Hancock Fabrics, Inc. v. Rowdec, LLC
Filing
44
MEMORANDUM OPINION re ( 62 in 1:12-cv-00222-SA-DAS, 43 in 1:12-cv-00131-SA-DAS) FINAL JUDGMENT. Signed by District Judge Sharion Aycock on 11/19/2013. Associated Cases: 1:12-cv-00131-SA-DAS, 1:12-cv-00222-SA-DAS (psk)
IN THE UNITED STATES DISTRICT COURT
FOR THE NORTHERN DISTRICT OF MISSISSIPPI
ABERDEEN DIVISION
HANCOCK FABRICS, INC.
PLAINTIFF
V.
CAUSE NO.: 1:12CV131-SA-DAS
ROWDEC, LLC d/b/a WESTLAKE ASSOCIATES
DEFENDANT
with
ROWDEC LLC
V.
PLAINTIFF
CAUSE NO.: 1:12CV222-SA-DAS
HANCOCK FABRICS, INC.
DEFENDANT
MEMORANDUM OPINION
Rowdec, LLC, d/b/a Westlake Associates (Westlake) filed a Motion to Confirm
Arbitration Award [34].1 After Hancock filed its response, and Westlake replied, Hancock
requested the opportunity to file a sur-reply [41]. Because the Court has considered all briefing
in this matter, the Motion for Leave to File Sur-Reply [41] is GRANTED, and Westlake’s
Motion to Confirm Arbitration Award [34] is GRANTED, but not to the extent requested.
Factual and Procedural Background
Westlake and Hancock Fabrics, Inc. (Hancock) entered into a Consulting and Sales
Agreement on February 9, 2009. During the six year term of the contract, Hancock was to pay a
guaranteed fee to Westlake the first two years for its consulting services, and thereafter to pay
royalties on Hancock’s net retail sales of “Identified Products.” “Identified Products” were those
“covered under this agreement that will be coded by [Hancock] in a mutually agreed upon
manner to ensure that [Westlake] is credited with sales attributable to its work under this
1
The Motion to Confirm Arbitration Award is docket [53] is cause number 1:12cv222, while the Motion for Leave
to File Sur-Reply is docket [60].
Agreement . . . .” The Agreement further provided a dispute resolution procedure requiring
consultation between the parties in the event of a disagreement or dispute arising under the
Agreement or parties’ performance thereunder. If a resolution could not be met, the Agreement
provided that “either party may apply for binding and confidential arbitration of the Disputed
Matter with the American Arbitration Association (‘AAA’).”
During the course of the contract, Westlake and Hancock failed to successfully resolve
their differences over the list of “Identified Products” from which Westlake’s royalties were to
be calculated under the Agreement. In August of 2011, after failed consultations, Westlake
applied for binding arbitration to determine whether Hancock breached the Consulting and Sales
Agreement by failing to pay royalties on the “Identified Products.”
The arbitration was
conducted over four days, February 6-9, 2012, in Dallas, Texas. The arbitrator issued the award
on March 22, 2012, and granted Westlake’s declaratory judgment against Hancock. In addition
to damages, the arbitrator additionally awarded $519,328.60 to Westlake for its “reasonable and
necessary attorney’s fees,” costs of $4,019.15, and administrative fees and expenses of the
American Arbitration Association totaling $25,485.22.
Within hours of the decision being announced, Hancock filed the instant action in the Lee
County Circuit Court, which was then removed. Hancock asserted that the arbitrator exceeded
his authority by awarding attorneys’ fees and future payments based on litigation necessary to
confirm the arbitrator’s award. Westlake filed a confirmation action in Texas, which was then
transferred to the Northern District of Mississippi and consolidated with the instant case. See
Rowdec , LLC v. Hancock Fabrics, Inc., Cause No. 1:12cv222 (N.D. Miss. Oct. 18, 2012). The
transferred cause of action seeks confirmation of the arbitrator’s Award in all respects, including
2
the imposition of attorneys’ fees and costs, as well as post-arbitration fees for successfully
responding to an objection to the confirmation of the award as provided in the arbitrator’s award.
