ORDER - IT IS ORDERED that the stipulation is approved and adopted; the parties have until September 8, 2011, to exchange their proposed claim constructions setting forth claim terms for the '288 Patent for which they contend construction is necessary and their proposed construction of those terms. All other dates for the progression of the case remain in force and effect. Ordered by Senior Judge Lyle E. Strom. (TEL)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NEBRASKA
PRISM TECHNOLOGIES, LLC,
)
)
Plaintiff,
)
)
v.
)
)
ADOBE SYSTEMS, INCORPORATED, )
AUTODESK, INC.; McAFEE, INC., )
NATIONAL INSTRUMENTS
)
CORPORATION; SAGE SOFTWARE,
)
INC., SYMANTEC CORPORATION;
)
THE MATHWORKS, INC., and
)
TREND MICRO INCORPORATED,
)
)
Defendants.
)
______________________________)
8:10CV220
ORDER
This matter is before the Court on the joint
stipulation to amend progression order (Filing No. 249).
The
Court finds the stipulation should be approved and adopted.
Accordingly,
IT IS ORDERED that the stipulation is approved and
adopted; the parties have until September 8, 2011, to exchange
their proposed claim constructions setting forth claim terms for
the ‘288 Patent for which they contend construction is necessary
and their proposed construction of those terms. All other dates
for the progression of the case remain in force and effect.
DATED this 2nd day of September, 2011.
BY THE COURT:
/s/ Lyle E. Strom
____________________________
LYLE E. STROM, Senior Judge