E3 Biofuels, LLC v. Biothane Corporation et al
Filing
41
ORDER - IT IS ORDERED: Non-Party Objectors Motion to Quash (filing 17 ) is granted, in part, and denied in part, as set forth above. PEI's Motion to Compel (filing 19 ) is granted, in part, and denied, in part. AltEn and Spectrum shall produce the documents detailed above within thirty days of this order. Ordered by Magistrate Judge F.A. Gossett. (TCL )
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NEBRASKA
E3 BIOFUELS, LLC,
Plaintiff,
V.
BIOTHANE CORPORATION, and
PERENNIAL ENERGY, INC.,
Defendants.
)
)
)
)
)
)
)
)
)
)
)
8:12CV441
ORDER
Spectrum Business Ventures, Inc. (“Spectrum”), AltEn, LLC (“AltEn”), AltEnergy
Holding, LLC (“AltEnergy”), and AltEn Opportunity I, LP (“AltEn Op”) (collectively
referred to herein as “Non-Party Objectors”) seek an order quashing each of the separate
subpoenas served upon them by Perennial Energy, Inc. (“PEI”). (Filing 17.) PEI has filed
a motion to compel (filing 19) Non-Party Objectors to respond to the subpoenas.
BACKGROUND
On February 8, 2011, E3 Biofuels, LLC (“E3") filed suit in this Court against PEI and
others, seeking to recover damages E3 allegedly sustained as a result of the construction of
an Ethanol Plant in Mead, Nebraska. See E3 Biofuels, LLC v. Biothane, LLC, Case No.
8:11CV44 (D. Neb. 2011). Generally, in that action, E3 alleges that the start-up of the
Ethanol Plant was not substantially completed, and the Ethanol Plant never operated as
intended, due to PEI’s failure to fabricate and install a fully functional Boiler System. E3
also maintains that as a result of PEI’s failure to provide a Boiler System, it was forced to
seek bankruptcy protection. In its Answer, PEI affirmatively alleges that E3's damages were
caused by E3's own negligence and/or acts or omissions of third parties.
On February 23, 2012, in the E3 Biofuels, LLC v. Biothane case (the “underlying
litigation”), PEI filed a motion to compel E3 to provide more complete discovery responses.
(Filing 123.) The undersigned issued an order on June 29, 2012 (the “Order”), granting
PEI’s motion, in part. (Filing 141.) The Order compelled E3 to produce some documents
post-dating the bankruptcy, finding that “discovery related to the construction problems
allegedly occurring at the Ethanol Plant is relevant to the issues involved in this case” and
“discovery requests seeking to determine to what extent, if any, other problems caused the
alleged failures or completion delays are clearly relevant to the claims and defenses in this
case.” (Id.) Following the issuance of the Order, PEI filed this miscellaneous action1 to
enforce the subpoenas served upon Non-Party Objectors.2 PEI’s subpoenas generally seek
documents relating to the construction and re-commissioning of the Ethanol Plant.
DISCUSSION
Non-Party Objectors argue that the subpoenas, which seek documents relating to the
Ethanol Plant, should be quashed because they place an undue burden on non-parties and
request irrelevant materials. Under Fed. R. Civ. P. 45, a district court may quash or modify
a subpoena if the subpoena fails to allow reasonable time for compliance, requires a nonparty to travel more than 100 miles, requires disclosure of privileged or protected matter or
subjects a person to undue burden. Fed. R. Civ. P. 45. In evaluating whether a subpoena
presents an undue burden, courts generally consider (1) the relevance of the requested
information; (2) the need of the party for the information; (3) the breadth of the request; (4)
the time period covered by the request; (5) the particularity with which the party describes
the requested information; and (6) the burden imposed. Wiwa v. Royal Dutch Petroleum Co.,
392 F.3d 812, 818 (5th Cir. 2004). “Further, if the person to whom the document request is
1
The miscellaneous action was filed in the United States District Court for the
Western District of Missouri. The suit was transferred to this Court on December 19, 2012.
(Filing 28.)
2
Non-Party Objector AltEn purchased the Ethanol Plant in November, 2010. AltEn
is a small company with a total of six full time employees, including the plant manager, an
assistant plant manager, three maintenance employees and an ethanol board operator. E3,
and its sole shareholder, Dennis Langley (“Langley”), own 30% of the stock of AltEn.
AltEnergy and AltEn Op are passive investors in AltEn. AltEnergy, AltEn Op and AltEn
were not in existence when the incident that forms the basis for the underlying lawsuit
occurred. Spectrum, which provides accounting and data management services for AltEn,
has an investment interest in AltEnergy and AltEn Op.
2
made is a non-party, the court may also consider the expense and inconvenience to the nonparty.” Id. at 818 (footnote omitted).
