MEMORANDUM AND ORDER - Defendant Casey's motion for partial summary judgment (filing 63 ) is granted in part and denied in part, as follows: 1. Count III of Plaintiff's complaint, together with those portions of any other counts which involve an alleged scope growth in cold small bore piping, are dismissed with prejudice. 2. In all other respects, the motion is denied. Ordered by Senior Judge Richard G. Kopf. (GJG)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NEBRASKA
FIDELITY & DEPOSIT COMPANY )
OF MARYLAND,
)
)
Plaintiff,
)
)
v.
)
)
CASEY INDUSTRIAL, INC., and
)
SAFECO INSURANCE COMPANY )
OF AMERICA,
)
)
Defendants.
)
)
8:12CV70
MEMORANDUM
AND ORDER
Casey Industrial, Inc. (“Casey”) was the general contractor on a project for the
construction of a power plant. Safeco Insurance Company of America (“Safeco”)
issued a payment bond for the benefit of Casey’s subcontractors and suppliers on the
project. Topps Mechanical, Inc. (“TMI,” “Topps” or “Topp’s”), was a subcontractor
for piping work on the project. Fidelity & Deposit Company of Maryland (“F&D”)
issued both a performance bond and a payment bond for TMI’s subcontract. After
Casey issued a notice of default, F&D provided financial and management assistance
to TMI for completion of the subcontract. F&D now seeks to recover damages from
Casey and Safeco, based on an assignment of claims from TMI and an alleged right
to equitable subrogation.
F&D’s complaint contains 7 counts, which may be summarized as follows: (1)
a claim against Casey for breach of contract; (2) a claim against Casey for equitable
subrogation; (3) a claim against Casey for breach of an implied duty of good faith and
fair dealing by failing to disclose to TMI the actual quantity of cold small bore
(“CSB”) piping that would be required on the project, about which Casey allegedly
had superior knowledge; (4) a claim against Casey for constructive acceleration; (5)
a claim against Casey for constructive changes; (6) a claim against Casey for unjust
enrichment; and (7) a claim against Safeco on its payment bond.
Casey has moved for partial summary judgment (1) dismissing all claims
associated with the alleged scope growth in CSB piping on the project, including
Count III, and (2) dismissing Count II (equitable subrogation claim) and capping
damages recoverable under the remaining counts to those costs that were incurred
directly by TMI, with no recovery for any costs that were paid by F&D. For the
reasons discussed below, the motion will be granted only with respect to the CSB
piping claims.
Summary Judgment Standard
Summary judgment is proper when the evidence, viewed in the light most
favorable to the non-moving party, demonstrates that no genuine issue of material fact
exists, and that the moving party is entitled to judgment as a matter of law. Rester v.
Stephens Media, LLC, 739 F.3d 1127, 1130 (8th Cir. 2014). An issue is “genuine” if
the evidence is sufficient to persuade a reasonable jury to return a verdict for the
nonmoving party. Heacker v. Safeco Ins. Co. of America, 676 F.3d 724, 727 (8th Cir.
2012). “As to materiality, the substantive law will identify which facts are material....”
Id. (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986)). “Only
disputes over facts that might affect the outcome of the suit under the governing law
will properly preclude the entry of summary judgment.” Anderson, 477 U.S. at 248.
Summary of the Parties’ Arguments
Casey contends the parol evidence rule defeats the CSB piping claims, and
notes there is an integration clause in the subcontract. Casey argues that Nebraska law,
which governs the subcontract, does not recognize a “superior knowledge” exception
to the parol evidence rule, nor does it impose an implied duty of good faith and fair
dealing with respect to contract negotiations (as opposed to performance). In response,
-2-
F&D contends Casey made fraudulent misrepresentations. F&D also argues that the
amount of CSB piping required for the project might naturally be the subject of a
separate agreement by the parties. Casey objects that F&D did not allege fraud and
maintains there is no evidence to support F&D’s claims.
Casey contends F&D cannot bring an equitable subrogation claim because it
acted as a volunteer, even though Casey had declared that TMI was in default. Casey
now claims F&D was not required to act until the subcontract was terminated, which
never occurred; Casey also claims F&D is precluded from asserting that Casey
breached the subcontract because the performance bond was conditioned on Casey
fulfilling its contractual obligations. Casey further claims that F&D cannot recover as
an assignee for additional costs that were incurred in completing the subcontract
because such costs were paid by F&D instead of TMI. F&D responds that Casey’s
arguments fail as a matter of law.
Undisputed Facts
This case relates to work performed on the Whelan Energy Center, Unit #2
power plant project located in Hastings, Nebraska, and owned by the Public Power
Generation Agency (“PPGA”). Black and Veatch (“B&V”) provided the project
design and acted as the owner’s construction manager for the project. Casey was
awarded the contract for mechanical construction on November 7, 2008.
On December 29, 2008, Casey entered into a subcontract with TMI. The scope
of work, as defined in Exhibit 3.1 to the subcontract, included, among other items, the
“[s]upply and erection of cold small bore piping plus supports” (filing 63-5 at 28).
Attached to Exhibit 3.1 is “a ‘Division of Responsibility’ document which is intended
to identify which material/equipment will be installed by which contractor” (id.). The
document listed numerous specifications and indicated whether they pertained to TMI
or Casey, or both. Some of the specifications pertaining to TMI were marked “xx,”
which was “intended to denote that this pipe is believed to be ‘cold small bore’” (id.
-3-
at 31). It was noted that “Topps must satisfy themselves as to the amount of pipe and
fittings required to complete this system” (id.).
When TMI prepared its bid for the subcontract work, it estimated that 10,000
linear feet of CSB piping would be needed for the project. The estimate was prepared
based on information obtained from B&V, including piping and instrumentation
drawings (“P&IDs”) and other drawings. TMI placed a “qualifier” in its bid stating
that it had “included installation costs for a total of 10,000 feet of 2O and smaller cold
small bore piping” (filing 63-8 at 4). Casey demanded the removal of this qualifier
from the bid, and it does not appear in the executed subcontract. The subcontract
includes an integration clause (section 32.7), which states:
This Subcontract embodies the entire agreement of the parties. There are
no promises, terms, conditions or obligations other than those contained
herein. This Subcontract shall supersede all prior communications,
representations or agreements, either oral or written, between the parties.
(Filing 63-5 at 19).
Section 10 of the subcontract required Casey to pay TMI a fixed price for
satisfactory completion of all subcontract work; there was no separate pricing for the
CSB piping work. According to F&D, the project actually required about 35,000
linear feet of CSB piping, resulting in a cost overrun in excess of $4 million.
Section 16.4 of the subcontract required TMI to furnish a performance bond “in
the form and with a surety acceptable to [Casey] per Exhibit 16.4” (filing 63-5 at 12).
This was accomplished on February 25, 2009. The performance bond provides in
relevant part:
Topp’s Mechanical, Inc., ... herein called Principal, and Fidelity and
Deposit Company of Maryland, ... herein called Surety, are held and
firmly bound unto Casey Industrial, Inc., .. as Obligee, in the amount of
-4-
... $18,900,927.00 ..., for the payment whereof Principal and Surety bind
themselves ... jointly and severally ....
WHEREAS, Principal has by written agreement dated December 29,
2008, entered into a subcontract with Obligee for Whelen Energy Center
Unit 2 Mechanical Construction Project ..., which subcontract is by
reference made a part hereof, and is referred to as subcontract.
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is
such that, if the Principal shall promptly and faithfully perform said
subcontract, then this obligation shall be null and void; otherwise to
remain in full force and effect.
