Flathead Irrigation District v. Jewell et al
Filing
76
ORDER granting 55 Motion to Dismiss for Lack of Jurisdiction; finding as moot 60 Motion for Order/Judgment; denying 66 Motion to Amend/Correct. Signed by Chief Judge Dana L. Christensen on 8/19/2015. (dle)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MONTANA
MISSOULA DIVISION
FLATHEAD IRRIGATION
DISTRICT; and FLATHEAD JOINT
BOARD OF CONTROL
CV 14–88–M–DLC
ORDER
Plaintiffs,
vs.
SARAH “SALLY” JEWELL,
Secretary of the Department of the
Interior; STANLEY SPEAKS,
Portland Area Director, Bureau of
Indian Affairs; JOSEPH “BUD”
MORAN, Superintendent, Flathead
Agency, Bureau of Indian Affairs; U.S.
DEPARTMENT OF THE INTERIOR;
and U.S. BUREAU OF INDIAN
AFFAIRS,
Defendants.
Plaintiffs Flathead Irrigation District (“FID”) and Flathead Joint Board of
Control (“FJBC”), filed this action seeking declaratory and injunctive relief
against the above-named Defendants, collectively “the United States,” for claims
arising out of the United States’ recent and historical actions with respect to the
Flathead Irrigation Project. The United States has moved to dismiss all of the
claims. After briefing on the United States’ motion to dismiss was completed,
1
Plaintiffs’ moved the Court for leave to file their Second Amended Complaint.
For the reasons explained, the Court grants the motion to dismiss and denies the
motion for leave to file the Second Amended Complaint.
BACKGROUND1
A.
Historical and Legal Background
This dispute has its origins in the formation of the Flathead Reservation in
1855, its allotment in 1904, and subsequent Congressional Acts over the next
100+ years, which together form the current legal landscape. Therefore, some
historical context and discussion of the evolving legal landscape is required.
By the Treaty of Hellgate of 1855, the Bitteroot Salish, the Pend d’Oreille,
and the Kootenai tribes (“the Tribes”) ceded to the United States all right, title,
and interest in a vast area of land formerly held by the Tribes under aboriginal
title. 12 Stat. 975 (1855). In exchange, the United States agreed to pay to the
1
Plaintiffs’ Statement of Disputed Facts is not in compliance with Local Rule 56.1(b).
Local Rule 56.1(b) requires a party opposing summary judgment to file a Statement of Disputed
Facts which sets forth verbatim the moving party’s Statement, and “adding only (A) whether
each fact in the moving party’s Statement is ‘undisputed’ or ‘disputed’; and (B) if ‘disputed,’
pinpoint to a [record document before the Court] to oppose each fact.” L.R. 56.1(b)(1) (emphasis
added). The rule does not allow for a response of “Undisputed and Qualified” or “Undisputed
but Qualified,” as submitted by Plaintiffs. If a fact is undisputed, the response must simply state:
“undisputed.” The rule does not allow for tangential flourishes to be tacked on to a response
when a fact is undisputed. That would defeat the purpose of the rule. If additional facts are
relied on to oppose a motion for summary judgment, those may be added separately, as provided
in L.R. 56.1(b)(2). Legal theories and arguments are not facts.
Accordingly, IT IS ORDERED that all portions of Plaintiffs’ Statement of Disputed Facts
that do not comply with Local Rule 56.1(b) are STRICKEN.
2
Tribes the sum of $120,000, and from the vast area of land ceded to the United
States, the Treaty of Hellgate reserved, “for the exclusive use and benefit” of the
Tribes, the Flathead Reservation. The Flathead Reservation is comprised of
approximately 1.317 millions acres and is located in northwest Montana. Id.
The nature of this large and undivided Indian reservation was dramatically
altered in 1904 with the passage of the Act of April 23, 1904, 33 Stat. 302, known
as the Flathead Allotment Act. Pursuant to the Flathead Allotment Act, the
Flathead Reservation was surveyed and divided into parcels. Certain of these
parcels were then “allotted” to individual Indians, but not all of them. The lands
not allotted to individual Indians were deemed “surplus lands,” and were opened
for purchase and settlement by non-Indians.
Relevant to this case, the Flathead Allotment Act directed that the proceeds
received from the sale of reservation “surplus lands” should be used to construct
irrigation works for the exclusive benefit of the Tribes. However, pursuant to the
Act of April 30, 1908, 35 Stat. 70, use of the irrigation works was authorized for
irrigation of both Indian and non-Indian lands within the boundaries of the
Flathead Reservation. Congress then prioritized the construction of irrigation
works on the Flathead Reservation and required that payment for the construction
and operating costs of the irrigation system be made through assessments to non3
Indian land purchasers. Flathead Joint Bd. of Control of Flathead, Mission and
Jocko Valley Irr. Dists. v. United States, 30 Fed. Cl. 287 (1993); 35 Stat. 444, 44850 (hereinafter “1908 Act”). Critical to this case, the 1908 Act contained a
“turnover” or “transfer” provision, which reads as follows:
When the payments required by this Act have been made
for the major part of the unallotted lands irrigable under
any system and subject to charges for construction thereof,
the management and operation of such irrigation works
shall pass to the owners of the lands irrigated thereby, to be
maintained at their expense under such form of
organization and under such rules and regulations as may
be acceptable to the Secretary of the Interior.
35. Stat. at 450.
These irrigation works, first authorized under the 1904 Act, are now known
as the Flathead Irrigation Project (“the Project”). The Project currently supplies
irrigation to approximately 127,000 acres of agricultural land in Flathead,
Missoula, Lake, and Sanders counties of Montana, and the Flathead Reservation.
