Wilson v. Siegel-Robert, Inc.
Filing
94
MEMORANDUM... The Court's order granting summary judgment to SRG, and against plaintiff Glenn Wilson, will stand. Third-party defendants R&M and LynnCo's motions for summary judgment will be granted, thus no issues remain for trial in this matter. Signed by Honorable Stephen N. Limbaugh, Jr on 11/8/2011. (JMC)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF MISSOURI
SOUTHEASTERN DIVISION
GLENN WILSON,
Plaintiff,
vs.
SIEGEL-ROBERT, INC. d/b/a
SIEGEL-ROBERT AUTOMOTIVE
PORTAGEVILLE,
Defendant/Third Party Plaintiff,
vs.
LYNNCO SUPPLY CHAIN
SOLUTIONS, INC,
and
R&M TRUCKING, LLC,
Third Party Defendants
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Case No. 1:10-CV-56 SNLJ
MEMORANDUM
On October 13, 2011, this Court granted summary judgment to the defendant, SiegelRobert, Inc., d/b/a SRG Global Portageville (“SRG”), and against the plaintiff on all plaintiff’s
claims (#77, 78). Later that same day, SRG filed its Notice of Settlement and Motion for
Extension of Time and for Continuance of Trial Date (#79), advising that SRG had settled
plaintiff’s claims against SRG and requesting, among other things, that the Court vacate its order
granting summary judgment to SRG. SRG also filed a Motion for Leave to File Second Amended
Third-Party Complaint (#80), seeking to add the details of the settlement to its claims for
indemnification from the third-party defendants.1 The third-party defendants filed memoranda in
opposition to the Motions, and SRG has replied. Plaintiff Glenn Wilson has also filed a
“Memorandum in Support of Notice of Settlement of Primary Claim,” and Third-Party Defendant
LynnCo Supply Chain Solution, Inc. has responded (#92, #93). At the same time, pending before
the Court are third-party defendant LynnCo Supply Chain Solution, Inc.’s motion for summary
judgment (#62), filed July 20, 2011, and third-party defendant R&M Trucking, LLC’s motion for
summary judgment (#71), filed August 30, 2011. Third-party plaintiff SRG2 has filed responses
in opposition. All four matters are now ripe for disposition.
I.
Case Summary
The plaintiff in this case, Glenn Wilson, filed a complaint against defendant SRG on
March 11, 2010, in the Circuit Court of New Madrid County. Plaintiff alleges that he fell on an
icy part of SRG’s premises on January 29, 2009, and that he sustained serious and permanent
injuries to his hip, leg, knee, and elsewhere on his body.
Defendant and third-party plaintiff SRG removed the case to this Court pursuant to 28
U.S.C. § 1332 and subsequently filed a third-party complaint against LynnCo Supply Chain
Solutions, Inc. (“LynnCo”) and R&M Trucking, LLC (“R&M”) pursuant to 28 U.S.C. § 1367,
alleging that those entities owed SRG indemnification for plaintiff’s claims.
1
Curiously, although SRG filed the proposed Amended Third Party Complaint as an
exhibit to its motion, SRG also filed its “Second Amended Third Party Complaint” as Document
Number 81.
2
Defendant was sued as “d/b/a Siegel-Robert Automotive Portageville,” but that name has
been inactive since December 22, 2009. Siegel-Robert, Inc. is currently doing business in
Portageville as SRG Global Portageville, a fictitious name on file with the Missouri Secretary of
State since December 22, 2009.
2
The Court granted summary judgment to SRG on both of plaintiff’s two counts on October
13, 2011 (#77, 78); however, SRG’s third-party complaint still survives, as SRG seeks attorney’s
fees and other costs incurred as a result of defending itself in this action.
Two contracts are at issue in SRG’s third-party complaint. First, SRG alleges that LynnCo
was contractually obligated to provide shipping services for SRG’s automotive parts business
under the so-called “LynnCo Agreement.” The LynnCo Agreement states that LynnCo
shall defend, hold harmless and indemnify [SRG], [SRG]’s officers, directors,
shareholders, and employees, against any claims, demands, damages, including
litigation costs and reasonable attorney’s fees (“Claim(s)”) that are threatened by or
awarded to any party arising out of death or injury as a result of the intentional or
negligent acts or omissions of [LynnCo], or its employees under the Agreement.