The Surety hereby waives notice of any modification or amendment to
the Subcontract made in accordance with the terms thereof, and any
alteration or extension of time made by or through the General
Contractor.
Whenever Principal shall be, and be declared by Obligee to be in default
under the subcontract, the Obligee having performed Obligee’s
obligations thereunder:
(1)
Surety may promptly remedy the default subject to the provisions
of paragraph 3 herein, or;
(2)
Obligee after reasonable notice to Surety may, or Surety upon
demand of Obligee, may arrange for the performance of
Principal’s obligation under the subcontract subject to the
provisions of paragraph 3 herein;
(3)
The balance of the subcontract price ... shall be credited against
the reasonable cost of completing performance of the subcontract.
If completed by the Obligee, and the reasonable cost exceeds the
balance of the subcontract price, the Surety shall pay to the
Obligee such excess, but in no event shall the aggregate liability
of the Surety exceed the amount of this bond. If the Surety
arranges completion or remedies the default, that portion of the
balance of the subcontract price as may be required to complete
-5-
the subcontract or remedy the default and to reimburse the Surety
for its outlays shall be paid to the Surety at the times and in the
manner as said sums would have been payable to Principal had
there been no default under the subcontract.
(Filing 63-11 at 2).
Section 24 of the subcontact addresses default and remedies. It provides in
relevant part:
Subcontractor [TMI] shall be in default if it fails or refuses to perform
any material obligation under this Subcontract on its part to be
performed. If Subcontractor fails within three (3) business days after
written notice thereof by Contractor [Casey] to commence and continue
satisfactory correction of such default with diligence and promptness,
Contractor shall have any or all of the following remedies:
24.1 Contractor may complete or perform the Subcontract Work
... and charge the cost thereof to Subcontractor ....
24.2 Contractor may contract with one or more additional parties
to perform ... and charge all direct and indirect costs thereof to
Subcontractor ....
24.3 In the event Contractor elects to perform the Subcontract
Work or contracts with another subcontractor by virtue of
Subcontractor’s default, Contractor or such replacement subcontractor
may lake and use any materials, implements, equipment, appliances or
tools furnished by, belonging or delivered to Subcontractor and located
at the Project site only if Subcontractor expressly agrees in writing to
permit such taking and use...
24.4 Contractor may withhold payment of any moneys otherwise
due Subcontractor pending corrective action to the extent required by
and to the satisfaction of Contractor.
-6-
24.5 If upon a second notice, Subcontractor fails to commence
and continue correction of the default within ten (10) business days,
Contractor may terminate this Subcontract, in which event Subcontractor
shall be liable for the costs of completing Subcontract Work.
24.6 The foregoing remedies are not exclusive. Contractor shall
be entitled to all remedies available at law or equity.
24.7 Notwithstanding the forgoing, if the event of default would
cause work cessation, then Contractor may require that Subcontractor
immediately commence and continue correction of the default.
Subcontractor’s failure to immediately commence and continue
correction or the inadequacy of Subcontractor’s efforts to cure the
default will give Contractor grounds to terminate this Subcontract, in
which event Subcontractor shall be liable for the costs of completing the
Subcontract Work.
(Filing 63-5 at 15-16).
On November 19, 2009, Casey directed TMI to accelerate its work because it
was failing to perform to the project schedule. TMI was advised that should it fail to
comply with this directive, “Casey shall, on 11-24-2009, provide notice of default in
accordance with Section 24 of the Subcontract” and, “[a]bsent timely cure by Topp’s,
Casey shall exercise Casey’s option under Subsection 24.1” (filing 71-8 at 10). Also
on November 19, 2009, Casey sent a letter to F&D advising that “[s]hould Topp’s fail
to meet the requirements of their subcontract and the notice sent today, Casey will
place them in default and be forced to call upon the attached bonds” (id. at 8).
On December 10, 2009, Casey sent a “Written Notice of Default” to TMI (filing
63-12 at 2). The notice stated:
Following the written notice of default delivered to you on November
19, 2009 by Steve Brague, and Topp’s continued failure to cure such
default in a timely manner (namely recovery of the project schedule),
Casey is taking steps to exercise our rights under Subcontract
-7-
0803009-01, Section 24, Default and Remedies. Your failure to
satisfactorily cure your schedule of work and show any recovery towards
the project schedule requirements, the written notice of default and cure
from PPGA to Casey, and the recent evidence today of your inability to
meet your financial obligations, forces Casey to take the following steps:
1.
Per Section 24.1, Casey shall perform the work in the areas
as listed in the meeting minutes of December 3, 2009 and
charge the cost of such work to Topp’s per the rates and
mark-up as previously communicated to you on December
10, 2009 at 8:00am, MST.
2.
Casey will also send notice to your Surety requesting their
immediate participation to satisfy all of Topp’s contractual
requirements.
Such default and remedies as detailed above, shall in no way cause any
work cessation on the part of Topp’s Mechanical. Casey fully expects
Topp’s to work with their surety in an effort to recover their schedule,
meet their financial obligations as it relates to this project, and complete
all work under this subcontract.
(Id.) Casey also sent a letter to F&D on December 10, 2009. It stated in part:
Topp’s has been behind schedule for some time and has continued to
progress further behind schedule. Through an ongoing effort of letters,
meetings, and other communications, Casey has been requesting from
Topp’s recovery schedules, cash flow projections, vendor information,
and other documents we feel necessary to evaluate their ability to recover
the schedule and meet all financial obligations. To date Topp’s has failed
to meet these requirements. Subsequently, Casey has received a notice
of default from our customer PPGA citing the short falls of Topp’s as it
relates to the schedule. Casey has been placed into a cure period in which
Casey must show PPGA our recovery plan, including the work of
Topp’s.
Due to the ongoing failures of Topp’s to provide required progress to
meet schedule obligations, the recent letter of default from PPGA to
-8-
Casey, and today’s confirmation of Topp’s inability to meet their
financial obligations (i.e. Casey’s last minute advance of payroll in the
amount of $670,534.73, which is the 3rd such advance), Casey has
officially placed Topp’s Mechanical in default of their Subcontract
0803009-01. Based on information communicated to Casey by Luke
Topp, he has been unable to secure adequate financing to cover their
projected use of cash.
Casey’s further concern also rests in the exposure that this subcontractor
brings to them in the area of “liquidated damages”.... Thus it is
imperative that Topp’s and their surety respond timely to the present
situation to preclude a default under this subcontract and the impact that
will result to Casey Industrial, Inc.
Therefore, Casey is putting you on notice, under the provided
performance and payment bonds for the referenced subcontract, of the
default and Casey requests that you and your principal respond to any
demands by Casey Industrial to fulfill the terms and conditions of this
subcontract and address the inability of Topp’s Mechanical to meet their
payment and performance obligations.
Casey would like to arrange a meeting at the earliest convenience so that
we can discuss an appropriate course of action relative to the issue
outlined herein....
(Filing 63-13 at 2-3).
On December 16, 2009, Casey sent another letter to F&D regarding an email
it received from one of TMI’s vendors, indicating that rental equipment being used on
the project would be picked up because of nonpayment, and that a mechanic’s lien
would be filed. Casey’s letter stated that “[a]s Casey has already placed Topp’s in
default of their Subcontract, Casey demands the Surety to step in and respond
immediately” (filing 71-8 at 34).1
1
F&D understood the December 16th demand letter to apply to the payment
bond rather than the performance bond (filing 63-3 at 9).
