Aurora Cooperative Elevator Company v. Aventine Renewable Energy Holdings, Inc. et al
Filing
64
MEMORANDUM AND ORDER granting 60 Motion for Leave. 1) The Co-op's motion to amend, (Filing No. 60 ), is granted. The Co-op's amended complaint, a copy of which is attached to its motion, shall be filed on or before June 22, 2015< /b>.2) The Co-op shall promptly serve NELLC.3) Counsel for the parties shall confer and, on or before July 29, 2015, they shall jointly file a Form 35 (Rule 26 (f)) Report. 4) If one or more of the parties believes a planning confe rence is needed to complete the Rule 26(f) Report, or if the parties cannot agree on one or more of the deadlines identified or case progression issues raised in the Rule 26(f) Report, on or before July 22, 2015, a party shall contact my chambers at (402) 437-1670, or by email addressed to zwart@ned.uscourts.gov, to arrange a conference call. Ordered by Magistrate Judge Cheryl R. Zwart. (JAB)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NEBRASKA
AURORA COOPERATIVE ELEVATOR
COMPANY,
4:14CV3032
Plaintiff,
vs.
MEORANDUM AND ORDER
AVENTINE RENEWABLE ENERGY
HOLDINGS, INC., AVENTINE
RENEWABLE ENERGY - AURORA
WEST, LLC,
Defendants.
The plaintiff has moved to amend its complaint. (Filing No. 60). For the reasons
discussed below, the motion will be granted.
Plaintiff Aurora Cooperative Elevator Company (“Co-op”) filed this lawsuit against
Aventine Renewable Energy Holdings, Inc. (“Aventine Holdings”) and Aventine Renewable
Energy – Aurora West, LLC (collectively “Aventine”) on February 4, 2014.
The Co-op’s
initial complaint alleged that under the parties’ contract, Aventine obtained access from its
Aurora West Ethanol Plant (“Plant”) to a Burlington Northern main line track via a rail line
that crossed Aurora’s land (the “Double Track Loop Agreement”). The complaint alleges
that in exchange for this rail line access, Aventine agreed to purchase the grain needed for
Plant operations from the Co-op (the “Aventine Grain Supply Agreement”). The complaint
alleges that the Double Track Loop Agreement would terminate immediately (and the Co-op
could thereby terminate Aventine’s rail access across the Co-op’s land) if either the Co-op or
Aventine terminated the Aventine Grain Supply Agreement. The Co-op’s initial complaint
alleges Aventine purported to unilaterally terminate the Grain Supply Agreement and seeks a
declaration that as a result of terminating that Agreement, Aventine is not permitted to use
the rail line and switch located on the Co-op’s land for any purpose. The Co-op also seeks
an order enjoining Aventine’s future use of that track and switch. (Filing No. 1).
Aventine moved to dismiss, (Filing No. 20), and while that was pending, the Co-op
moved for a temporary restraining order to avert a looming Friday-night confrontation
between the parties at the track site. (Filing No. 34). On Friday, November 21, 2014, while
Aventine’s motion to dismiss was still pending, Aventine moved machinery and equipment
into place to begin removing a section of the Exterior Track Loop and install a “diamond
crossing” (“the Diamond Crossing”) in its place. (Filing No. 48, at CM/ECF p. 3). See also
Filing No. 60-1, at ¶¶ 7-8, 59-63.
Judge Gerrard denied the Co-op’s motion for a restraining order, stating the Co-op
produced no evidence refuting the claim of Nebraska Energy, LLC, (“NELLC”) an affiliate
of Aventine, that the Diamond Crossing would benefit NELLC’s use of the property.
(Filing No. 48, at CM/ECF p. 7). Judge Gerrard’s order stated, however, that Aurora Co-op
might be entitled to relief if Aventine’s and NELLC’s use of the Diamond Crossing could be
shown to interfere with Aurora Co-op’s use and enjoyment of the property. (Filing No. 48,
at CM/ECF p. 9). Judge Gerrard held:
The modification of the tracks themselves will not significantly affect Aurora's
ability to use the Subject Premises—so long as Aventine and NELLC provide
Aurora with reasonable notice of any construction project, and so long as any
resulting downtime of the Exterior Loop does not significantly interfere with
Aurora's business. And the Court finds that the proposed use of the new
crossing by Aventine and NELLC—for a total of approximately 6 hours each
week—cannot, by any stretch of the imagination, be considered "materially
adverse" to Aurora's right to the use and quiet enjoyment of the Subject
Premises.
(Filing No. 48, at CM/ECF p. 7).
In the aftermath of that ruling, the Co-op’s motion seeks leave to file an amended
complaint which adds NELLC as a party, and adds a claim for declaratory relief and for an
injunction prohibiting Aventine and NELLC from sending rail cars over the Diamond
Crossing. (Filing No. 60; Filing No. 60-1, at CM/ECF p. 24). The proposed amended
2
complaint alleges the use of the Diamond Crossing by Aventine and NELLC interferes with
the Co-op’s right to quiet enjoyment of the Exterior Loop. (Filing No. 60-1, at ¶ 72, 75-76.)
