer Automotive Corporation
Filing
24
ORDER Granting Partial 18 Motion to Dismiss, Dismissing Count 4 of Plaintiff's Complaint with Prejudice, and Cancelling Motion Hearing. Signed by District Judge Thomas L. Ludington. (Sandusky, K)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF MICHIGAN
NORTHERN DIVISION
CALLEN MANUFACTURING CORPORATION,
Plaintiff/Counter-Defendant,
v.
Case No. 15-cv-11363
Honorable Thomas L. Ludington
NEXTEER AUTOMOTIVE CORPORATION,
Defendant/Counter-Claimant.
_______________________________________/
ORDER GRANTING PARTIAL MOTION TO DISMISS, DISMISSING COUNT 4 OF
PLAINTIFF’S COMPLAINT WITH PREJUDICE, AND CANCELLING MOTION
HEARING
Callen Manufacturing Corporation filed a Complaint against Nexteer Automotive
Corporation on April 14, 2015. Compl., ECF No. 1. The Complaint alleged six counts for relief.
Callen’s claims arise from Nexteer’s termination of a purchase order for the delivery of certain
goods. On May 11, 2015, Nexteer filed a motion to dismiss Counts 4 & 5 of Callen’s complaint.
See Def.’s Mot. to Dismiss, ECF No. 7. Nexteer argued in its first motion to dismiss that those
counts seek lost profits but that the purchase order, under which the disagreement between the
parties arises, forecloses Callen from obtaining such relief. After Nexteer filed its first motion to
dismiss, Callen filed a First Amended Complaint that removed its claim for lost profits in Count
5. Am. Compl., ECF No. 16.
Nexteer, still believing Count 4 of the Amended Complaint, which is entitled “Plaintiff’s
Lost Profits for Defendant’s Failure to Buy Requirements of Controller Covers through
December 2016”, to be improper, refiled its motion to dismiss. Nexteer now seeks to dismiss the
remaining claim for lost profits. As with its prior motion, Nexteer claims that this count should
be dismissed because the purchase order at issue expressly precludes lost profits as a remedy for
termination of the purchase order. Because the parties agree that the purchase order lawfully
precludes a claim for lost profits and that Nexteer rightfully terminated the purchase order1,
Count 4 of Callen’s Amended Complaint does not state a claim upon which relief may be
granted. That count will be dismissed.
I.
Callen is an Illinois corporation engaged in the business of die casting. “Die casting is a
manufacturing process whereby molten metal is poured into a die or mold. The metal is allowed
to cool, thus taking the form of the mold.” Am. Compl. ¶ 4, ECF No. 16. Nexteer is a “global
leader in manufacturing advanced steering and driveline systems.” Id. at ¶ 5.
A.
On December 14, 2011, Nexteer issued Callen a purchase order for the purchase of assist
covers and controller covers. Id. at ¶ 6. The purchase order bore the number SAG90i7548. Def.’s
Mot. to Dismiss, Ex. 1, ECF No. 18-2. Callen accepted Nexteer’s offer. Under the agreement,
Nexteer would pay for the covers provided by Callen within 47 days of the covers being shipped.
Am. Compl. ¶ 10, ECF No. 16. The parties agreed to amend the purchase order from time to time
in order to reflect differences in the prices of the covers. Id. at ¶ 9.
The purchase order agreement between the parties incorporated Nexteer’s General Terms
and Conditions. Def.’s Mot. to Dismiss, Ex. 3, ECF No. 18-3. The document contains a number
of contractual terms and conditions that govern Nexteer’s relationship with sellers, here Callen.
Of importance to the present dispute are two termination provisions. Section 10 is titled
1
Nexteer claims in its Answer and its briefing that the purchase order was terminated as a result of Callen’s breach.
The purchase order forecloses a claim for lost profits if Callen breaches the contract or if Nexteer terminates the
contract for convenience. Thus, it is not necessary to the disposition of the motion to determine the exact reason for
why the purchase order was terminated. Callen admits that, at a minimum, Nexteer validly terminated the purchase
order pursuant to its convenience termination rights.
-2-
“Termination for Breach” and permits Nexteer to “terminate all or any part” of the purchase
order if Callen breaches the agreement. Id. at § 10. Under such a termination Nexteer is not
subject to any liability to Callen. Id. Section 11 is titled “Termination for Convenience” and
permits Nexteer to terminate the purchase order “at any time and for any reason, by notifying
[Callen] in writing.” Id. at § 11. The provision sets forth a formula for determining the extent of
Nexteer’s liability to Callen for a termination for convenience. The section does not, however,
authorize the recovery of lost profits and provides that “[p]ayments made under this Article will
not exceed the aggregate price for finished goods that would be produced by [Nexteer] under
delivery of release schedules outstanding at the date of termination.” Id.
B.