-9-
In connection with F&D’s issuance of the payment and performance bonds in
February 2009, TMI executed an “Agreement of Indemnity” which included an
assignment to F&D of “[a]ll rights of the Contractor [TMI] in, and growing in any
manner out of, all contracts referred to in the Bonds, or in, or growing in any manner
out of the Bonds” as collateral security (filing 1-5 at 2-3). The agreement also
provided that “[i]n the event of any breach or default asserted by the obligee in any
said Bonds, ...the Surety [F&D] shall have the right, at its option ..., to take possession
of any part of the work under any contract or contracts covered by said Bonds, and at
the expense of the Contractor ... to complete or arrange for the completion of the
same, and the Contractor ... shall promptly upon demand pay to the Surety all losses,
an expenses so incurred” (id. at 3).
On September 8, 2010, a “Financing and Collateral Agreement” was executed
by TMI and F&D (filing 63-14). In a contemporaneously executed addendum, it was
agreed that “[t]he Surety [F&D] will waive its indemnity rights, collection rights,
rights to collect amounts deemed to have been loaned to the Principal [TMI]”
conditioned upon TMI remaining on the project and not filing for bankruptcy, among
other requirements (filing 63-15 at 2-3).
On September 15, 2010, TMI assigned to F&D all of its “right, title and interest
in and to any and all monies payable to or received by [TMI] under or in connection
with the Subcontract ..., including but not limited to monies earned and to be earned,
payment of retained percentages and final payments due or to become due to [TMI]
of every kind or nature under the Project, including payment for all extras, claims,
requests for equitable adjustments, bonuses, waivers or reductions on assessed
liquidated damages and/or damages of any other kind or nature which may be received
by [TMI] for the Project and the Subcontract, ... together with all rights of action
accrued or which may accrue thereunder” (filing 71-8 at 36).
CSB Piping Claims
-10-
“The parol evidence rule states that if negotiations between the parties result in
an integrated agreement which is reduced to writing, then, in the absence of fraud,
mistake, or ambiguity, the written agreement is the only competent evidence of the
contract between them.” R and B Farms, Inc. v. Cedar Valley Acres, Inc., 798 N.W.2d
121, 129-30 (Neb. 2011). “This rule gives legal effect to the contracting parties’
intention to make their writing a complete expression of the agreement that they
reached, to the exclusion of all prior or contemporaneous negotiations.” Id. at 130.
The subcontract in this case obligated TMI to “[s]upply and erect[ ] ... cold
small bore piping plus supports” (filing 63-5 at 28). No quantity was specified for
the CSB piping. It was expressly agreed that the subcontract “supersede[d] all prior
communications, representations or agreements, either oral or written, between the
parties,” and that “[t]here are no promises, terms, conditions or obligations other than
those contained [t]herein” (id. at 19).
F&D does not allege that the subcontract is ambiguous. See Davenport Ltd.
Partnership v. 75th & Dodge I, L.P., 780 N.W.2d 416, 423 (Neb. 2010) (“A written
instrument is open to explanation by parol evidence when its terms are susceptible to
two constructions or where the language employed is vague or ambiguous.”). Nor
does F&D specifically allege that the subcontract should be corrected to include
additional compensation for CSB piping because of a mutual mistake concerning the
quantity required for the project or because of any fraud committed by Casey.2 See
2
Under federal pleading practice, “a party must state with particularity the
circumstances constituting fraud or mistake.” Fed. R. Civ. P. 9(b). “In other words,
Rule 9(b) requires plaintiffs to plead the who, what, when, where, and how: the first
paragraph of any newspaper story.” Crest Const. II, Inc. v. Doe, 660 F.3d 346, 353
(8th Cir. 2011) (quoting Summerhill v. Terminix, Inc., 637 F.3d 877, 880 (8th Cir.
2011)). A failure to plead fraud with particularity can result in the dismissal of a claim
on a defendant’s motion for summary judgment. See, e.g., Mayer v. Countrywide
Home Loans, 647 F.3d 789, 792 (8th Cir. 2011); Mitec Partners, LLC v. U.S. Bank
Nat. Ass’n, 605 F.3d 617, 622 (8th Cir. 2010).
-11-
R and B Farms, 798 N.W.2d at 130 (“A court may reform a written agreement only
when there has been either a mutual mistake or a unilateral mistake caused by fraud
or inequitable conduct on the part of the party against whom reformation is sought.”).
F&D instead alleges Casey breached an implied duty of good faith and fair
dealing and claims Casey had “superior knowledge.” Specifically, F&D alleges in
Count III of the complaint:
57. In entering into the Subcontract, Casey impliedly covenanted
to act in good faith and to deal fairly with Topps.
58. In entering into the Subcontract, Casey was prohibited from
doing anything which would prevent, hinder or impede Topps’ right to
receive the benefit of its bargain under the Subcontract.
59. When Topps prepared its bid, it undertook performance
without vital information necessary to complete the Subcontract work,
which greatly affected Topps’ costs of performance.
60. At the time Topps prepared and submitted its bid, Casey
assured Topps that any risks associated with the actual required amount
of linear feet of CSB Piping on the Project would be minimal. Topps had
no reason to doubt Casey and otherwise had no knowledge of any
information to the contrary and/or any reason to obtain such information.
61. The relevant contract specifications and Casey’s actions
related to the CSB Piping misled Topps, or did not put Topps on notice
to inquire further.
62. Casey failed to provide Topps with the relevant information
related to the total amount of linear feet necessary for completion of the
CSB Piping on the Project.
63. Topps was damaged by Casey’s breach of the implied duty of
good faith and fair dealing and failure to disclose superior knowledge.
-12-
64. By virtue of the assignment and the Indemnity Agreement,
F&D is the proper party plaintiff to bring these claims against Casey.
(Filing 1 at 9-10). Additional allegations pertaining to the CSB piping claims, which
are incorporated by reference into Count III, include the following:
15. In late Summer 2008, Topps prepared a preliminary estimate
for the Project.
16. Casey advised Topps that Casey would help Topps prepare a
bid for the piping work on the Project. Thereafter Casey was actively
involved and engaged with Topps in Topps’ preparation of its bid. After
receiving input by Casey, Topps’ estimate was significantly lowered.
17. In order to prepare its bid, Topps requested specific
information from Casey related to the Project, Casey provided that
information, and Topps relied upon the information.
18. In preparing its bid on the Project and in calculating its
anticipated labor and material costs and expenses, Topps relied upon
plans and specifications provided by Casey as well as the projected labor
rates for construction work undertaken during the period of time
identified in Casey’s Project schedule.
19. Casey did not provide adequate documentation and
information to Topps upon which Topps could estimate the quantity of
Cold Small Bore Piping (“CSB Piping”) that would be required to
complete the Project.
20. Topps’ bid for CSB Piping on the Project was based on an
estimated need for 10,000 linear feet of piping. Casey assured Topps that
any risks associated with the actual required amount of linear feet of
CSB Piping on the Project would be minimal. Due to routing
requirements on the Project not known to Topps at the time of the
preparation of its bid, the actual amount of CSB Piping needed for
completion of the Project was in excess of 35,000 linear feet. Casey’s
failure to provide Topps with information regarding this material fact
damaged Topps.
-13-
21. During performance, Topps expended significantly more man
hours installing significantly more linear feet of CSB Piping than was
anticipated in the Subcontract.
(Id. at 3-4).
“The superior knowledge doctrine is a narrow exception to the general rule that
contractors in a firm, fixed-price contract assume the risk of increased performance
costs.” P & K Contracting, Inc. v. United States, 108 Fed.Cl. 380, 394-95 (Fed.Cl.
