The Erection Company v. Archer Western Contractors, LLC et al
Filing
239
ORDER Granting in Part and Denying in Part 218 Motion for Clarification as stated Herein: It is Ordered that Motions 151 , 152 , 154 , 161 , 163 , and 201 Motions are denied. It is further Ordered that 153 , 158 , 159 , 160 , and 162 Motions are granted. Signed by Judge Miranda M. Du on 3/4/2015. (Copies have been distributed pursuant to the NEF - DC)
1
2
3
4
5
6
7
8
UNITED STATES DISTRICT COURT
9
DISTRICT OF NEVADA
10
***
11
THE ERECTION COMPANY, et al.,
Plaintiffs,
12
v.
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
ARCHER WESTERN CONTRACTORS,
LLC, et al.,
Defendants.
ARCHER WESTERN
CONTRACTORS, LLC,
Counterclaimant
v.
THE ERECTION COMPANY,
Counterdefendant.
ARCHER WESTERN
CONTRACTORS, LLC,
Cross-Claimant,
v.
POSTEL INDUSTRIES, INC.,
Cross-Defendant.
ARCHER WESTERN
CONTRACTORS, LLC,
Third-Party Plaintiff,
v.
TRAVELERS CASUALTY & SURETY
COMPANY OF AMERICA, et al.,
Third-Party Defendants.
Case No. 2:12-cv-00612-MMD-NJK
ORDER
1
I.
SUMMARY
2
This Order addresses the following pending motions: (1) The Erection Company’s
3
(“TEC”) Motion for Summary Judgment Against Postel Industries (“Postel”)1 on Its
4
Counter-Claim (Re: Postel’s Abandonment) (dkt. no. 151); (2) TEC’s Motion for
5
Summary Judgment Against Archer Western Contractors (“Archer”) on All Claims (Re:
6
Invalid Assignment) (dkt. no. 152); (3) TEC’s Motion for Partial Summary Judgment
7
Against Archer on Its Affirmative Claims (Re: Standing In Postel’s Shoes) (dkt. no. 153);
8
(4) Postel’s Motion for Summary Judgment Against TEC (dkt. no. 154); (5) Defendant
9
Travelers Casualty and Surety Company of America’s (“Travelers”) Motion for Partial
10
Summary Judgment (dkt. no. 158); (6) Archer’s Motion for Partial Summary Judgment on
11
The Third Cause of Action of Its Crossclaim Against Postel (dkt. no. 159); (7) Archer’s
12
Motion for Summary Judgment on the Third and Fourth Causes of Action of Postel’s
13
Crossclaims Against Archer (dkt. no. 160); (8) Archer’s Motion for Summary Judgment
14
on Plaintiff’s First and Second Claims for Relief (dkt. no. 161); (9) Archer’s Motion for
15
Partial Summary Judgment on Plaintiff’s Third Claim for Relief (dkt. no 162); (10)
16
Archer’s Motion for Partial Summary Judgment on the First Cause of Action of its
17
Counterclaim Against Plaintiff (dkt. no. 163); (11) Archer’s Motion to Strike or Disregard
18
the Affidavit of Danny Lucas (dkt. no. 201); and (12) TEC’s Motion for Clarification and/or
19
Relief from Order (dkt. no. 218).2 Travelers joined in all four of TEC’s motions. (Dkt. nos.
20
155, 156, 157, 219.)
21
///
22
///
23
1
24
25
26
27
28
TEC names three Postel entities: Postel Erection Group, LLC; Postel West, Inc.;
and Postel Industries, Inc. (Dkt. no. 48.) The first two entities were dismissed pursuant to
the parties’ stipulation. (Dkt. no. 150.)
2
TEC filed three separate motions for partial summary judgment while Archer filed
five separate motions. Why these separate motions were not filed as one consolidated
motion by each party is beyond contemplation. The separate motions result in
duplicative filings, repetitive recitations of claimed undisputed facts and standards of
review, and a burden on the Court in having to review multiple duplicative filings and
tracking multiple responses, replies, joinders and response to joinders.
2
1
II.
BACKGROUND
2
This dispute arises from the construction of a new air traffic control tower at
3
McCarran International Airport (“the Project”). Clark County leased the property to the
4
Federal Aviation Administration (“FAA”) in order to build the control tower. (Dkt. no. 86-
5
2.) On September 3, 2010, the FAA hired Archer to be the general contractor on the
6
Project. (Dkt. no. 85 at 3; dkt. no. 96 at 8.) In May 2011, Archer hired Postel as the
7
subcontractor for steel fabrication and installation, and Postel, in turn, hired TEC as the
8
subcontractor for steel installation.3 (Dkt. no. 85 at 3-4; dkt. no. 96 at 10; dkt. no. 27 at
9
10.) The contract between Archer and Postel (“Postel Subcontract”) expressly
10
incorporated the prime contract between Archer and the FAA (dkt. no. 96-4 at 2); the
11
contract between Postel and TEC (“TEC Subcontract”) expressly incorporated the Postel
12
Subcontract (dkt. no 88-5 at 2).4 Archer obtained a payment bond and a performance
13
bond from Travelers. (Dkt. no. 85 at 9; dkt. no. 96 at 8.)