On November 13, 2014, Nexteer’s Commercial Supervisor Chadde Stevens sent a letter
terminating the December 14, 2011 purchase order to Callen’s Vice President of Sales &
Marketing Donald Marsh. Def.’s Mot. to Dismiss, Ex. 3, ECF No. 18-4. In the letter Stevens
wrote that he was confirming the “verbal notice” of termination communicated to Callen on
November 7, 2014. Id. Stevens informed Callen that the reason for the termination letter “is
principally under Section 10, for breach, because of the ongoing and well-documented quality
issues, and Callen’s recent threat to stop shipment based on the communication from Busche, its
machining subcontractor. In the alternative only, the reason for Nexteer’s termination is under
Section 11, for convenience.” Id.
The letter from Stevens further states that termination with respect to Callen’s supply of
assist covers (part number 28262919) “is immediate.” Id. With respect to control covers (part
number 38000591), “termination is effective December 31, 2014.” Id. Termination with respect
to controller covers was delayed because it “hope[d] to use the next six weeks to exhaust finished
-3-
goods, [work in progress], and raw materials within releases, in an attempt to minimize potential
obsolescence for Callen.” Id.
C.
Because the termination letter sent by Nexteer contemplated an exhaustion of certain
parts used by Callen in producing controller covers, the purchase order did not immediately
terminate. Indeed, the letter contemplated a continued life of six weeks for the purchase order.
Pursuant to that future termination, Nexteer issued a purchase order amendment on November
24, 2014. Def.’s Mot. to Dismiss, Ex. 4, ECF No. 18-5. Callen contends that this document is a
separate and distinct purchase order from the December 14, 2011 purchase order.
But the amendment bears the same purchase order number as the 2011 purchase order:
SAG90I75482 and underneath the purchase order number the November 24, 2014 document
reads “ALTERATION 73780.” Id. The 2014 alteration also lists the same date for the “ORDER
ISSUE DATE” as the original SAG90I7548 purchase order: December 14, 2011. Id.
Furthermore, the content of the 2014 alteration details only a price change and states that “THE
FOLLOWING PRICE [IS] EFFECTIVE 12/01/14” and then lists a purchase price for controller
covers, part number 38000591. Id. Lastly, the 2014 alteration comes with the caveat that “THIS
CHANGES, AMENDS OR SUPERSEDES A PURCHASE ORDER IN YOUR POSSESSION.”
Id.
Callen believes that the 2014 alteration constitutes a separate contractual agreement
between the parties and argues that Nexteer has not terminated that order. As a result, it has
brought suit seeking, in part, lost profits for the controller covers it would have produced and
sold to Nexteer under the 2014 alteration.
2
The purchase order number is written with the “I” alternatively capitalized and non-capitalized. The number is the
same.
-4-
II.
This Court may dismiss a pleading for “failure to state a claim upon which relief can be
granted.” FED. R. CIV. P. 12(b)(6). A pleading fails to state a claim if it does not contain
allegations that support recovery under any recognizable legal theory. Ashcroft v. Iqbal, 556 U.S.
662, 678 (2009). In considering a Rule 12(b)(6) motion, the Court construes the pleading in the
non-movant’s favor and accepts the allegations of facts therein as true. See Lambert v. Hartman,
517 F.3d 433, 439 (6th Cir. 2008). The pleader need not have provided “detailed factual
allegations” to survive dismissal, but the “obligation to provide the ‘grounds’ of his
‘entitle[ment] to relief’ requires more than labels and conclusions, and a formulaic recitation of
the elements of a cause of action will not do.” Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 555
(2007). In essence, the pleading “must contain sufficient factual matter, accepted as true, to ‘state
a claim to relief that is plausible on its face.’” Iqbal, 556 U.S. at 678 (quoting Twombly, 550 U.S.
at 570).
III.
Nexteer claims that the current dispute is a simple one. The purchase order under which
the dispute arises, issued in 2011, precludes Callen from obtaining lost profits. Callen responds
that yes, Nexteer did validly terminate the 2011 purchase order but there is a separate 2014
purchase order under which Nexteer is liable for lost profits. The interplay between the 2011
purchase order and what Callen alleges is a separate and distinct 2014 purchase order has
germinated into the primary dispute between the parties. Callen concedes that if the 2011
purchase order is the sole contract for delivery of goods that defines the parties’ relationship,
then they are not entitled to lost profits. Conversely, Callen asserts that if the 2014 purchase
order is separate and distinct, Nexteer cannot claim that lost profits are precluded because the
-5-
purchase order was never terminated by Nexteer. Nexteer denies that the alleged 2014 purchase
order is an independent agreement. Rather, it explains that it is nothing more than a market-price
modification of the original purchase order and does nothing to displace their termination of the
2011 agreement.
Callen and Nexteer agree that the 2011 purchase order is a contract for the delivery of
goods that is governed by Article 2 of the Uniform Commercial Code. They also agree that under
Article 2, a contract for the delivery of goods can limit remedies available to one or both of the
contracting parties. Furthermore, the parties agree that the 2011 purchase order limits Callen’s
remedies in the event of their own breach or a voluntary termination by Nexteer. Lastly, the
parties agree that the remedy limitation in the 2011 purchase order precludes Callen from
recovering lost profits.