2012). As applied to government contracts, the doctrine generally covers situations
where “(1) a contractor undertakes to perform without vital knowledge of a fact that
affects performance costs or duration, (2) the government was aware the contractor
had no knowledge of and had no reason to obtain such information, (3) any contract
specification supplied misled the contractor or did not put it on notice to inquire, and
(4) the government failed to provide the relevant information.” Philadelphia Authority
for Industrial Development v. United States, 114 Fed.Cl. 519, 528 (Fed.Cl. 2014)
(quoting Hercules, Inc. v. United States, 24 F.3d 188, 196 (Fed.Cir. 1994)). “Although
the government is not a fiduciary toward its contractors, ... where the balance of
knowledge is so clearly on its side ... [it] can no more betray a contractor into a
ruinous course of action by silence than by the written or spoken word.” Helene Curtis
Industries, Inc. v. United States, 312 F.2d 774, 778 (Ct.Cl. 1963).
In Nebraska, “[a]s a general rule, a party to a transaction does not have a duty
to disclose facts to the other unless there is a fiduciary relationship between the
parties.” National American Ins. Co. v. Constructors Bonding Co., 719 N.W.2d 297,
303 (Neb. 2006). “[W]here persons are dealing with each other upon equal terms, and
no confidential relation exists between them, neither is bound to disclose superior
information he may have respecting the transaction, and, in the absence of fraud or
deception to induce the contract, the courts can afford no relief.” Id. (quoting Jones
v. Stewart, 87 N.W. 12, 13 (Neb. 1901) (emphasis supplied)).
-14-
With respect to fraudulent concealment, the Nebraska Supreme Court has
followed Restatement (Second) of Torts § 551 (1977) in determining whether a duty
to disclose exists. See Streeks, Inc. v. Diamond Hill Farms, Inc., 605 N.W.2d 110,
118-20 (Neb. 2000), overruled in part on other grounds by Knights of Columbus
Council 3152 v. KFS BD, Inc., 791 N.W.2d 317 (Neb. 2010).3 Among other situations
creating a duty to disclose, the Restatement provides that “[o]ne party to a business
transaction is under a duty to exercise reasonable care to disclose to the other before
the transaction is consummated, ... facts basic to the transaction, if he knows that the
other is about to enter into it under a mistake as to them, and that the other, because
of the relationship between them, the customs of the trade or other objective
circumstances, would reasonably expect a disclosure of those facts.” Restatement
(Second) of Torts § 551(2)(e) (1977). “Existence of a duty to disclose the fact in
question is a matter for the determination of the court, although, if there are disputed
facts bearing upon the existence of the duty, they are to be determined by the trier of
fact under appropriate instructions as to the existence of the duty.” Zawaideh v.
Nebraska Dept. of Health and Human Services Regulation and Licensure, 792
N.W.2d 484, 496 (Neb. 2011).
The record is devoid of any facts indicating that TMI should reasonably have
expected Casey to disclose to it at the time of contracting the quantity of CSB piping
that would be needed for completion of the project. The subcontract’s “Division of
3
“[T]o prove fraudulent concealment, a plaintiff must prove these elements:
(1) The defendant had a duty to disclose a material fact; (2) the defendant, with
knowledge of the material fact, concealed the fact; (3) the material fact was not within
the plaintiff’s reasonably diligent attention, observation, and judgment; (4) the
defendant concealed the fact with the intention that the plaintiff act or refrain from
acting in response to the concealment or suppression; (5) the plaintiff, reasonably
relying on the fact or facts as the plaintiff believed them to be as the result of the
concealment, acted or withheld action; and (6) the plaintiff was damaged by the
plaintiff’s action or inaction in response to the concealment.” Knights of Columbus
Council, 791 N.W.2d at 334.
-15-
Responsibility” document even cautioned that “Topps must satisfy themselves as to
the amount of pipe and fittings required to complete this system” (filing 63-5 at 31).
Although F&D alleges that “Casey was actively involved and engaged with Topps in
Topps’ preparation of its bid” (complaint (filing 1), ¶ 16), TMI’s designated
representative testified during a Rule 30(b)(6) deposition4 that Casey had no
involvement in the estimating process for the CSB piping (TMI depo. (filing 63-2) at
16:18-17:6), and that the allegation about TMI lowering its bid after receiving input
from Casey does not relate to the CSB piping (id. at 27:12-30:9; 45:22-48:7).
Luke Topp explained how the estimate was made: “We took a general
arrangement drawing and the P&ID’s, which is all we had to work with and took our
knowledge that we had as a company and did the linear footage aground the building
times the floors, and then that’s how we came to the 10,000 linear feet” (id. at 17:1015). TMI had experience bidding similar projects in the same fashion (id. at 17:1920:7). “[I]t was standard practice” (id. at 26:4-19). Although the estimate assumed the
piping could be routed in straight lines (id. at 157:20-158:12), TMI understood it
would be responsible for designing the actual routing while on the job (id. at 78:2179:14). As F&D states in its brief: “The actual amount of CSB piping that was
necessary for the Project was not fully known until all design drawings and Isometric
drawings (“ISOs”) were approved by B&V during the construction process (rather
than during the initial estimating phase)” (filing 70 at 4). TMI is not aware of either
Casey or Black & Veatch performing their own pre-contract estimate of CSB piping
quantities (TMI depo. (filing 63-2) at 32:1-12).
F&D alleges TMI underbid its subcontract work because it did not have
information concerning the “routing requirements on the Project” (complaint (filing
4
Federal Rule of Civil Procedure 30(b)(6) provides that a party may name a
corporation as the deponent and “describe with reasonable particularity the matters for
examination.” The corporation then must designate one or more persons to testify on
its behalf.
-16-
1), ¶ 20). Casey allegedly “fail[ed] to provide Topps with information regarding this
material fact” and “did not provide adequate documentation and information to
Topps upon which Topps could estimate the quantity of Cold Small Bore Piping” (id.,
¶¶ 20, 19). F&D does not specifically allege Casey had this information when the
subcontract was executed, nor has it produced any evidence to substantiate this
essential element of fraudulent concealment.
In fact, TMI’s designated representative admitted there is no factual basis for
a claim of fraudulent concealment. Luke Topp was asked the following questions and
gave the following answers during the Rule 30(b)(6) deposition:
Q ... Is it the plaintiff’s position that there was any information –
actual information, facts, that Casey had prior to the date of the
subcontract being signed about the actual quantities or the quantities of
CSB that they did not share with Topps?
A I don’t understand that question.
Q Okay. Is it plaintiff’s belief that Casey was holding out on
Topps and not giving them some information that they had?
A No, I don’t believe so.
(TMI depo. (filing 63-2) at 41:2-11). TMI’s position is simply that the P&IDs and
general arrangement drawings that were available at the time of bidding did not
contain enough information (id. at 36:9-37:6).
The evidence also indicates Casey and TMI had equal access to information
before the subcontract was signed. Another designated representative, Terry
Valentine, testified as follows:
Q The – during the bid phase, am I right that Black & Veatch
conveyed drawings and documents to the parties using basically an FTP
site?
A Yes.
Q And that’s their iBack-up site?
-17-
A If they call it that. All I know is they would put files out there,
they’d notify us, and we’d download them off of that.
Q And am I correct that for at least a period of time, Topps had a
password to that site and would download the documents themselves,
correct?
A That is correct.
Q At some point did at that time change?
A Yes.
Q When was that?
A When the contract [was] signed with Casey. Casey wanted
everything – they would download everything, and then they would send
us what we needed.
Q So you’re saying that you stopped logging directly onto the
system – Topps stopped logging directly onto the system after it signed
its contract with Casey?
A Yes, because we didn’t have user rights anymore.
Q Prior to that, Topps did?
A Yes.
(Id. at 173:17-174:17).
F&D speculates that Casey obtained more information from Black & Veatch
during a pre-letting meeting in Kansas City, which was also attended by TMI.
