Varco Pruden Buildings v. Scott Steel Erectors Inc.
Filing
42
ORDER granting 33 Defendant's Second Motion for Leave to Amend its Answer; denying 34 Defendant's Motion to Stay the Case; denying as moot 35 Defendant's Motion to Amend the Scheduling Order. Signed on November 16, 2021, by District Judge Greg Kays. (Law Clerk)
IN THE UNITED STATES DISTRICT COURT FOR THE
WESTERN DISTRICT OF MISSOURI
WESTERN DIVISION
VARCO PRUDEN BUILDINGS,
a division of BLUESCOPE BUILDINGS
NORTH AMERICA, INC.,
Plaintiff,
v.
SCOTT STEEL ERECTORS INC,
Defendant.
)
)
)
)
)
)
)
)
)
)
)
No. 4:20-CV-00438-DGK
ORDER ON MOTIONS TO AMEND AND MOTION TO STAY
This case involves a dispute over payment for steel building materials used in the
construction of a hockey arena in Northern Canada. The Yukon Government hired Scott Design
Build (“SDB”) as its general contractor to construct a hockey arena in Carmacks, Yukon. SBD in
turn contracted with Defendant Scott Steel Erectors Inc. (“Scott Steel”) to erect a pre-engineered
metal building as part of the arena project. Scott Steel then made a purchase order with Plaintiff
Varco Buildings, a division of BlueScope Buildings North America, Inc. (“BBNA”), for the
provision of engineering services and materials necessary to construct the metal building. BBNA
filed a three-count lawsuit in this Court to recover the amount that Scott Steel still allegedly owes
BBNA for the materials and services it provided to Scott Steel.
Now before the Court are Scott Steel’s Second Motion for Leave to Amend its Answer
(ECF No. 33), Motion to Stay the Case (ECF No. 34), and Motion to Amend the Scheduling Order
(ECF No. 35). For the reasons stated below, the Court GRANTS the Second Motion for Leave to
Amend its Answer, DENIES the Motion to Stay the Case, and DENIES AS MOOT the Motion to
Amend the Scheduling Order.
Scott Steel shall file its amended answer within two business days of this order. As outlined
below, the Court finds that BBNA has not proven that the amendment is futile on the current
record, but it should be given the opportunity to test the pleading via a motion to dismiss.
Therefore, to the extent BBNA wishes to move to dismiss the counterclaim, the parties shall adhere
to the following schedule: (1) BBNA shall file any motion to dismiss on or before December 7,
2021; (2) Scott Steel shall file its opposition on or before December 21, 2021; and (3) BBNA shall
file its reply, if any, by January 4, 2022. The Court will issue a revised case schedule via a separate
order.
Procedural Background
On June 4, 2020, BBNA filed this three-count breach of contract lawsuit to recover the
amounts Scott Steel allegedly owes BBNA for the building materials it constructed and provided
to Scott Steel. ECF No. 1. Scott Steel answered. ECF No. 13. The Court then entered a scheduling
order, which set the date to amend pleadings as November 4, 2020. ECF No. 19. On that date,
Scott Steel moved for leave to amend its answer to raise a permissive counterclaim against BBNA.
ECF No. 20. The Court granted Scott Steel’s motion. ECF No. 21.
On December 22, 2020, the Court amended the scheduling order at the parties’ request to
extend the discovery deadline to December 2, 2021. ECF No. 26. The parties then unsuccessfully
tried to resolve the dispute via a mediation in March 2021. The failed mediation led to BBNA
moving to dismiss Scott Steel’s counterclaim, ECF No. 27, and moving to amend the scheduling
order to specify that a party with the burden of proof had to file its expert designations by August
3, 2021, while a party without the burden of proof was required to file its expert designations by
October 5, 2021, ECF No. 29. On April 14, 2021, the Court granted BBNA’s motion to amend
2
the scheduling order. ECF No. 30. Later that same day, Scott Steel dismissed its counterclaims
rather than respond to the motion to dismiss. ECF No. 31.
