Wake Plumbing and Piping, Inc. v. McShane Mechanical Contracting, Inc. et al
Filing
57
ORDER denying 50 Motion for Partial Summary Judgment. Signed by District Judge Victoria A. Roberts. (CPin)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF MICHIGAN
SOUTHERN DIVISION
WAKE PLUMBING AND PIPING, INC.,
Plaintiff,
Case No: 2:12-cv-12734
Honorable Victoria A. Roberts
v.
MCSHANE MECHANICAL CONTRACTING, INC.
AND TRAVELERS CASUALTY AND
SURETY COMPANY OF AMERICA,
Defendants.
_________________________________________/
ORDER DENYING DEFENDANTS’ MOTION FOR PARTIAL SUMMARY JUDGMENT
I.
INTRODUCTION
This contract dispute arises from a construction project in Fort Bragg, N.C. The
general contractor subcontracted plumbing work to Plaintiff Wake Plumbing and Piping,
Inc. (“Wake”), and HVAC work to Defendant McShane Mechanical Contracting, Inc.
(“McShane”). McShane subcontracted a portion of its HVAC work to Wake.
McShane asks the Court to dismiss Wake’s claims for promissory estoppel and
unjust enrichment (Counts II and III); it says there is no dispute that an express contract
exists between the parties. Wake opposes the motion. While both parties assert the
existence of an express contract, the parties disagree over the contract terms.
The Court must first determine whether there is a contract between the parties
before it can rule on promissory estoppel and unjust enrichment claims. The Court finds
that there is a genuine issue of fact concerning the existence of an express contract.
McShane’s motion is DENIED.
1
II.
BACKGROUND AND PROCEDURAL HISTORY
Suffolk Construction Company, Inc. (“Suffolk”) was the general contractor for
Irwin Intermediate School (the “Project”). Suffolk subcontracted plumbing work on the
Project to Wake; it also subcontracted heating, ventilation, and air conditioning
(“HVAC”) work to McShane. McShane then subcontracted Wake to complete two
different components of the HVAC work: a) “Underground Work” and b) “Aboveground
Work.” Accordingly, Wake was to perform three separate and distinct phases of work
on the Project:
1) Plumbing for Suffolk;
2) Underground Work for McShane; and,
3) Aboveground Work for McShane.
On May 3, 2011, Wake sent McShane a proposed lump sum bid of $296,000 for
both Underground and Aboveground Work, including labor and materials. Over the next
few weeks, the parties negotiated terms and conditions, the scope, and the price for
Aboveground Work. Because McShane was worried about delays, Wake says
McShane advised it on June 6, 2011 to perform the Aboveground Work despite the
absence of drawings or materials. Wake agreed, and over the next few weeks moved
forward with piping preparations for the Aboveground Work, consistent with a May 3rd
piping price quote of $267,100.
On June 17, 2011, McShane sent Wake a purchase order for the Aboveground
Work, the “53 subcontract,” for $267,000. Despite the absence of an express
agreement on terms and conditions, Wake performed in connection with the 53
subcontract; it assumed it would be paid consistent with this document. Wake now says
2
it accepted the 53 subcontract by performance and further, that this document is part of
the parties’ course of dealings.
On July 5, 2011, McShane unilaterally and without notice or discussion, voided
the 53 subcontract by writing “DELETED 07/05/11 per Phil.” across the top. Phillip
McShane testified that he had concerns about Wake’s ability to perform the job; he
wanted to proceed with the Aboveground Work on a time and material basis. McShane
also testified that he did not know the start date for the Aboveground Work, but believed
Wake’s men were on site after July 14, 2011.
On July 14, 2011, McShane faxed Wake a new document, the “73 subcontract.”