Luke Topp testified that when the topic of CSB piping came up, he “made the
qualifier of 10,000 linear feet,” whereupon an unidentified B&V representative
“turned ... red, ... jumped up, ... pointed across the room at Rick Lawrence [of TMI],
and they both left. A few minutes later they came back in, and we went to – we went
to talking about other things” (id. at 32:13-33:5). Luke Topp had “no clue” what the
B&V representative and Rick Lawrence discussed while outside the room, and they
gave no indication of what had been discussed when they returned (id. at 33:2434:15). During their absence, however, another B&V representative may have
commented about the 10,000 linear feet estimate. When asked what was said, Luke
Topp replied: “I don’t recall. They thought it might be light, but they never really
said. They just kind of – you know, they didn’t want to – they danced around the
-18-
question” (id. at 34:16-35:22). “In that meeting they had talked, you know, if 10,000
was enough or not, but, you know, they didn’t really know. They didn’t really – you
know, they didn’t give it a qualifier, and they wouldn’t” (id. at 33:6-9).
Luke Topp stated that TMI did not revise its 10,000 linear feet estimate after
this meeting because “[t]he estimate had already been issued to Casey,” which was
“one of the two [potential general contractors] left ... on the bid to Black & Veatch or
PPGA” and “[a]t that point there was no – no way to change it” (id. at 35:23-36:8).
Luke Topp then testified about subsequent conversations he had with Casey’s
representatives concerning the CSB piping and the qualifier of 10,000 linear feet:
A I had two conversations. One was at the Kansas City meeting in
the parking lot with Rick Lawrence. He asked me about it, and, I said,
“You know, it is what it is, Rick, but we’ve got the qualifier in there of
10,000 feet.” And he says, “Well, what if there’s more?” I said, “well, if
there’s more, it’s more money, obviously.” And he says, “Well, we’ll
have to leave that in there, I believe, but,” he says, “we’ll take care of
you if there’s, you know.” He says, “We’ll work with you.” He said,
“Don’t worry about it.”
***
A The other conversation was with Steve [Brague] a day or so
later. Steve called me.… And he pretty much asked me the same
question, and we had the same conversation. I mean, almost to the letter.
And Steve, you know, he’d give me the assurance. “I understand that
you’re nervous about it,” but he says, “we’ll work with you. Don’t worry
about it. It’s going to be okay.” He says that, ‘You know, Black &
Veatch, obviously, that made them a little nervous, but we’re okay with
it, and we’ll work with it.”
(Id. at 38:19-40:9).
The foregoing testimony is not sufficient to create a genuine issue of material
fact regarding Casey’s alleged superior knowledge or fraudulent concealment. F&D
argues that the court “must draw all justifiable inferences related to the hallway
meeting between Mr. Lawrence and B&V personnel in TMI’s favor” (filing 70 at 15),
-19-
but this must be done “without resort to speculation.” Phelps-Roper v. Koster, 713
F.3d 942, 947 (8th Cir. 2013); see also Bayside Holdings, Ltd. v. Viracon, Inc., 709
F.3d 1225, 1228 (8th Cir. 2013) (to withstand a motion for summary judgment,
“[t]he nonmoving party may not rely on mere speculation or conjecture”). It might
reasonably be inferred from what Luke Topp witnessed that B&V did not like the
10,000 linear foot qualifier – indeed, Steve Brague evidently told Luke Topp a day or
two later that the qualifier made B&V “a little nervous” – but it would be pure
speculation to conclude that Casey was informed by B&V that additional CSB piping
would necessarily be required for the project.
F&D also claims in its brief that TMI entered into the subcontract as a result of
fraudulent misrepresentations.5 Specifically, it contends “Casey represented to TMI
that any risks associated with the required amount of linear feet of CSB piping on the
Project would be minimal and that TMI would be taken care of in the event more than
10,000 linear feet of CSB piping was necessary” (filing 70 at 14).
When asked to describe during TMI’s Rule 30(b)(6) deposition how Casey had
represented that TMI’s risks would be “minimal,” Luke Topp only referenced the
conversations he had with Rick Lawrence and Steve Brague following the Kansas
City meeting (TMI depo. (filing 63-2) at 38:10-40:23). As recounted by Luke Topp,
however, in neither conversation was a representation made that TMI’s risks would
be “minimal.” F&D also points to a statement allegedly made by Casey’s mechanical
estimator, John Ramondo, at a meeting in Denver after TMI had developed its 10,000
linear feet estimate. There is evidence Ramondo said that Casey had performed a
“comparable job” where 12,000 linear feet of CSB was installed, that TMI’s estimate
5
“To state a claim for fraudulent misrepresentation, a plaintiff must allege (1)
that a representation was made; (2) that the representation was false; (3) that when
made, the representation was known to be false or made recklessly without knowledge
of its truth and as a positive assertion; (4) that the representation was made with the
intention that the plaintiff should rely on it; (5) that the plaintiff did so rely on it; and
(6) that the plaintiff suffered damage as a result.” Zawaideh, 825 N.W.2d at 212.
-20-
was “probably pretty close,” and that he “would feel comfortable with that number”
(id. at 30:10-31:10; 165:5-167:2). This individual’s thoughts about the accuracy of
TMI’s estimate cannot provide the basis for a claim of fraudulent misrepresentation.
“To constitute a false representation, a statement must be made as a statement of fact,
not merely the expression of an opinion.” Kliewer v. Wall Const. Co., 429 N.W.2d
373, 380 (Neb. 1988); see also Fast Ball Sports, LLC v. Metropolitan Entertainment
& Convention Authority, 835 N.W.2d 782, 791 (Neb.App. 2013) (“A fraudulent
statement relates to a present or preexisting fact.”) (quoting Linch v. Carlson, 56
N.W.2d 101, 105 (Neb. 1952) (quotation omitted)).
The alleged representation that TMI would be “taken care of” if more CSB
piping was needed for the project is also linked to the conversations Luke Topp had
with Rick Lawrence and Steve Brague following the meeting in Kansas City. At the
time those statements allegedly were made, however, TMI’s bid contained a qualifier
of 10,000 linear feet for the CSB piping, and TMI indicated it would demand more
money if additional piping became necessary. Casey subsequently demanded that the
qualifier be removed, and it was. Luke Topp testified that “the qualifier was in the
documents the day before Christmas when we argued about it and finally signed the
contract when they talked me out of – talked me into pulling it out” (TMI depo. (filing
63-2) at 52:21-24). He said, “Rick Lawrence wouldn’t sign it unless it was gone” (id.
at 53:16-17). Luke Topp admitted that “during this Christmas Eve conversation,
[Casey] didn’t say once again that they would take care of anything over 10,000” (id.
at 54:10-14). Terry Valentine also participated in the Christmas Eve conversation and
confirmed that the qualifier was removed by TMI in order to get Casey to sign the
subcontract (id. at 160:15-161:12). He admitted that as a result “Topps was taking on
the risk associated with the quantity of cold small bore being over 10,000 feet” (id. at
161:20-162:9). In short, there is no evidence of any misrepresentation.
While “[t]he implied covenant of good faith and fair dealing exists in every
contract and requires that none of the parties to the contract do anything which will
injure the right of another party to receive the benefit of the contract,” RSUI Indem.