In 1926, Congress appropriated funds for continued construction of a power
plant at the Project. The Act also appropriated funds for construction and
maintenance of the irrigation division of the Project. 44 Stat. 453, 465. As a
condition precedent for the appropriation of these funds, Congress required that
irrigation districts be formed under state law and that those districts execute
4
repayment contracts with the United States for previously unpaid construction
costs. Flathead, 30 Fed. Cl. at 290. To help defray costs, Congress directed that
the net revenues from the power plant be paid to the United States to liquidate
construction, operation, and maintenance costs for the Project. 35 Stat. 453, 465.
As of 1948, the amounts owed from irrigators for the Project remained
unpaid. Congress therefore created a repayment schedule to pay back all thenexisting construction debt over a 50 year period, and required the irrigation
districts to execute amendatory repayment contracts.. Flathead, 30 Fed. Cl. at
290-91; 62 Stat. 269 (“1948 Act”). The 1948 Act provided that annual
installments initially be paid from net power revenues from the power division,
and then by an assessment against lands chargeable with the construction costs.
Id. at 291.
The United States’ policy with respect to Indian peoples changed in 1934.
In 1934 the United States policy of allotment “was repudiated . . . with the passage
of the Indian Reorganization Act.” Montana v. United States, 450 U.S. 544, 559,
n. 9 (1981)(citing 48 Stat. 984, at 25 U.S.C. § 461 et seq). Under the Indian
Reorganization Act, the Secretary of the Interior was “authorized to restore to
tribal ownership the remaining surplus lands of any Indian reservation heretofore
opened” to sale to non-Indians. 25 U.S.C. § 463(a). Pursuant to this authority, in
5
1936 the Secretary restored certain surplus lands on the Flathead Reservation to
the Tribes.
The United States policy with respect to Indian peoples changed again with
the passage of the Indian Self-Determination and Education Assistance Act
(“Indian Self-Determination Act”) in 1975. Through the Indian SelfDetermination Act, Congress declared its commitment to “assuring maximum
Indian participation in the direction of educational as well as other Federal
services to Indian communities.” 25 U.S.C. § 450a. Congress sought to
accomplish this goal:
through the establishment of a meaningful Indian
self-determination policy which will permit an orderly
transition from the Federal domination of programs for,
and services to, Indians to effective and meaningful
participation by the Indian people in the planning, conduct,
and administration of those programs and services.
25 U.S.C. § 450a. Consistent with this goal, Congress authorized the Secretary of
the Interior and tribes to enter into contracts, commonly referred to as selfdetermination or P.L. 638 contracts, “in which tribes promise to supply federally
funded services, for example tribal health services, that a Government agency
would otherwise provide.” Cherokee Nation of Oklahoma v. Leavitt, 543 U.S.
631, 634 (2005) (citing 25 U.S.C. § 450f).
6
In 1986, the Tribes entered into such a P.L. 638 contract with the Secretary
in order to assume operation and management of the Power Division of the
Project. In response, in 1992, the FJBC sued the United States in the United
States Court of Federal Claims. In that suit, the FJBC “alleg[ed] that, under the
1908 Act, they were entitled to operation of both the irrigation and power
divisions and that defendant's failure to turn over those operations was a breach of
statutory (four counts) and contractual (seven counts) obligations. Plaintiffs
further alleged that [the United States’] failure to turn over the operation and
maintenance of the irrigation and power divisions, and [the United States’]
contract with the tribes to operate the power division, constituted a temporary
taking for which they were entitled to just compensation under the Fifth
Amendment to the Constitution.” Flathead, 30 Fed. Cl. at 291. All but three of
the claims were dismissed for either lack of jurisdiction or failure to state a claim.
Id. at 296. The only claims that survived were contract claims based on alleged
breaches of amendatory repayment contracts signed by the irrigation districts in
accordance with the 1948 Act.
B.
The Current Dispute
The current dispute stems from a breakdown in the efforts to transfer
operation and management of the Project to the landowners in accordance with the
7
1908 Act. Plaintiff FJBC is a public corporation under Montana law that serves as
the central control agency of the Flathead, Mission, and Jocko Irrigation Districts.2
Plaintiff FID is a public corporation under Montana law with the authority and
responsibility to represent landowners within the boundaries of the FID as to
irrigation matters.3 FID is one of three irrigation districts that comprise the FJBC.
Until 2010, Defendant BIA was responsible for the operation and
management of the Project. In 2004, the final portion of the construction costs of
the Project was repaid,4 and thus, pursuant to the Act of 1908, operation and
management of the Project was then to be transferred to the owners of the land
irrigated by the Project. 35 Stat. 444, 449-450. Accordingly, in March of 2010,
the FJBC and the Tribes entered into the Cooperative Management Entity
Agreement. This Agreement created the Cooperative Management Entity
(“CME”), which was comprised of an equal number of appointed representatives
2
Given that two of the three irrigation districts have withdrawn from the FJBC, it is not
clear whether the FJBC is currently constituted.
3
Plaintiffs allege that the FJBC is a “local governmental entity,” (Doc. 14 at 2), and that
the FID is an “elected local government[],” id. at 3, but these allegation are plainly contrary to
Montana law, which provides that “[e]very irrigation district . . . is a public corporation.” Mont.
Code Ann. § 85-7-109. This is true despite the fact that irrigation districts have annually elected
commissioners and the authority to levy taxes or assessments on lands within an irrigation
district.
4
As noted above, the actual method of repayment of the construction and operating costs
was modified numerous times by Congressional Acts.
8
of the Tribes and the FJBC and was formed to jointly manage and operate the
Irrigation Division of the Project. Upon execution of the Cooperative
Management Entity Agreement, the FJBC, the Tribes, and the Department of the
Interior entered into the “Transfer Agreement,” which permitted the CME to
assume management and operational control of the Irrigation Division of the
Project in accordance with the 1908 Act.5
The Transfer Agreement and CME Agreement represented the culmination
of several years of negotiations between the BIA, the FJBC, and the Tribes to
effectuate transfer in accordance with the 1908 Act. Significantly, the Transfer
Agreement contained a provision for the “emergency reassumption of the
operation and management of all or part of the Project” by the BIA if the Secretary
of the Interior determined such emergency reassumption was necessary. (Doc. 282 at 14.)