14
According to TEC, it expected to start work after Archer installed the rebar and
15
concrete to form the tower walls up to approximately the fifth level. (Dkt. no. 86 at 4.) At
16
that point, TEC would begin installing structural steel anchored to the concrete walls to
17
support the stairs, landings, and deck that it would also install. (Id.) TEC would then
18
generally follow behind Archer’s work by about two floors. (Id.) TEC commenced work on
19
November 14, 2011, and completed work through level 12. (Id.) However, a dispute
20
arose about alleged performance and payment that led Postel to assign the TEC
21
Subcontract to Archer, and that prompted TEC to issue notices of intent to stop work.
22
With respect to performance, on November 19, 2011, Archer put Postel on notice
23
that the FAA’s inspectors had discovered deficiencies in the stairs that Postel had
24
25
26
27
28
3
The parties offer different dates for the two pertinent subcontracts. Both
subcontracts identify May 20, 2011 as the agreement date, but the Postel Subcontract
was signed several months later. (Dkt. no. 96-4; dkt. no. 88-6.) TEC asserts that the TEC
Subcontract was signed on November 8, 2011. (Dkt. no. 86 ¶ 10.)
4
TEC disputes that the TEC Subcontract incorporated the Postel Subcontract.
(Dkt. no. 182 at 6.)
3
1
delivered to the Project and that the issue was affecting the Project schedule. (Dkt no.
2
96-5.) On January 3, 2012, Archer requested that Postel submit a recovery schedule for
3
stair no. 3 because Postel and TEC were behind schedule and were more than two
4
floors below Archer’s concrete operation. (Dkt. no. 96-7.) On January 13, 2012, Archer
5
sent Postel another letter to relate that Postel had not provided a recovery schedule and
6
to provide notice that Archer would be withholding all future payments to Postel until
7
issues identified in the letter had been addressed. (Dkt. no. 96-8.) On February 20,
8
2012, Archer served Postel with a “Notice to Cure,” stating that Postel had failed to
9
comply with the parties’ contract terms and that Postel had informed Archer that it “no
10
longer wishes to perform contractual obligations.” (Dkt. no. 86-9.)
11
In the meantime, on February 16, 2012, TEC issued to Postel a “Notice of Intent
12
to Stop Work” because, according to TEC, it had yet to be paid for any of its work. (Dkt.
13
no. 85 at 14; dkt. no. 86-8.) In that Notice, TEC stated that Postel owed at least
14
$80,000.00 for two months of base-contract work and for extra work billed; TEC
15
demanded payment within ten (10) days. (Dkt. no. 88-8.) On February 22, 2012, TEC
16
notified Postel that it had learned from Archer that Postel had abandoned the Project,
17
which TEC construed to be a material breach of the TEC Subcontract. (Dkt. no. 86-10.)
18
TEC stated that it “is immediately stopping all work on the Project.” (Id.) On February 24,
19
2012, TEC notified Archer that it would be stopping work on February 28, 2012.5 (Dkt.
20
no. 86-15.) TEC stopped work as noticed.6 (Dkt. no. 86-16.)
21
On February 24, 2012, Archer sent TEC a letter along with payment on behalf of
22
Postel in the amount of $54,645.30 for what Archer characterized as “properly supported
23
24
25
26
27
28
5
In the same letter, TEC referenced Archer’s rejection of its proposed “Time &
Materials Agreement,” the purpose of which was to allow TEC to continue working on the
Project. (Dkt. no. 86-15.)
6
The records offer conflicting dates as to when TEC stopped work on the Project.
TEC’s February 22, 2012, letter stated it was stopping work immediately (dkt. no. 86-10),
but TEC’s February 24, 2012, letter to Archer stated that it would stop work on February
28, 2012, and would demobilize on February 29, 2012 (dkt. no. 86-15). Thus, at the
latest, TEC stopped work on February 29, 2012.
4
1
and documented pay applications through the end of December, 2011.”7 (Dkt. no. 96-9.)
2
In the same letter, Archer acknowledged that there may be invoices for extra work but
3
contended that TEC had not submitted proper supporting documents; Archer invited
4
TEC to provide the documentation. (Id.) Archer claims that TEC did not submit the
5
requested documentation. (Dkt. no. 96-1 ¶ 29.) TEC claims no further documentation
6
was needed because it had provided all supporting documents to Postel. (Dkt. no. 182 at
7
6; dkt. no. 86 at 5-6.) In a letter dated February 27, 2012, Archer informed TEC that
8
Postel had not abandoned the Project and was involved and committed to work with
9
Archer to fulfill Postel’s contractual obligations to Archer. (Dkt. no. 96-10.) Archer
10
contended that the Postel Subcontract, which was incorporated into the TEC
11
Subcontract, provides for the assignment of the TEC Subcontract to Archer. (Id.) Archer
12
also insisted that TEC had no legitimate reason to stop work. (Id.) On February 28, 2012,
13
TEC gave Postel further Notice of Intent to Terminate in fifteen (15) days (on March 14,
14
2012).8 (Dkt. no. 86-18.) On March 2, 2012, TEC notified Postel that it had ceased work
15
and demobilized from the Project as a result of Postel’s failure to pay and abandonment
16
of the Project. (Dkt. no 86-19.)
17
On March 1, 2012, Archer and Postel entered into an Assignment Agreement
18
(“the Assignment”) where Postel agreed to assign all of “its rights and obligations under
19
the TEC Subcontract” to Archer. (Dkt. no. 96-1 ¶ 32; dkt. no. 96-11.) The next day,
20
Archer notified TEC that it had taken an assignment of the TEC Subcontract. (Dkt. no.