-21-
Co. v. Bacon, 810 N.W.2d 666, 674 (Neb. 2011), Casey’s alleged nondisclosures and
misrepresentations preceded the execution of the subcontract. “A violation of the
covenant of good faith and fair dealing occurs only when a party violates, nullifies,
or significantly impairs any benefit of the contract.” Id. Thus, the covenant only
applies to “the performance of a contract.” See id. “[Casey] could not have breached
the covenant of good faith and fair dealing by its pre-award conduct because the
covenant did not exist until the [sub]contract was signed.” Scott Timber Co. v. United
States, 692 F.3d 1365, 1372 (Fed.Cir. 2012); see also Cimino v. FirsTier Bank, N.A.,
530 N.W.2d 606, 616 (Neb. 1995) (“In order for the implied covenant of good faith
and fair dealing to apply, there must be in existence a legally enforceable contractual
agreement.”).
Finally, F&D argues that “[c]alculating the total amount of CSB piping after
contract execution is the type of agreement that might naturally be made by separate
agreement” (filing 70 at 19), and claims this fact creates an exception to the parol
evidence rule.6 In support of this argument, F&D cites Traudt v. Nebraska Public
Power Dist., 251 N.W.2d 148, 150 (Neb. 1977), in which the Nebraska Supreme
Court discussed the exception provided in Restatement of Contracts § 240 (1932):
(1) An oral agreement is not superseded or invalidated by a
subsequent or contemporaneous integration, nor a written agreement by
a subsequent integration relating to the same subject-matter, if the
agreement is not inconsistent with the integrated contract, and
(a) is made for separate consideration, or
6
As evidence of a separate agreement, F&D references a February 2009 email
from Black & Veatch to Casey that proposed a “Unit Price Quantity Reconciliation
Procedure” which was intended to reduce the number of change orders that would be
submitted by Casey (filing 63-10). The email does not show there was an agreement
between Casey and TMI for additional compensation for CSB piping.
-22-
(b) is such an agreement as might naturally be made as
separate agreement by parties situated as were the parties to the
written contract.
(2) Where no consideration is stated in an integration, facts
showing that there was consideration and the nature of it, even if it was
a promise, or any other facts that are sufficient to make a promise
enforceable, are admissible in evidence and are operative.
This exception does not apply when the transaction is completely integrated.
See Traudt, 251 N.W.2d at 150. The subcontract that was entered into between Casey
and TMI “embodies the entire agreement of the parties” (filing 63-5 at 19). F&D’s
claim that TMI was entitled to receive additional compensation for the CSB piping is
inconsistent with the express terms of the subcontract.
In conclusion, Casey’s motion for partial summary judgment will be granted
with respect to Count III of F&D’s complaint and any other counts which involve an
alleged scope growth in CSB piping. Parol evidence is not admissible to vary the
terms of the subcontract under any of the various theories advanced by F&D.
Equitable Subrogation Claim
“The theory of equitable subrogation is based on the view that the triggering of
a surety’s bond obligation gives rise to an implied assignment of rights by operation
of law whereby the surety ‘is subrogated to the [principal obligor’s] property rights
in the contract balance.’” Lumbermens Mut. Cas. Co. v. United States, 654 F.3d 1305,
1312 (Fed. Cir. 2011) (quoting Balboa Ins. Co. v. United States, 775 F.2d 1158, 1161
(Fed.Cir. 1985)). “That is, the surety ‘step[s] into the shoes’ of the principal obligor
and is entitled to all of its rights relating to the construction contract.” Id. (quoting
Insurance Co. of the West v. United States, 243 F.3d 1367, 1374 (Fed.Cir.2001)).
-23-
More generally, “[t]he doctrine of subrogation includes every instance in which
one person pays a debt for which another is primarily liable, and which in equity and
good conscience should have been discharged by the latter, so long as the payment
was made under compulsion or for the protection of some interest of the one making
the payment and in discharge of an existing liability.” Cagle, Inc. v. Sammons, 254
N.W.2d 398, 403 (Neb. 1977) (quoting Sheridan v. Dudden Implement, Inc., 119
N.W.2d 64 (Neb. 1962)). “It is well settled, however, that subrogation is never
awarded in equity to one who is merely a volunteer in paying the debt of one person
to another.” Id.
F&D apparently expended $16 million in connection with TMI’s completion
of the subcontract work (filing 63-3 at 4-5).7 Casey contends F&D acted as a volunteer
because it was not legally obligated to remedy TMI’s default or provide funds for the
completion of the subcontract work until such time as the subcontract was terminated
by Casey. In other words, Casey denies that the demand letters it sent in December
2009 triggered the performance bond.
In making this argument, Casey relies on the Fifth Circuit’s decision in L&A
Contracting Co. v. Southern Concrete Services, Inc., 17 F.3d 106 (5th Cir. 1994), in
which a general contractor (“L&A”) sued a subcontractor and the surety (“F&D”) on
the subcontractor’s performance bond for damages arising from the subcontractor’s
breach of contract. The district court held the subcontractor and F&D were both liable
to L&A. On appeal, Fifth Circuit affirmed the judgment against the subcontractor but
reversed the judgment against F&D, finding that the subcontractor was not “declared
... to be in default,” as required by the performance bond. The evidence showed L&A
sent a letter to the subcontractor and F&D in May 1987, stating that the subcontractor
had breached the subcontract; the subcontractor was given five days to cure the
deficiencies in its performance. The subcontractor’s performance improved for
7
An additional $2 million apparently was paid out for claims made under the
payment bond (filing 63-3 at 4-5).
-24-
several months thereafter. In January 1988, however, L&A sent another letter to the
subcontractor and F&D in which it requested “that the Bonding Company take the
necessary steps to fulfill this contract to prevent any further delays and costs to L&A.”
F&D did not respond to the letter and took no action. The subcontractor subsequently
completed its work on the project, and at no time did L&A refuse to accept the
subcontractor’s performance.
L&A, relying on dictionary definitions of “declare” and “default,” contended
the performance bond only required it to make clear that the subcontractor had failed
to fulfill a contract or duty. The Court of Appeals rejected this contention, stating:
Three factors counsel rejection of L&A’s popular dictionary
authority. First, L&A’s proffered definition misapprehends the legal
nature of the “default” that is required before the obligee’s claim against
the surety matures. Although the terms “breach” and “default” are
sometimes used interchangeably, their meanings are distinct in
construction suretyship law. Not every breach of a construction contract
constitutes a default sufficient to require the surety to step in and remedy
it. To constitute a legal default, there must be a (1) material breach or
series of material breaches (2) of such magnitude that the obligee is
justified in terminating the contract. Usually the principal is unable to
complete the project, leaving termination of the contract the obligee’s
only option. The definition of “default” implicit in L&A’s dictionary
analogy impermissibly blurs the distinct concepts of “breach” and
“default”.
Second, L&A’s definition is impractical. A definition of a contract
term that leads to impractical or commercially absurd results is
unreasonable. Serious legal consequences attend a “declaration of
default”, particularly in cases such as this case involving multi-milliondollar construction projects. Before a declaration of default, sureties face
possible tort liability for meddling in the affairs of their principals. After
a declaration of default, the relationship changes dramatically, and the
surety owes immediate duties to the obligee. Given the consequences
that follow a declaration of default, it is vital that the declaration be made
in terms sufficiently clear, direct, and unequivocal to inform the surety
-25-
that the principal has defaulted on its obligations and the surety must
immediately commence performing under the terms of its bond. Sureties
deprived of a clear rule for notices of default would be reluctant to enter
into otherwise profitable contracts. Nothing in the record suggests that
the parties intended such an impractical result.
Finally, L&A’s definition does not promote the purpose for which
the parties probably included a notice of default provision in F&D’s
bond. That purpose was to avoid the common-law rule that a secondary
obligor such as F&D is not entitled to notice when the time for its
performance is due. That purpose is not served if L&A can fulfill its duty
to provide “notice of default” to F&D by sending letters containing no
mention of a default.