Following the execution of the Transfer Agreement, the CME managed the
Project from 2010 through early 2013. However, beginning in May of 2013,
during the FJBC’s regularly scheduled elections, certain FJBC board members
who were supportive of the Transfer Agreement were voted off the Board. Soon
5
As noted above, since 1986, the Power Division of the Project has been operated by
the Tribes pursuant to a P.L. 638 Contract.
9
afterward, significant disagreements concerning the CME’s operation and
management of the Project arose among the three irrigation districts. In December
of 2013, two of the three irrigation districts comprising the FJBC, the Mission and
Jocko irrigation districts, voted to withdraw from the FJBC, and the FJBC was
effectively dissolved.
The Commissioners of the two withdrawing districts then wrote to the BIA
and formally requested that the BIA temporarily reassume Project operations in
order to “safeguard the [P]roject and trust assets.” (Doc. 28-4 at 3.) Consistent
with this request, in a letter dated January 15, 2014, the BIA invoked the
emergency reassumption provision of the Transfer Agreement, and informed the
chairmen of the CME that it would resume operation and management of the
Project “in a limited capacity” in order “[t]o protect its federal assets and the trust
resources of the CSKT.” (Doc. 28-5 at 2.) The BIA intended that its reassumption
of operation of the management of the Project would be limited, temporary, and
serve only as a stop-gap measure in order to maintain services to irrigators during
the 2014 irrigation season while the parties negotiated a long term solution.
By letter of February 3, 2014, the BIA proposed reconstituting a modified
version of the CME to serve as the legal entity with responsibility for operating
and managing the Project. Under the proposal, the modified CME would be
10
comprised of nine members, rather than eight — the CSKT would appoint four
members, the FID would appoint two members, the remaining two irrigation
districts would appoint one member each, and the BIA would appoint one
member. The BIA member was to serve as the Chair of the CME, but would not
vote on any issues unless there was a tie. The BIA asked that the parties indicate
their acceptance of the proposal by February 7, 2014. By February 7, 2014, the
Mission Irrigation District, Jocko Valley Irrigation District, and the Tribes voted
to approve the proposal.
The FID did not respond to the proposal by February 7th. Instead, on
February 19, 2014, the FID sent to the BIA a “counterproposal.” Among other
provisions, the counterproposal required that an entity called the New
Management Entity (“NME”) should serve as the legal entity for operation and
management of the Project. The NME would consist of thirteen members and,
among other requirements, would be comprised of two representatives for the
CSKT, two representatives for the Mission Irrigation District, one representative
for the Jocko Valley Irrigation District, and eight representatives for Plaintiff FID.
These terms were not acceptable to the BIA, the Secretary of the Interior, or
any of the other irrigation districts, and the BIA formally rejected the terms of the
counterproposal in a letter to all CME Chairmen dated March 11, 2014. In the
11
same letter, the BIA informed the Chairmen that, in accordance with the
emergency reassumption provision of the Transfer Agreement and the authority
reserved in 1908 Act, it would fully reassume the operation and management of
the Project. The BIA stated that its decision to resume operation and management
of the Project was based on the need to protect federal assets and the trust
resources of the Tribes, and to ensure that the Project’s real property was
maintained and safety requirements were met. The BIA further stated that its
management and operation of the Project would “continue indefinitely pending
resolution of the issues that would allow the BIA to transfer Project O&M
consistent with the requirements of the 1908 statute.” (Doc. 28-8 at 5.)
Plaintiffs responded by initiating this lawsuit on April 2, 2014. Plaintiffs’
Complaint alleged that the BIA’s reassumption of control of the Project violated
the 1908 Act. Plaintiffs also alleged that the CME lacked proportional
representation as required under Montana law. The United States moved for a
more definitive statement.
C.
Plaintiffs’ Amended Complaint
Rather than respond to the motion for a more definite statement, Plaintiffs
filed their Amended Complaint on July 28, 2014. The Amended Complaint asserts
six counts, all of which seek either declaratory or injunctive relief. The Amended
12
Complaint also seeks attorneys’ fees.
Count One asks the Court to order the formation of an entity to operate and
manage the Project. Count One further requests that the Court declare that this
entity’s “permanent features” include essentially all of the features of the NME as
proposed by the FID in its counterproposal. (Doc. 14 at 32.) Count One also asks
the Court to declare that the 1908 Act requires turnover of the operation and
management of the entire Project, including both the Irrigation and Power
Divisions of the Project. In a related claim for injunctive relief, Count Four asks
the Court to permanently enjoin “the federal takeover of operation of the Project.”
Id. at 34.
Count Two asks the Court to declare that “the United States has been and
continues to transfer land that was or is owned in fee within the Project into trust
status in violation of 25 U.S.C. § 463(a).” Id. at 33. In a related claim for
injunctive relief, Count Five asks the Court to enjoin the United States from any
further transfer of land within the Project from fee to trust status.
Count Three asks the Court to declare that “since the early 1990's” the
Power Division of the Project has been operated in contravention of 62 Statute
269, Act of May 25, 1948 (“1948 Act”), “in a variety of ways that will be
demonstrated through the course of this litigation.” Id. at 33. In a related claim
13
for injunctive relief, Count Six requests an injunction prohibiting the continued
operation of the Power Division “in contravention of the 1948 Act.” Id. at 34.
Count Seven seeks attorneys’ fees under the Equal Access to Justice Act.
The United States moved to dismiss the Amended Complaint, and in the
alternative for summary judgment on October 23, 2014. The motion was fully
briefed on February 20, 2015. Due to failure to comply with Local Rule, the Court
denied the motion to dismiss without prejudice on March 4, 2015.
On March 13, 2015, the United States renewed its motion to dismiss, and in
the alternative, for summary judgment. The motion was completely briefed on
April 10, 2015, when the United States filed its reply brief in support of the
renewed motion to dismiss.
D.