While the case was percolating here, the underlying construction project in Canada ran into
various snags that resulted in a separate lawsuit. The Yukon Government issued notices of default
to SDB in August and November 2020 and officially terminated SBD as general contractor in
December 2020. On February 12, 2021, the Yukon Government filed a lawsuit (“Yukon Lawsuit”)
against SBD and its insurer Echelon Financial Holdings Inc. for damages related to the failed
construction project, including approximately $10 million in damages from SDB and $7 million
from Echelon. Neither Scott Steel nor BBNA are a party to that lawsuit. 1 On April 13, 2021, SBD
filed its answer and counterclaim against the Yukon Government. In that document, SBD alleges
broadly that a combination of various design issues and changes, brutally cold weather, and
COVID-19 restrictions all contributed to delay the project. ECF No. 39-1. As pertinent here, SBD
specifically alleges that Scott Steel is an affiliated company of SBD, that Scott Steel was the
subcontractor tasked with constructing the pre-engineered arena building, that BBNA supplied the
component parts for the pre-engineered building, that BBNA discovered a flaw in the design
provided to it by one of the Yukon Government’s design firms, that BBNA worked with the firm
to fix the design flaw, and that the design flaw led to a delay in BBNA delivering the materials to
the construction site. Id. ¶¶ 3-11.
Back here in Missouri, on July 23, 2021, Scott Steel filed the instant motion to amend its
answer to add a counterclaim allegedly based on the occurrences in the Yukon Lawsuit. ECF No.
33, 34.
Scott Steel’s proposed amended answer includes a counterclaim for “equitable
Some allegations in Scott Steel’s proposed counterclaim suggests—though do not state—that it is a party in the
Yukon Lawsuit and could be found directly liable therein. That does not appear to be the case based on the pleadings
submitted from that lawsuit. As best the Court can tell, Scott Steel is not a party. So unless it has been added recently,
the only liability it could incur appears to be derivative, downstream liability after that case concludes.
1
3
indemnification” against BBNA for its alleged delay in delivering the materials to Scott Steel that
in turn led to delays in the project. ECF No. 33-1. According to Scott Steel, these alleged delays
contributed to the Yukon Government cancelling its contract with SBD and suing it. Id. And if
SBD, Echelon, and/or Scott Steel are held liable in that action, then equity demands that BBNA
should indemnify Scott Steel. See id. at 14. Contemporaneous with this motion, Scott Steel also
moved to stay this action pending the resolution of the Yukon Lawsuit, ECF No. 34, and it also
moved to amend the expert designation descriptions in the scheduling order, ECF No. 35. These
motions are now ripe for ruling.
Standard
Both Scott Steel’s motion to amend its answer as well as its motion to amend the scheduling
order must satisfy Federal Rule of Civil Procedure 16(b)(4). See Sherman v. Winco Fireworks,
Inc., 532 F.3d 709, 716 (8th Cir. 2008) (holding that motion to amend pleadings after the
scheduling deadline to amend has passed must satisfy Rule 16(b)(4)); see also Fed. R. Civ. P.
16(b)(4). To accomplish this, Scott Steel must establish “good cause.” See Sherman, 532 F.3d at
716. As for its motion to amend its answer, Scott Steel must also establish that the proposed
amendment is proper under Rule 15(a). See Fed. Trade Comm’n v. Next-Gen, Inc., No. 4:18-cv00128-DGK, 2018 WL 5310416, at *3 (W.D. Mo. Sept. 24, 2018). Rule 15(a)(2) broadly provides
that “[t]he court should freely give leave [to amend] when justice so requires.”
As for Scott Steel’s motion to stay, “the district court ha[s] the inherent power to grant [a]
stay in order to control its docket, conserve judicial resources, and provide for a just determination
of the case[] pending before it.” Contracting Nw, Inc. v. City of Fredericksburg, 713 F.2d 382,
387 (8th Cir. 1983). The proponent of the stay bears the burden of establishing the need for it.
Nken v. Holder, 556 U.S. 418, 433–34 (2009). And where, as here, the proponent seeks to stay a
4
case pending resolution of another case, it must typically show a “clear case of hardship or inequity
in being required to go forward.” Landis v. N. Am. Co., 299 U.S. 248, 254–55 (1936).
Discussion
Scott Steel has moved to amend its answer to assert a counterclaim for equitable
indemnification, to stay this case until the Yukon Lawsuit concludes, and to modify the scheduling
order regarding expert designations. BBNA opposes all three requests. The Court addresses each
motion in turn.
I.
Scott Steel is granted leave to amend its answer to assert a counterclaim for
equitable indemnification.
Scott Steel contends that it should be allowed to amend its answer to assert a claim for
equitable indemnification because it satisfies Rule 16(b)(4) and Rule 15(a)(2). BBNA counters
that it fails both standards. The Court holds that Scott Steel has satisfied both standards here.