The 73 subcontract changed the terms for the Aboveground Work to time and material,
with a not—to—exceed price of $140,000. Wake objected by email to the 73
subcontract on July 18, 2011. Doc. 52-7. Wake continues to believe the 53 subcontract
is one basis for its agreement with McShane. On the other hand, McShane believes the
73 subcontract supersedes the 53 subcontract and that Wake accepted and performed
under the former. Doc. 50, Pg ID 564-565; see also Doc. 52-13 Pg ID 751 lines 20-22.
The factual issues in dispute include, but are not limited to: 1) which document –
if either – created an express contract for Aboveground Work; 2) the scope of work to
be completed by Wake; 3) the scope of work that was actually completed; 4) the start
date for Aboveground Work; and, 5) the price for Aboveground Work.
III.
STANDARD OF REVIEW
Rule 56 entitles the moving party to judgment as a matter of law “if the pleadings,
depositions, answer to interrogatories, and admissions on file, together with affidavits, if
any, show there is no genuine issue as to any material fact.” Celotex Corp. v. Catrett,
3
477 U.S. 317, 323 (1986). Summary judgment is appropriate where the non-moving
party, after adequate time for discovery on material matters at issue, fails to make a
showing sufficient to establish the existence of a material disputed fact. Id. The moving
party bears the initial burden to show the absence of a genuine issue of material fact.
Id. Once this burden is met, the non-moving party must establish facts showing a
genuine issue for trial. Matsushita Elec. Indus. Co v. Zenith Radio Corp., 475 U.S. 574,
587 (1986).
In evaluating a motion for summary judgment, the evidence must be viewed in
the light most favorable to the non-moving party. Adcock v. Firestone Tire & Rubber
Co., 822 F.2d 623, 626 (1987). The non-moving party “may not rest upon the mere
allegations or denials” of its pleadings. Fed. R. Civ. P. 56(e). Instead, it “must set forth
specific facts showing that there is a genuine issue for trial.” Id. The existence of a
mere scintilla of evidence in support of the non-moving party’s position will not suffice; it
must provide evidence on which a jury could reasonably find for the non-moving party.
Hopson v. Daimler Chrysler Corp., 306 F.3d 427 (6th Cir. 2002).
IV.
ANALYSIS
A. The Express Agreement
The parties agree that there was a contract for the Aboveground Work; they
disagree on its terms.
An express contract requires a meeting of the minds on all essential terms and is
an actual agreement of the parties, openly declared, either orally or in writing. Hall v.
Small, 267 Mich. App. 330 (2005). In order for a contract to be enforceable there must
be a valid offer, a valid acceptance, and adequate consideration. Turner Associates,
4
Inc. v. Small Parts, Inc., 59 F. Supp. 2d 674, 680 (E.D. Mich. 1999). The parties’ course
of conduct dictates the terms of an express contract. Quality Products and Concepts
Co. v. Nagel Precision, Inc., 469 Mich. 362 (2003). A meeting of the minds can be
found from performance and acquiescence in that performance. DaimlerChrysler Corp.
v. Wesco Distribution, Inc., 281 Mich. App. 240, 247 (2008).
Whether an express contract for the Aboveground Work exists is a question of
fact for the jury. The parties appear to have been negotiating contract terms for roughly
a month and a half. During that time, McShane created two potential offers: the 53
subcontract and the 73 subcontract.
The 73 subcontract is not an express contract between the parties; Wake
objected to it by email on July 18. Therefore, the 53 subcontract is the only written
document that could reasonably create an express agreement. While it is clear that
neither party gave explicit verbal or written consent to the 53 subcontract, the law allows
for acceptance by performance. DaimlerChrysler, 281 Mich. App. 240 at 247. There is
a genuine issue of fact as to whether Wake accepted the 53 subcontract by
performance; therefore, summary judgment is not appropriate.
If the 53 subcontract created an express contract, a jury will determine whether
McShane accomplished rescission; jurors will consider the quality of Wake’s services
and whether performance caused a material breach. In deciding whether the alleged
breach is material, a jury will determine terms and conditions of the agreement, the
scope of work that was supposed to be completed, and, what work was actually
completed.