Plaintiffs’ Proposed Second Amended Complaint
On May 21, 2015, Plaintiffs filed a motion to amend their complaint, again.
Plaintiffs attached as an exhibit their Proposed Second Amended Complaint
(“Proposed Complaint”)—a 40-page complaint with over 400 pages of attached
exhibits. The Proposed Complaint adds new parties, including two new plaintiffs,
the Mission Irrigation District and the Jocko Valley Irrigation District, and one
14
new defendant, the State of Montana.6
There are some stylistic changes and corrections of typographical errors,
but substantively the Proposed Complaint alleges that the recent ratification of the
Confederated Salish and Kootenai Tribes Water Compact (“the Water Compact”),
by passage of Montana Senate Bill 262, is “an illegal attempt to preempt the FAA
Turnover provision.” (Doc. 66-1 at 36.) Plaintiffs seek a declaration that the
Compact is invalid, null, and void because it is preempted by federal law.
Plaintiffs also seek associated injunctive relief. The Proposed Complaint also
alleges that certain funds held by the CME that were derived in part from
Operation and Maintenance monies paid by irrigators “are scheduled to be
transferred to another entity at the end of May 2015.” Id. at 32-33. The Proposed
Complaint alleges that this scheduled transfer “to another entity” is wrongful and
seeks a declaration “ordering turnover of the CME funds to the FJBC” and
injunctive relief. Id. at 37. Finally, the Proposed Complaint alleges that since the
BIA took over management of the Project, it has mismanaged the Project, resulting
in additional damages to Plaintiffs.
The United States opposes the motion for leave to file the Proposed
6
In its brief in support of the motion to amend, Plaintiffs fail to address the fact that the
Proposed Complaint seeks to add two new plaintiffs.
15
Complaint, arguing that the motion should be denied for a variety of reasons,
including that the proposed amendments are futile because all of the new claims
and allegations are subject to dismissal under Rule 12(b). Plaintiffs’ motion to
amend was completely briefed on July 27, 2015. All motions are now ripe for
decision.
DISCUSSION
For the reasons explained below, the Court determines that Plaintiffs’
Amended Complaint must be dismissed pursuant to Rule 12(b). Additionally, the
Court denies Plaintiffs’ motion for leave to file their Proposed Complaint because
it finds that the proposed amendments are futile and subject to dismissal under
Rule 12(b). Because the reasons in large part for dismissal of the Amended
Complaint are the same for finding that leave to file Plaintiffs’ Proposed
Complaint is futile, the Court first addresses the United States’ motion to dismiss
Plaintiffs’ Amended Complaint and then addresses Plaintiffs’ motion for leave to
file the Proposed Complaint.
I.
Motion to Dismiss Amended Complaint
Legal Standard
Pursuant to Rule 12(b)(1), a Court may dismiss a complaint, or any claim,
for lack of subject matter jurisdiction. When considering a Rule 12(b)(1) motion
16
that substantively challenges the existence of jurisdiction, the Court is not limited
to the allegations in the complaint but may consider materials outside the
pleadings. Assoc. of Am. Med. Colleges v. United States, 217 F.3d 770, 778 (9th
Cir. 2000). No presumption of truthfulness applies to the allegations of a
complaint in deciding a substantive challenge to jurisdiction. Thornhill Pub. Co.,
Inc. v. General Tel. & Electronics Corp., 594 F.2d 730, 733 (9th Cir. 1979). Once
challenged by Rule 12(b)(1) motion, the burden of establishing jurisdiction is on
the plaintiff. Thomson v. Gaskill, 315 U.S. 442, 446 (1942).
Rule 12(b)(6) motions test the legal sufficiency of a pleading. Under
Federal Rule of Civil Procedure 8(a)(2), a pleading must contain “a short and plain
statement of the claim showing that the pleader is entitled to relief.” Fed.R.Civ.P.
8(a)(2). “To survive a motion to dismiss, a complaint must contain sufficient
factual matter, accepted as true, to ‘state a claim to relief that is plausible on its
face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atlantic Corp. v.
Twombly, 550 U.S. 544, 570 (2007)). A claim has facial plausibility when the
court can draw a “reasonable inference” from the facts alleged that the defendant
is liable for the misconduct alleged. Id.
17
Analysis
A. Counts One and Four—Turnover
Count One asks the Court to declare, and create out of whole cloth, an entity
to operate and manage the Project whose permanent features would be tailored to
Plaintiffs’ liking. The entity proposed in Plaintiffs’ Amended Complaint mirrors
in all material respects the “NME” which was described in Plaintiffs’
counterproposal of February 19, 2014. Notably, the parties to this lawsuit do not
dispute whether the management and operation of the Project must, in accordance
with the 1908 Act, pass to the owners of the lands irrigated thereby. The sticking
point has been, and is, “under [what] form or organization and under [what] rules
and regulations” the transfer of operation and management must occur. 35. Stat. at
450. Plaintiffs contend that the form and rules proposed in their Amended
Complaint constitute the appropriate form. The United States rejects this proposed
form because it contends that this proposed form and associated rules are not
“acceptable to the Secretary of the Interior.” 35. Stat. at 450.
The United States contends that Plaintiffs’ claims associated with turnover
must be dismissed for lack of jurisdiction, and even assuming jurisdiction, for lack
of merit. The Court agrees with the United States.
“It is elementary that the United States, as sovereign, is immune from suit
18
save as it consents to be sued.” United States v. Mitchell, 445 U.S. 535, 538
(1980)( (citation omitted)). Thus, in challenging the BIA’s reassumption of
management and operation of the Project, and in seeking the transfer, by judicial
declaration, of the operation and management of the Project to Plaintiffs’ proposed
entity, the Court must determine whether there is an applicable waiver of
sovereign immunity.