Westlake now files a Motion to Confirm Arbitration Award in both cases seeking a
declaration that the arbitrator had authority to award attorneys’ fees and post-arbitration fees, and
that the Award required Hancock to pay royalties to Westlake on all Identified Products sold by
Hancock in all stores and by internet. Hancock has responded bringing procedural issues as well
as substantive arguments to light.
The Court’s Obligation in Reviewing the Arbitration Award
The FAA provides the means for enforcing arbitral awards by way of a judicial decree
confirming, vacating, modifying or correcting an award. See Hall St. Assocs., LLC. v. Mattel,
Inc., 552 U.S. 576, 582, 128 S. Ct. 1396, 170 L. Ed. 2d 254 (2008). Section 9 of the Federal
Arbitration Act requires the Court, upon motion of a party, to confirm an arbitration award
“unless the award is vacated, modified, or corrected as prescribed in sections 10 and 11 of [the
FAA].” 9 U.S.C. § 9; see Householder Grp. v. Caughran, 354 F. App’x 848, 850 (5th Cir. 2009)
(citing Hall St. Assocs., 552 U.S. at 582, 128 S. Ct. 1396); Schlobohm v. Pepperidge Farm, Inc.,
806 F.2d 578, 580 n.2 (5th Cir. 1986). The party moving to vacate the arbitral award bears the
burden of proof. See In re Arbitration Between Trans Chem. Ltd. & China Nat’l Mach. Import &
Export Corp., 978 F. Supp. 266, 303 (S.D. Tex. 1997), aff’d, 161 F.3d 314 (5th Cir. 1998).
Section 10 of the FAA provides the exclusive grounds for which a Court may vacate an
arbitration award:
(1) where the award was procured by corruption, fraud, or undue means;
(2) where there was evident partiality or corruption in the arbitrators, or either
of them;
3
(3) where the arbitrators were guilty of misconduct in refusing to postpone the
hearing, upon sufficient cause shown, or in refusing to hear evidence
pertinent and material to the controversy; or of any other misbehavior by
which the rights of any party have been prejudiced; or
(4) where the arbitrator exceeded his powers, or so imperfectly executed them
that a mutual, final, and definite award upon the subject matter submitted
was not made.
9 U.S.C. § 10(a); see Householder Group, 354 F. App’x at 850.
Section 11 provides the only grounds for modification of an award:
(a) where there was an evident material miscalculation of figures or an
evident material mistake in the description of any person, thing or property
referred to in the award.
(b) where the arbitrators have awarded upon a matter not submitted to them,
unless it is a matter not affecting the merits of the decision upon the matter
submitted.
(c) where the award is imperfect in matter of form not affecting the merits of
the controversy.
The order may modify and correct the award, so as to affect the intent thereof
and promote justice between the parties.
9 U.S.C. § 11.
The Court’s review of an arbitration award made under the FAA is “extraordinarily
narrow” and “exceedingly deferential.” Prestige Ford v. Ford Dealer Computer Servs., Inc., 324
F.3d 391, 393 (5th Cir. 2003). The Court must “defer to the arbitrator’s decision when possible.”
Am. Laser Vision, P.A. v. Laser Vision Inst., LLC, 487 F.3d 255, 258 (5th Cir. 2007) (internal
quotation marks omitted). See also Anderman/Smith Operating Co. v. Tenn. Gas Pipeline Co.,
918 F.2d 1215, 1218 (5th Cir. 1990) (court “will defer to the arbitrators’ resolution of the dispute
whenever possible”). And, as the Supreme Court made clear in Hall Street Associates, vacatur or
modification is available only on the limited grounds set forth in Sections 10 and 11. 552 U.S. at
588, 128 S. Ct. 1396. No non-statutory bases exist for vacating or modifying an award, and
4
parties may not contract to expand judicial review beyond the bases set forth in the statutes. Id.,
128 S. Ct. 1396 (reasoning that “[a]ny other reading opens the door to the full-bore legal and
evidentiary appeals that can ‘rende[r] informal arbitration merely a prelude to a more
cumbersome and time-consuming judicial review process,’ and bring arbitration theory to grief
in post-arbitration process”) (citation omitted).
