Choice Construction, Inc. v. JMR Construction Corp. et al
Filing
35
ORDER Granting 19 Defendant JMR's Motion to Stay. Proceedings against JMR are stayed until the Federal Claims Court issues a final decision in 1:11-cv-187. JMR shall file status reports with this Court every three months. IT IS FURTHER ORDERED that 21 Defendant Great American Insurance Company's Motion to Stay is DENIED. Signed by Judge Miranda M. Du on 7/16/12. (Copies have been distributed pursuant to the NEF - EDS)
1
2
3
4
5
6
7
UNITED STATES DISTRICT COURT
8
DISTRICT OF NEVADA
9
***
10
11
CHOICE CONSTRUCTION, INC.,
Case No. 2:12-cv-00192-MMD-PAL
Plaintiff,
12
ORDER
v.
13
14
JMR CONSTRUCTION CORPORATION,
et al.,
(Defendant JMR‟s Motion to Stay–dkt. no.
19; Defendant GAIC‟s Joinder to JMR‟s
Motion to Stay–dkt. no. 21)
15
Defendants.
16
17
I.
SUMMARY
18
Before the Court is Defendant JMR Construction Corporation‟s Motion to Stay
19
(dkt. no. 19), which Defendant Great American Insurance Company joins (dkt. no. 21).
20
For the reasons set forth below, the Court grants JMR‟s motion and denies GAIC‟s
21
motion.
22
II.
BACKGROUND
23
On or about June 26, 2007, Defendant JMR Construction Corporation (“JMR”)
24
entered into a contract with the United States Army Corps of Engineers (“COE” or
25
“government”) for JMR to perform construction services as the general contractor for the
26
BRAC Aircraft Maintenance Shop Facilities at Nellis Air Force Base in Las Vegas,
27
Nevada (the “prime contract”). Defendant Great American Insurance Company (“GAIC”)
28
issued a surety on behalf of JMR as principal in July 2007.
1
On or about August 29, 2007, Plaintiff Choice Construction, Inc. (“Choice”)
2
entered into a subcontract agreement (the “subcontract”) whereby Choice agreed to
3
complete certain electrical work for the BRAC project.
4
On August 13, 2007, COE issued JMR a Notice to Proceed, setting an initial
5
completion date for October 6, 2008. JMR exceeded this deadline by 333 days. COE
6
excused only 59 days of the 333 day overrun, and withheld $59,976 in liquidated
7
damages from JMR. (Dkt. no. 19 at ¶ 4.) JMR blames the government for the delayed
8
completion and filed a lawsuit, JMR Construction v. United States, No. 1:11-cv-187, in
9
the Court of Federal Claims against COE to recover damages and associated monetary
10
costs under the Contract Disputes Act, 41 U.S.C. §§ 601-613. (Dkt. no. 19-4.)1
11
On January 6, 2012, Choice sued JMR and GAIC in Nevada‟s Eighth Judicial
12
district for failure to compensate Choice the full amount agreed upon in the subcontract.
13
The complaint also alleges that GAIC violated Nevada‟s Unfair Claims Practices Act,
14
NRS 686A.310, because it failed to investigate Choice‟s Miller Act claim against JMR as
15
required under the act.2
16
jurisdiction. (Dkt. no. 1.) JMR filed a counterclaim alleging that if the delays in the
17
BRAC project were not caused by the government, Choice was the responsible party.
18
(Dkt. no. 19-5 at 7-13.)
19
III.
GAIC timely removed to this Court under its diversity
DISCUSSION
20
A.
Legal Standard
21
The “power to stay proceedings is incidental to the power inherent in every court
22
to control the disposition of the causes on its docket with economy of time and effort for
23
24
25
26
27
28
1
Before filing the lawsuit against COE, JMR submitted a claim in the form of a
Request for Equitable Adjustment to the contracting officer of COE. On March 25, 2010,
the contracting officer issued a final decision rejecting JMR‟s claim. (Dkt. no. 19 at ¶ 5).
2
The Miller Act “requires a general contractor on a federal construction project to
furnish a payment bond „for the protection of all persons supplying labor and material in
the prosecution of work provided for in [the] contract.‟” U.S. for Use & Benefit of Walton
Tech., Inc. v. Weststar Eng’g, Inc., 290 F.3d 1199, 1205 (9th Cir. 2002) (citing 40 U.S.C.