Aventine opposes the motion to amend, claiming the Co-op's proposed amendments,
either “fail to state a claim for which relief can be granted or are not ripe for declaratory
judgment because no active controversy exists.” (Filing No. 62, at CM/ECF p. 2). Aventine
claims that “to the extent the Co-op’s proposed amendments seek to reverse the installation
of the Diamond Crossing and enjoin the usage of the Diamond Crossing . . . , the Co-op’s
proposed amendments are futile because they fail to state a claim for which relief can be
granted under either the Double Track Loop Agreement or the NELLC Easement
Agreement.” (Filing No. 62, at CM/ECF p. 6). And no active controversy exists at this time
because Judge Gerrard has already ruled that Aventine’s anticipated use is not materially
adverse to the Co-op's right to quiet enjoyment of its easement. (Filing No. 62, at CM/ECF
p. 7).
The motion before this court is a motion to amend a complaint. When reviewing such
motions, “a court assumes all facts in the complaint to be true and construes reasonable
inferences most favorably to the complainant.” U.S. ex rel. Raynor v. National Rural Util.,
690 F.3d 951, 955 (8th Cir. 2012). A motion for leave to amend on the basis of futility
means the district court has “reached the legal conclusion that the amended complaint could
not withstand a motion to dismiss under Rule 12(b)(6).” Moody v. Vozel, 771 F.3d 1093,
1095-96 (8th Cir. 2014) (internal citations omitted).
The Co-op’s proposed complaint alleges that the construction and use of the Diamond
Crossing by Aventine and NELLC will interfere with Aurora Co-op’s right to quiet
enjoyment and use of its easement, that Aventine and NELLC intend to expand that usage
even further, and this use of the Diamond Crossing not only interferes with the Co-op’s use,
but violates the NELLC Easement and Use Agreement because the Diamond Crossing “is
not necessary or desirable for the safety, protection, operation, or preservation of the real
3
estate owned by NELLC or the easement granted to Aurora Co-op.” (Filing 60-1 at ¶¶ 7477.)
The amended complaint alleges that Aventine has refused to confirm that the
statements of anticipated use made at the TRO hearing were or remain accurate. Considered
in the totality, the proposed amended complaint provides sufficient information to “give the
defendant fair notice of what the . . . claim is and the grounds upon which it rests.” Bell Atl.
Corp. v. Twombly, 550 U.S. 544, 555 (2007) (quoting Conley v. Gibson, 355 U.S. 41, 47
(1957). The allegations within the proposed complaint are sufficient to allege a claim that
Aventine’s and NELLC’s use and anticipated use of the Diamond Crossing violates the Coop’s common law and contractual right to quiet enjoyment of the Exterior Loop.
Aventine claims the court has already ruled against the Co-op and its proposed new
allegations, and absent any claim that Aventine has or will use the Diamond Crossing more
frequently than discussed at the TRO hearing, the plaintiff’s claims have already been
considered and rejected by the court and no justiciable controversy exists. (Filing No. 62, at
CM/ECF p. 7). Aventine therefore claims the motion to amend must be denied as futile.
Given the limited purpose of TRO hearings, and “the haste that is often necessary if
[the parties’] positions are to be preserved,” the procedures implemented are less formal and
the ruling is made based on evidence that is less complete than a trial on the merits. As such,
the findings of fact and conclusions of law made on a motion for temporary restraining order
are not binding at a trial on the merits. Univ. of Texas v. Camenisch, 451 U.S. 390, 395
(1981) (discussing preliminary injunction rulings). At the TRO stage of this case, Judge
Gerrard relied on the affidavit of Aventine’s CEO, Mark Beemer, when assessing Aventine’s
anticipated use of the Diamond Crossing and the impact of that use on the Co-op. (Filing
No. 48, at CM/ECF p. 3; Filing No. 60-1, ¶¶ 67-68). Beemer did not testify live, and the Coop was not afforded the opportunity to cross-examine him or otherwise challenge (with the
benefit of discovery) the veracity of Aventine’s statements. Under such circumstances, using
Judge Gerrard’s TRO ruling as the basis for denying the Co-op’s motion to amend as futile
4
would improperly convert the TRO ruling into a final determination, wholly undermining the
Co-op’s right to fully and fairly litigate that issue.
Accordingly,
IT IS ORDERED:
1)
The Co-op’s motion to amend, (Filing No. 60), is granted. The Co-op’s
amended complaint, a copy of which is attached to its motion, shall be filed on
or before June 22, 2015.
2)
The Co-op shall promptly serve NELLC.
3)
Counsel for the parties shall confer and, on or before July 29, 2015, they shall
jointly file a Form 35 (Rule 26 (f)) Report, a copy of which can be found at
http://www.ned.uscourts.gov/forms in Word and WordPerfect format.
4)
If one or more of the parties believes a planning conference is needed to
complete the Rule 26(f) Report, or if the parties cannot agree on one or more
of the deadlines identified or case progression issues raised in the Rule 26(f)
Report, on or before July 22, 2015, a party shall contact my chambers at (402)
437-1670, or by email addressed to zwart@ned.uscourts.gov, to arrange a
conference call.
June 18, 2015.
BY THE COURT:
s/ Cheryl R. Zwart
United States Magistrate Judge
*This opinion may contain hyperlinks to other documents or Web sites. The U.S. District Court for the District of
Nebraska does not endorse, recommend, approve, or guarantee any third parties or the services or products they
provide on their Web sites. Likewise, the court has no agreements with any of these third parties or their Web sites.
The court accepts no responsibility for the availability or functionality of any hyperlink. Thus, the fact that a
hyperlink ceases to work or directs the user to some other site does not affect the opinion of the court.
5
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?