In Anderman/Smith Operating Co., the court observed that where parties have bargained
for an arbitration process which would determine the facts and construe disputed contract
provisions, there is no injustice in holding them to their bargain. 918 F.2d at 1219 (citing
Manville Forest Prod. Corp. v. United Paperworkers Int’l Union, 831 F.2d 72, 74 (5th Cir.
1987)). Consistent with the parties’ choice, therefore, it is for the arbitrator, not the court, to
decide the merits of the parties’ dispute; and it is for the arbitrator, not the court to find the facts
and to decide and apply the law. This point was highlighted by the court in Kergosien v. Ocean
Energy, Inc., when it stated:
“Courts are not authorized to review the arbitrator’s decision on the merits despite
allegations that the decision rests on factual errors or misinterprets the parties’
agreement.” Major League Baseball Players Ass’n v. Garvey, 532 U.S. 504, 509,
121 S. Ct. 1724, 149 L. Ed. 2d 740 (2001) (citing United Paperworkers Int’l
Union, AFL-CIO v. Misco, Inc., 484 U.S. 29, 36, 108 S. Ct. 364, 98 L. Ed. 2d 286
(1987)). “If ‘an arbitrator is even arguably construing or applying the contract and
acting within the scope of his authority,’ the fact that ‘a court is convinced he
committed serious error does not suffice to overturn his decision.’” Id. (quoting
Misco, 484 U.S. at 38, 108 S. Ct. 364). “[E]ven ‘serious error’ on the arbitrator’s
part does not justify overturning his decision, where, . . . he is construing a
contract and acting within the scope of his authority.” Id. at 510, 121 S. Ct. 1724
(quoting Misco, 484 U.S. at 38, 108 S. Ct. 364). “Established law ordinarily
precludes a court from resolving the merits of the parties’ dispute on the basis of
its own factual determinations, no matter how erroneous the arbitrator’s
decision.” Id. (citing Misco, 484 U.S. at 40, n.10, 108 S. Ct. 364). “When an
arbitrator resolves disputes regarding the application of a contract, and no
dishonesty is alleged, the arbitrator’s ‘improvident, even silly, factfinding’ does
not provide a basis for a reviewing court to refuse to enforce the award.” Id.
(quoting Misco, 484 U.S. at 39, 108 S. Ct. 364). “‘[C]ourts . . . have no business
5
weighing the merits of the grievance [or] considering whether there is equity in a
particular claim.’” Id. (quoting Misco, 484 U.S. at 37, 108 S. Ct. 364).
390 F.3d 346, 357-58 (5th Cir. 2004), rev’d on other grounds, Citigroup Global Markets, Inc. v.
Bacon, 562 F.3d 349 (5th Cir. 2009). See also Hamel-Schwulst v. Country Place Mortg. Ltd.,
406 F. App’x 906, 914 (5th Cir. 2010) (“[C]ourts do not vacate an arbitration award based on the
merits of a party’s claim.”) (citing Misco, 484 U.S. at 38, 108 S. Ct. 364); Apache Bohai Corp.
LDC v. Texaco China BV, 480 F.3d 397, 401 (5th Cir. 2007) (holding that an award may not be
vacated or modified for a mere mistake of fact or law) (citing Brabham v. A.G. Edwards & Sons
Inc., 376 F.3d 377, 380 (5th Cir. 2004)).
Analysis and Discussion
Westlake seeks by motion to “confirm” that the attorneys’ fee awarded by the arbitrator
was within his discretion, and that Hancock is obligated to pay royalties on the sale of all
Identified Products wherever sold. Pursuant to the standard outlined above, the Court must first
determine whether Hancock has carried its burden to vacate the award on the basis that the
arbitrator exceeded his authority by awarding attorneys’ fees.
I.