21
86-20.) Archer again disputed TEC’s contention that Postel had abandoned the Project
22
and that TEC had not been paid for all properly supported payment applications through
23
December. (Id.) Archer further took the position, which TEC disputes, that TEC was in
24
default and issued a notice to cure. (Id.) TEC acknowledged notice of the assignment of
25
7
26
27
28
TEC received the letter on February 27, 2012. (Dkt. no. 85 at 10.) TEC contends
that, by that time, the payment from Archer still left a balance of over $250,000.00. (Dkt.
no. 86 at 11; dkt. no. 86-19.)
8
TEC asserts that it acted pursuant to advice of counsel to comply with Nevada’s
Prompt Payment Act. (Dkt. no. 85 at 17.)
5
1
the TEC Subcontract and indicated its willingness to re-mobilize and return to the Project
2
provided that Archer pay three enumerated past due amounts totaling about $52,147.00.
3
(Dkt. no. 96-13.) Archer rejected TEC’s payment demand and insisted that TEC
4
remobilize and agree to “the terms of the new project recovery schedule via change
5
order and accept a back charge in the amount of $72,356 for the direct delay” caused by
6
TEC. (Dkt. no. 96-14.) On March 15, 2012, Archer declared TEC to be in default. (Dkt.
7
no. 96-15.)
8
TEC’s First Amended Complaint asserts claims for breach of contract, breach of
9
the implied covenant of good faith and fair dealing, and unjust enrichment against Postel
10
and Archer. (Dkt. no. 48.) Archer asserts claims for breach of contract and negligence
11
against TEC, and claims for contractual indemnity and breach of contract against Postel.
12
(Dkt. no. 9.) Postel similarly asserts claims for breach of contract and negligence against
13
TEC, and claims for contractual indemnity and breach of contract against Archer. (Dkt.
14
no. 27.) All three parties assert separate claims against Travelers on the payment and
15
performance bonds. (Id.; dkt. nos. 48, 9.)
16
TEC subsequently moved for summary judgment against Postel on its
17
counterclaim for breach of contract. (Dkt. no. 85.) The Court denied TEC’s motion, and
18
TEC now seeks clarification and reconsideration. (Dkt. nos. 217, 218.)
19
III.
LEGAL STANDARD
20
A.
Summary Judgment
21
The purpose of summary judgment is to avoid unnecessary trials when there is no
22
dispute as to the facts before the court. Nw. Motorcycle Ass’n v. U.S. Dep’t of Agric., 18
23
F.3d 1468, 1471 (9th Cir. 1994). Summary judgment is appropriate when the pleadings,
24
the discovery and disclosure materials on file, and any affidavits “show there is no
25
genuine issue as to any material fact and that the movant is entitled to judgment as a
26
matter of law.” Celotex Corp. v. Catrett, 477 U.S. 317, 330 (1986). An issue is “genuine”
27
if there is a sufficient evidentiary basis on which a reasonable fact-finder could find for
28
the nonmoving party and a dispute is “material” if it could affect the outcome of the suit
6
1
under the governing law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49 (1986).
2
Where reasonable minds could differ on the material facts at issue, however, summary
3
judgment is not appropriate. Warren v. City of Carlsbad, 58 F.3d 439, 441 (9th Cir.
4
1995). “The amount of evidence necessary to raise a genuine issue of material fact is
5
enough ‘to require a jury or judge to resolve the parties' differing versions of the truth at
6
trial.’” Aydin Corp. v. Loral Corp., 718 F.2d 897, 902 (9th Cir. 1983) (quoting First Nat’l
7
Bank v. Cities Service Co., 391 U.S. 253, 288–89 (1968)). In evaluating a summary
8
judgment motion, a court views all facts and draws all inferences in the light most
9
favorable to the nonmoving party. Kaiser Cement Corp. v. Fishbach & Moore, Inc., 793
10
F.2d 1100, 1103 (9th Cir. 1986).
11
The moving party bears the burden of showing that there are no genuine issues
12
of material fact. Zoslaw v. MCA Distrib. Corp., 693 F.2d 870, 883 (9th Cir. 1982). “In
13
order to carry its burden of production, the moving party must either produce evidence
14
negating an essential element of the nonmoving party’s claim or defense or show that
15
the nonmoving party does not have enough evidence of an essential element to carry its
16
ultimate burden of persuasion at trial.” Nissan Fire & Marine Ins. Co. v. Fritz Cos., 210
17
F.3d 1099, 1102 (9th Cir. 2000). Once the moving party satisfies Rule 56’s requirements,
18
the burden shifts to the party resisting the motion to “set forth specific facts showing that
19
there is a genuine issue for trial.” Anderson, 477 U.S. at 256. The nonmoving party “may
20
not rely on denials in the pleadings but must produce specific evidence, through
21
affidavits or admissible discovery material, to show that the dispute exists,” Bhan v. NME
22
Hosps., Inc., 929 F.2d 1404, 1409 (9th Cir. 1991), and “must do more than simply show
23
that there is some metaphysical doubt as to the material facts.” Orr v. Bank of Am., 285
24
F.3d 764, 783 (9th Cir. 2002) (internal citations omitted). “The mere existence of a
25
scintilla of evidence in support of the plaintiff’s position will be insufficient.” Anderson,
26
477 U.S. at 252.
27
///
28
///
7
1
B.
