Fidelity and Deposit Company of Maryland v. Big Town Mechanical, LLC et al

Filing 152

ORDER DENYING 89 Motion for Partial Summary Judgment. IT IS FURTHER ORDERED that the deadline for the parties to file motions for summary judgment is extended until 45 days from the filing of this order. Signed by Judge Jennifer A. Dorsey on 3/23/2017. (Copies have been distributed pursuant to the NEF - DC)

Download PDF
1 2 UNITED STATES DISTRICT COURT 3 DISTRICT OF NEVADA 4 5 FIDELITY AND DEPOSIT COMPANY OF MARYLAND, a Maryland corporation, 6 2:13-cv-00380-JAD-GWF Order Denying Defendants’ Motion for Partial Summary Judgment Plaintiff 7 v. [ECF No. 89] 8 9 10 11 BIG TOWN MECHANICAL, LLC, a Nevada limited liability company; TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA, a Connecticut corporation; DOES I through X; and ROE CORPORATIONS I-X; inclusive, 12 Defendants 13 14 This case is a battle between two sureties over who should foot the bill for a project that 15 ended up costing more than anyone expected. Clark County School District hired defendant Big 16 Town Mechanical, LLC to modernize the heaters and air conditioners in several Clark County 17 elementary schools.1 The district required Big Town to purchase a bond guaranteeing that it would 18 finish the job; Big Town bought that bond from defendant Travelers Casualty and Surety Company 19 of America. 20 Big Town then got to work—or rather, it hired subcontractor F.A.S.T. Systems to do the 21 work. Big Town, like the district, wanted a bond from F.A.S.T. guaranteeing that it would complete 22 the project. F.A.S.T. bought its bond from plaintiff Fidelity and Deposit Company of Maryland. 23 Thus: Travelers promised the district that Big Town would finish the repairs; Fidelity promised Big 24 Town that F.A.S.T. would finish the repairs. 25 26 The project ended up being tougher than expected, and F.A.S.T. fell through. So Fidelity took the project over and spent significant funds attempting to complete it. But Fidelity’s 27 28 1 ECF No. 1 at ¶ 6. Page 1 of 5 1 subcontractors, too, failed, so Travelers stepped in and hired new contractors, spent more money, and 2 completed the job to the district’s specifications.2 All in all, everyone spent more on the repairs than 3 they expected. 4 Fidelity sues Big Town and Travelers, seeking to be reimbursed for the money it spent trying 5 to finish the project. Travelers counterclaims, arguing that Fidelity must cover the whole bill 6 because it did shoddy work in the first place. Among other things, Fidelity defends against these 7 counterclaims by arguing that its bond with Big Town caps its potential liability in this case. 8 Travelers now brings a motion for partial summary judgment, seeking a ruling that if Fidelity is 9 eventually found liable on some theory, the set sum in its bond will not cap its liability. I deny 10 Traveler’s motion because it is premature. 11 Discussion 12 Generally, a surety on a performance bond promises that another party will complete some 13 performance—and that if they do not, the surety will pay up to a sum-certain amount to cover that 14 default (the penal sum).3 Here, Fidelity promised Big Town (and now Travelers, standing in its 15 shoes) that F.A.S.T. would complete the school repairs, and that if it did not, Fidelity would cover 16 the losses caused by F.A.S.T.’s default (up to a set sum).4 17 But some courts treat this process differently when, instead of acting as a passive bankroll for 18 losses caused by a default, the surety elects to take over for the defaulting party and complete the 19 performance itself.5 The advantage to the surety is that it can try to keep costs low so that it does not 20 21 2 I find these motions suitable for disposition without oral argument. Nev. L.R. 78-1. 22 3 Archer W. Contractors, LLC v. Int’l Fid. Ins. Co., 2017 WL 882401, at *3 (S.D. Cal. Mar. 6, 2017). 23 24 25 26 27 28 4 The original project was broken up into several pieces, and the parties entered into multiple, identical bonds with varying penal sums. Because the bonds are all identical for relevant purposes, I treat them together for purposes of this order. 5 Caron v. Andrew, 284 P.2d 544, 549 (Cal. 1955); see also Vander Kley v. Acstar Ins. Co., 256 F. App’x 905, 906–07 (9th Cir. 2007) (holding that a surety takes on the obligations of its principal when it takes over its performance); Employers Mut. Cas. Co. v. United Fire & Cas. Co., 682 N.W.2d 452, 457 (Iowa Ct. App. 2004) (“When a surety assumes the performance of the contract, the surety becomes subrogated to the rights of the principal, and necessarily becomes subject to the Page 2 of 5 1 have to pay out the bond’s entire penal sum. On the other hand, the surety, now standing in the 2 shoes of its principal, may have opened itself to the various liabilities its principal faced in 3 performing under its original contract: 4 Upon breach by the principal, the surety is, unless otherwise specifically provided in the contract, free to rest upon the contract of suretyship and if it does it cannot be held beyond the limit of its bond and it may invoke any defense open to it as surety. If, however, upon breach by the principal it elects to . . . step into the place of its principal and perform that principal’s contract, it then makes itself subject to the principal’s