In their Amended Complaint and brief in response to the motion to dismiss,
Plaintiffs reference the Declaratory Judgment Act, 28 U.S.C. § 2201, and general
federal question statute, 28 U.S.C. § 1331, as supplying the Court with jurisdiction
over their claims. It is well-established, however, that neither the Declaratory
Judgment Act nor the general federal question statute provide the necessary
waiver of sovereign immunity for suits against the United States. Morongo Band
of Mission Indians v. Calif. State Bd. Of Equalization, 858 F.2d 1376, 1382–83
(9th Cir.1988)(Declaratory Judgment Act); Dunn & Black, P.S. v. United States,
492 F.3d 1084, 1088, n.3 (9th Cir. 2007)(federal question).
Because Plaintiffs cite no other possible waiver of sovereign immunity, the
Court presumes that Plaintiffs are attempting to bring a claim under the
Administrative Procedures Act (“APA”), 5 U.S.C. §§ 702 and 706, though this is
not clear from a review of Plaintiffs’ Amended Complaint. As it is not clear that
19
Plaintiffs intend to bring an APA claim, it is also not clear under what section of
the APA Plaintiffs intend to bring suit. But, because § 706 appear to be possibly
applicable, the Court will assume that Plaintiffs intend to seek judicial review of
the BIA’s action under § 706 of the APA.
Even liberally construing Plaintiffs’ Amended Complaint in this fashion, it
is clear that Count One fails for lack of jurisdiction because the 1908 Act, on
which Plaintiffs rely, “is drawn so that a court would have no meaningful standard
against which to judge the agency’s exercise of discretion.” Heckler v. Chaney,
470 U.S. 821, 830 (1985). Accordingly, the challenged agency action is not
subject to judicial review under the APA.
The 1908 Act clearly vests the Secretary with discretion to establish an
entity to manage and operate the Project. Its terms require neither immediate
turnover upon repayment nor turnover in any particular fashion. It requires
turnover, but only turnover “under such form of organization and under such rules
and regulations as may be acceptable to the Secretary of the Interior.” 35 Stat. at
450. This requirement provides “no meaningful standard against which to judge”
the Secretary’s actions with respect to BIA’s challenged actions. Heckler, 470
U.S. at 830. Given the broad discretion vested in the Secretary to determine the
form and fashion of turnover, Count One of Plaintiff’s Amended Complaint is not
20
subject to judicial review under the APA because such discretionary acts are
outside of the scope of review provided under 5 U.S.C. § 701(a)(2). Accordingly,
the Court lacks jurisdiction over this claim and it must be dismissed.
Furthermore, even if the BIA’s decision to resume operation and
management of the Project were subject to judicial review under the APA, Count
One still fails. The 1908 Act makes clear that turnover may occur only in the form
and under such rules as are acceptable to the Secretary. Plaintiffs specifically
request that this Court, by judicial edict, form an entity of their design responsible
for operating and managing the Project that would be, without question,
understandably unacceptable to the Secretary. The BIA formally rejected an
identical proposal in its March 11, 2014 letter, and the fact of this suit makes clear
that its position has not changed. Even assuming jurisdiction under the APA,
Plaintiffs cannot compel its requested agency action. Indeed, had the BIA acted as
Plaintiffs request the Court to act, the BIA’s action would have been ultra vires
because, in contravention of the 1908 Act, the BIA would have transferred
operation and management of the Project to an entity that was unacceptable to the
Secretary. Plaintiffs’ contention that proportional representation is required is
wholly detached from the language of any law and appears to be merely a creation
of their own desire.
21
Under no set of facts would Plaintiffs ever be entitled to the requested
declaratory relief. The Court has no authority to order the formation of an
operation and management entity that contravenes the will of the Secretary.
Accordingly, even assuming jurisdiction, Count One must be dismissed for failure
to state a plausible claim for relief.
For the same reasons, Count Four also fails to state a plausible claim for
relief, and must be dismissed. In Count Four, Plaintiffs ask the Court to enjoin the
BIA from operating and managing the Project. The BIA’s authority to resume
operation and management, however, was specifically reserved in the Transfer
Agreement under the emergency reassumption provision, and implicitly reserved
under the 1908 Act . The Transfer Agreement’s emergency reassumption
provision was acceptable to the Secretary. The Court cannot order that the BIA be
forever enjoined from operating and managing the Project, because this would be
in contravention of the will of the Secretary, and thus contrary to the 1908 Act.
Though Plaintiffs contend that the Transfer Agreement is void because the
CME became defunct when the FJBC dissolved, this makes no difference.
Through the 1908 Act, the Secretary reserved to itself the discretion to determine
the form and organization of any entity that would operate and manage the Project.
In agreeing to transfer operation and management of the Project to the CME under
22
the Transfer Agreement, the BIA memorialized this reserved authority through
every provision of the Transfer Agreement, including the emergency reassumption
provision. Until such time as an acceptable form and organization for operation
and management of the Project by the landowners could be established, turnover is
not required.
The 1908 Act reserved to the Secretary the authority to protect federal assets
and fulfill trust responsibilities owed to the Confederated Tribes. The 1908 Act
authorized the Secretary to “perform any and all acts to make such rules and
regulations as may be necessary and proper for the purpose of carrying the
provision of [the 1908 Act] into full force and effect.” 35 Stat. at 448. Plaintiffs
rely entirely on the 1908 Act in seeking to declare the Secretary’s reassumption of
operation and management illegal, but as set forth above, the 1908 Act vests the
Secretary with significant discretion and reserves to the Secretary the authority to
operate and manage the Project until an entity comprised of landowners can be
established that is acceptable to the Secretary.
As with the requested declaratory relief, under no set of facts would
Plaintiffs ever be entitled to the requested injunction because the BIA’s authority
to manage and operate the Project in the absence of any other acceptable entity to
manage it was reserved in the 1908 Act. Accordingly, Count Four fails to state a
23
plausible claim to relief and must be dismissed.