That leaves only the proper interpretation of the alleged 2014 purchase order. Callen
claims that this purchase order is a distinct delivery agreement. In its response to Nexteer’s
motion, Callen itemizes all the ways in which the 2011 purchase order and the alleged 2014
purchase order are different. To wit:
1. The 2011 purchase order is for assist covers and controller covers. The 2014
purchase order is for controller covers only.
2. The 2011 purchase order incorporates blueprints dated 12/15/09 for assist
covers and blueprints dated 11/29/11 for controller covers. The 2014 purchase
order incorporates blueprints dated 5/15/13.
3. The 2011 purchase order states that its terms are 47 days paid weekly. The
2014 purchase order omits terms of payment.
4. The 2011 purchase order does not include a section title COMMODITY
ADJUSTMENT. Such a section is included in the 2014 purchase order.
5. The 2011 purchase order does not incorporate Nexteer’s tooling terms and
conditions. The 2014 purchase order does incorporate Nexteer’s tooling terms and
conditions.
-6-
Pl.’s Resp. Br. 11, ECF No. 22. Callen concludes that “[w]hile the two purchase orders
undoubtedly contain some similar terms, that is because both purchase orders are for the sale of
controller covers produced by Callen and purchased by Nexteer. Nexteer fails to acknowledge
the many differences between the two contracts.” Id. at 11-12. The argument is without merit.
Despite identifying some differences between the 2011 and 2014 purchase orders, Callen
disregards the plain language of the 2014 agreement that it is simply a price modification of the
2011 purchase order. Indeed, what Callen claims to be a separate 2014 purchase order actually
retains the 2011 purchase order’s identification number: SAG90I7548. Def.’s Mot. Dismiss, Ex.
4, ECF No. 18-5. The 2014 document then, just below the 2011 purchase order number, bears
the mark “ALTERATION 73780.” Id. In addition, in the item description area the 2014
document states that “THIS ORDER IS EFFECTIVE 12/14/11 AND EXPIRES 12/31/16.” Id. It
would indeed be curious for an independent and complete purchase order issued on November
24, 2014 to have an effective date almost three years prior. Further, the description area also
communicates to Callen that “THE FOLLOWING HAS BEEN CHANGED TO READ” and
then sets forth a price adjustment to controller covers, nothing more. Id. Nothing in the body of
the 2014 document could reasonably be read to establish an independent agreement for the
acquisition of controller covers. Indeed, Callen acknowledges in its Complaint that “[f]rom time
to time, the [2011] purchase order was amended to reflect differences in the price of the Covers.”
Am. Compl. ¶ 9, ECF No. 16. The November 24, 2014 document is just such an amendment.
The basis of Callen’s claim for lost profits is that Nexteer did not terminate the 2014
document, an independent purchase order. But as explained, the 2014 document is not a new and
independent purchase order and indeed bears the same purchase order number, 90I7548, as the
2011 purchase order. Nexteer terminated purchase order 90I7548 in a letter from Commercial
-7-
Supervisor Chadde Stevens to Callen’s Vice President of Sales & Marketing Donald Marsh on
November 13, 2014. Def.’s Mot. to Dismiss, Ex. 3, ECF No. 18-4. While Callen questions how a
document from November 13 can effectuate the termination of a document issued November 24,
the body of Nexteer’s cancellation letter provides the answer. Nexteer explains in the letter that,
as to controller covers, “termination is effective December 31, 2014. [Nexteer] hope[s] to use the
next six weeks to exhaust finished goods, WIP, and raw material within releases in an attempt to
minimize potential obsolescence for Callen.” Id. Nexteer acknowledges in the letter that its
relationship with Callen for the purpose of purchasing controller covers will continue up to
December 31, 2014. As a result, it was necessary for Nexteer to issue one final price amendment
which, as noted above, is something that Callen concedes was commonplace.
Callen cannot state a claim for lost profits. Nexteer’s motion to dismiss will be granted
and Count 4 of Callen’s Amended Complaint will be dismissed with prejudice.
IV.
Accordingly, it is ORDERED that Defendant Nexteer Automotive Corporation’s Motion
to Dismiss, ECF No. 18, is GRANTED.
It is further ORDERED that Count 4 of Plaintiff Callen Manufacturing Corporation’s
First Amended Complaint is DISMISSED with prejudice.
It is further ORDERED that the motion hearing scheduled for August 27, 2015 at 3:00
p.m. is CANCELLED.
Dated: August 13, 2015
s/Thomas L. Ludington
THOMAS L. LUDINGTON
United States District Judge
-8-
PROOF OF SERVICE
The undersigned certifies that a copy of the foregoing order was served
upon each attorney or party of record herein by electronic means or first
class U.S. mail on August 13, 2015.
s/Karri Sandusky
Karri Sandusky, Acting Case Manager
-9-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?