§ 270a(a)(2)).
2
1
itself, for counsel, and for litigants.” Landis v. N. Am. Co., 299 U.S. 248, 254 (1936).
2
“How this can best be done calls for the exercise of judgment, which must weigh
3
competing interests and maintain an even balance.”
4
requirement that “before proceedings in one suit may be stayed to abide the
5
proceedings in another[] the parties to the two causes must be shown to be the same
6
and the issues identical.” Id. at 254.
Id. at 254-55.
There is no
JMR’s Motion to Stay
7
B.
8
JMR seeks to stay this proceeding pending resolution of the Federal Claims
9
action pursuant to Section 11.4 of the contract and this Court‟s inherent authority.
1.
10
JMR argues that Section 11.4 of the subcontract requires staying this proceeding.
11
12
Staying the Action Pursuant to the Subcontract
The provision states:
16
in the event the provision for resolution of disputes between the Contractor
and the Owner contained in the Subcontract Documents do not permit
consolidation or joinder with disputes of third parties, such as the
Subcontractor, resolution of disputes between the Subcontractor and
Contractor involving in whole or in part disputes between the Contractor
and the Owner shall be stayed pending conclusion of any dispute
resolution proceeding between the Contractor and the Owner.
17
The parties do not present evidence regarding why Choice could not have been
18
joined in the Claims Court action or why the two cases could not have been
19
consolidated. In fact, JMR‟s counsel conceded during oral argument that one reason for
20
not joining Choice was to preserve JMR‟s argument that the COE was the sole cause of
21
the delay in support of JMR‟s Federal Claims action. Section 11.4 of the subcontract
22
therefore does not apply to provide an express contractual basis for staying this action.
13
14
15
23
2.
Staying the Action Pursuant to the Court’s Inherent Authority
24
On balance, the competing interests of the parties favor staying the proceedings.
25
First, the COE action and JMR‟s counterclaim are so inter-related that there is a risk of
26
inconsistent judgments if this proceeding is not stayed. Second, the balance of the
27
equities favors staying the proceedings.
28
///
3
a.
1
This Action is Related to the Claims Court Proceeding
2
JMR argues that this action and the Federal Claims action are related because, in
3
its counterclaim, it argues that if the Federal Claims court determines that the
4
government is not responsible for the contract delay and resulting damages, then JMR
5
alleges that Choice is responsible. Therefore the viability of JMR‟s counterclaims, or the
6
very fact of JMR raising the counterclaims in this case at all, depends on the outcome of
7
the Federal Claims action.
8
Choice counters that the two actions are not related; that this is a simple breach
9
of contract claim. Choice points to JMR‟s requested damages in the COE action and
10
asserts that they “relate to claims for added contract value, not for contract balance as
11
Choice seeks from JMR[,]” and that therefore “JMR has been fully paid for Choice‟s
12
[w]ork” on the BRAC project. (Dkt. no. 24 at 8.) If this is the case, then staying this
13
matter is not necessary because the COE action and this action are not sufficiently
14
related for the purposes of a stay.
15
Choice is correct that its claims against JMR are simple breach of contract claims,
16
unrelated to JMR‟s action against the government. However, JMR‟s counterclaim in this
17
case is inherently related to its claims in the Federal Claims Court. There, JMR argues
18
that the government is solely responsible for the delay, and must compensate JMR
19
accordingly.
20
delays, Choice was responsible. The nature of the Federal Claims lawsuit further helps
21
to demonstrate why the two cases are inextricably related. JMR‟s claims against the
22
government concern Eichleay damages under the Contract Disputes Act, 41 U.S.C. §
23
601-613. These damages involve a specific formula used to calculate how much the
24
government owes a contractor. See Charles G. Williams Const., Inc. v. Sec. of the
25
Army, 326 F.3d 1376, 1379 (Fed. Cir. 2003). To prove Eichleay damages, the contractor
26
must first prove that there was a government-caused delay to contract performance that
27
was not concurrent with a delay caused by the contractor or some other reason. P.J.