Second, LynnCo in turn contracted with R&M to provide shipping services for the SRG facility at
issue in this case under the so-called “Broker Agreement.” The “Broker Agreement” provided
that R&M
shall defend, indemnify and hold [LynnCo] and its shipper customer [SRG] harmless
from any claims, actions or damages arising out of its performance under the terms
of this Agreement, including cargo loss and damage, theft, delay, damage to property
and personal injury or death...
Plaintiff Wilson was an employee of R&M, and he was on SRG’s premises on the day of his
accident to take a load of auto parts to Tennessee. SRG tendered the lawsuit filed by Wilson to
R&M and then, when R&M denied indemnification, to LynnCo, which also denied
indemnification. SRG seeks a judgment from this Court that R&M and LynnCo are in breach of
the agreements and are responsible for SRG’s damages, which include any monies paid to the
plaintiff in addition to other costs and attorneys’ fees incurred in the defense of the litigation.
SRG also seeks to amend its complaint to reflect that SRG purportedly entered into a
binding settlement with the plaintiff on September 30, 2011 for $155,000.00. SRG also quantifies
3
its costs and attorneys’ fees in this matter at $41.594.33, which includes attorneys’ fees amounting
to $31,285.00.
II.
Motions to Vacate and Amend Complaint
The Court will first address SRG’s request that the Court vacate its summary judgment
order in SRG’s favor. Both third-party defendants point out that the request, which was made in
SRG’s Notice of Settlement, failed to cite to any rule or case that would authorize vacatur of the
order. Federal Rule of Civil Procedure 60(b) sets forth the grounds for relief from a final
judgment, order, or proceeding. That rule states as follows:
On motion and just terms, the court may relieve a party or its legal representative
from a final judgment, order, or proceeding for the following reasons:
(1) mistake, inadvertence, surprise, or excusable negligent;
(2) newly discovered evidence that, with reasonable diligence, could not have
been discovered in time to move for a new trial under Rule 59(b);
(3) fraud, misrepresentation, or misconduct by an opposing party;
(4) the judgment is void;
(5) the judgment has been satisfied, released or discharged; it is based on an
earlier judgment that has been reversed or vacated; or applying it prospectively is no
longer equitable; or
(6) any other reason that justifies relief.
Fed. R. Civ. P. 60(b).
In its Reply memoranda, SRG states that Rule 60(b)(5) or (6) should apply to its request.
The Court disagrees that Rule 60(b)(5) applies to SRG. The judgment in question is a judgment
for SRG, and it has not been “satisfied, released, or discharged.” It is also counterintuitive to
suggest that SRG could seek relief from an order in its favor.
The Court further disagrees that “any other reason...justifies relief” under these
circumstances pursuant to Rule 60(b)(6). SRG suggests that because “summary judgment was
entered on the exact same day that Plaintiff and Defendant SRG had set to file their notice of
settlement of claim with the Court,” such timing justifies relief. SRG states that its “binding”
4
settlement with plaintiff was final on September 30, which was one week after briefing was
completed on all three summary judgment motions that were then-pending in this case, and nearly
two weeks before the Court ruled on SRG’s Motion for Summary Judgment, which had by then
been pending — with no response from plaintiff — for more than three months. Notably, the
parties participated in Alternative Dispute Resolution and notified the Court that they failed to
achieve a settlement on August 5, 2011 (#66). Plaintiff or SRG could have notified the Court that
settlement negotiations were in fact underway, and SRG could have either withdrawn its Motion
for Summary Judgment or asked that the Court hold it in abeyance pending settlement
discussions. Attempting to explain its delay in notifying the Court of the September 30
settlement, SRG states that it and the plaintiff were waiting on Medicare to approve the
settlement. The Court still cannot fathom any reason why the plaintiff and/or SRG would not
notify the Court of the settlement as of September 30, whether or not they were waiting on a nonparty to approve the settlement, particularly in light of SRG’s pending, unopposed summary
judgment motion.
Most important to the Court’s consideration, however, is that vacatur of the summary
judgment in favor of SRG would severely prejudice the third-party defendants, both of whom are
alleged to be liable to defend SRG against the plaintiff’s negligence claims. The Court
determined — based on SRG’s submissions to which plaintiff failed to respond — that SRG was
not negligent, yet SRG wishes to now hold LynnCo and R&M responsible for paying the
$155,000 award to plaintiff. Vacating that judgment prejudices third parties LynnCo and R&M,
and the Court declines to do so.
