First Dakota National Bank v. Eco Energy, LLC

Filing 44

ORDER - After conferring with counsel today regarding setting the case for trial, IT IS ORDERED the defendant's anticipated motion to conduct discovery out of time shall be filed on or before February 6, 2015. After the court resolves that issue, an additional conference call will be set to determine the progression schedule for final resolution of this lawsuit. Ordered by Magistrate Judge Cheryl R. Zwart. (JAB)

Download PDF
IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA FIRST DAKOTA NATIONAL BANK, Plaintiff, 8:13CV270 vs. ORDER ECO ENERGY, LLC, a Tennessee limited liability company; Defendant. The parties’ cross-motions for summary judgment did not fully resolve this case. The court conferred with counsel today regarding setting the case for trial. The plaintiff argues the case is ready for trial—the discovery deadline has passed, and no additional discovery should be permitted. The defendant argues that in light of Judge Gerrard’s ruling, additional discovery is required before this case can be tried. As set by this court’s progression order, the discovery deadline was July 1, 2014. (Filing No. 17). As such, Defendant’s opposed request to conduct further discovery must meet the standard set forth in Sherman v. Winco Fireworks, Inc., 532 F.3d 709 (8th Cir. 2008). Accordingly, IT IS ORDERED the defendant’s anticipated motion to conduct discovery out of time shall be filed on or before February 6, 2015. After the court resolves that issue, an additional conference call will be set to determine the progression schedule for final resolution of this lawsuit. January 27, 2015. BY THE COURT: s/ Cheryl R. Zwart United States Magistrate Judge

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?