Electric Power Systems International, Inc. v. Zurich American Insurance Company
Filing
67
MEMORANDUM AND ORDER. (See Full Order.) IT IS HEREBY ORDERED that defendant Zurich American Insurance Company's Motion for Summary Judgment 49 is GRANTED. IT IS FURTHER ORDERED that plaintiff Electric Power Systems International, Inc.'s Motion for Partial Summary Judgment on Count I 53 is DENIED. A separate Judgment is entered this date. Signed by District Judge Catherine D. Perry on 9/19/2016. (CBL)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF MISSOURI
EASTERN DIVISION
ELECTRIC POWER SYSTEMS
INTERNATIONAL, INC.,
Plaintiff,
v.
ZURICH AMERICAN INSURANCE
COMPANY,
Defendant.
)
)
)
)
)
)
)
)
)
)
)
No. 4:15 CV 1171 CDP
MEMORANDUM AND ORDER
In July 2014, plaintiff Electric Power Systems International, Inc. (EPS), made
a claim under its commercial general liability insurance policy to defendant Zurich
American Insurance Company for damage that occurred to a transformer while EPS
was working on it. Zurich denied the claim based on two of the Policy’s
exclusions. The undisputed evidence shows that the Policy’s “your work”
exclusion applies to EPS’s claim, and so the Policy provides no coverages. I will
therefore grant Zurich’s motion for summary judgment on all of EPS’s claims and
will deny EPS’s motion. Judgment will be entered in favor of Zurich.
Background
Louisville Gas and Electric Company (LGE) contracted for EPS to remove
and crate parts of a transformer so that the transformer could be transported from
Wisconsin to Kentucky. During the course of removing one of the transformer’s
bushings, EPS failed to extract one of the bolts that secured the bushing to an
electrical lead from the internal coil of the transformer. As a result, when EPS
lifted the bushing from its position on the transformer, the lead that remained bolted
to the bushing was likewise lifted and yanked from the internal coil. Because of the
damage to the coil, the transformer was rendered useless. EPS made a claim under
its commercial general liability policy to its insurance carrier, defendant Zurich.
Zurich denied coverage based on the Policy’s exclusions.
EPS brought this three-count action against Zurich claiming that Zurich
breached the insurance contract by failing to provide coverage for LGE’s claim that
EPS damaged the transformer; that Zurich acted in bad faith when it failed to
effectuate a prompt settlement of LGE’s claim; and that Zurich’s failure to provide
coverage constituted a vexatious refusal to pay. Zurich now moves for summary
judgment on all of EPS’s claims, arguing that the Policy’s exclusions apply to the
property damage at issue here, therefore barring any recovery under the Policy
which, in turn, precludes recovery on EPS’s claims of bad faith failure to settle and
vexatious refusal to pay. EPS moves for summary judgment on its breach of
contract claim, arguing that the Policy exclusions do not apply in the circumstances
of this case.
-2-
Summary Judgment Standard
Summary judgment must be granted when the pleadings and proffer of
evidence demonstrate that no genuine issue of material fact exists and that the
moving party is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(c);
Celotex Corp. v. Catrett, 477 U.S. 317, 322-23 (1986); Torgerson v. City of
Rochester, 643 F.3d 1031, 1042 (8th Cir. 2011) (en banc). I must view the facts in
the light most favorable to the nonmoving party, “but only ‘if there is a genuine
dispute as to those facts.’” RSA 1 Ltd. P'ship v. Paramount Software Assocs., Inc.,
793 F.3d 903, 906 (8th Cir. 2015) (quoting Torgerson, 643 F.3d at 1042).
The parties agree that the relevant facts are not in dispute, but each argues that
the law as applied to those facts requires that judgment be entered in their respective
favor. For the following reasons, Zurich is entitled to judgment as a matter of law
on the undisputed facts of this case.
Evidence before the Court on the Motions
In July 2014, LGE purchased a used transformer from American
Transmission Company (ATC) under a Transformer Sales Agreement that provided
for LGE to test the transformer at the ATC site in Wisconsin and then transport the
transformer from the ATC site to a power plant site in Kentucky. Under the
Agreement, LGE would take title to the transformer upon successful and satisfactory
completion of tests, oil removal, and internal inspection.
-3-
LGE contracted for EPS to test the transformer, drain the oil, assist in the
inspection of the transformer, and remove and crate all parts necessary to relocate
the transformer. The parts to be removed and crated included the transformer’s
bushings. LGE contracted for a separate company, ABB, to conduct the internal
inspection.
On July 24 and 25, 2014, EPS conducted the tests, removed the oil, and
prepared the transformer for internal inspection. ABB completed the internal
inspection the morning of July 29, after which LGE took title to the transformer.
EPS then began its disassembly of the external components, beginning with the
bushings.
