MEMORANDUM AND ORDER - OMNI's motion for summary judgment, Filing No. 211 , is granted. DSN's motion for summary judgment, Filing No. 218 , is granted. Autism Center's motion for summary judgment, Filing No. 229 , is granted. A Judgment in favor of the defendants and against the plaintiff shall be issued in conjunction with this Memorandum and Order. Ordered by Senior Judge Joseph F. Bataillon. (Copy mailed to pro se party)(LKO)
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 1 of 12 - Page ID # 1418
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NEBRASKA
IRIS KITCHEN,
Plaintiff,
8:20CV8
vs.
DEVELOPMENTAL SERVICES OF
NEBRASKA, INC., AUTISM CENTER OF
NEBRASKA, INC., and OMNI
BEHAVIORAL HEALTH,
MEMORANDUM AND ORDER
Defendants.
This matter is before the Court on defendants’ Omni Behavior’s motion for
summary judgment, Filing No. 211, Developmental Services motion for summary
judgment, Filing No. 218, and Autism Center’s motion for summary judgment, Filing No.
229.
Plaintiff Iris Kitchen (hereinafter “Plaintiff”) brought this lawsuit alleging
discrimination in employment in violation of the Civil Rights Act of 1964, discrimination in
contractual benefits in violation of 42 U.S.C. § 1981, retaliation for engaging in protected
conduct in violation of 42 U.S.C. § 2000e 3(a), and breach of contract, unjust enrichment,
and emotional distress under Nebraska state law. Filing No. 1 at 3–6.
BACKGROUND
Plaintiff was contracted with Developmental Services of Nebraska (hereinafter
“Developmental Services” or “DSN”) and Autism Center of Nebraska (hereinafter “Autism
Center” or “ACON”) to provide foster care to minor children. Filing No. 1 at 2. Plaintiff
worked for DSN on or about December 1, 2017, through June 30, 2018. Filing No. 8 at
4 and Filing No. 41-1 at 4–5. Prior to serving as an independent contractor for DSN,
1
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 2 of 12 - Page ID # 1419
Plaintiff was an independent contractor for ACON. Filing No. 27-1 at 2.1 OMNI was all
times relevant hereto a Nebraska non-profit organization which provided developmental
disabilities services and habilitative services for individuals in the State or Nebraska.
Affidavit of Morgan P. Kelly at ¶ 5–8; OMNIKitchen Independent Contractor’s Agreement
for M.W. (Doc #8 at 2/182); OMNIKitchen Independent Contractor’s Agreement for J.W.
(Doc #8 at 8/182). At all times relevant hereto, Nebraska Department of Health & Human
Services (“NDHHS”) contracted with OMNI to provide habilitation to individuals with
developmental disabilities. Id. Under Plaintiff’s contracts, it provides that: “Each party is
an independent contractor and as such will not have the authority to bind or commit the
other,” additional language states that the agreement is not to be construed as creating
“a joint venture, partnership, fiduciary, or agency relationship between the parties for any
purpose.” Id. at 4, 10.
ACON was, at all times relevant hereto, a Nebraska Non-Profit Corporation that
provided habilitation, vocational rehabilitation, residential, community inclusion and other
services to individuals with autism or other developmental disabilities. Filing No. 1 at 1
and Filing No. 27-1 at 1. DSN was at all times relevant hereto a Nebraska Non-Profit
Corporation that provided habilitation services in a residential context to developmentally
disabled individuals. Filing No. 1 at 1 and Filing No. 41-1 at 1.
Pursuant to the terms of the contract between DSN and Plaintiff, Plaintiff was to
provide habilitation services to two individuals for whom DSN had recently been tasked
with providing habilitation services. Filing No. 8 at 4, Filing No. 27-1 at 2, and Filing No.
41-1 at 2. Plaintiff alleges she was to be paid a certain percentage of a mandated rate
1
This Court previously set out this Background in its Memorandum and Order, Filing No. 45.
2
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 3 of 12 - Page ID # 1420
per the contracts. Filing No. 1 at 2. According to Plaintiff, she was supposed to receive
80% of funds from the state for each of the clients and DSN was supposed to receive
20%. Filing No. 8 at 4. Defendants allegedly paid Plaintiff only 20% of the wages
disbursed by the government for the care she gave to foster care minor children and
allegedly kept 80% of the proceeds. Filing No. 1 at 2.