A. Scott Steel has established “good cause” for the amendment, and the amendment
will not prejudice BBNA.
Scott Steel argues that it should be granted leave to include a claim for equitable
indemnification, because this counterclaim arose from the Yukon Lawsuit that was filed after the
amendment deadline here, it diligently pursued the amendment after researching the claim and
mediating in good faith, and the amendment would not prejudice BBNA since it revolves around
the same facts at the heart of this litigation. Mot. Leave to Amend, ECF No. 33 at 6–9. BBNA
counters that Scott Steel was dilatory in seeking leave to amend by waiting five months after
hearing of the lawsuit to make this motion, and it argues that it would be prejudiced since the
expert deadlines have passed and since it would have to conduct additional discovery. Opp’n to
Mot. Leave to Amend and Stay, ECF No. 39 at 6–9.
5
The inquiry of “good cause” under Rule 16(b)(4) primarily focuses upon “the movant’s
diligence in attempting to meet the order’s requirements.” Sherman, 532 F.3d at 716. But it may
also be proven “by pointing to a change in the law, newly discovered facts, or another significant
changed circumstance that requires amendment of a party’s pleading.” Ellingworth v. Vermeer
Mfg. Co., 949 F.3d 1097, 1100 (8th Cir. 2020). Most motions flounder on the diligence inquiry
but, for those that survive it, the Court must also consider any prejudice that the nonmovant might
suffer from the amendment. See Sherman, 532 F.3d at 717.
Scott Steel’s motion passes these inquiries. The Yukon Lawsuit could be considered either
newly discovered facts or a significant changed circumstance. That lawsuit was not filed until
many months after the amendment deadline, and the proposed counterclaim appears to be
contingent upon the outcome of that case. While it is true that Scott Steel did not file the motion
right after the Yukon Lawsuit was filed, its delay does not seem unreasonable when considered in
context. See Smith v. Truman Rd. Dev., LLC, No. 4:18-cv-670-NKL, 2019 WL 11646255, at *2
(W.D. Mo. Mar. 26, 2019) (“While Rule 16’s ‘good cause’ standard requires diligence on the part
of the movant, the requirement is not so stringent as to require instantaneous amendment.”). The
parties engaged in mediation in March in hopes of settling this matter and, following the failed
mediation, Scott Steel spent time researching the factual and legal viability of its claim. This led
Scott Steel to filing the motion a few months after the mediation, but four months before the current
fact discovery deadline. The Court finds both diligence and changed circumstances here.
Turning to prejudice, it is true that the expert deadlines have passed and that BBNA may
have to conduct further discovery into Scott Steel’s new claim. But this poses no true prejudice to
BBNA, because the Court is extending expert and discovery deadlines to accommodate this new
claim. Not only that, but the new claim is based on the same core facts already at the heart of this
6
litigation and the parties’ previous discovery. Indeed, BBNA concedes as much when it states that
Scott Steel raised BBNA’s delay in providing materials as an affirmative defense on July 28, 2020.
Opp’n to Mot. Amend Scheduling Order, ECF No. 36 at 1. Thus, BBNA has long known about
the factual basis of this claim; only the legal hook has been altered from simply an affirmative
defense to an affirmative claim by the filing of the Yukon Lawsuit. So BBNA will not be
prejudiced by the amendment here. See Glob. Control Sys., Inc. v. Luebbert, No. 4:14-cv-657DGK, 2016 WL 8730159, at *6 (W.D. Mo. Jan. 15, 2016).
The Court thus holds that Scott Steel has satisfied Rule 16(b)(4).
B. Scott Steel has established that amendment is proper under Rule 15(a)(2).
Scott Steel argues that it also satisfies the requirements under Rule 15(a)(2), because there
is no evidence of undue delay, bad faith, or undue prejudice. Mot. Leave to Amend, ECF No. 33
at 4–6. Scott Steel further argues the amendment is not futile. Id. at 5. BBNA disagrees on all
four fronts, largely repeating the arguments it raised against good cause under Rule 16(b)(4).
Opp’n to Mot. Leave to Amend and Stay, ECF No. 39 at 9–13. But it also claims there is additional
evidence of bad faith or undue delay, because Scott Steel allegedly stonewalled discovery
responses about the Yukon Lawsuit and did not move to amend the pleadings when BBNA moved
to change the expert deadlines. Id. at 10–11. BBNA further makes a largely factual argument that
the amendment is futile. Id. at 11–13.