5
As a result, the Court denies SRG’s Motion for Leave to file Second Amended Third-Party
Complaint, which is premised entirely on SRG’s request that the Court vacate its order granting
summary judgment to SRG.
III.
Summary Judgment Motions
Next the Court turns to the still-pending summary judgment motions filed by LynnCo and
R&M.
A.
Legal Standard
Courts have repeatedly recognized that summary judgment is a harsh remedy that should
be granted only when the moving party has established his right to judgment with such clarity as
not to give rise to controversy. New England Mut. Life Ins. Co. v. Null, 554 F.2d 896, 901 (8th
Cir. 1977). Summary judgment motions, however, “can be a tool of great utility in removing
factually insubstantial cases from crowded dockets, freeing courts’ trial time for those that really
do raise genuine issues of material fact.” Mt. Pleasant v. Associated Elec. Coop. Inc., 838 F.2d
268, 273 (8th Cir. 1988).
Pursuant to Federal Rule of Civil Procedure 56(c), a district court may grant a motion for
summary judgment if all of the information before the court demonstrates that “there is no
genuine issue as to material fact and the moving party is entitled to judgment as a matter of law.”
Poller v. Columbia Broadcasting System, Inc., 368 U.S. 464, 467 (1962). The burden is on the
moving party. Mt. Pleasant, 838 F.2d at 273. After the moving party discharges this burden, the
nonmoving party must do more than show that there is some doubt as to the facts. Matsushita
Elec. Industrial Co. v. Zenith Radio Corp., 475 U.S. 574, 586 (1986). Instead, the nonmoving
party bears the burden of setting forth specific facts showing that there is sufficient evidence in
6
its favor to allow a jury to return a verdict for it. Anderson v. Liberty Lobby, Inc., 477 U.S. 242,
249 (1986); Celotex Corp. v. Catrett, 477 U.S. 317, 324 (1986).
In ruling on a motion for summary judgment, the court must review the facts in a light
most favorable to the party opposing the motion and give that party the benefit of any inferences
that logically can be drawn from those facts. Buller v. Buechler, 706 F.2d 844, 846 (8th Cir.
1983). The court is required to resolve all conflicts of evidence in favor of the nonmoving party.
Robert Johnson Grain Co. v. Chem. Interchange Co., 541 F.2d 207, 210 (8th Cir. 1976).
A district court sitting in diversity applies the law of the state in which it sits. Prudential
Ins. Co. of America v. Kamrath, 475 F.3d 920, 924 (8th Cir. 2007). However, both contracts at
the heart of SRG’s third-party complaint state that Oklahoma law governs the agreements.
Although R&M suggests that Missouri’s “most significant relationship” test should apply (with
the result being that Missouri law governs), under Missouri law, a choice-of-law clause in a
contract generally is enforceable unless application of the agreed-to law is “contrary to a
fundamental policy of Missouri.” Cicle v. Chase Bank USA, 583 F.3d 549, 553 (8th Cir. 2009).
There is no suggestion here that application of Oklahoma law would be contrary to Missouri
policy, and thus the Court will apply Oklahoma law to questions of contract interpretation.
With these principles in mind, the Court turns to the discussion.
B.
LynnCo’s Motion for Summary Judgment
Neither LynnCo nor SRG articulate the elements of SRG’s breach of contract claim.3
Generally speaking, “an indemnity agreement is a valid agreement in Oklahoma.” Fretwell v.
Protection Alarm Co., 764 P.2d 149, 152 (Okla. 1988). To recover on breach of contract in
3
LynnCo mentions that the “fourth element of a claim for breach of contractual
indemnity” is a “breach on the obligation of indemnity,” but LynnCo does not cite to any case or
list the other factors elsewhere in its motion or memoranda.
7
Oklahoma, the plaintiff must prove “(1) formation of a contract; (2) breach of the contract; and
(3) damages as a direct result of the breach.” Digital Design Group, Inc. v. Information Builders,
Inc., 24 P.3d 834, 843 (Okla. 2001).
SRG alleges that LynnCo has a contractual duty to defend and indemnify SRG against
plaintiff Wilson’s claims. SRG’s contract with LynnCo states that LynnCo
shall defend, hold harmless and indemnify [SRG], [SRG’s] officers, directors,
shareholders, and employees, against any claims, demands, damages, including
litigation costs and reasonable attorney’s fees (“Claim(s)”) that are threatened by or
awarded to any party arising out of death or injury as a result of the intentional or
negligent acts or omissions of [LynnCo], or its employees under the Agreement.