Moreover, Plaintiff is African American and contends that white contractors doing
the same work received more than she did in violation of Title VII. Filing No. 1 at 3 and
Filing No. 8 at 4. Prior to working for DSN, Plaintiff argues she was being paid more for
the care of two clients in her home, and after starting with DSN in December 2017, she
was paid less for the same clients. Filing No. 8 at 4. Plaintiff contends she filed with the
Equal Employment Opportunity Commission (“EEOC”) and asserts that she received a
right to sue letter. Filing No. 1 at 3; see also Filing No. 8.
Plaintiff further alleges that she lost her contractual rights to compensation as a
result of the behavior of the Defendants in violation of 42 U.S.C. § 1981. Filing No. 1 at
4. Plaintiff also claims the Defendants violated Title VII by terminating her in retaliation
for protected activity, that is, reporting the conduct of the Defendants to the Legislature.
Id. Plaintiff also alleges a claim for breach of contract for failure to pay her the government
wage for her services. Id. at 5. Plaintiff further alleges an unjust enrichment claim
because Defendants unjustly enriched themselves by depriving Plaintiff of her due
compensation for services rendered. Id. As a result of Defendants’ behaviors, Plaintiff
alleges she has suffered emotional distress. Id.
According to Defendants, when one of the two individuals for whom DSN had been
tasked with providing habilitation services was placed under the service and support of
3
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 4 of 12 - Page ID # 1421
DSN, an error was made by the Nebraska Department of Health and Human Services as
to the proper rate of service authorization for care providers. Filing No. 27-1 at 2 and
Filing No. 41-1 at 2. An incorrect rate of $214.06 per service unit was utilized by the
Nebraska Department of Health and Human Services for the one individual in question
when the proper rate per service unit should have been $13.35 for such individual. This
error in service authorization rate as assigned by the Nebraska Department of Health and
Human Services resulted in an overpayment by DSN to Plaintiff under Plaintiff’s contract
with DSN in the amount of $5,632.51. Filing No. 27-1 at 2 and Filing No. 41-1 at 2.
Pursuant to the terms of Plaintiff’s contract with DSN, DSN sought reimbursement
of the overpayment and entered into agreement with Plaintiff for such reimbursement.
Filing No. 27-1 at 2 and Filing No. 41-1 at 2. In June of 2018, DSN began attempts to
contact Plaintiff to have her execute a new contract to provide services as an independent
contractor for DSN. Filing No. 27-1 at 2 and Filing No. 41-1 at 2. On or about June 27,
2018, Plaintiff allegedly informed Defendant that she would not be executing a new
contract with DSN until certain conditions had been met. Filing No. 27-1 at 2 and Filing
No. 41-1 at 2. According to Plaintiff, after receiving messages from DSN employees
informing her that the two clients were being removed from Plaintiff’s home because she
refused to sign the new contract that was given to her on May 19, 2018, Plaintiff told DSN
she would sign the contract. Filing No. 8 at 4. However, Plaintiff contends she was
informed that the decision had already been made by APS Caseworker, Angela Mitchell,
who did not want Plaintiff providing services anymore. Id. The two clients were ultimately
removed from Plaintiff’s home, and on or about June 30, 2018, Plaintiff’s contract with
4
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 5 of 12 - Page ID # 1422
DSN expired and no new contract was executed or has been executed since. Filing No.
8 at 4, Filing No. 27-1 at 3, and Filing No. 41-1 at 2.
STANDARD OF REVIEW
Summary judgment should be granted “if the movant shows that there is no
genuine dispute as to any material fact and the movant is entitled to judgment as a matter
of law.” Fed. R. Civ. P. 56. “Summary judgment is appropriate when, construing the
evidence most favorably to the nonmoving party, there is no genuine issue of material
fact and the moving party is entitled to judgment as a matter of law.” Crozier v. Wint, 736
F.3d 1134, 1136 (8th Cir. 2013). “Summary judgment is not disfavored and is designed
for ‘every action.’” Torgerson v. City of Rochester, 643 F.3d 1031, 1043 (8th Cir. 2011)
(en banc) (quoting Celotex Corp. v. Catrett, 477 U.S. 317, 327 (1986)). In reviewing a
motion for summary judgment, the court will view “all evidence and mak[e] all reasonable
inferences in the light most favorable to the nonmoving party.”
Aluminum, LLC, 728 F.3d 816, 819 (8th Cir. 2013).
Inechien v. Nichols
Credibility determinations, the
weighing of evidence, and the drawing of legitimate inferences from the facts are jury
functions, not those of a judge.