Clarification And Reconsideration
2
Under Fed. R. Civ. P. 60(b), a court may relieve a party from a final judgment,
3
order or proceeding only in the following circumstances: (1) mistake, inadvertence,
4
surprise, or excusable neglect; (2) newly discovered evidence; (3) fraud; (4) a void
5
judgment; (5) a satisfied or discharged judgment; or (6) any other reason justifying relief
6
from the judgment. Backlund v. Barnhart, 778 F.2d 1386, 1387 (9th Cir. 1985). “Relief
7
under Rule 60(b)(6) must be requested within a reasonable time, and is available only
8
under extraordinary circumstances.” Twentieth Century-Fox Film Corp. v. Dunnahoo,
9
637 F.2d 1338, 1341 (9th Cir. 1981) (internal citations omitted). A motion for
10
reconsideration must set forth the following: (1) some valid reason why the court should
11
revisit its prior order; and (2) facts or law of a “strongly convincing nature” in support of
12
reversing the prior decision. Frasure v. United States, 256 F. Supp. 2d 1180, 1183 (D.
13
Nev. 2003). On the other hand, a motion for reconsideration is properly denied when the
14
movant fails to establish any reason justifying relief. Backlund 778 F.2d at 1388 (holding
15
that a district court properly denied a motion for reconsideration in which the plaintiff
16
presented no arguments that were not already raised in his original motion).
17
IV.
TEC’S MOTION FOR CLARIFICATION/RECONSIDERATION (DKT. NO. 218)
18
TEC’s motion seeks both clarification and reconsideration of the Court’s Order
19
denying summary judgment (“Order”). (Dkt. no. 217.) In that Order, the Court ruled on
20
the primary issue presented in TEC’s motion for summary judgment — whether
21
Nevada’s Prompt Payment Act (“PPA”) applies to the TEC Subcontract dispute. The
22
Court found that the Nevada PPA does not apply because it is preempted by federal law.
23
(Id.) TEC suggests that the parties may misconstrue the Order to hold that TEC is barred
24
from pursuing its state law remedies. Archer’s response clarifies that there is no such
25
misinterpretation. Nevertheless, to the extent there is any confusion about the scope of
26
the Court’s Order, the Court clarifies that the Order does not address the merits of TEC’s
27
breach of contract claim. As for TEC’s request that the Court clarify that the Order is not
28
intended to adjudicate any violation of federal law or TEC’s right to pursue the payment
8
1
bond under the Miller Act, there is no need for clarification since these issues were
2
neither presented in TEC’s motion for summary judgment nor considered by the Court.
3
Again, Archer’s response shows there is no confusion as to these issues. The Court thus
4
grants TEC’s request for clarification in part as stated. The Court denies TEC’s request
5
for reconsideration as TEC has not offered any convincing arguments to persuade the
6
Court that it made a mistake.
7
V.
TRAVELERS’ MOTION (DKT. NO. 158)
8
Travelers seeks a ruling that TEC is barred from recovering lost profits under the
9
payment bond. (Dkt. no. 158.) TEC did not file a response. The Court agrees with
10
Travelers that the Miller Act, 40 U.S.C. § 3131 et seq., bars a subcontractor such as
11
TEC from recovery of unrealized profits. Travelers’ motion (dkt no. 158) is granted.
12
VI.
REMAINING MOTIONS
13
The remaining motions raise issues that are so intertwined that the Court will
14
address them in groups. Several motions rely on facts that the Court finds to be in
15
dispute. The remainder of the motions generally relates to the Assignment and will be
16
addressed collectively.
17
A.
18
Viewing the evidence in the light most favorable to the non-moving parties, the
19
Court finds a genuine issue exists as to the following material facts. These disputes
20
preclude summary judgment as discussed further below.
21
Factual Disputes
1.
Postel’s Alleged Abandonment of the Project
22
The parties have presented a genuine issue of material fact as to whether Postel
23
abandoned the Project. TEC argues that Postel abandoned the Project and Archer
24
acknowledged this fact. As support, TEC offers Archer’s February 20, 2012, Notice to
25
Cure to Postel and TEC’s February 22, 2012, letter to Postel, in which TEC stated it had
26
learned from Archer that Postel had abandoned the Project. (Dkt. nos. 86-9, 86-10.)
27
However, in a subsequent letter dated February 28, 2012, TEC claimed it was receiving
28
conflicting information as to whether Postel had abandoned the Project. (Dkt. no. 86-16.)
9
1
In letters dated February 27 and March 2, 2012, Archer disputed TEC’s contention that
2
Postel had abandoned the Project. (Dkt. nos. 96-10, 86-20.) In fact, Archer stated in the
3
February 27, 2012, letter that Postel was then involved and committed to work with
4
Archer to fulfill Postel’s contractual obligations to Archer. (Dkt. no. 96-10.)
5
6
Two of TEC’s motions are premised on the Court’s finding that Postel abandoned
the Project. (Dkt. nos. 151, 153.) These two motions are therefore denied.9
2.