LynnCo denies that the contractual indemnification provision applies (thus there could have been
no breach) because, LynnCo argues, plaintiff Wilson’s injuries were not the result of LynnCo’s
“intentional or negligent acts or omissions.” LynnCo states that because it had no right to
exercise control over the premises where plaintiff fell, it could not have been negligent.
SRG counters that although LynnCo did not control SRG’s premises, LynnCo — as the
broker for plaintiff Wilson’s employer R&M Trucking — did control plaintiff’s very presence at
SRG’s facility. Thus, SRG argues, because plaintiff’s Count II was that SRG was negligent by
“requiring employees, contractors, and other individuals . . . to remain and continue working on
the premises,” Count II necessarily implicates LynnCo, who SRG says had control over plaintiff.
SRG then states that if SRG is found to be negligent as to the issue of whether plaintiff
should have been present on the date of injury, a jury will also have to assess whether LynnCo
shares some of that negligence. This Court has already determined that, with respect to Count I,
SRG was not negligent in its failure to remove the ice from its parking lot.
As to plaintiff Wilson’s Count II, plaintiff did not allege that LynnCo had been negligent.
The LynnCo Agreement’s indemnification provision states that LynnCo shall indemnify SRG
8
against “any claims...threatened by or awarded to any party arising out of...injury as a result of
the intentional or negligent acts or omissions” of LynnCo. Although the plaintiff’s complaint
does allege that SRG was negligent by requiring plaintiff, among others, to be on the premises
following the ice storm, the complaint does not allege that LynnCo was in any way negligent.
Indeed, it specifically states that it was SRG, not LynnCo, who required individuals to be on the
premises that day. Furthermore, there is no question that if anyone was responsible for plaintiff’s
appearance at the SRG facility that day, it was SRG, not LynnCo. SRG’s witness testified that
she contacts LynnCo for expedited shipping requests, and the delivery for which plaintiff Wilson
was present that day was not an expedited request; LynnCo was therefore not involved with
plaintiff Wilson’s particular shipment on that day.
Finally, SRG states in its response memorandum that the “thrust” of its claim is that
“should SRG be found negligent on some form of control theory, as set out in Count II of the
Petition, then Lynnco shares some of that negligence, along with the other Third-Party Defendant
R&M.” (Emphasis in original.) This Court held in its October 13 Memorandum (#77) that
The undisputed facts are, however, that the SRG plant was closed on that day, no one
from SRG could compel plaintiff to come to SRG’s facilities, and plaintiff himself
ultimately made the decision to come to SRG on that day. Plaintiff does not make
any effort to contend otherwise. Thus, plaintiff’s claim fails, and summary judgment
will be granted to defendant SRG.
This Court has already held that SRG was not negligent; therefore, by SRG’s own argument,
LynnCo’s own negligence is no longer in question. To the extent that SRG argues that LynnCo
was negligent in some other way not set out in plaintiff Wilson’s complaint, there is no factual
basis to support that any “intentional or negligent acts or omissions” attributable to LynnCo
existed in the underlying action. Thus, there could be no basis for any obligation to indemnify.
As a result, summary judgment will be granted to LynnCo.
9
C.
R&M’s Motion for Summary Judgment
The Broker Agreement to which R&M and LynnCo are parties, and to which SRG is a
third-party beneficiary, provides that R&M
shall defend, indemnify and hold [LynnCo] and its shipper customer [SRG] harmless
from any claims, actions or damages arising out of its performance under the terms
of this Agreement, including cargo loss and damage, theft, delay, damage to property
and personal injury or death...
R&M’s arguments for summary judgment differ from those made by LynnCo. R&M argues that
(1) the Broker Agreement is not valid because it was a contract of adhesion, (2) the
indemnification provision is unenforceable because it is unconscionable, and (3) even if the
contract were valid, plaintiff Wilson’s accident did not arise out of R&M’s performance under
the Broker Agreement, so the indemnification provision does not apply. Because the Court will
grant R&M’s motion based on R&M’s second argument, the Court need not address R&M’s
other arguments.
R&M argues that to the extent that the indemnification provision is read to provide
indemnification for SRG’s own negligence, that the provision is unconscionable and
unenforceable. The provision states that R&M will indemnify SRG for “any claims, actions or
damages arising out of its performance,” apparently regardless of who may be at fault.