B. Counts Two and Five—Land into Trust
Count Two asks the Court to declare that “the United States has been and
continues to transfer land that was or is owned in fee within the Project into trust
status in violation of 25 U.S.C. § 463(a).” Id. at 33. The United States contends
that Count Two must be dismissed for lack of jurisdiction, exceeding the statute of
limitations, failure to exhaust administrative remedies, and failure to state a claim.
The Court agrees that Count Two fails to identify any discrete agency action as
would give the Court jurisdiction under the APA. Furthermore, assuming that
Plaintiffs mean to challenge the United States’ restoration of lands to tribal
ownership in 1936 or 1937, the claim is well beyond the statute of limitations.
Count Two is therefore dismissed.
Though the Amended Complaint is far from clear on this point, the Court
must again assume that Plaintiffs are attempting to bring Count Two under the
APA because the APA provides the only vehicle for a waiver of sovereign
immunity. To proceed under the APA, Plaintiffs must identify and challenge a
discrete agency action. Norton v. Southern Utah Wilderness Alliance, 542 U.S. 55,
65 (2004). Count Two fails to do so. Count Two fails to identify any specific
transfer of land on which Plaintiffs base their allegation that the United States has
24
violated 25 U.S.C. § 463(a). Plaintiffs identify neither a date of any transfer of
lands nor the size or precise location of the lands involved in the alleged transfer.
Plaintiffs’ presumptive APA claim cannot rest on such bare allegations. For this
reason alone, Count Two fails to state a plausible claim for relief and must be
dismissed.
Assuming that Plaintiffs mean to challenge the specific restoration of lands
to tribal ownership that the United States admits that it performed in 1936 or 1937,
the claim fails because it far exceeds the statute of limitations. The United States
admits that in 1936 or 1937 it restored certain unallotted federal surplus lands to
tribal ownership pursuant to 25 U.S.C. § 463(a). If Plaintiffs intend, obliquely, to
base their claim on these 1936 or 1937 transfers, the statute of limitations for such
a claim has long-since passed. 28 U.S.C. § 2401(a). Plaintiffs provide no
explanation as to why any tolling theory would apply to such a dated claim.
Plaintiffs are also not entitled to discovery to attempt to “uncover” other
allegedly illegal transfers. Plaintiffs Amended Complaint fails to meet the
pleading standard required under Rule 8 of the Federal Rules of Civil Procedure.
Iqbal, 556 U.S. at 678 (“a complaint must contain sufficient factual matter,
accepted as true, to state a claim to relief that is plausible on its face”). It must
therefore be dismissed.
25
Count Five asks the Court to enjoin the United States from any further
transfers of land within the Project from fee to trust status. The United States
contends this claim must be dismissed for lack of standing. The Court agrees.
Plaintiffs’ request for prospective injunctive relief rests entirely on
speculation. Plaintiffs fail to identify any potential future transfer of land under 25
U.S.C. § 463(a) that has even been proposed by the United States. Therefore,
Plaintiffs fail to invoke the Court’s jurisdiction, which is limited to “Cases” and
“Controversies.” U.S.C.A. Const. Art. III § 2. Plaintiffs are not entitled to
injunctive relief from a hypothetical future injury. Lujan v. Defenders of Wildlife,
504 U.S. 555, 560-61 (1992). Plaintiffs entirely fail to identify a concrete,
particularized injury that is redressable through the requested injunctive relief.
Instead, Plaintiffs merely assert a conjectural or hypothetical future injury whose
redressability through the requested injunctive relief is speculative. Plaintiffs
therefore lack standing for Count Five, and it is accordingly dismissed.
C. Counts Three and Six— Power Division of the Project
Count Three asks the Court to declare that “since the early 1990's” the
Power Division of the Project has been operated in contravention of the 1948 Act
“in a variety of ways that will be demonstrated through the course of this
litigation.” Id. at 33. Count Six requests an injunction prohibiting the continued
26
operation of the Power Division “in contravention of the 1948 Act.” Id. at 34.
Both Count Three and Count Six refer to violations of the 1948 Act, but in the
factual recitation of the Amended Complaint, and in Plaintiffs’ brief in response to
the motion to dismiss, Plaintiffs appear to also assert violations of the Indian SelfDetermination Act. For instance, in the Amended Complaint Plaintiffs allege the
following: “The Power Division of the Project is now operated by the CSKT
under a contract with the Defendant BIA in violation of P.L. 638.” (Doc. 14 at 29.)
But, in Plaintiffs’ Brief in Response to the Motion to Dismiss, Plaintiffs contend
that: “Count Three of the Amended Complaint alleges violation of the Indian SelfDetermination and Education Assistance Act.” (Doc. 58 at 24.) The United States
contends that regardless of this confusion both claims must be dismissed for lack
of jurisdiction. The Court agrees.
Whether Plaintiffs are alleging violations of the 1948 Act or the Indian SelfDetermination Act, or both, Plaintiffs’ claims related to tribal operation of the
Power Division of the Project must be dismissed for lack of jurisdiction. Again,
these claims must be construed as APA claims, because otherwise there is no
identifiable waiver of sovereign immunity and the claims are subject to dismissal
for lack of jurisdiction. However, Plaintiffs themselves are apparently unsure if
Count Three is, or can be, brought under the APA. They seek to premise judicial
27
review on the Declaratory Judgment Act, which they cannot, and in a hedged but
conclusory fashion assert that Count Three is “potentially” subject to review under
the APA. (Doc. 58 at 31.) Plaintiffs make no attempt to demonstrate that Count
Six is subject to review under the APA.
Once challenged, the burden is on the plaintiff to demonstrate that the Court
has subject matter jurisdiction to hear a claim. Thomson v. Gaskill, 315 U.S. 442,
446 (1942). Plaintiffs’ tentative and unsupported assertion that these claims might
be subject to review under the APA are insufficient to sustain this burden.
Accordingly, Counts Three and Six must be dismissed for lack of jurisdiction.