The Bushings
The transformer had a number of bushings to be removed and crated for
shipment. Each bushing was attached to the transformer in such a way that the
bottom portion was located inside the transformer and the top portion extended
about nine feet from the top of the transformer. Each bushing had several
connecting bolts, including bolts located on the interior of the transformer as well as
others located externally. The bushings here were bottom-bolted bushings,
meaning that the lead cable from the winding coil of the internal core of the
transformer was bolted to the bottom of the bushing. Therefore, to remove a
bushing from the transformer, the lead cable had to be disconnected from it, which
-4-
required someone to go into the internal components of the transformer and remove
the bolts that attached the bushing to the lead. Removing the bushing from the
transformer without first disconnecting the coil’s lead cable would result in pulling
on the interior core of the transformer and pulling out part of the winding coil.
The Incident
After LGE took title to the transformer on July 29, EPS began the process to
remove the bushings. Only EPS employees worked on the transformer at this time.
During the attempted removal of the first bushing, two members of the EPS
crew were inside the transformer to remove the bolts and disconnect the coil’s lead
cable. Two additional members of the crew were outside the transformer: one
operated the crane to lift the disconnected bushing from the transformer, and the
other was on top of the transformer to guide the bushing as it was being lifted.
When the EPS crew thought that all bolts to the bushing had been removed, the crane
proceeded to lift the bushing from the transformer. However, EPS had failed to
remove an internal bolt that attached the coil’s lead cable to the bushing. The lead
thus remained attached to the bushing when the crane began to lift the bushing from
the transformer.
The crane experienced some resistance in lifting the bushing but continued to
pull upward. A final thrust from the crane forcibly yanked the bushing from the
transformer, causing the bushing in turn to yank the attached lead cable from the
-5-
winding coil, damaging the coil and rendering the transformer useless and beyond
repair. The bushing itself was not damaged.
The Policy and the Claim
At the time of the incident, a commercial general liability policy of insurance
was in effect whereby Zurich agreed to pay sums that EPS was legally obligated to
pay as damages “because of ‘bodily injury’ or ‘property damage’ to which this
insurance applies.” (ECF 54-1, EPS Exh. 1 at p. 1.) The Policy further stated:
We will have the right and duty to defend the insured against any “suit”
seeking those damages. However, we will have no duty to defend the
insured against any “suit” seeking damages for “bodily injury” or
“property damage” to which this insurance does not apply. We may,
at our discretion, investigate any “occurrence” and settle any claim or
“suit” that may result.
(Id.) The Policy defined “property damage” as
a. Physical injury to tangible property, including all resulting loss of
use of that property. All such loss of use shall be deemed to occur at
the time of the physical injury that caused it; or
b. Loss of use of tangible property that is not physically injured. All
such loss of use shall be deemed to occur at the time of the
“occurrence” that caused it.
(Id. at p. 15.)
Under the Policy’s exclusions, insurance did not apply to, inter alia,
j. Damage to Property
“Property damage” to:
...
-6-
(4) Personal property in the care, custody or control of the
insured;
. . . ; or
(6) That particular part of any property that must be restored,
repaired or replaced because “your work” was incorrectly
performed on it.
(Id. at pp. 4-5.)
On July 30, 2014, EPS informed Zurich that damage occurred to the LGE
transformer while a team of EPS employees was disassembling it at the ATC site,
and it asked that a claim be started. On August 11, Zurich informed EPS that it
disclaimed coverage for the incident under Exclusion j(4) of the Policy, that is, the
“care, custody or control” exclusion; and Exclusion j(6) of the Policy, the “your
work” exclusion. After additional investigation into the incident, Zurich continued
to deny EPS’s claim based on these exclusions.1
This action followed.
Discussion
EPS claims that the property damage exclusions invoked by Zurich do not
apply to this incident. With respect to Exclusion j(4), EPS argues that the
transformer was not in its exclusive care, custody, or control when it was damaged
1
EPS avers that it ultimately settled LGE’s claim for $376,706.21, citing “Exhibit 12, Release.”
See Pltf.’s Stmnt. of Uncontroverted Facts, ECF 54 at p. 8. Although Zurich admits to this
averment, see ECF 56-1 at p. 23, neither “Exhibit 12” nor any “Release” has been submitted to the
Court in relation to the parties’ cross motions for summary judgment.
-7-
but was instead under the care, custody, and control of LGE and ATC. With respect
to Exclusion j(6), EPS argues that the particular part on which it was working at the
time of the damage was the bushing and not the coil or core of the transformer, and
thus that the “your work” exclusion would apply only to the bushing and not to the
remainder of the transformer.
For the following reasons, Zurich properly disclaimed coverage of the claim
under Exclusion j(6) of the Policy, the “your work” exclusion.
The parties agree that I must apply Missouri law in this diversity action.