Oklahoma law “strictly construe[s] an agreement which would have the result of
indemnifying one against his own negligence, but where the intention to do so is unequivocally
clear from an examination of the contract, such an agreement is enforceable.” Fretwell, 764 P.2d
at 152-53. In Fretwell, the Oklahoma Supreme Court upheld a contract that provided for
indemnification of a security alarm company. In that case, the alarm company provided
monitoring services for its client, and the client agreed to “indemnify, defend and hold [alarm
company] harmless from any and all claims and lawsuits including the payment of all damages,
10
expenses, costs and attorneys fees whether these claims be based upon ... negligence ... on the
part of [alarm company], its agents, servants or employees.” Id. at 152 (emphasis added). The
plaintiff argued that the indemnity clause was unenforceable because it indemnifies the alarm
company from its own negligence, but the Oklahoma Supreme Court disagreed. That court
stated that “it is now the prevailing rule that a contract may validly provide for the
indemnification of one against, or relieve him from liability for, his own future acts of negligence
provided the indemnity against such negligence is made unequivocally clear in the contract.” Id.
(quoting 41 Am. Jur. 2d Indemnity § 9 (1968)). An examination of the contract between the
plaintiff and the alarm company in that case “clearly expresses an intention that the [alarm
company] be indemnified from its own negligence, and we find this agreement to be
enforceable.” 764 P.2d at 153. See also Otis Elevator Co. v. Midland Red Oak Realty, Inc., 483
F.3d 1095, 1103-4 (10th Cir. 2007) (applying Oklahoma law and upholding indemnity provision
that covered indemnitee’s own negligence where the provision allowed for indemnification of
claims “caused by the negligence of [indemnitee]”).
In contrast, courts applying Oklahoma law have held that an indemnitee’s own negligence
is not covered by an indemnification provision that does not contain the “broad and
comprehensive language relating to exculpation from negligence which Oklahoma law requires.”
Transpower Constructors, a Div. of Harrison Intern. Corp. v. Grand River Dam Auth., 905 F.2d
1413, 1421 (10th Cir. 1990) (applying Oklahoma law and citing Standard Ins. Co. v. Ashland Oil
& Refining Co., 186 F.2d 44, 46-47 (10th Cir. 1950)); see also Sinclair Oil & Gas Co. v. Brown,
333 F.2d 967, 968-69 (10th Cir.1964), cited by Transpower, 905 F.2d at 1421 (refusing to
enforce as an indemnification provision a clause which provided, “Contractor ... agrees ... to hold
11
[Sinclair] harmless from any and all liability for damages to the person ... of any and all persons
resulting from the operation of Contractor hereunder”).
Unlike the Fretwell indemnification provision, which specifically stated that “claims . . .
based upon . . . negligence . . . on the part of” the alarm company were to be indemnified, the
Broker Agreement’s indemnification provision does not specifically state that SRG’s negligence
was to be indemnified. Neither plaintiff Wilson nor SRG have claimed that R&M committed any
negligent act or omission. Rather, SRG clearly seeks to hold R&M responsible for a claim of
negligence against SRG. Because the Broker Agreement’s indemnification provision does not
specifically permit indemnification for SRG’s own negligence, R&M did not breach its contract
when it declined to defend and indemnify SRG for plaintiff Wilson’s claim.4 Summary judgment
will therefore be granted to third-party defendant R&M.
IV.
Conclusion
The Court’s order granting summary judgment to SRG, and against plaintiff Glenn
Wilson, will stand. Third-party defendants R&M and LynnCo’s motions for summary judgment
will be granted, thus no issues remain for trial in this matter.
Dated this
8th
day of November, 2011.
UNITED STATES DISTRICT JUDGE
4
The Court is mindful that it addressed a similar argument raised in R&M’s motion to
dismiss. There, R&M argued that the indemnification provision did not apply in the case of
SRG’s own negligence based on this contract term: “Neither Party shall be liable to the other for
any claims, actions or damages due to the negligence of the other Party, or the shipper.” As the
Court held, that contract term limits liability between R&M and LynnCo (the parties to the
agreement) for the negligence of R&M, LynnCo, or SRG (the shipper) — it did not address
R&M’s liability for a third party’s negligence claims. (See #51.) Notably, R&M’s motion to
dismiss did not raise the argument that it raises here: that the indemnification provision could
not apply in this case because Oklahoma courts strictly construe agreements to indemnify a party
against its own negligence.
12