The Court also agrees with the United States that Plaintiffs have not pled
sufficient factual matter to support standing.7 In conclusory fashion, Plaintiffs
allege that since the execution of the P.L. 638 contract, “the revenues of the Power
Division have been systematically generated and, to some degree, misdirected in
violation of the 1948 Act in a variety of ways.” (Doc. 14 at 33.) No factual
allegations in the Amended Complaint support this sweeping allegation.
Critically, no facts suggest that any “misdirected” revenues were intended to
7
A plaintiff must demonstrate standing to invoke the jurisdiction of the federal courts.
L.A. Haven Hospice, Inc. v. Sebelius, 638 F.3d 644, 645 (9th Cir. 2011). Standing has three
requirements: injury in fact, a causal connection between the injury and the conduct complained
of, and a likelihood that the injury will be redressed by a favorable decision. Defenders of
Wildlife, 504 U.S. at 560.
28
benefit Plaintiffs. Thus, Plaintiffs have failed to plead an injury in fact. Plaintiffs’
contention, supplied only in their response brief, that standing for this claim may
be premised on the allegation of a “lack of accounting for net revenues” only
underscores the insufficiency of the alleged injury. See Defenders of Wildlife, 504
U.S. at 575. Plaintiffs have not alleged a particularized injury. Rather, Plaintiffs
assert only a “generalized grievance” that the United States has violated the law.
Id. It is well-established that such claims are insufficient to invoke a federal
court’s jurisdiction under Article III. Id.
Plaintiffs also fail to plead any facts showing that the above-described
generalized grievance is traceable to the United States. Perhaps it could be
inferred that Plaintiffs are obliquely attempting to premise traceability on the
United States’ execution of the P.L. 638 contract with the Tribes to operate the
Power Division, but such a claim is clearly beyond the statute of limitations.
Claims against the United States are subject to a six year statute of limitation. 28
U.S.C. § 2401(a). The Tribes entered into the P.L. 638 contract to operate and
manage the Power Division of the Project in 1986. There is no question that
Plaintiffs were aware of this because in 1988 Plaintiffs filed suit against the
United States and the Tribes seeking to enjoin the enforcement of the contract.
Joint Board of Control of the Flathead, Mission and Jocko Irrigation Districts,
29
No. CV 86-216-M-CCL (Doc. 56-2). The discovery doctrine is thus inapplicable,
Shiny Rock Mining Corp. v. United States, 906 F.2d 1362, 1364 (9th Cir. 1990).
To the extent that traceability is premised on the execution of the P.L. 638
contract, the statute of limitations has long since passed.8 Because Plaintiffs have
failed to establish either a particularized injury in fact or traceability, redressability
is entirely speculative.
For all of the reasons described, Counts Three and Six must be dismissed.9
II.
Plaintiffs’ Motion for Leave to Amend the Complaint
After the United States filed a motion for a more definite statement with
respect to Plaintiffs original Complaint, Plaintiffs filed their Amended Complaint.
Ten months later, after the second round of briefing on the United States’ motion
to dismiss the Amended Complaint had been completed, Plaintiffs filed the instant
motion for leave to file a the Proposed Second Amended Complaint. As noted
8
Such a claim is also likely barred by claim preclusion doctrines.
9
The United States also assert that Counts Three and Six are subject to dismissal for
failure to exhaust administrative remedies under 25 C.F.R. § 2.6, citing White Mtn. Apache Tribe
v. Hodel, 840 F.2d 675, 677 (9th Cir. 1988). Plaintiffs make no attempt to address this argument.
Additionally, the United States asserts that Counts Three and Six are subject to dismissal to the
extent that they are based on violations of the Indian Self Determination Act because Plaintiffs’
lack statutory standing for such claims. citing Joint Board of Control of the Flathead, Mission
and Jocko Irrigation Districts, No. CV 86-216-M-CCL (Doc. 56-2). The Court need not address
these arguments because the Court finds that Plaintiffs lack Article III standing to assert these
claims.
30
above, the Proposed Complaint adds two new plaintiffs and a new defendant. It
also adds two new claims and alleges new damages stemming from its claim
alleging wrongful turnover (Counts One and Four, dismissed above). Each
substantive amendment will be addressed in turn.
Legal Standard
Leave to amend a complaint should be freely granted “when justice so
requires.” Fed.R.Civ.P. 15(a). Courts must consider four factors when assessing a
motion to amend a complaint: (1) bad faith on the part of the party seeking
amendment; (2) undue delay; (3) prejudice to the opposing party; and (4) futility
of the proposed amendment. Lockheed Martin Corp. v. Network Solutions, Inc.,
194 F.3d 980, 986 (9th Cir. 1999). “Leave to amend need not be given if a
complaint, as amended, is subject to dismissal.” Moor v. Kayport Package Exp.,
Inc., 885 F.2d 531, 538 (9th Cir. 1989); see also Lipton v. Pathogenesis Corp.,
284 F.3d 1027, 1039 (9th Cir. 2002).
Under Rule 15(d), a court “may permit supplementation” for “any
transaction, occurrence, or event that happened after the date of the pleading.”
Fed.R.Civ.P. 15(d); see also Eid v. Alaska Airlines, Inc., 621 F.3d 858, 874 (9th
Cir. 2010). Rule 15(d) is a “tool of judicial economy and convenience” designed
to “avoid the cost, delay and waste of separate actions.” Keith v. Volpe, 858 F.2d
31
467, 473 (9th Cir. 1988). In order to properly invoke Rule 15(d), “some
relationship must exist between the newly alleged matters and the subject of the
original action.” Id. Rule 15(d) “cannot be used to introduce a ‘separate, distinct
and new cause of action.’” Planned Parenthood of S.Ariz. v. Neely, 130 F.3d 400,
402 (9th Cir. 1997)(per curiam)(quoting Berrsebrugge v. Luce Mfg. Co., 30
F.Supp. 1010, 102 (W.D. Mo. 1939)). The factors for assessing a motion to
supplement under Rule 15(d) overlap with the factors, detailed above, for
assessing a motion to amend under Rule 15(a). Glatt v. Chicago Park Dist., 87
F.3d 190, 194 (7th Cir. 1996).