liabilities.6 5 6 7 8 And in the event that the surety uses up all the money in the bond and still fails to complete 9 performance, it may open itself to another sort of claim: breach of the bond itself.7 Parties to a bond 10 can sue for breach of that bond, just like any other contract. The beneficiary can claim that the surety 11 improperly used the bond’s funds—or, in other words, that the beneficiary would have used that 12 money more wisely to accomplish more.8 13 But although Fidelity is not wholly shielded by its bond from any potential liability, I cannot 14 give Travelers the answer that it seeks because the nature of its claims is not yet sufficiently 15 developed. To the extent that Travelers argues that Fidelity cannot have any protection under the 16 bond because it opted to do some work on the project, that position is not supported either by 17 authority or the bond’s language.9 Both parties make much out of language in the bond, but its terms 18 19 principal’s liabilities.”); Federal Sur. Co. v. Lalonde, 31 F.2d 673, 674 (9th Cir. 1929) (finding surety who took over work from contractor may be liable in excess of penalty bond). 20 6 21 Id. 7 22 23 24 25 26 27 28 Penick-Nordic, JV v. Interstate Plumbing & Air Conditioning, LP, 2013 WL 12114012, at *5 (C.D. Cal. June 6, 2013). 8 For example, Travelers might establish that Fidelity cannot offset the bond’s penal sum with its unreasonable expenses—and thus that although the bond’s penal sum still applies, Fidelity is still liable for the entire bond amount. I simply cannot say at this juncture. 9 None of Travelers’ cases hold that the bond’s penal sum is totally nullified because the surety elected to start performing for the principal, they just hold that the surety can become liable under the principal’s original contract. See E. Quincy Servs. Dist. v. Gen. Accident Ins. Co. of Am., 88 Cal. App. 4th 239, 244 (Cal. Ct. App.2001) (holding that once a surety elects to perform for its principle, it can be liable for breaching the principal’s contract); Caron, 284 P.2.d at 544 (same); Employers Page 3 of 5 1 shed no additional light in this murk. Bonds are governed by general contract principles.10 And the 2 bond’s plain language says only two relevant things: (1) if Big Town completed the performance on 3 its own, it could seek reimbursement from Fidelity up to the bond’s penal sum; and (2) if Fidelity 4 completed the performance on its own, it could seek reimbursement up to the price of the original 5 contract between Big Town and F.A.S.T..11 What the bond does not expressly say is what happens 6 when Fidelity either wastes the bond’s money or commits additional breaches of its own. 7 Depending on how this case proceeds, Fidelity’s liability may indeed by capped by its bond’s 8 penal sum. If Travelers ultimately seeks to be reimbursed under the bond, and it cannot show that 9 Fidelity breached the bond, the cap might apply. If Travelers fails to establish that Fidelity 10 committed any other breach—and it turns out that the project was simply more expensive than 11 anyone expected—it may be that the bond’s penal sum applies because both parties are entitled to 12 offsets for the work they did. On the other hand, if Travelers establishes that Fidelity independently 13 breached the bond or that it breached F.A.S.T.’s contract—the cap might not apply. The uncertainty 14 created by these alternative scenarios is compounded by the fact that when Travelers filed this 15 motion discovery was still ongoing, leaving significant gaps in the record.12 16 Travelers’ motion effectively asks me for an advisory opinion: will Fidelity be shielded by 17 its bond’s penal sum in any of several alternative circumstances that may or may not come to pass in 18 this case? The federal courts are not empowered to issue advisory opinions and I decline to guess at 19 this hypothetical.13 If Travelers succeeds on some claims, the cap might not apply; if it succeeds on 20 others, it may. That determination will turn on the nature of the claims Travelers succeeds on, and 21 22 23 Mut. Cas. Co., 682 N.W.2d at 457 (holding that surety became potentially liable under its principal’s contract once it took over contract). 24 10 Union Indem. Co. v. Lang, 71 F.2d 901, 906 (9th Cir. 1934). 25 11 ECF No. 1 at ¶ 11. 26 12 27 Indeed, Fidelity argues that Traveler’s motion should be denied under Fed. R. Civ. P. 56(d) (and attaches a supporting declaration) because of these outstanding factual questions. I agree. 28 13 F.C.C. v. Pacifica Found., 438 U.S. 726, 735 (1978). Page 4 of 5 1 precisely how it frames those claims as this case proceeds. The parties and I will benefit from 2 briefing that takes into account any new factual developments during the last year of discovery. 3 4 5 6 7 8 Conclusion Accordingly, IT IS HEREBY ORDERED, ADJUDGED, AND DECREED that defendants’ motion for partial summary judgment (ECF No. 89) is DENIED. IT IS FURTHER ORDERED that the deadline for the parties to file motions for summary judgment is extended until 45 days from the filing of this order. Dated this 23rd day of March, 2017. 9 10 11 _________________________________ Jennifer A. Dorsey United States District Judge 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Page 5 of 5

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?