7
TEC’s Responsibilities under the TEC Subcontract
8
The Court finds that there is a genuine factual dispute as to whether TEC
9
breached the TEC Subcontract and whether TEC was justified in demobilizing from the
10
Project and in refusing to remobilize until three invoices were paid. The parties offer
11
conflicting evidence about TEC’s progress, Postel’s work, and alleged delays to the
12
Project caused by either Postel and/or TEC. First, TEC contends that it completed work
13
through level 12. (Dkt. no. 86 at 4.) Archer argues that Postel and TEC were behind
14
schedule and that it notified Postel that Archer would be withholding payments to Postel
15
until deficiencies that Archer identified — including Postel’s failure to provide a recovery
16
schedule — had been addressed. (Dkt. no. 96-8). In fact, in the February 20, 2012,
17
Notice to Cure to Postel, Archer took the position that Postel had failed to comply with
18
the parties’ contract terms. (Id.) This Notice, however, does not address any contention
19
about TEC’s alleged failure to perform.
20
With regard to payments made to TEC, the parties dispute why TEC was not paid
21
as it demanded (i.e., because of insufficient documentation and applications for
22
payment), but they agree that Archer only paid TEC the $54,645.30 referenced in
23
24
25
26
27
28
9
In one of these motions, TEC raises the legal issue of Archer’s right to assert its
negligence claim. (Dkt. no. 153 at 9.) This argument defies logic. TEC contends that
because Archer had no contractual privity with TEC, Archer cannot assert a claim for
negligence where it only seeks economic loss. At the same time, TEC argues that
Archer’s rights acquired by assignment of the TEC Subcontract are limited by Postel’s
rights under the same agreement because Archer stands in the shoes of Postel.
Applying this same logic, the assignment of the TEC Subcontract establishes Archer’s
contractual privity with TEC.
10
1
Archer’s February 24, 2012, letter (dkt. no. 96-9), after TEC had notified both Archer and
2
Postel that more invoices were outstanding. (See Notice to Postel, dkt no. 86-8 (TEC
3
stated that Postel owed at least $80,000.00); Letter to Archer, dkt. no. 96-13 (TEC
4
demanded payments on three invoices before it would remobilize).) In fact, in one of
5
Archer’s letters, Archer acknowledged that there may be invoices for extra work but
6
contended that proper supporting documents had not been submitted and invited TEC to
7
provide the supporting documentation. (Dkt. no. 96-9.) Archer claims that TEC did not
8
submit the requested documentation to support additional payments (dkt. no. 96-1 ¶ 29)
9
while TEC asserts that no further documentation was needed because it had provided all
10
supporting documents to Postel (dkt. no. 182 at 6; dkt. no. 86 at 5-6.) TEC also disputes
11
that its work was defective and offers evidence that it submitted a proposed “Time &
12
Materials Agreement” to Archer to continue work on the Project. (Dkt. no. 86 at 9-13; dkt.
13
no. 182 at 9; dkt. no. 86-15.) Moreover, Archer’s demand that TEC remobilize came with
14
a condition that TEC agree to “the terms of the new project recovery schedule via
15
change order and accept a back charge in the amount of $72,356 for the direct delay”
16
caused by TEC. (Dkt. no. 96-14.) As discussed, TEC’s contention is that it is owed more,
17
not that it owed Archer for any delays.
18
Given these genuine factual disputes, the Court cannot find that TEC breached
19
the TEC Subcontract when it stopped work and refused to return as Archer demanded.
20
The fact that Postel does not believe Archer breached the Postel Agreement does not
21
resolve these factual disputes. (See dkt. no. 162-1 at 4.) Accordingly, Archer’s motion for
22
summary judgment on its first counterclaim for breach of contract against TEC (dkt. no.
23
163) is denied.
24
3.
Postel’s Alleged Performance under the TEC Subcontract
25
The gist of TEC’s claims involves payments for work performed under the TEC
26
Subcontract and Postel and Archer’s alleged failure to perform their contractual
27
obligations. (Dkt. no 48 at 4-5.) TEC claims it was not paid in part because Postel failed
28
to submit payment applications to Archer while Archer contends that certain payment
11
1
applications were inadequate and that invoices for extra work were not properly
2
supported. It is not clear from the records whether these issues were communicated to
3
TEC.
4
Archer’s communications to Postel show that Archer had issues with Postel’s
5
performance and its failure to follow the work schedule under the Postel Subcontract.
6
(See, e.g., dkt. nos. 96-7, 96-8, 86-9.) Postel seems to dispute both TEC’s and Archer’s
7
allegations by claiming that it was merely a pass-through subcontractor and that it could
8
not pay TEC if Archer failed to pay. There is a genuine dispute as to whether Postel
9
timely and properly billed Archer for TEC’s work as required under the TEC Subcontract,
10
and whether Postel was deficient in paying TEC. (Dkt. no. 192 at 3-14.) Postel raises the
11
“pay-when-paid” provision in the TEC Subcontract, contending that it was never paid for
12
TEC’s work and that Archer never approved or paid any change order requests
13
submitted by TEC. (Dkt. no. 154 at 6-11.) This argument misses the point. TEC claims
14
Postel did not submit timely payment, so the fact that Archer did not pay would not
15
necessarily absolve Postel of its responsibility under the TEC Subcontract. TEC further
16
claims that apart from payments under the Postel Subcontract, Postel received a benefit
17
for extra work that TEC performed at Postel’s request and for which TEC was not
18
compensated. (Dkt. no. 192 at 31-32.)
19
The intertwined and disputed allegations relating to payments under the Postel
20
Subcontract and the TEC Subcontract alone create a genuine issue of fact. These
21
disputes preclude summary judgment in favor of Postel on TEC’s claims for breach of
22
contract, breach of the implied covenant of good faith and fair dealing, and unjust
23
enrichment. Postel’s motion for summary judgment against TEC (dkt. no. 154) is denied.