Under Missouri law, “the interpretation of an insurance contract is generally a
question of law[.]” D.R. Sherry Constr., Ltd. v. American Family Mut. Ins. Co.,
316 S.W.3d 899, 902 (Mo. banc 2010). “Under Missouri rules of construction, the
language in an insurance contract is given its plain meaning if the language is plain
and unambiguous.” Becker Metals Corp. v. Transportation Ins. Co., 802 F. Supp.
235, 239 (E.D. Mo. 1992). If an insurance policy is open to different constructions,
Missouri courts will adopt the construction most favorable to the insured. St. Paul
Fire & Marine Ins. Co. v. Missouri United Sch. Ins. Council, 98 F.3d 343, 345 (8th
Cir. 1996). The policy must be read as a whole to determine the intent of the
parties. Columbia Mut. Ins. Co. v. Schauf, 967 S.W.2d 74, 77 (Mo. banc 1998); The
Renco Group, Inc. v. Certain Underwriters at Lloyd’s, London, 362 S.W.3d 472,
478 (Mo. Ct. App. 2012).
-8-
“Under Missouri law the plaintiff [insured] has the burden of showing that the
loss and damages are covered by the policy; the defendant insurer has the burden of
demonstrating the applicability of any exclusions on which it relies.” American
States Ins. Co. v. Mathis, 974 S.W.2d 647, 649 (Mo. Ct. App. 1998). Insurance
policy exclusions are to be strictly construed against the insurer. Capitol Indem.
Corp. v. 1405 Assocs., Inc., 340 F.3d 547, 550 (8th Cir. 2003) (applying Missouri
law).
Business risk exclusions, such as the “your work” exclusion in j(6) of the
Policy here, “are based on the apparently simple premise that general liability
coverage is not intended as a guarantee of the quality of an insured’s product or
work.” Schauf, 967 S.W.2d at 77-78. They are “designed to exclude from
coverage the business risk of faulty workmanship.” Id. at 79. EPS argues that the
“your work” exclusion does not apply to its claim for damage to the transformer
because it was working on only the bushing when the damage occurred. EPS
contends that because the bushing was the “particular part” on which it was working,
Exclusion j(6) applies only to the bushing and not to the remainder of the
transformer. The undisputed evidence shows EPS’s work not to have been so
limited, however.
Policy Exclusion j(6) excludes coverage for property damage to a particular
part of any property on which EPS performed work, if EPS’s work was incorrectly
-9-
performed on it. When EPS worked to remove the bushing from the transformer, it
performed work on the coil’s lead cable by removing the bolts that attached the lead
to the bushing. It was EPS’s action in failing to detach the lead from the bushing
that caused the lead to be pulled from the coil, which is the damage for which EPS
claims coverage. While “detach lead cable from bushing” was not specifically
included in its contract with LGE, EPS’s work to detach the lead was an integral part
in removing the bushing from the transformer. Indeed, disconnecting the lead was
part and parcel of this work –– the bushing simply could not have been removed if
EPS’s work on the lead was not properly performed. Therefore, the coil’s lead
cable was a “particular part” of the property on which EPS worked. See Spirtas Co.
v. Nautilus Ins. Co., 715 F.3d 667, 672 (8th Cir. 2013) (applying Missouri law);
Brake Landscaping & Lawncare, Inc. v. Hawkeye-Sec. Ins. Co., 625 F.3d 1019,
1023 (8th Cir. 2010) (applying Missouri law). Since the damage to the coil was
caused by EPS’s incorrect performance of its work in detaching the coil’s lead cable
from the bushing, Exclusion j(6) applies and there is no coverage for the claimed
damage.
Because the Policy’s “your work” exclusion applies to EPS’s claim for
coverage here, I need not consider whether the “care, custody or control” exclusion
also applies. In addition, because there was no coverage under the Policy, Zurich
cannot be found to have acted in bad faith in failing to settle the claim. See Purscell
- 10 -
v. TICO Ins. Co., 959 F. Supp. 2d 1195, 1200-01 (W.D. Mo. 2013) (insurer could not
have acted in bad faith in failing to settle claim where question existed as to whether
there was even coverage). Nor can Zurich be found to have vexatiously refused to
pay the claim. See Arch Ins. Co. v. Sunset Fin. Servs., Inc., 475 S.W.3d 730, 735
(Mo. Ct. App. 2015).
Accordingly,
IT IS HEREBY ORDERED that defendant Zurich American Insurance
Company’s Motion for Summary Judgment [49] is GRANTED.
IT IS FURTHER ORDERED that plaintiff Electric Power Systems
International, Inc.’s Motion for Partial Summary Judgment on Count I [53] is
DENIED.
A separate Judgment is entered this date.
_________________________________
CATHERINE D. PERRY
UNITED STATES DISTRICT JUDGE
Dated this 19th day of September, 2016.
- 11 -