Vacation of the Award
Hancock claims that under the terms of the Agreement’s dispute resolution procedures,
the only “Disputed Matter” between Hancock and Westlake was the parties’ “differences over
the list of ‘Identified Products.’” Under the Agreement, Hancock asserts that the arbitrator was
only authorized to resolve the “Disputed Matter,” and that in awarding attorney’s fees and future
attorney’s fees, the arbitrator exceeded his powers and issued an award that “goes beyond the
subject matter that Westlake submitted to arbitration, namely, ‘differences over the list of
‘Identified Products.’” Westlake claims that because the arbitration clause was broad, and there
is no express limitation on the arbitrator’s authority to award attorneys’ fees, that award is
6
proper. Moreover, Westlake contends that the AAA Rules, which the parties agreed upon,
empower the arbitrator to award attorneys’ fees. Finally, Westlake asserts that because both
parties requested attorneys’ fees, the issue was properly before the arbitrator, and his authority
was not exceeded in making such award.
As noted above, the applicable provision in the underlying Agreement provides that the
“parties shall attempt in good faith to resolve such Disputed Matter through binding arbitration
pursuant to the Commercial Arbitration Rules of the AAA . . . .” The contract defines “Disputed
Matter” as “[a]ny dispute, disagreement, claim or controversy between the parties arising under
or relating to this Agreement or the parties’ performance thereunder . . . .”
The Court finds that the arbitration provision at issue is broad enough to support the
imposition of attorneys’ fees and contains no limits relevant to the instant dispute. See Timegate
Studios, Inc. v. Southpeak Interactive, LLC, 713 F.3d 797, 2013 U.S. App. Lexis 7184, at *15
(5th Cir. Apr. 9, 2013) (noting the broad implication of the arbitration clause where such clause
related to “any dispute”). Moreover, the “arbitrator’s selection of a particular remedy is given
even more deference than his reading of the underlying contract.” Executone Info. Sys., Inc. v.
Davis, 26 F.3d 1314, 1325 (5th Cir. 1994). “The remedy lies beyond the arbitrator’s jurisdiction
only if ‘there is no rational way to explain the remedy handed down by the arbitrator as a logical
means of furthering the aims of the contract.’” Id. (quoting Brotherhood of R.R. Trainmen c.
Central of Georgia Ry. Co., 415 F.2d 403, 412 (5th Cir. 1969)). As such, a remedy including
attorneys’ fees is a rational remedy pursuant to the Agreement providing for “binding and
confidential arbitration of the Disputed Matter” which is “[a]ny dispute . . . [or] claim . . .
between the parties arising under or relating to this Agreement or the parties performance
thereunder . . .”
7
Aside from the Court’s finding that the broad implication of the arbitration clause would
permit the arbitrator to award attorneys’ fees, the award of attorneys’ fees must also be upheld as
Hancock sought its own attorneys’ fees during the arbitration. As this Court has held, “[t]he
arbitrators’ authority, however, is limited only by the scope of the agreement between the
parties.” Wing v. J.C. Bradford & Co., 678 F. Supp. 622, 626 (N.D. Miss. 1987) (citing French v.
Merrill Lynch, Pierce, Fenner and Smith, Inc., 784 F.2d 902, 908 (9th Cir. 1986)).
The submissions made by Hancock and Westlake to the arbitrators included cross-claims
for attorneys’ fees. Thus, it would appear that the arbitrator was “acting within the scope of [his]
authority in granting attorneys’ fees” to Westlake. Id.; Netknowledge Techs. LLC v. Rapid
Transmit Techs., 269 F. App’x 443, 444-45 (5th Cir. 2008) (affirming an arbitral award of
attorneys’ fees where “both parties requested attorneys’ fees while this matter was before the
Arbitrator, thereby permitting the Arbitrator to award attorneys’ fees under the Rules of the
American Arbitration Association.”) (citing Commercial Arbitration Rule R-43(d)(ii)).
Hancock’s Response to Westlake’s Arbitration Demand, found in the record as Exhibit D to the
Motion to Confirm Arbitration, included a request that “Hancock be awarded reasonable
attorneys’ fees and costs incurred in defending this action.” In the opinion of the Court, Hancock
therefore agreed to allow the arbitrator to consider Westlake’s claim for attorneys’ fees and
expenses. Inasmuch as the parties’ Demand for Arbitration and Response explicitly empowered
the arbitrator to decide the issue of attorneys’ fees and expenses, the Court construes the
arbitrator’s award as having been within the scope of his authority. See United Steel Workers of
Am. v. Warrior & Gulf Navigation Co., 363 U.S. 574, 585, 80 S. Ct. 1347, 4 L. Ed. 2d 1409
(1960). Therefore, Hancock has failed to meet its burden to vacate the arbitral award.