28
Dick v. Sec. of Veteran’s Affairs, 324 F.3d 1364, 1370 (Fed. Cir. 2003). Because of this,
Here, JMR argues that if the government was not responsible for the
4
1
only if the government prevails against JMR will JMR‟s counterclaims be cognizable
2
here.
3
Moreover, principles of judicial economy and a desire for consistency in judicial
4
decision-making support staying this action. If JMR prevails against the government,
5
because of the nature of Eichleay damages, it could not pursue its counterclaim against
6
Choice in this case.
7
possibility of inconsistent judgments. This could happen were the Claims Court to hold
8
the government solely responsible for the delays and this Court to hold that Choice was
9
responsible for the delays. Should this occur, Choice would likely file a new case after
10
the resolution of the Claims Court decision to attempt to recover the damages it paid
11
JMR. Such a lengthy chain of events would result in duplicative discovery, inconsistent
12
judgments, and delayed verdicts. Staying this action until the resolution of JMR‟s suit
13
against COE is universally beneficial in light of these concerns.
However, if the Court does not stay this action, there is the
14
b.
15
The Balance
Proceeding
of
Hardships
Favors
Staying
this
16
Second, the balance of hardships favors staying this lawsuit. While it is true that
17
Choice‟s potential recovery will be delayed by this decision, Choice foresaw and agreed
18
to a potential delay such as this one when it signed the subcontract. Although the
19
automatic stay provision, Section 11.4, is inapplicable here, the parties did agree that
20
Choice‟s claims against JMR may be stayed in certain circumstances so Choice knew
21
the potential risks if disputes were to occur as it did here. Moreover, in Sections 6.4 and
22
6.5.2 the parties contemplated a stay in any proceeding involving a subcontractor and
23
the contractor when the contractor has also sued the owner. Section 6.4 holds that “the
24
Subcontractor shall be liable to the Contractor for liquidated damages . . . to the same
25
extent the Contractor shall be liable to the Owner.” (Dkt. no. 24-2.) Here, it has yet to be
26
determined to what extent JMR is liable to the government – that issue is currently in
27
front of the Claims Court. But inherent in Section 6.4‟s requirement that Choice pay JMR
28
whatever liquidated damages JMR owes the government is the requirement that the
5
1
parties must wait until those damages are determined before JMR may request those
2
damages from Choice.
3
Further, Section 6.5.4 of the subcontract requires that
4
In the event of any dispute or claim between Contractor and Owner which
directly or indirectly involves the work required to be performed by
Subcontractor . . . Subcontractor agrees to be bound by the terms of the
Owner-Contractor Agreement and by all decisions, findings, or
determinations made hereunder, whether by . . . administrative agency or
court of competent jurisdiction . . . If any dispute or claim is prosecuted or
defended by Contractor, and Subcontractor is not directly a party or litigant,
Subcontractor agrees to cooperate fully with Contractor and to furnish all
documents, statements, witnesses, and other information required by
Contractor for such purpose . . .
5
6
7
8
9
10
(Dkt. no. 24-2 at 14.) In the plain terms of the contract Choice agreed to be bound by
11
any decision in the Claims Court proceeding and to fully cooperate with JMR in that
12
proceeding. To that end, Choice must wait for a resolution in that proceeding before
13
proceeding with its claims here.
Choice’s Request for Discovery
14
C.
15
Choice requests that before ruling on this motion, the Court should allow it to
16
engage in limited discovery to determine whether JMR‟s claims against the government
17
are related to Choice‟s claims against JMR. However, the evidence Choice asserts it
18
would collect in discovery relate to the underlying merits of its lawsuit against JMR and
19
JMR‟s counterclaims. It does not relate to the critical question in this Motion: whether
20
this lawsuit and JMR‟s lawsuit against the government are related.
21
Choice asserts that JMR has refused to agree to an accounting to show how
22
much of the amount already paid by the government was allocated for Choice‟s work on
23
the BRAC project. But whatever those damages may be, they relate to the merits of
24
Choice‟s underlying breach of contract claim. Obtaining an accounting of those figures
25
will not help Choice demonstrate that this action and JMR‟s Claims Court lawsuit are
26
unrelated.