Analysis
A.
Additional Damages
Plaintiffs’ Proposed Amended Complaint contains new factual allegations
asserting a variety of damages stemming from the BIA’s operation and
management of the Project. No new count is added with respect to these damages.
These new allegations are rooted in Plaintiffs’ claim that the BIA’s reasssumption
of operation and management is wrongful and that turnover is mandated. For all
of the reasons explained above, Counts One and Four, related to turnover are
subject to dismissal. Thus, the portions of the Proposed Complaint detailing
additional damages related to turnover are also subject to dismissal. Granting
32
leave to add these allegations is denied as adding them would be futile.
B.
Claims against the State of Montana
Plaintiffs’ Proposed Complaint adds the State of Montana as a defendant.
However, none of the Counts are directed specifically against the State of
Montana. Rather all counts are asserted against all Defendants without further
specificity. It is obvious that the State of Montana is not responsible for many of
the allegations. For instance, no facts are alleged that would implicate the State of
Montana in the BIA’s reassumption of operation and management of the Project,
or in transferring land from fee into trust, or in distribution of revenues from the
Power Division of the Project. To the extent that factual allegations in the
Proposed Complaint implicate the State of Montana, Plaintiffs’ claims appear to
be premised on the ratification of the Water Compact by passage of Senate Bill
262.10
The United States contends that granting leave to amend to add the State of
Montana would be futile because (1) the State of Montana is immune from the suit
10
It does not appear that Plaintiffs’ preemption claim is directed against the United
States. Obviously, the United States is not responsible for passage of Montana Senate Bill 262.
To the extent that Plaintiffs’ preemption claim is supposed to be directed against the United
States, the claim fails. No facts alleged plausibly suggest that the United States is liable for any
alleged harm associated with Plaintiffs’ preemption claim, and Plaintiffs have certainly not
alleged any final federal agency action with respect to the preemption claim.
33
by virtue of the Eleventh Amendment; (2) as a political subdivision of the State of
Montana, Plaintiffs lack standing; (3) Plaintiffs’ preemption claim is subject to
dismissal because there is no conflict between the Water Compact and federal law;
and (4) Plaintiffs’ claims are not ripe. The United States further submits that the
proposed amendment should not be granted as it is contrary to judicial efficiency
because the primary subject of this litigation, i.e., whether the BIA’s reassumption
of operation and management of the Project is proper, is wholly distinct from the
proposed preemption claim against the State of Montana for passage of the Water
Compact.
The Court agrees that Plaintiffs’ claim against the State of Montana is both
contrary to judicial efficiency and futile. Plaintiffs claim against the State of
Montana is based on its passage of Senate Bill 262. This action has been primarily
focused on the BIA’s reassumption of operation and management of the Project
pursuant to the Act of 1908 and the Transfer Agreement. With the addition of this
new claim against the State of Montana, Plaintiffs are attempting bring in all new
allegations that are wholly distinct from the subject of the original action.
Amendment is therefore improper under Rule 15(d). Keith, 858 F.2d 467, 474;
Planned Parenthood of S.Ariz., 130 F.3d 400, 402.
Furthermore, Plaintiffs concede, as they must, that the Water Compact still
34
must be ratified by Congress and the Tribes before the settlement will go into
effect. Water Compact, Art. VII (Doc. 70-1 at 48-49). Since the Water Compact,
absent ratification by the Tribes and Congress has no legal effect, Plaintiffs’
claims are not yet ripe. Worse, if Congress does ratify the Water Compact,
Plaintiffs’ preemption claim will fail because the Water Compact will then become
federal law. Cuyler v. Adams, 449 U.S. 433, 440 (1981). Accordingly,
amendment or supplementation to add this claim would be futile.
For all of these reasons, the Court denies Plaintiffs’ motion for leave to
amend the Amended Complaint by adding the State of Montana.
C.
CME Funds Transfer
The Proposed Complaint also alleges that certain funds held by the CME
that were derived in part from Operation and Maintenance monies paid by
irrigators “are scheduled to be transferred to another entity at the end of May
2015.” Id. at 32-33. The Proposed Complaint alleges that this scheduled transfer
“to another entity” is wrongful, and seeks declaratory and injunctive relief
“ordering turnover of the CME funds to the FJBC.” Id. at 37. The Proposed
Complaint alleges that these unspecified “CME funds” are held in a bank account
that “the CME continues to maintain.” Id. at 32. The CME, which is allegedly
“defunct,” id., is not a party to this lawsuit.
35
These allegations do not plausibly support a claim for relief against any of
the Defendants, including the State of Montana. Plaintiffs do not allege any facts
suggesting that the United States or the State of Montana has control over these
unspecified CME funds. Nor do Plaintiffs allege any facts suggesting that the
United States or the State of Montana has “scheduled” the alleged transfer. Id. In
sum, it is not even clear which Defendant these claims are supposed to be directed
against. If the claims are supposed to be directed against the United States, there
is nothing to suggest that they are viable under the APA. See, e.g. Norton v.
Southern Utah Wilderness Alliance, 542 U.S. 55, 61-62 (2004)(“the ‘agency
action’ complained of must be ‘final agency action.’”). If the claims are against
the State of Montana, there is nothing to suggest that it is responsible for
scheduling the transfer or for controlling the CME funds.
Accordingly, leave to amend to add claims associated with the alleged
wrongful scheduled transfer of funds held by CME is denied, as amendment would
be futile.
IT IS ORDERED that:
(1)
Defendants’ motion to dismiss (Doc. 55) is GRANTED.
(2)
Plaintiffs’ motion for leave to amend (Doc. 66) is DENIED.
(3)
All other pending motions are DENIED AS MOOT.
36
The Clerk of Court is ordered to enter judgment in favor of Defendants and
against Plaintiffs. This case is CLOSED.
DATED this 19th day of August, 2015.