Hapner et al v. Tidwell et al
Filing
112
ORDER denying 108 Motion to Stay. Signed by Judge Donald W. Molloy on 10/19/2011. (dle)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MONTANA
MISSOULA DIVISION
NATIVE ECOSYSTEMS COUNCIL,
ALLIANCE FOR THE WILD
ROCKIES, and SHARON J. HAPNER,
)
)
)
)
Plaintiffs,
)
)
)
v.
)
)
TOM TIDWELL, Regional Forester of
)
Region One of the U.S. Forest
)
Service, and UNITED STATES FOREST )
SERVICE, an agency of the U.S.
)
Department of Agriculture,
)
)
Defendants,
)
)
v.
)
)
JANET G. HARTMAN and
)
RONALD E. HARTMAN,
)
)
Defendant-Intervenors.
)
___________________________________ )
CV 08-92-M-DWM
CV 09-79-M-DWM
(consolidated)
ORDER
This case presents a challenge to the Smith Creek Project, an “integrated
vegetation treatment” project intended to modify wildfire behavior in the
wildland-urban interface near the Smith Creek Subdivision in the Livingston
Ranger District of the Gallatin National Forest. On July 12, 2011, this Court
1
entered an Order granting the Federal Defendants’ motion to dissolve the
injunction against the Smith Creek Project and closing the case file. Doc. No. 102.
The Plaintiffs then filed a motion to alter or amend the judgment and for relief
from judgment, which was denied on August 11, 2011. Doc. No. 105. The
Plaintiffs filed a Notice of Appeal on September 21, 2011, and have now filed a
motion to stay the dissolution of the injunction pending the outcome of the appeal.
The motion is denied.
This litigation began with an action filed July 1, 2008, in which Plaintiffs
alleged the Project was approved in violation of NEPA and NFMA because the
Environmental Assessment was inadequate and the Project violated the Forest
Plan. The Court denied the Plaintiff’s motion for a preliminary injunction and
denied their motion to stay pending appeal of the denial of a preliminary
injunction. Doc. Nos. 7, 19. On summary judgment, the Federal Defendants
prevailed on every claim except one related to elk mapping, and the Court
enjoined the Project and remanded to the Forest Service to fulfill its legal
obligation to map key habitat components for elk. Doc. No. 40. After
supplementing the Environmental Assessment with elk mapping information, the
Forest Service re-approved the Project on March 6, 2009.
Plaintiffs challenged the re-approved Project, the prescribed actions of
2
which were unchanged from the original, in a new lawsuit, Native Ecosystems
Council v. Tidwell, CV 09-79-M-DWM. The Court consolidated the newly filed
case with this action and dismissed all claims that had already been adjudicated,
leaving a single issue to be decided: whether the Service had met its elk mapping
responsibility such that the injunction against the Project should be dissolved. The
Court held that the Service had complied with the law regarding elk mapping, and
issued an Order dissolving the injunction on October 8, 2009. Doc. No. 70.
Plaintiffs appealed, challenging both the decision to dissolve the injunction and
the Court’s earlier Order on summary judgment. They filed another motion to stay
pending appeal, which was denied. Doc. No. 80.
The Ninth Circuit issued an Order dated February 8, 2010, staying this
Court’s Order dissolving the injunction pending the issuance of a written opinion.
Doc. No. 83. The appellate panel filed its opinion on September 15, 2010,
reversing this Court’s Order dissolving the injunction and remanding the case.
Hapner v. Tidwell, 621 F.3d 1239 (9th Cir. 2010). The court of appeals held that
the Plaintiffs’ NFMA challenge to the Service’s elk hiding cover calculation was
their “single meritorious argument” on appeal. Id. at 1250. Following remand
from the Ninth Circuit, this Court remanded to the agency “to remedy the error
described in the Ninth Circuit Court of Appeals’ opinion[.]” Doc. No. 86.
3
On remand, the Forest Service performed a new hiding cover calculation
and determined that the Project complies with the Gallatin Forest Plan’s hiding
cover requirements. The Federal Defendants then moved to dissolve the
injunction, and the Court granted the motion and closed the case. Doc. No 102.
The Court subsequently denied the Plaintiffs’ motion to alter or amend the
judgment and from relief from judgment, explaining:
The motion boils down to a disagreement over whether the Ninth
Circuit made an express factual finding when it wrote, while
describing one of the two insufficient calculations of hiding cover
offered by the Forest Service, “The other calculation suggested 62%
elk cover under a canopy cover definition.” Hapner v. Tidwell, 621
F.3d 1239, 1250 (9th Cir. 2010). Plaintiffs view the statement as a
finding of fact that there is 62 percent hiding cover under a canopy
cover definition. For the reasons set forth in detail in the Dissolution
Order, Doc. No. 102 at 5-11, the Court takes a different view, and
finds that the statement is merely a characterization of one of the
calculations that the panel found lacking. The fact that the Forest
Service did an unsatisfactory job of calculating hiding cover the first
time around does not mean it is estopped from doing a better job on
remand. See Dissolution Order, id. at 26.
