MEMORANDUM AND ORDER - The plaintiff's final Motion for Default Judgment against M & S Irrigation Service, Inc. and Murray M. Winslow, (Filing No. 44 ), is granted. Judgment shall be entered in favor of Plaintiff, Reinke Manufacturing Co. In c., and against Defendants M&S Irrigation Service, Inc. and Murray M. Winslow, finding them jointly and severally liable to Plaintiff in the amount of $69,761.00, plus post-judgment interest and the costs of this suit. Ordered by Magistrate Judge Cheryl R. Zwart. (GJG, )
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NEBRASKA
REINKE MANUFACTURING CO., INC.,
Plaintiff,
v.
M & S IRRIGATION SERVICE, INC., a
North Carolina Corporation, GEORGE S.
PERRY, an Individual, and MURRAY M.
WINSLOW, an Individual,
Defendants.
)
)
)
)
)
)
)
)
)
)
)
)
Case No: 4:11-CV-03193
ORDER GRANTING MOTION
FOR ENTRY OF
FINAL JUDGMENT BY DEFAULT
THE COURT, having reviewed Plaintiff’s Motion for Entry of Final Judgment by
Default, hereby finds and orders as follows:
1)
Pursuant to the Court’s June 16, 2012, order (Filing No. 34), Defendants M&S
Irrigation Service, Inc. and Murray M. Winslow were given until July 9, 2012, to contest the
entry of default;
2)
Defendants M&S Irrigation Service, Inc. and Murray M. Winslow did not file any
pleadings or briefs in response to the Court’s order from June 16, 2012 and default was
subsequently entered by the Court;
3)
The amount due and owing by Defendants M&S Irrigation Service, Inc. and
Murray M. Winslow under Reinke’s First Claim for Relief to Reinke under the Loan Agreement
is $30,621.17.
4)
The amount due and owing by Defendant M&S Irrigation Service, Inc., under
Reinke’s Second Claim for Relief is $39,139.83.
5)
The amount due and owing by Defendant Murray M. Winslow under Reinke’s
Third Claim for Relief is $69,761.00. This amount includes what is owed to Reinke under its
First and Second Claims for Relief.
6)
Defendants are not infants or incompetent persons.
7)
Plaintiff has established that the amounts due and owing by Defendants are a sum
certain.
Accordingly,
IT IS ORDERED:
1)
The plaintiff’s final Motion for Default Judgment against M & S Irrigation
Service, Inc. and Murray M. Winslow, (Filing No. 44), is granted.
2)
Judgment shall be entered in favor of Plaintiff, Reinke Manufacturing Co. Inc.,
and against Defendants M&S Irrigation Service, Inc. and Murray M. Winslow,
finding them jointly and severally liable to Plaintiff in the amount of $69,761.00,
plus post-judgment interest and the costs of this suit.
Dated: April 8, 2013
BY THE COURT:
s/ Cheryl R. Zwart
United States Magistrate Judge
522628
-2-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?