MEMORANDUM AND ORDER - The pretrial conference and jury trial are continued pending further order of the court. Within ten (10) days after the summary judgment ruling, the parties shall contact the undersigned magistrate judge's chambers to re-s hedule the pretrial conference and trial. Defendant Casey Industrial, Inc.'s Motion to Extend Certain Daubert Deadlines and for Shortened Briefing Schedule, (Filing No. 105 ), is granted in part and denied in part. The deadline for submission of Daubert Motions related to the expert testimony of Pearson Management Group, Apprill Resources, LLC, and Demand Construction Services, Inc., up to and including May 5, 2014. Casey Industrial's requestfor an expedited briefing schedule is denied as moot due to the continuance of the pretrial conference and trial. Ordered by Magistrate Judge Cheryl R. Zwart. (AOA)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NEBRASKA
FIDELITY & DEPOSIT COMPANY
OF MARYLAND, as subrogee and
assignee of;
8:12CV70
Plaintiff,
MEMORANDUM AND ORDER
vs.
CASEY INDUSTRIAL, INC., SAFECO
INSURANCE COMPANY OF AMERICA,
Defendants.
A pretrial conference is scheduled in this case for May 13, 2014 and the jury trial
is scheduled for May 27, 2014. Defendant's motion for summary judgment is pending.
Additionally, Defendant Casey Industrial, Inc.’s Motion to Extend Certain Daubert
Deadlines and for Shortened Briefing Schedule, (Filing No. 105).
Accordingly,
IT IS ORDERED:
1)
The pretrial conference and jury trial are continued pending further order of
the court. Within ten (10) days after the summary judgment ruling, the parties shall
contact the undersigned magistrate judge’s chambers to re-schedule the pretrial
conference and trial.
2)
Defendant Casey Industrial, Inc.’s Motion to Extend Certain Daubert
Deadlines and for Shortened Briefing Schedule, (Filing No. 105), is granted in part and
denied in part. The deadline for submission of Daubert Motions related to the expert
testimony of Pearson Management Group, Apprill Resources, LLC, and Demand
Construction Services, Inc., up to and including May 5, 2014. Casey Industrial’s request
for an expedited briefing schedule is denied as moot due to the continuance of the pretrial
conference and trial.
Dated this 11th day of April, 2014.