5
Since essential contract terms for the Aboveground Work are in dispute, the
Court cannot decide whether an express contract exists.
B. Claims for Promissory Estoppel and Unjust Enrichment
Wake claims that if the Court finds no express agreement, it is entitled to
alternative relief under promissory estoppel and unjust enrichment, according to FRCP
8(a)(3); FRCP (d)(2); and, FRCP 8(d)(3). If a jury finds that there is an express
contract, Wake is only entitled to relief under that contract, and nothing beyond it.
Damages would be determined based on how much work a jury believes Wake actually
completed, less $35,000 already paid by McShane.
Promissory estoppel is a substitute for consideration where there are no mutual
promises. Huhtala v. Travelers Ins. Co., 401 Mich. 118, 133; 257 N.W.2d 640 (1977).
For the court to apply promissory estoppel under Michigan law, it must find an implied
agreement exists between the parties, in the absence of an express contract. APJ
Assocs., Inc. v. N. Am. Phillips Corp., 317 F.3d 610, 617 (6th Cir. 2003). Further, “to
support a claim for unjust enrichment a plaintiff must demonstrate: 1) a benefit
conferred by a plaintiff upon a defendant; 2) knowledge by the defendant of the benefit;
and, 3) retention of the benefit by the defendant under circumstances where it would be
unjust to do so without payment.” Bower v. Int'l Bus. Machines, Inc., 495 F. Supp. 2d
837, 844 (S.D. Ohio 2007).
If the jury finds no express contract between the parties, it will determine whether
Wake conferred a benefit on McShane and whether Wake is entitled to compensation
for services it has not been paid for. Nonetheless, Wake has a right under the law to
6
plead these alternate theories for recovery. The Court DENIES McShane’s request to
dismiss Counts II and III for promissory estoppel and unjust enrichment.
C. Calculating Potential Damages
In the event damages cannot be calculated under an express contract, Wake
believes that damages under promissory estoppel and unjust enrichment can be
calculated through certified payroll records. These records were provided to the Court
as an attachment to Wake’s response to McShane’s motion. They were reviewed by
Eric Berlin (“Berlin”), first year attorney for Wake’s counsel. At oral hearing, McShane
argued that promissory estoppel and unjust enrichment claims should be dismissed
because Wake did not provide the certified payroll records until after discovery ended.
The Court will not dismiss claims for promissory estoppel and unjust enrichment
as a matter of law. Nonetheless, McShane is at a great disadvantage because it was
not able to investigate the accuracy of these records or the methods used by Berlin to
calculate damages.
“A party asserting a claim has the burden of proving its damages with reasonable
certainty.” Berrios v. Miles, Inc., 226 Mich. App. 470, 478, 574 N.W.2d 677, 680, 543
(1997). However, “although damages based on speculation or conjecture are not
recoverable, Stutter v. Biggs, 377 Mich. 80, 86 . . . damages are not speculative merely
because they cannot be ascertained with mathematical precision. Godwin v. Ace Iron &
Metal Co., 376 Mich. 360, 368 . . .. It is sufficient if a reasonable basis for computation
exists, although the result be only approximate.” McCullagh v.Goodyear Tire & Rubber
Co., 342 Mich. 244, 255; supra.
7
The certified payroll records might provide a sufficient basis to calculate
damages. McShane did not have a fair opportunity to object to Wake’s calculations and
propose its own figures. The Court will allow McShane to depose Berlin and obtain any
other documentation related to certified payroll records. Wake must comply with
McShane’s discovery request.
V.
CONCLUSION
McShane’s Motion for Partial Summary Judgment is DENIED. There are issues
of fact for a jury to decide.
IT IS ORDERED.
S/Victoria A. Roberts
Victoria A. Roberts
United States District Judge
DATED: July 29, 2014
8
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?