24
25
B.
Issues Involving the Assignment
1.
Validity
26
TEC advances two challenges to the validity of the Assignment: first, the
27
Assignment violates paragraph 8.8 of the Postel Subcontract because Archer and Postel
28
claim that Postel was not in default; and second, paragraph 24.5 of the TEC Subcontract
12
1
prevents Postel from assigning the TEC Subcontract. Archer counters that the
2
Assignment did not occur under paragraph 8.8 of the Postel Subcontract and argues that
3
paragraph 24.5 of the TEC Subcontract does not restrict assignment by Postel. The
4
Court agrees with Archer.
5
A contract is unambiguous if it is not susceptible to more than one interpretation.
6
See Margrave v. Dermody Props., 878 P.2d 291, 293 (Nev. 1994). The Court finds that
7
the pertinent provisions of the Assignment — paragraph 8.8 of the Postel Subcontract
8
and paragraph 24.5 of the TEC Subcontract — are not susceptible to more than one
9
meaning. In fact, the parties do not contend that these provisions are ambiguous.
10
“[W]here a document is clear and unambiguous on its face, the court must
11
construe it from the language therein.” S. Trust Mortg. Co. v. K&B Door Co., Inc., 763
12
P.2d 353, 355 (Nev. 1988). Additionally, when construing a contract, a court should
13
consider the contract as a whole and “should not interpret a contract so as to make
14
meaningless its provisions.” Phillips v. Mercer, 579 P.2d 174, 176 (Nev. 1978). In terms
15
of assignment, “a contractual right is assignable unless assignment materially changes
16
the terms of the contract or the contract expressly precludes assignment.” Easton Bus.
17
Opportunities, Inc. v. Town Exec. Suites-E. Marketplace, LLC, 230 P.3d 827, 830 (Nev.
18
2010) (citing Restatement (Second) of Contracts § 317(2)(a)-(c) (1981)).10 Moreover,
19
“anti-assignment clauses are narrowly construed.” Id. (citation and internal quotation
20
marks omitted).
21
Applying these contract principles here, the TEC Subcontract does not limit
22
assignment to Archer only upon termination for Postel’s default. Paragraph 8.8 requires
23
Postel to contingently assign all of its “subcontracts and purchase orders relating to the
24
Project.” (Dkt. no. 96-4 ¶ 8.8.) Paragraph 8.8 then states that such assignment “shall
25
26
27
28
10
The TEC Subcontract provides that “the laws of the State where the Project is
located” (Nevada) govern their contract dispute. (Dkt. no. 86-5, ¶ 24.1.) The Court thus
looks to Nevada law. The decision in Easton is the latest case where the Nevada
Supreme Court addresses the validity and effect of an assignment.
13
1
take effect only upon Subcontractor’s [Postel’s] termination for default.” (Id.) TEC argues
2
that the phrase “only upon” Postel’s termination shows the parties’ intent to allow
3
assignment to Archer only when Postel has defaulted. Paragraph 8.8 contains no such
4
limitation. The use of the phrase “only upon” Postel’s termination expresses when the
5
conditional assignment would take effect; it does not limit assignment to Archer only in
6
the event of Postel’s default.
7
TEC argues that because paragraph 8.8 does not expressly authorize assignment
8
to Archer under any other circumstances, and because the Postel Subcontract was
9
incorporated into the TEC Subcontract, Archer and Postel promised that the TEC
10
Subcontract would not be assigned other than upon Postel’s termination for default. To
11
support this argument, TEC offers a construction of paragraph 24.5 of the TEC
12
Subcontract that is contrary to its plain meaning. Paragraph 24.5 of the TEC Subcontract
13
states as follows:
14
15
This Subcontract shall not be subcontracted or assigned in whole or in part
by the subcontractor [TEC] except with the written consent of the Company
[Postel]. Any attempt to effectuate a subcontract or an assignment shall be
null and void ab initio.
16
17
(Dkt. no 88-5 ¶ 24.5.) TEC argues that the second sentence in paragraph 24.5 restricts
18
all assignments, whether from TEC or Postel. TEC’s construction, however, ignores the
19
first sentence, which restricts only assignments by TEC. The second sentence must be
20
read in context of the entire paragraph. Viewed as a whole, the first sentence restricts
21
TEC from assigning the TEC Subcontract without Postel’s written consent, while the
22
second sentence addresses the effect of an assignment by TEC without Postel’s
23
consent (i.e., the assignment would be void). Moreover, under TEC’s construction, TEC
24
may assign with Postel’s consent, but Postel may not assign at all. Paragraph 24.5 does
25
not support this broad construction. “To be effective, an anti-assignment clause should
26
contain a specific prohibition on the power to make an assignment and specifically state
27
that any attempted assignments will be void or invalid.” Easton, 230 P.3d at 830 (quoting
28
29 Richard A. Lord, Williston on Contracts § 74:22 (4th ed. 2003)) (alterations and
14
1
internal quotation marks omitted). The assignment clause in paragraph 24.5 contains no
2
express prohibition on Postel’s power to make an assignment. Because the TEC
3
Subcontract does not expressly prohibit assignment by Postel, Postel may assign it to
4
Archer. See id.
In sum, the Court finds that the Assignment is valid. TEC’s motion requesting that
5
6
the Court find the Assignment to be invalid (dkt. no. 152) is denied.