Torgerson, 643 F.3d at 1042 (quoting Reeves v.
Sanderson Plumbing Prod., Inc., 530 U.S. 133, 150 (2000). But the nonmovant must do
more than simply show that there is some metaphysical doubt as to the material facts.
Torgerson, 643 F.3d at 1042; and see Briscoe v. Cnty. of St. Louis, Missouri, 690 F.3d
1004, 1011 (8th Cir. 2012) (stating that the nonmoving party “must come forward with
‘specific facts showing that there is a genuine issue for trial.’”).
Where the nonmoving party will bear the burden of proof at trial on a dispositive
issue, the moving party need not negate the nonmoving party’s claims by showing “the
5
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 6 of 12 - Page ID # 1423
absence of a genuine issue of material fact.” 477 U.S. at 325 (quoting Adickes v. S. H.
Kress & Co., 398 U.S. 144, 159 (1970)). Instead, “the burden on the moving party may
be discharged by ‘showing’ . . . that there is an absence of evidence to support the
nonmoving party’s case.” Celotex Corp., 477 U.S. at 325. In response to the movant’s
showing, the nonmoving party’s burden is to produce specific facts demonstrating “‘a
genuine issue of material fact’ such that [its] claim should proceed to trial.” Nitro Distrib.,
Inc. v. Alticor, Inc., 565 F.3d 417, 422 (8th Cir. 2009) (quoting Matsushita Elec. Indus. Co.
v. Zenith Radio Corp., 475 U.S. 574, 586 (1986)). “The mere existence of a scintilla of
evidence in support of the [nonmovant’s] position will be insufficient; there must be
evidence on which the jury could reasonably find for the [nonmovant]. Anderson v. Liberty
Lobby, Inc., 477 U.S. 242, 252 (1986)); see Quinn v. St. Louis Cnty., 653 F.3d 745, 751
(8th Cir. 2011) (stating “[T]he mere existence of some alleged factual dispute between
the parties’” will not defeat an otherwise properly supported motion for summary
judgment) (quoting Anderson, 477 U.S. at 247–48). Where the record taken as a whole
could not lead a rational trier of fact to find for the nonmoving party, there is no genuine
issue for trial. Torgerson, 643 F.3d at 1042.
DISCUSSION
All three defendants filed motions for summary judgment. Defendants contend
that plaintiff has failed to show there exists any material facts to support her claims against
the defendants. Filing Nos. 211, 218 and 229.
The Court ordered the plaintiff to respond to these motions. Filing No. 248. The
plaintiff responded to all three motions in Filing No. 243. Defendant argues that the
plaintiff has failed to set forth any evidence to support her claim that defendants are not
6
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 7 of 12 - Page ID # 1424
entitled to summary judgment. The Court finds that plaintiff has failed to respond to any
of defendant’s statement of material facts, and more importantly, she has failed to
substantiate her many allegations with evidence to support her claims.
A. OMNI
OMNI first argues that the plaintiff failed to file a charge of discrimination with the
EEOC and/or the NEOC. The Court finds that plaintiff did not exhaust her administrative
remedies against OMNI, and thus all Title VII causes of action are barred as a matter of
law. Second, OMNI argues that plaintiff was an independent contractor who is not
covered under Title VII. In this regard, independent contractors are not protected under
Title VII. Zeb v. Benes, No. 4:20-CV-3075, 2021 WL 50454, at *2 (D. Neb. Jan. 6, 2021)
(citing to Wortham v. Am. Fam. Ins. Grp., 385 F.3d 1139, 1141 (8th Cir. 2004)). See also,
Omni Behav. Health, No. A-20-482, 2021 WL 2325282 *5 (Neb. Ct.App. June 8, 2021)
(factors of independent contractor versus an agent). The Court likewise determines that
there is no showing on the part of the plaintiff that she is anything but an independent
contractor. The contract is clear in that regard.
As for the § 1981 claim, plaintiff must show a prima facie case of discrimination.
A prima facie case has four elements, which are: (1) The employee belonged to a
protected class; (2) she was qualified to perform her job; (3) she suffered an adverse
employment action; and (4) she was treated differently from similarly situated employees.
Nagaraj v. Physician Network, No. 4:20-CV-3021, 2021 WL 3032672, at *3 (D. Neb. July
19, 2021), citing to Turner v. Gonzales, 421 F.3d 688, 698 (8th Cir. 2005). Plaintiff has
failed to introduce any evidence that she was treated differently than other similarly
situated worker. In addition, there is no evidence presented that plaintiff was qualified to
7
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 8 of 12 - Page ID # 1425
perform her job. However, the Court assumes the defendants would not have entered
into a contract with the plaintiff unless she was qualified.