Under Rule 15(a)(2), a motion to amend may be denied only “if there are compelling
reasons such as undue delay, bad faith, or dilatory motive, repeated failure to cure deficiencies by
amendments previously allowed, undue prejudice to the non-moving party, or futility of the
amendment.” Reuter v. Jax Ltd., Inc., 711 F.3d 918, 922 (8th Cir. 2013). An amended complaint
7
is futile if it could not withstand a Rule 12(b)(6) motion to dismiss. See In re Senior Cottages of
Am., LLC, 482 F.3d 997, 1001 (8th Cir. 2007).
The Court finds no evidence of undue delay, bad faith, dilatory motive, or undue prejudice.
The Court has already explained there was not undue delay or prejudice. And Scott Steel’s
discovery responses and failure to move for amendment earlier does not rise to the level of bad
faith or a dilatory motive. While Scott Steel’s objection to BBNA’s discovery about the Yukon
Lawsuit as “irrelevant” is meritless, Scott Steel states in its reply that it has withdrawn that
objection and agreed to produce the responsive documents. To the extent Scott Steel obstructs
discovery on these points with baseless objections, this can be dealt with via the Court’s discovery
dispute mechanism. It is not a reason to deny amendment. Further, although Scott Steel could
have moved to amend earlier, the couple month lag does not definitively prove dilatory motive
given the significant amount of time left in the discovery period.
Futility is a closer call. BBNA makes a strong factual argument that Scott Steel’s claim
for equitable indemnification seems too conditional and hypothetical to be truly viable. At bottom,
Scott Steel’s counterclaim seeks to hold BBNA liable if SBD is found liable in the Yukon
Government case and if SBD then later has a viable claim against Scott Steel for contributing to
that liability. Ultimately, this claim may not sufficiently state a claim under the governing law,
may not be ripe for adjudication, or may not even pass the Article III standing test. But the problem
at this stage is that BBNA has not sufficiently demonstrated under Rule 12(b)(6) that the proposed
counterclaim should be dismissed. As an initial matter, neither party identifies precisely which
state’s law applies to this claim: BBNA cites a Missouri law case, while Scott Steel cites a Virginia
law case. While Missouri law appears to apply based on what little information is available, the
8
only Missouri law case BBNA cites is one in which a motion to dismiss was denied. The Court,
thus, cannot definitively say that amendment would be futile.
Although amendment cannot be said to be futile on the current record, BBNA should have
the opportunity to test the sufficiency of the pleadings. Even Scott Steel suggests as much. Reply
Br. ISO Mot. to Amend Pleadings, ECF No. 40 at 7 (“Much of BBNA’s remaining arguments are
suited for a motion to dismiss, not a response opposing leave to amend.”). If BBNA intends to file
a motion to dismiss, it must do so in accordance with the schedule set forth in this order. But for
now, Scott Steel has satisfied the standards to be given leave to amend to its answer to assert a
counterclaim. It must make the appropriate filing in accordance with the Court’s directives in the
introduction.
II.
Scott Steel has failed to show that a stay is appropriate.
Scott Steel seeks to stay this entire case through the resolution of the Yukon Lawsuit. Scott
Steel argues that it would suffer hardship and inequity by moving forward with its counterclaim
without knowing the exact scope of its potential liability from that lawsuit. Mot. to Stay, ECF No.
34 at 3–6. It also contends that judicial economy would be served by allowing that case to proceed
through discovery and then using the findings and discovery from that case to narrow the issues
here. Id. BBNA argues that it would suffer substantial prejudice by having this case stayed and,
instead, the cases should proceed in parallel. Opp’n to Mot. Leave to Amend and Stay, ECF No.
39 at 13–15.
The parties agree that where, as here, a court considers a request to stay a case in favor of
a parallel and overlapping action, it typically considers the following three factors: “(1) potential
prejudice to the nonmoving party; (2) hardship and inequity to the moving party if the action is not
stayed; (3) the judicial resources that would be saved by avoiding duplicative litigation.” U.S. Bank
9
Nat’l Ass’n v. Moses, No. 4:16-cv-730-CEJ, 2016 WL 7178750, *2 (E.D. Mo. Dec. 9, 2016).