Id. at 110-11 (footnotes omitted). The Court concluded:
A declaration of default sufficient to invoke the surety’s obligations
under the bond must be made in clear, direct, and unequivocal language.
The declaration must inform the surety that the principal has committed
a material breach or series of material breaches of the subcontract, that
the obligee regards the subcontract as terminated, and that the surety
must immediately commence performing under the terms of its bond.
Id. at 111 (emphasis supplied).
Similarly, in Elm Haven Construction Ltd. v. Neri Construction LLC, 376 F.3d
96 (2d Cir. 2004), the Second Circuit concluded that the surety was not liable on a
performance bond because the general contractor (“Elm Haven”) failed to declare the
subcontractor (“Neri”) in default and allow the surety to cure the default before hiring
a replacement subcontractor. As in the present case, the performance bond provided
that “[w]henever Principal shall be, and be declared by Obligee to be in default under
the subcontract, the Obligee having performed Obligee’s obligations thereunder, ...
(1) Surety may promptly remedy the default ... or (2) Obligee after reasonable notice
to Surety may, or Surety upon demand of Obligee, may arrange for the performance
of Principal’s obligation under the subcontract ....” Id. at 98. Also as in the present
case, “[t]he subcontract agreement outlined procedures to be followed in the event of
-26-
a default by Neri. Elm Haven was required to give Neri 72 hours written notice to cure
a default, and if Neri did not cure, Elm Haven could perform the work itself, withhold
payment from Neri, and/or terminate its subcontract agreement with Neri and hire
another subcontractor.” Id. In other words, “a partial default under the subcontract
agreement did not require a termination of that agreement.” Id.
About two months after work began on the project, Neri and Elm
Haven began complaining about each other’s performance. Elm Haven
sent several letters to Neri, copied to USF&G, detailing its complaints
about Neri’s performance and failure to respond to inquiries from Elm
Haven. It also sent letters to USF&G requesting its “assistance in this
matter.” Beginning in April, several letters informed USF&G and Neri
that certain portions of the work for which Neri was responsible would
be performed by others because Neri had either failed to perform, or
claimed that it was not contractually required to perform, that work.... On
May 17, 2001, Elm Haven contracted with another subcontractor ... to
replace Neri. Moreover, two of Neri’s sub-subcontractors or suppliers
made payment claims against Elm Haven, and one of them filed a
mechanic’s lien against Elm Haven. Elm Haven paid the lienholder
claimant directly, without seeking approval from Neri or USF&G.
Finally, on June 26, 2001, Elm Haven wrote directly to USF&G,
noting that it had been “forced to supplement NERI forces in completing
the balance of contract work,” that Neri had “virtually abandoned” the
project as of April 30, and that Elm Haven had incurred an estimated loss
of $942,102. USF&G responded by stating that it was not liable to Elm
Haven under the Performance Bond.
Id. at 99.
The Second Circuit affirmed the district court’s decision to grant summary
judgment to the surety. It stated:
In order to trigger USF&G’s liability under the Performance
Bond, two conditions had to be met. First, Neri had to be “in default”
under the subcontract agreement, and second, Elm Haven had to
“declare[ ] [Neri] to be in default under the” subcontract agreement.
-27-
Such a declaration of default had to be made to USF&G in precise terms.
See [United States Fid. & Guar. Co. v. Braspetro Oil Servs. Co., 369
F.3d 34, 57 (2d Cir. 2004)] (a “condition precedent to the Sureties’
obligations under the Bonds was a clear notice of default terminating the
[principal’s] rights under the Contracts.”)8; L&A Contracting Co., 17
F.3d at 111 (“A declaration of default sufficient to invoke the surety’s
obligations under the bond must be made in clear, direct, and
unequivocal language. The declaration must inform the surety that the
principal has committed a material breach or series of material breaches
of the subcontract, that the obligee regards the subcontract as terminated,
and that the surety must immediately commence performing under the
terms of its bond.”). In Braspetro, this court quoted L&A Contracting
for the proposition that “‘evidence [is] insufficient as a matter of law to
establish a declaration of default’ where ‘[n]one of the letters [obligeegeneral contractor] sent to [principal-subcontractor] and [surety] even
8
The bond in Braspetro was in the form of an American Institute of Architects
(“AIA”) Document A312 Performance Bond. Before the sureties’ obligations under
the bond could arise, the project owner (“Brasoil”) had to satisfy three conditions
precedent. “Specifically, Brasoil was required to: (i) notify the Consortium [of
contractors] and the Sureties that Brasoil was considering declaring a default and
attempt to arrange a conference ... to resolve the situation; (ii) “declare[ ] a Contractor
Default and formally terminate[ ] the [Consortium’s] right to complete the
[C]ontract”; and (iii) agree “to pay the Balance of the Contract Price ... in accordance
with the terms of the ... Contract.” Braspetro. 369 F.3d 34 at 41; see also Developers
Sur. and Indem. Co. v. Dismal River Club, LLC, No. 4:07CV03148-RGK-DLP, 2008
WL 2223872, *7-8 (D.Neb. 2008) (predicting Nebraska Supreme Court would
consider notice provisions of AIA A312 performance bond to be conditions precedent
to surety’s obligations under the bond). The bond in Elm Haven (and the present case)
was in the form of an American Institute of Architects Document A311 Performance
Bond, which does not contain an express requirement that the obligee formally
terminate the principal’s right to complete the contract. Indeed, one of the options
available to the surety under the AIA A311 performance bond is to “remedy the
default,” which “would appear to allow the surety to finance the principal in order to
remedy the default.” William Schwartzkopf, Prac. Guide Construction Cont. Surety
Claims § 11.02 (2014). The AIA A312 performance bond also allows a contractor to
perform and complete the construction contract with financing from the surety
following the declaration of default, but only with the consent of the owner. See id.
-28-
contained the word “default” and where ‘other items of correspondence’
did not contain an ‘unequivocal declaration of default.’” Braspetro, 369
F.3d at 57 (quoting L&A Contracting, 17 F.3d at 111).
The notice of default requirement of the Performance Bond was
not met in this case prior to the June 26, 2001 letter. None of Elm
Haven’s previous letters “even contained the word ‘default’” or an
“unequivocal declaration of default.” Id. At best, the earlier letters
notified Neri and USF&G that Elm Haven was exercising its rights under
the default provisions of the subcontract agreement. However, the letters
clearly evidenced Elm Haven’s desire to continue its arrangements with
Neri and to keep the subcontract agreement in force. If Elm Haven
wanted to trigger the Performance Bond at that point, it would have had
to terminate its relationship with Neri and give USF&G an opportunity
to complete the project itself or hire others to do so. None of Elm
Haven’s pre-June 26 letters demonstrates an intent to end its relationship
with Neri and allow USF&G to take over the project; to the contrary,
these letters provided notice that part of Neri’s work would be performed
by others, indicating only that Neri would continue to perform some
work under the agreement and requesting USF&G’s help in improving
the ongoing relationship with Neri.
USF&G concedes that the June 26 letter functioned as a
declaration of default. By that date, however, Elm Haven had breached
its obligation to USF&G under the Performance Bond to give USF&G
the option to cure Neri’s default. As noted, Elm Haven hired a
replacement subcontractor five weeks before declaring default in the
June 26 letter, and incurred further payment obligations in hiring
replacement subcontractors before actually defaulting Neri. Thus, Elm
Haven failed to meet the requirements of the Performance Bond,
excusing USF&G from its performance.
Id. at 100-01.
The facts of the present case are materially different in two important respects.