27
///
28
///
Further, at oral argument Plaintiff‟s counsel stated that he would like to
6
1
conduct discovery regarding which party caused the delay on the BRAC project.3 Yet
2
with this request, Plaintiff essentially concedes that this case is related to JMR‟s suit
3
against COE, because Choice admits that it must conduct discovery regarding the issue
4
of delay on the BRAC project for this case, and delay is the central issue in the Claims
5
Court action.
For these reasons, the Court determines that Choice‟s request for limited
6
7
discovery in this case is denied.
GAIC’s Joinder
8
D.
9
GAIC argues that Plaintiff‟s Nevada‟s Unfair Claims Practices Act, NRS 686A.310,
10
should be stayed for many of the same reasons given by JMR regarding Plaintiff‟s breach of
11
contract claims. However, Plaintiff‟s claims against GAIC are wholly different and unrelated
12
to JMR‟s suit against COE. Plaintiff alleges that GAIC had a duty to investigate and affirm
13
or deny Choice‟s claim against JMR within a reasonable time after having received
14
Choice‟s claim, and that because it did not, Choice did not file a Miller Act complaint
15
within the required timeframe. This has nothing to do with the inter-related breach of
16
contract claims involving Choice, JMR, and COE.
GAIC‟s other arguments as to why Plaintiff‟s NRS 686A.310 claim should be stayed
17
18
are likewise unavailing.
First, GAIC argues that a surety is entitled to assert any defenses
19
personal to the principal.
20
does not raise any defenses to Choice‟s NRS 686A.310 claim as Choice does not allege
21
that JMR violated the act. Second, GAIC argues that Choice‟s Unfair Claims Practices
22
allegation raises a difficult and unanswered question of state law–whether NRS 686A.310
23
extends to the surety context. Because of this, GAIC contends that the Court should abstain
24
from deciding Plaintiff‟s claim against it under Colorado River abstention principles. See
25
///
Even if that is the case, it is of no consequence because JMR
26
27
28
3
Plaintiff‟s counsel stated that in discovery, he would “inquire as to this 400
megahertz equipment [the electrical equipment Choice installed on the BRAC project],
what the delays the real delays were on that.”
7
1
Colorado River Water Conservation Dist. v. United States, 424 U.S. 800, 814 (1976).4 Yet in
2
this argument GAIC asks for a different type of relief than JMR on distinct grounds. Such an
3
unrelated request in a joinder motion is improper. Because of this, and because the Court
4
finds no other reason to stay the proceeding against GAIC, the Court denies GAIC‟s motion.
5
IV.
6
CONCLUSION
Accordingly, IT IS HEREBY ORDERED that Defendant JMR‟s Motion to Stay is
7
GRANTED.
8
Claims Court issues a final decision in JMR Construction v. United States, No. 1:11-cv-
9
187. The Court instructs Defendant JMR to file status reports regarding the progress of
10
JMR Construction v. United States with this Court every three months. The Court will
11
revisit this Order once discovery is completed in that case.
12
The proceedings against Defendant JMR are stayed until the Federal
IT IS FURTHER ORDERED THAT Defendant GAIC‟s Motion to Stay is DENIED.
13
14
ENTERED THIS 16th day of July 2012.
15
16
UNITED STATES DISTRICT JUDGE
17
18
19
20
21
22
23
24
25
26
27
28
4
Colorado River abstention is appropriate in only “rare circumstances,” and when
there are parallel state or federal proceedings involving the same parties and same
issues. See Federated Rural Elec. Ins. Corp. v. Ark. Elec. Coop., Inc., 48 F.3d 294, 297
(8th Cir. 1995). This is not such a case, because the Federal Claims matter does not
concern Nevada surety law, nor are GAIC or Choice parties to that proceeding. Rather,
abstention under Louisiana Power & Light Co. v. City of Thibodaux, 360 U.S. 25 (1959),
is the applicable abstention doctrine when a federal court refrains from exercising federal
jurisdiction because a case raises “difficult questions of state law bearing on policy
problems of substantial public import whose importance transcends the result in the case
then at bar.” Polygon Ins. Co., Ltd. v. Honeywell Int’l Inc., 143 F. Supp. 2d 211, 213-14
(D. Conn. 2001) (discussing when Thibodaux abstention is proper).
8
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?