PEI requests that Non-Party Objectors produce documents related to the Ethanol Plant
for three distinct time periods: (1) pre-bankruptcy; (2) post-bankruptcy, but before AltEn
purchased the Plant, and (3) after the sale of the Plant.
With respect to pre-purchase materials, Non-Party Objectors represent that
substantially all, in not all, the documents AltEn has in its possession were provided to E3,
which, in turn, produced the documents to PEI.3 AltEn admits, however, that it may have
retained some pre-purchase licenses and permits related to the Plant. Non-Party Objectors
also maintain that AltEnergy and AltEn Op are passive investors and, other than accounting
records and invoice payment records that may be held by Spectrum, any records they may
have would be duplicative of any records held by AltEn.
AltEn further represents to the Court that it took no actions with respect to the
operation, repair, construction, moth-balling or re-commissioning of the Ethanol Plant prior
to its purchase of the Plant on November 22, 2010. AltEn claims that substantially all of its
records for this time period are documents relating to the purchase of the Plant. These
documents consist of pleadings and sale documents filed in the bankruptcy proceeding.
AltEn argues that it should not have to produce these documents because they are readily
available through the Court’s electronic filing system.
Accepting Non-Party Objectors’ representations as true, the Court will grant the
motion to quash in its entirety as it relates to AltEnergy and AltEn Op. It does not appear
that these entities have any relevant documents that cannot be obtained from other sources.
The Court will also grant the motion to quash as it pertains to any pre-purchase materials
held by Spectrum. The Court will deny the motion to quash, however, as it relates to the pre-
3
Non-Party Objectors have represented to the Court that E3's counsel has agreed to
review the pre-bankruptcy materials it received from AltEn to ensure that all responsive
materials have, in fact, been produced. The Court will not require AltEn to obtain and review
documents previously given to E3 in order to respond to the subpoenas.
3
purchase permits and licences that could be in AltEn’s possession. The Court will also deny
the motion to quash as it pertains to the pleadings and sale documents filed in the bankruptcy
proceeding because if the documents are truly readily available, it should not be overly
burdensome for AltEn to produce them.4 The motion to quash is otherwise granted as to prepurchase materials sought from AltEn.
As to documents from the post-sale period, AltEn claims that it has extensive records,
documents and things relating to the on-going construction of the Plant. Spectrum maintains
that it has accounting and data files relating to the post-acquisition construction. AltEn and
Spectrum assert that these records involve dozens of post-acquisition engineering contracts,
purchase orders, project assessment records, correspondence, accounting records and other
miscellaneous materials and would encompass thousands of documents.
As this Court previously held in the underlying litigation, based on the allegations
contained in the Complaint, as well as PEI’s asserted defenses, discovery requests seeking
to determine to what extent, if any, other problems caused the alleged failures or completion
delays at the Plant are relevant. Still, even this being true, the relevance of these documents
deteriorates as more time passes from the primary event triggering this lawsuit, namely, the
boiler explosion which occurred on February 9, 2007. Although the Court previously
ordered E3 to produce some documents in its possession post-dating the bankruptcy, the
Order did not necessarily encompass documents post-dating E3's sale of the Plant on
November 22, 2010. It is one thing to order a party to produce documents for an
approximate four-year time period following a precipitating event, and quite another to ask
a non-party to produce a substantial number of documents generated up to six years after the
same event.
In an effort to resolve this dispute, AltEn offered to produce post-purchase documents
that relate to moving the Plant’s boiler, replacing the damaged boiler, Plant improvements
4
AltEn claims that if other documents relating to the purchase exist, they would
consist of drafts of pleadings, emails and other communications stored in AltEn’s computers.
Based on AltEn’s representations, the Court sees no need for AltEn to review emails and
other communications stored on its computers related to the purchase of the Plant.
4
made and work done since AltEn purchased the Plant. AltEn and Spectrum also agreed to
provide checks and invoices on purchases and expenditures made at the Plant since AltEn
purchased the Plant. At this point, the Court believes this scope of production is appropriate.
If, at a later time, and following consultation with opposing counsel, PEI can point to specific
categories of post-purchase documents it requires based on the information it receives in
response to the subpoenas, it may renew its motion to compel.
The parties’ requests for costs and sanctions is denied.
Accordingly,
IT IS ORDERED:
1.
Non-Party Objectors Motion to Quash (filing 17) is granted, in part, and
denied in part, as set forth above.
2.
PEI’s Motion to Compel (filing 19) is granted, in part, and denied, in part.
AltEn and Spectrum shall produce the documents detailed above within thirty
days of this order.
DATED March 27, 2013.
BY THE COURT:
S/ F.A. Gossett
United States Magistrate Judge