2.
7
Effect
8
Archer raises the issue of the effect of the Assignment in three motions. In the
9
motion against TEC, Archer argues that TEC’s two contract-based claims are legally
10
tenuous because Archer had no contractual relationship with TEC before March 1, 2012,
11
the effective date of the Assignment. (Dkt. no. 161.) In a motion against Postel (dkt. no.
12
159), Archer argues that Postel owes a duty to indemnify Archer for any conduct that
13
occurred before the effective date of the Assignment. In another motion against Postel
14
(dkt. no. 160), Archer seeks partial summary judgment on Postel’s third and fourth
15
claims for breach of contract relating to the Assignment. The Court agrees with Archer in
16
part.
17
In arguing that the Assignment is valid, Archer acknowledges the general rule that
18
an assignment is invalid if it “materially changes the terms of the contract.” Easton, 230
19
P.3d at 830. But Archer seeks to impose the terms of the Assignment to limit TEC’s
20
rights under the TEC Subcontract.11 Archer ignores the effect of an assignment of a
21
contractual right.
22
An assignment “is a separate agreement between the assignor and assignee
23
which merely transfers the assignor’s contract rights, leaving them in full force and effect
24
as to the party charged.” Easton, 230 P.3d at 831 (quoting Citibank, N.A. v.
25
Tele/Resources, Inc., 724 F.2d 266, 269) (2d Cir. 1983)). Archer in fact cites to this
26
27
28
11
TEC does not contend that the Assignment results in any material changes in
the terms of the TEC Subcontract.
15
1
same language in its brief. (Dkt. no. 190 at 11.) However, Archer then seeks to import
2
the terms of the Assignment into the TEC Subcontract, which would change the terms of
3
the TEC Subcontract. Archer cannot have it both ways.12
4
The Assignment unambiguously expresses the rights assigned: Postel “hereby
5
assigns, transfers and sets over to Archer Western Contractors, LLC (“Assignee”) all
6
rights, title and interest held by the Assignor [Postel] in and to the following described
7
contract: [TEC Subcontract].” (Dkt. no. 96-11 at 2.) The Assignment thus puts Archer in
8
the place and stead of Postel under the TEC Subcontract. See Citibank, 724 F.3d at 269
9
(citing 3 Williston on Contracts § 432, at 182 (3d ed.)) (“Insofar as an assignment
10
touches on the obligations of the other party to the underlying contract, the assignee
11
simply moves into the shoes of the assignor.”)
12
Archer argues that the Assignment contains an additional paragraph delineating
13
what Archer and Postel agree to be the scope of the Assignment. True enough. This
14
paragraph, however, identifies the parties’ assumptions, not the assignment — Archer
15
“assumes and agrees” to “perform all remaining and executory obligations of” Postel and
16
to “indemnify and hold the Assignor [Postel] harmless from any claim or demand
17
resulting from non-performance by the Assignee from the date of this Assignment
18
forward.” (Dkt. no. 96-11 at 2.) This paragraph contains a reciprocal agreement from
19
Postel to assume and agree to remain responsible for contractual obligations existing
20
before the date of the Assignment and to indemnify and hold Archer harmless. (Id.)
21
According to Archer, this paragraph limits its liability to TEC under the TEC Subcontract
22
to conduct that occurred before the Assignment. The paragraph does limit liability, but
23
only between Archer and Postel in that it allocates these two parties’ respective
24
responsibilities and assumptions of liabilities. It does not limit or modify the obligations
25
26
27
28
12
Archer is not alone. TEC claims it is undisputed that TEC did not have any
privity of contract with Archer. (Dkt. no. 182 at 11.) Yet, TEC asserts two contract-based
claims against Archer premised on the TEC Subcontract and opposes dismissal of these
claims. (See dkt. nos. 48, 189.)
16
1
under the TEC Subcontract, and Archer cannot seek to import this paragraph to the TEC
2
Subcontract.13
3
Because the Assignment puts Archer in the place and stead of Postel under the
4
TEC Subcontract, TEC can assert its two contract-based claims against Archer. Archer’s
5
motion for summary judgment on TEC’s first and second claims for relief (dkt. no. 161) is
6
therefore denied. The Court agrees with Archer that the existence of a contractual
7
relationship between the parties renders the unjust enrichment claim unavailable. 14 See
8
Leasepartners Corp. v. Robert L. Brooks Trust Dated Nov. 12, 1975, 942 P.2d 182, 187
9
(Nev. 1997) (citing 66 Am. Jur. 2d Restitution § 6 (1973) (“An action based on a theory of
10
unjust enrichment is not available when there is an express, written contract, because no
11
agreement can be implied when there is an express agreement.”)). Archer’s motion for
12
partial summary judgment on TEC’s third claim for unjust enrichment (dkt. no. 162) is
13
granted.
14
In its motion against Postel, Archer seeks summary judgment on its third claim for
15
contractual indemnity under the Assignment. (Dkt. no. 159.) TEC’s claims are premised
16
on events that allegedly occurred before TEC demobilized from the Project, including the
17
alleged failure to pay TEC for work performed under the TEC Subcontract. (Dkt. no. 48.)