First, the surety is not contesting its liability under the performance bond; to the
contrary, the general contractor is contending the surety acted as a “volunteer” in
-29-
performing its obligations under the bond. Second, Casey’s demand letters repeatedly
used the term “default.”9
The subcontract was expressly incorporated by reference into the performance
bond. The terms of the performance bond were also specified by Section 16.4 of the
subcontract and attached Exhibit 16.4. It is reasonable to assume, therefore, that the
term “default” has the same meaning in the performance bond as in the subcontract.
“Instruments made in reference to and as part of the same transaction are to be
considered and construed together.” McCord & Burns Law Firm, LLP v. Piuze, 752
N.W.2d 580, 586 (Neb. 2008).
Section 24 of the subcontract defines “default” as TMI’s “fail[ure] or refus[al]
to perform any material obligation under this Subcontract on its part to be performed”
(filing 63-5 at 15). A “default” will provide grounds for termination, but only if it is
not remedied within an allotted period of time after notice has been given by the
general contractor. See Sections 24.5 and 24.7 (id. at 16).
“A surety on a performance bond is bound in the manner and to the extent
provided in the obligation.” State ex rel. Wagner v. Gilbane Bldg. Co., 757 N.W.2d
194, 200 (Neb. 2008). “There is no language in the performance bond ... which
requires termination of the subcontract as a condition precedent to [F&D’s] surety
9
Casey notified F&D on December 10, 2009, that it had “officially placed
Topp’s Mechanical in default of their Subcontract” and requested F&D to “respond
to any demands by Casey Industrial to fulfill the terms and conditions of this
subcontract and address the inability of Topp’s Mechanical to meet their payment and
performance obligations” (filing 63-13 at 2). In the written notice of default, Casey
stated it was requesting F&D’s “immediate participation to satisfy all of Topp’s
contractual requirements” (filing 63-12 at 2). Six days later, Casey reiterated that had
“already placed Topp’s in default of their Subcontract” and “demand[ed] the Surety
to step in and respond immediately” (filing 71-8 at 34).
-30-
obligations arising in the event of a default by [TMI].” DCC Constructors, Inc. v.
Randall Mechanical, Inc., 791 So.2d 575, 576 (Fla.App. 2001) (interpreting bond
language identical to that at issue this case; distinguishing L&A Contracting); see also
Nova Cas. Co. v. Turner Const. Co., 335 S.W.3d 698, 704 n. 3 (Tex.App. 2011)
(refusing to imply termination requirement in performance bond and distinguishing
L&A Contracting because obligee specifically notified surety of principal’s default).
Casey argues that F&D acted as a volunteer because “what F&D sought to
avoid by keeping Topps in business was a termination of Topps by Casey that would
have resulted in substantially more bond losses” (filing 63 at 29). This argument fails
to recognize, however, that the doctrine of equitable subrogation is not limited to
situations where a payment is legally required. “The doctrine [also] applies where a
party is compelled to pay the debt of a third person to protect his own rights or
interest, or to save his own property.” Rawson v. City of Omaha, 322 N.W.2d 381, 384
(Neb. 1982) (holding that motorist whose vehicle struck pothole and collided with two
other vehicles was entitled to reimbursement from city for amounts paid in settlement
of personal injury and property damage claims brought by others).
“While it is true that subrogation is never awarded in equity to one who is
merely a volunteer in paying the debt of another, one who pays the debt of another in
order to protect his own property or interest is not considered a volunteer for purposes
of equitable subrogation.” Id. at 384-85. “The doctrine of subrogation is not
administered by courts of equity as a legal right, but the principle is applied to
subserve the ends of justice and to do equity in the particular case under consideration.
It does not rest on contract and no general rule can be laid down which will afford a
test for its application in all cases. The facts and circumstances of each case determine
whether the doctrine is applicable.” Id. at 384.10
10
Not all of the facts and circumstances of this case are before the court on
Casey’s pending motion. For example, it appears that following the December 2009
demand letters there were two in-person meetings in Chicago that were attended by
-31-
Casey next asserts that F&D’s obligation to perform under the bond was
expressly conditioned upon Casey’s “having performed [its] obligations [under the
subcontract]” (filing 63-11 at 2).11 Casey argues, without citing any cogent authority,12
that F&D cannot claim Casey breached the subcontract and at the same time claim a
right to equitable subrogation. The “volunteer” rule certainly does not require this
result. Indeed, it has been held that “[t]he payment of a claim presented by its obligee
is sufficient to entitle a surety to subrogation if it is made in good faith and because
of the surety’s supposed liability on its undertaking.” American Mfrs. Mut. Ins. Co.
v. Payton Lane Nursing Home, Inc., No. CV–05–5155 (SJF), 2007 WL 674691, *8
(E.D.N.Y. 2007) (emphasis supplied).
As a final matter, Casey argues that if F&D cannot claim a right to equitable
subrogation, but instead must rely on the assignments that were executed by TMI, then
F&D cannot recover any costs it incurred in completing the project because TMI was
released from its obligation to indemnify F&D and therefore has suffered no damages.
This argument is not adequately developed on either the law or the facts, although
Casey suggests the Court of Claims’ decision in Severin v. United States, 99 Ct.Cl.
435 (1943), should be applied by analogy to limit F&D’s recovery. “The [Severin]
representatives of Casey, TMI, and F&D (filing 63-3 at 8-9, 14-15). What transpired
at those meetings is not evidence. Deposition testimony indicates, however, that F&D
promptly hired a consultant to investigate the claimed default and, in February or
March 2010, directed the consultant to take over the day-to-day management of the
subcontract work (filing 63-3 at 6-7). The consultant’s personnel evidently were on
site every day thereafter (id.).
11
The bond requires performance by the surety “[w]henever Principal shall be,
and be declared by Obligee to be in default under the subcontract, the Obligee having
performed Obligee’s obligations thereunder” (filing 63-11 at 2) (emphasis supplied).
Casey’s performance of its obligations under the subcontract may be a condition
precedent to F&D’s obligation to perform under the bond, but even a condition
precedent can be waived. See Pearce v. ELIC Corp., 329 N.W.2d 74, 79 (Neb. 1982).
12
On the other hand, F&D provides no opposing authority.
-32-
doctrine holds that a prime contractor may sue the federal government for damages
incurred by its subcontractor through the fault of the government, only when the prime
contractor has suffered actual damages itself, either because it has reimbursed the
subcontractor or remains liable to the subcontractor for those damages.” Contracting
Northwest, Inc. v. City of Fredericksburg, 713 F.2d 382, 385 n. 2 (8th Cir. 1983). The
Severin doctrine “is based on the federal government’s limited waiver of its sovereign
immunity for breach of contract and on a federal statute prohibiting assignments of
contract claims against the federal government,” id., and has no obvious application
in the present case.
In conclusion, and for the reasons stated,
IT IS ORDERED that Defendant Casey’s motion for partial summary judgment
(filing 63) is granted in part and denied in part, as follows:
1.
Count III of Plaintiff’s complaint, together with those portions of any
other counts which involve an alleged scope growth in cold small bore
piping, are dismissed with prejudice.
2.
In all other respects, the motion is denied.
March 19, 2014.
BY THE COURT:
Richard G. Kopf
Senior United States District Judge
* This opinion may contain hyperlinks to other documents or Web sites. The U.S. District
Court for the District of Nebraska does not endorse, recommend, approve, or guarantee any third
parties or the services or products they provide on their Web sites. Likewise, the court has no
agreements with any of these third parties or their Web sites. The court accepts no responsibility
for the availability or functionality of any hyperlink. Thus, the fact that a hyperlink ceases to work
or directs the user to some other site does not affect the opinion of the court.
-33-