8
II.
Confirmation of the Award
Westlake seeks a “confirmation” that the arbitral award obligates Hancock to pay
royalties to Westlake on all “Identified Products” that Hancock sells. Hancock has taken the
position that it only owes royalties for all “Identified Products” covered by the Agreement,
which Hancock claims limits the payment to royalties on “Identified Products” sold from those
stores with craft departments.
A review of the arbitral award shows the pertinent findings of the Arbitrator as to the
definition of “Identified Products” as follows:
-
“At the time the CSA was signed, Hancock did not have a craft department.”
-
“The stated purpose of the CSA was for Westlake to consult with and advise Hancock
during the Development Period on building a new craft department.”
-
“The ‘work’ of Westlake under the CSA was to design and build a craft department
for Hancock.”
-
“Westlake fully performed its duties under the CSA and delivered to Hancock a
comprehensive plan, design and installation plan for all products within the craft
department.” (footnote omitted).
-
“Westlake is entitled to royalties based on Hancock’s ‘Net Retail Sales’ as set forth in
Schedule ‘B’ to the CSA.”
-
“The CSA states in paragraph 3(c) that ‘Net Retail Sales’ shall mean actual sales
minus returns on products covered by this agreement that will be coded by the
Company [Hancock] in a mutually agreed upon manner to ensure that the Consultant
[Westlake] is credited with sales attributable to its work under the Agreement [CSA]
9
as measured by the Point of Sale (the ‘Identified Products’). [inserts and emphasis
added by the Arbitrator].”
-
“Neither party pled, urged or argued that any portion of the CSA, including the
specific language quoted in this Award, was ambiguous. As finding in this case, the
language is determined not to be ambiguous.”
-
“The actual sales minus returns on products covered by the CSA that are subject to
payment of the royalty percentages set forth in Schedule B to the CSA means all
products sold in the Hancock craft department during the six year term of the
CSA.” (bold emphasis added).
Because Hancock has failed to offer a sufficient basis for vacation or modification of the
arbitral award, the Award is hereby confirmed.
Conclusion
The imposition of attorneys’ fees by the Arbitrator was within his authority. Because
FAA § 9’s “provision for judicial confirmation carries no hint of flexibility,” Hall St., 552 U.S.
at 587, 128 S. Ct. 1396, the Award is therefore confirmed. Indeed,
[o]n application for an order confirming the arbitration award, the court “must
grant” the order “unless the award is vacated, modified, or corrected as prescribed
in sections 10 and 11 of this title.” There is nothing malleable about “must grant,”
which unequivocally tells courts to grant confirmation in all cases, except when
one of the “prescribed exceptions applies.”
Id., 128 S. Ct. 1396. Thus, because Hancock has failed to prevail in vacating or modifying the
award, the award is hereby CONFIRMED. Westlake’s request to clarify the definition of
“Identified Products” is not well taken.
The arbitral award is unambiguous and shall be
confirmed.
10
Westlake additionally requests that the Court impose the post-arbitration fees the
Arbitrator warned would be “reasonable” if Westlake “successfully confront[ed] an objection to
the confirmation of this Award.” Because Hancock did not pose an objection to the confirmation
of this Award, but merely challenged the Arbitrator’s authority to enter the Award, the Court
finds the imposition of those fees is inappropriate.
Therefore, the Court finds against Hancock in their request for a declaratory judgment in
Cause Number 1:12cv131. As to cause number 1:12cv222, the Court hereby CONFIRMS the
arbitral award, but not to the extent requested by Westlake. Both cases are CLOSED.
SO ORDERED, this the 19th day of November, 2013.
/s/ Sharion Aycock_________
U.S. DISTRICT JUDGE
11
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?