Courts may also consider whether a stay would “narrow[] the factual and legal issues in
the…proceeding,” Lockyer v. Mirant Corp., 398 F.3d 1098, 1112 (9th Cir. 2005), as well as “the
time reasonably expected for resolution of the ‘other case’,” Wedgeworth v. Fireboard Corp., 706
F.2d 541, 545 (5th Cir. 1983).
These factors weigh against a stay. First, the potential prejudice to BBNA could be
substantial, because it could take years for the Yukon Lawsuit to conclude and, even then, the
result of the lawsuit may have absolutely no impact on this case. For example, given the seemingly
conditional nature of Scott Steel’s counterclaim, SBD may not even be found liable in that lawsuit
or SBD may be held liable but decide not to impose any derivative liability on Scott Steel. BBNA
should not be made to wait potentially years to prosecute its claims.
Second, the Court cannot say that Scott Steel will suffer substantial inequity or hardship
by moving forward with this case. As stated above, it is far from certain that Scott Steel would
incur any downstream liability from the Yukon Lawsuit. And it is not a party there, so it will not
be suffering hardship from fighting a two-front battle. Nor has it shown that it definitively cannot
bring its proposed counterclaim in a future action should it eventually be held liable.
Third, a stay would not necessarily conserve judicial resources. While both the cases
sprung from the same construction project, the core allegations in the cases are different. Contrary
to Scott Steel’s characterization, the Yukon Lawsuit’s pleadings do not center around the work
performed by Scott Steel or BBNA. The parties there seem to be primarily focused on other
reasons for the delays and failures in the project. So there is no guarantee that waiting for the
conclusion of that lawsuit will narrow the legal or factual issues in this case or materially reduce
the discovery that needs to be conducted here. Since the Yukon Lawsuit is still in its relative
10
infancy with little to no discovery having taken place, it makes no sense for this case to be stayed
potentially for years in deference to a lawsuit that may have no impact here.
For all these reasons, the Court declines to stay this case.
III.
Scott Steel’s motion to amend the scheduling order is denied as moot.
Scott Steel finally moves to amend the expert designation deadlines in the scheduling order.
The operative scheduling order states that: “1. Party with the burden of proof’s expert designations
shall be filed on or before August 3, 2021”; and “2. Party without the burden of proof’s expert
designations shall be filed on or before October 5, 2021.” ECF No. 30. Scott Steel does not want
to change the dates in the current order, but it asks to revert the language to “Plaintiff’s expert
designations shall be filed on or before August 3, 2021” and “Scott Steel’s expert designations
shall be filed on or before October 5, 2021.” Mot. to Amend Scheduling Order, ECF No. 35 at 3.
BBNA complains that Scott Steel has not shown good cause for the change since it waited until
just a few days before the first expert deadline to move to amend instead of doing so months ago.
Opp’n to Mot. to Amend Scheduling Order, ECF No. 36 at 1.
The Court is disappointed that the parties could not resolve what seems to be an
inconsequential and a semantical debate over the scheduling order. But the Court need not wade
into this debate between the parties, because it finds that the assertion of the new counterclaim will
require discovery to be extended. It will set a new deadline for expert disclosures as well as all
the remaining deadlines in this case. In so doing, the Court will impose a single deadline for all
expert designations regardless of who has the burden on a claim or defense. All opening expert
designations must be filed by this deadline. The Court will also set a rebuttal expert deadline, but
that is just for unexpected rebuttal issues that arise from the first phase of expert designations and
discovery. The Court has successfully used this type of schedule in many other cases, including
11
ones far more complex than this one. The Court is hopefully that the parties will not have any
further need to amend the schedule after entry of the revised schedule. But should a pressing need
to amend arise, the parties are strongly advised to work together and present a joint proposal.
Conclusion
For the foregoing reasons, the Court GRANTS Scott Steel’s Second Motion for Leave to
Amend its Answer, DENIES Scott Steel’s Motion to Stay the Case, and DENIES AS MOOT Scott
Steel’s Motion to Amend the Scheduling Order. Scott Steel must file its amended answer within
two business days of this order. If BBNA chooses to file a motion to dismiss, the following
schedule shall apply: (1) BBNA shall file any motion to dismiss on or before December 7, 2021;
(2) Scott Steel shall file its opposition on or before December 21, 2021; and (3) BBNA shall file
its reply, if any, by January 4, 2022. The Court will issue a revised case schedule via a separate
order.
IT IS SO ORDERED.
Date: November 16, 2021
/s/ Greg Kays
GREG KAYS, JUDGE
UNITED STATES DISTRICT COURT
12
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?