18
TEC demobilized from the Project on February 29, 2012 (supra note 7), before the
19
effective date of the Assignment (March 1, 2012). As discussed above, the Assignment
20
expressly delineated Archer and Postel’s respective rights and liabilities. Postel assumed
21
liabilities for “all obligations, responsibilities and liabilities of Assignor [Postel] under the
22
Contract existing prior to the date of this Agreement and agrees to indemnify and hold
23
24
25
26
27
28
13
In fact, if the paragraph does modify liability under the TEC Subcontract, then
the Assignment is not valid. See Easton, 230 P.3d at 830 (an assignment is invalid if it
makes material changes to the underlying contract).
14
Postel did not raise this argument in seeking summary judgment against TEC.
Postel argues that TEC’s unjust enrichment claim fails because Postel did not receive
any money on behalf of TEC. (Dkt. no. 154 at 22.) In response, TEC claims that it
provided extra work at Postel’s request that benefited Postel and for which Postel did not
bill Archer. (Dkt. no. 192 at 31-32.)
17
1
the Assignee [Archer] harmless from any claim or demand resulting or arising from such
2
pre-existing liabilities.” (Dkt. no. 96-11 at 2.) As alleged, TEC’s claims existed before the
3
Assignment and thus fall within Postel’s responsibilities and liabilities under the TEC
4
Subcontract. Postel assumed and agreed to indemnify Archer for these liabilities.
5
Archer’s motion (dkt. no. 159) with respect to Postel’s indemnification obligations under
6
the Assignment is granted.
7
Archer’s motion (dkt. no. 159) with respect to Postel’s indemnification duty under
8
paragraph 9.3 of the Postel Subconstract is also granted.15 Paragraph 9.3 of the Postel
9
Subcontract requires Postel to indemnify Archer from claims “arising out of or resulting
10
from Subcontractor’s actual or alleged failure to perform under this Agreement in
11
accordance with the terms of this Agreement and the Contract Documents.” (Dkt. no. 96-
12
4.) TEC’s claims raise questions as to Postel’s performance on the Project and fall within
13
paragraph 9.3’s ambit. Postel thus has a duty to indemnify Archer under paragraph 9.3
14
of the Postel Subcontract. This finding also resolves a related motion — Archer’s motion
15
to strike or disregard the affidavit of Danny Lucas (dkt. no. 201) — which the Court
16
denies as moot.
17
The Court’s findings regarding Archer and Postel’s allocation of liability under the
18
Assignment also resolve Archer’s motion for partial summary judgment on Postel’s third
19
and fourth claims in Archer’s favor. (Dkt. no. 160.) It was Postel, not Archer, who
20
assumed liabilities under the TEC Subcontract that existed before the date of the
21
Assignment. (Dkt. no. 96-11 at 2.) The Assignment does not support Postel’s third claim
22
for contractual indemnity under the Assignment. Nor does it support Postel’s fourth claim
23
for breach of contract. The gist of Postel’s argument is that in the Assignment, Archer
24
represented that it paid TEC $54,645.30 for money owed to TEC, such that TEC’s claim
25
26
27
28
15
Archer also references paragraph 9.1 of the Postel Subcontract, but that
paragraph addresses liabilities resulting from “bodily injury, sickness, disease or death,
or to injury to or destruction of tangible property.” (Dkt. no. 96-4 ¶ 9.1.) Archer
characterizes TEC’s claims as relating to labor and equipment provided to Postel before
March 1, 2012, not injury to person or property. (Dkt. no. 159 at 10.)
18
1
that it is owed more payments means that Archer breached the Assignment. But there is
2
no dispute that Archer paid TEC the amount identified in the Assignment. For these
3
reasons, Archer’s motion for partial summary judgment (dkt. no. 160) is granted.
4
VII.
CONCLUSION
5
The Court notes that the parties made several arguments and cited to several
6
cases not discussed above. The Court has reviewed these arguments and cases and
7
determines that they do not warrant discussion as they do not affect the outcome of the
8
parties’ motions.
9
10
It is therefore ordered that TEC’s motion for clarification and/or reconsideration
(dkt. no. 218) is granted in part and denied in part as stated herein.
11
It is ordered that the following motions are granted: (1) TEC’s motion for partial
12
summary judgment against Archer relating to their contractual relationship (dkt. no. 153);
13
(2) Archer’s motion for partial summary judgment on its third crossclaim for
14
indemnification against Postel (dkt. no. 159); (3) Archer’s motion for partial summary
15
judgment on Postel’s third and fourth crossclaims (dkt. no. 160); (4) Archer’s motion for
16
partial summary judgment on plaintiff’s third claim for unjust enrichment (dkt. no. 162);
17
(5) Traveler’s motion for summary judgment (dkt. no. 158).
18
It is further ordered that the following motions are denied: (1) TEC’s motion for
19
summary judgment on its counterclaim relating to Postel’s abandonment (dkt. no. 151);
20
(2) TEC’s motion for summary judgment against Archer relating to invalidity of the
21
Assignment (dkt. no. 152); (3) Postel’s motion for summary judgment against TEC (dkt.
22
no. 154); (4) Archer’s motion for summary judgment on TEC’s first and second claims
23
(dkt. no. 161); (5) Archer’s motion for partial summary judgment on its first counterclaim
24
against TEC (dkt. no. 163); and (6) Archer’s motion to strike or disregard the affidavit of
25
Danny Lucas (dkt. no. 201).
26
DATED THIS 4th day of March 2015.
27
MIRANDA M. DU
UNITED STATES DISTRICT JUDGE
28
19
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?