Plaintiff’s next claim against OMNI is one for breach of contract. To recover in a
breach of contract action, the plaintiff must plead and prove the existence of a promise,
its breach, damage, and compliance with any conditions precedent that activate the
defendant’s duty. Henriksen v. Gleason, 263 Neb. 840, 847 (2002). Unless a contract is
ambiguous, parol evidence cannot be used to vary its terms. Thrower v. Anson, 276 Neb.
102, 109 (2008). The meaning of an unambiguous contract is a question of law. Eagle
Run Square II, L.L.C. v. Lamar's Donuts Int'l, Inc., 15 Neb. App. 972, 977 (2007). The
alleged breach is that, pursuant to the contract, Defendants were to “provide Plaintiff with
80% of the wages provided to them by the government for her services.” Filing No. 1,
Complaint at ¶ 26; see also id. at ¶ 10. The Court can find no evidence in the record
wherein OMNI promises to pay Plaintiff 80% of a sum at any time.2 OMNI paid plaintiff a
daily rate for her services and room and board. There is no evidence that OMNI failed to
pay any of these payments.
Next, OMNI argues that there is no evidence of any damages at all. While plaintiff
has requested several million in damages, there is no evidence of any damages.
Defendant also argues that the unjust enrichment claim is barred as a matter of
law. Unjust enrichment is used to create an implied or quasi-contractual relationship in
the absence of an express contract between parties and has been defined as the unjust
retention of a benefit to the loss of another, or the retention of money or property of
another against the fundamental principles of justice or equity and good conscience.
2
There is a provision that talks about 80% in the contract with DSM, but there is not one with OMNI.
8
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 9 of 12 - Page ID # 1426
Kisicki v. Mid-Am. Fin. Inv. Corp., No. A-01-708, 2002 WL 31654490, at *6 (Neb. Ct. App.
Nov. 26, 2002). A party cannot be liable for both breach of contract and unjust enrichment
for the same conduct. First Express Servs. Grp., Inc. v. Easter, 286 Neb. 912, 928 (2013).
Again, this claim is based on the 80% argument discussed above. The Court determines
that there is no basis for this argument under the contract. There is zero evidence in this
regard. Likewise, there is no basis for this argument under a claim for unjust enrichment.
There is an express agreement herein, and it is binding on the parties.
Next, defendant contends that plaintiff’s emotional distress claim also fails as a
matter of law. Brandon ex rel. Est. of Brandon v. Cnty. of Richardson, 261 Neb. 636, 656
(2001) (to recover on a claim for IIED, Plaintiff must prove (1) that there has been
intentional or reckless conduct, (2) that the conduct was so outrageous in character and
so extreme in degree as to go beyond all possible bounds of decency and is to be
regarded as atrocious and utterly intolerable in a civilized community, and (3) that the
conduct caused emotional distress so severe that no reasonable person should be
expected to endure it). There is no conduct alleged that rises to the level required for a
claim for emotional distress. The Court finds that as a matter of law this claim is entitled
to summary judgment.
Defendant argues that all causes of action are barred by the applicable statute of
limitations. Plaintiff did not bring her claims until March 13, 2019, more than five years
and seven months after Plaintiff ceased working with OMNI and the contract ended. Filing
No. 1, Complaint, Case No. 8:19-cv-107. Plaintiff has made no argument for tolling.
Plaintiff would have had to bring any of these causes of action within a 4 or 5 year window,
and she failed to do so. Plaintiff contracted with OMNI in 2011 and the relationship
9
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 10 of 12 - Page ID # 1427
ceased in July of 2013. Plaintiff’s Section 1981 cause of action is subject to the federal
“catch all” statute of limitations of four years. Jones v. Carter, No. 8:19CV288, 2019 WL
3429821, at *2 (D. Neb. July 30, 2019) citing to Jones v. R.R. Donnelley & Sons Co., 541
U.S. 369 (2004). Plaintiff’s breach of contract (written) claim is subject to a five-year
statute of limitations period. Neb. Rev. Stat. § 25-205. Plaintiff’s unjust enrichment cause
of action is subject to the four-year statute of limitations period. Schmidt v. Sportsman's
Gallery, LLC, No. A-21-008, 2022 WL 29478, at *9 (Neb. Ct. App. Jan. 4, 2022). Plaintiff’s
cause of action for emotional distress, which is construed as a claim for intentional
infliction of emotional distress is subject to the four year statute of limitations under Neb.