Doc. No. 105 at 3.
In its Order denying the motion to alter or amend the judgment and for relief
from judgment, the Court also observed that “[t]he claims alleged in this action
have been heard on summary judgment, heard in the court of appeals, heard on
remand in this Court, and twice remanded to the agency.” Doc. No. 105 at 2. To
that lengthy procedural history the Plaintiffs now add a third motion to stay
4
pending appeal.
The standard for evaluating an injunction pending appeal mirrors the
standard for granting a preliminary injunction. Lopez v. Heckler, 713 F.2d 1432,
1435 (9th Cir. 1983). Injunctive relief is appropriate if the plaintiff “establish[es]
that he is likely to succeed on the merits, that he is likely to suffer irreparable harm
in the absence of preliminary relief, that the balance of equities tips in his favor,
and that an injunction is in the public interest.” Winter v. Natural Resources
Defense Council, Inc., 555 U.S. 7, 20 (2008). “A preliminary injunction is an
extraordinary remedy never awarded as of right.” Id. at 24. Following Winter, in
Alliance for the Wild Rockies v. Cottrell, 632 F.3d 1127 (9th Cir. 2011), the Ninth
Circuit clarified that its “serious questions” approach to preliminary injunctions
survives Winter when applied as part of the four-part Winter test. Id. at 1132.
Thus, once a plaintiff has shown a likelihood of irreparable injury and that the
injunction is in the public interest, an injunction is warranted if the plaintiff can
further show that there are “‘serious questions going to the merits’ and the balance
of hardships tips sharply towards the plaintiff.” Id. at 1135.
Plaintiffs argue that the Court may not engage in its own analysis of the
Winter factors because the Ninth Circuit has already done so, and the appellate
court’s holdings in that regard may not be revisited by the district court. Plaintiffs
5
refer to the Ninth Circuit panel’s December 21, 2009, Order, in which the panel
held that the Plaintiffs had established all of the Winter factors as to all but 435
acres of the Project area, and the panel’s February 8, 2010, Order, finding the
standard established as to the entire Project area. Doc. Nos. 82, 83. Plaintiffs say
that to the extent the Ninth Circuit has determined that any of the Winter factors
are met with regard to the proposed agency action, the Court is bound by that
determination so long as there has been no material change in circumstances. For
support they rely on Vizcaino v. U.S. Dist. Court for Western Dist. of Washington,
in which the Ninth Circuit stated, “On remand, the trial court can only consider
‘any issue not expressly or impliedly disposed of on appeal.’” 173 F.3d 713, 719
(9th Cir. 1999) (quoting Firth v. United States, 554 F.2d 990, 993 (9th Cir. 1977)).
The argument has some merit because, as the Federal Defendants concede,
the planned Project activities have remained unchanged throughout this litigation.
Nor have the Federal Defendants or Defendant-Intervenors identified any change
in the circumstances on the ground in the surrounding area, such as factors leading
to heightened fire danger, that would justify revisiting the matters already decided
by the Ninth Circuit. Thus, the panel’s application of the Winter factors remains
relevant and controlling with respect to three of the four factors: the Plaintiffs are
likely to suffer irreparable harm in the absence of preliminary relief; the balance of
6
equities tips in their favor; and a stay is in the public interest. Doc. Nos. 82, 83.
It is as to the fourth factor, i.e, serious questions going to the merits, that a
change in circumstances has left the Plaintiffs unable to meet the Winter standard.
The Ninth Circuit found the Plaintiffs likely to succeed on the merits of their
appeal because the Forest Service had failed to calculate elk hiding cover as
required by the Forest Plan. As this Court has twice explained, see Doc. Nos. 102
and 105, the Forest Service’s actions on remand directly addressed that deficiency
and brought the Project into full compliance with the Forest Plan, triggering
dissolution of the injunction. The Plaintiffs’ arguments against dissolution,
addressed in detail in the in the Dissolution Order, Doc. No. 102 at 5-11, are not
based on the language of the applicable statute or the Forest Plan standard; instead
they are based on a fundamental misinterpretation of the Ninth Circuit’s opinion
and do not raise serious questions going to the merits. The Plaintiffs have
therefore failed to meet the standard for a stay pending appeal.
Accordingly, IT IS HEREBY ORDERED that the Plaintiffs’ motion for a
stay of dissolution pending appeal (Doc. No. 108) is DENIED.
Dated this 19th day of October, 2011.
7