Paul Reed Construction & Supply, Inc. v. Arcon, Inc. et al

Filing 74

ORDER: The stay in the case is lifted. On or before July 15, 2013, the parties shall file a joint stipulation including proposed amended progression deadlines Ordered by Magistrate Judge F.A. Gossett. (KMG)

Download PDF
IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA PAUL REED CONSTRUCTION & SUPPLY, INC., a Nebraska corporation, Plaintiff/CounterclaimDefendant, vs. ARCON, INC., a Colorado corporation, Defendant/Counterclaimant, GRANITE RE, INC., an Oklahoma corporation, Defendant. ARCON, INC., a Colorado corporation, Third-Party Plaintiff, vs. WESTERN SURETY COMPANY, Third-Party Defendant. ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) Case No. 8:12cv48 ORDER Pursuant to the Court's Text Order (#73), the parties have submitted a Joint Status Report via email, requesting that the stay in this case be lifted and the deadlines in the Order Setting Final Schedule for Progression (#62) be amended. Therefore, IT IS ORDERED: 1. The stay in the case is hereby lifted. 2. On or before July 15, 2013, the parties shall file a joint stipulation including proposed amended progression deadlines. DATED: July 1, 2013. BY THE COURT: s/ F.A. Gossett, III United States Magistrate Judge -2-

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?