Rev. Stat. § 25-207. Infante v. City of Hastings, No. A-19-211, 2019 WL 5884208, at *4
(Neb. Ct.App. Nov. 12, 2019), citing to Kant v. Altayar, 270 Neb. 501 (2005) (intentional
infliction of emotional distress). Accordingly, summary judgment is likewise granted for
this reason.
In summary, the Court finds insufficient evidence to support any of these claims
against OMNI. Accordingly, summary judgment will be granted as to all claims.
B. DEVELOPMENT SERVICES
Development Services makes the same claim regarding Title VII as did OMNI,
namely that TITLE VII does not protect independent contractors. For the reasons set
forth herein with regard to OMNI, the Court finds that Title VII bars the action against
Developmental Services. The same is true for the same reasons as to the claim against
Development Services for the § 1981 claim.
With regard to the breach of contract claim, plaintiff’s contract with DSN states that
the “Company agrees to reimburse the Independent Contractor at the rate of 80% of the
10
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 11 of 12 - Page ID # 1428
NDHHS payment to Company.” Filing No. 221, Ex. 1, Kanter Dec., Attachment A, p. 1.,
DSN Contract for Provision of Extended Family Home Services for J.W.; Filing No. 221,
Attachment B, p. 1., DSN Contract for Provision of Extended Family Home Services for
M.W.. The contract also says, however that “Reduction of NDHHS payment to Company
for services provided under this Contract shall result in a corresponding reduction in
payment by Company to Independent Contractor. The Independent Contractor agrees
to make prompt repayment of funds recovered or payment of fines levied by NDHHS in
relation to services and supports provided under this Contract.” Filing No. 221, Ex. 1,
Kanter Dec., Attachment A, p. 7., DSN Contract for Provision of Extended Family Home
Services for J.W.; Filing No. 221, Attachment B, p. 7., DSN Contract for Provision of
Extended Family Home Services for M.W.. NDHHS notified defendant that there was an
overpayment to the plaintiff, as she was placed in an incorrect tier of funding. Pursuant
to the contract, DSN sought to recover the funds overpaid to the plaintiff. This is the only
allegation of breach of contract made by the plaintiff against this defendant. Accordingly,
the Court finds as a matter of law that the contract clearly permitted the defendant to
collect overpayment of funds levied by NDHHS. Further, plaintiff failed to provide any
evidence that this was an incorrect assessment against the plaintiff or to in any way
support her breach of contract claim.
As for plaintiff’s unjust enrichment claim, and with regard to the emotional distress
claim, these claims failure for the same reason already set forth with regard to OMNI.
Accordingly, the Court finds that summary judgment will be granted as to all of the
claims made by the plaintiff against Developmental Services.
11
8:20-cv-00008-JFB-MDN Doc # 269 Filed: 01/18/23 Page 12 of 12 - Page ID # 1429
C. AUTISM CENTER OF NEBRASKA
Defendant Autism Center makes the same arguments with regard to Title VII, as
does OMNI, in terms of the independent contractor status. For the same reasons, Autism
contends that the plaintiff’s § 1981 claim must fail as a matter of law, namely, there is no
evidence to show that any contractors were treated differently. Likewise, Autism Center
argues that there is no basis for the breach of contract cause of action, as there is no
evidence presented by the plaintiff to support the claim. Autism Center likewise makes
the same arguments as OMNI as to the Unjust Enrichment claims by the plaintiff that they
are barred by the express agreement of the parties. And last, Autism Center of Nebraska
also argues that the emotional distress claim fails as a matter of law.
The Court finds that all claims against Autism Center fail. There is no evidence to
support any of the claims, and the Court finds they fail as a matter of law for the reasons
already stated in this Memorandum and Order.
THEREFORE, IT IS ORDERED THAT:
1. OMNI’s motion for summary judgment, Filing No. 211, is granted.
2. DSN’s motion for summary judgment, Filing No. 218, is granted.
3. Autism Center’s motion for summary judgment, Filing No. 229, is granted
4. A Judgment in favor of the defendants and against the plaintiff shall be issued
in conjunction with this Memorandum and Order.
Dated this 18th day of January, 2023.
BY THE COURT:
s/ Joseph F. Bataillon
Senior United States District Judge