Fidelity and Deposit Company of Maryland v. Big Town Mechanical, LLC et al

Filing 354

ORDER that 327 Travelers's Motion for Partial Summary Judgment is GRANTED in part and DENIED in part. Summary judgment is granted on the narrow issues that the subcontracts signed on August 30, 2010, govern, and FAST breached these subcontr acts by missing the project-completion dates. But summary judgment is denied as to Travelers's claim that Fidelity subsequently breached the subcontracts and performance bonds by not completing the commissioning process.FURTHER ORDERED that 287 Fidelity's Motion for Partial Summary Judgment on reimbursement-related damages is DENIED.FURTHER ORDERED that 329 Fidelity's Motion for Partial Summary Judgment is DENIED. FURTHER ORDERED that this case is REFERRED to a magis trate judge for a MANDATORY SETTLEMENT CONFERENCE. The parties' obligation to file their joint pretrial order is STAYED until 10 days after that settlement conference. Signed by Judge Jennifer A. Dorsey on 9/21/2018. (Copies have been distributed pursuant to the NEF - MMM)

Download PDF
1 UNITED STATES DISTRICT COURT 2 DISTRICT OF NEVADA 3 Fidelity and Deposit Company of Maryland, 4 Plaintiff 5 v. 6 Travelers Casualty and Surety Company of America, et al., 7 Defendants 8 And all related matters. Case No.: 2:13-cv-00380-JAD-GWF Order Granting in Part & Denying in Part Travelers’s Motion for Partial Summary Judgment; Denying Fidelity’s Motion for Partial Summary Judgment on Reimbursement-Related Damages & Final Motion for Partial Summary Judgment [ECF Nos. 287, 327, 329] 9 10 This surety coverage dispute involves two tiers of contracts, bonds, sureties, and 11 principals, and the consequences that resulted when the lower-tier principal defaulted. Travelers 12 Casualty and Surety Company of America issued surety bonds for the prime contractor that 13 Clark County School District (CCSD) hired to modernize the heating, ventilation, and air 14 conditioning (HVAC) systems at five of its schools. Fidelity and Deposit Company of Maryland 15 issued surety bonds for a subcontractor. When that subcontractor defaulted, Fidelity attempted 16 to complete the project, but it too failed to deliver functioning systems. CCSD eventually 17 declared the prime contractor in default, prompting Travelers to step in and successfully 18 complete the projects, albeit several years behind schedule. 19 After Travelers refused to pay Fidelity for its work, Fidelity sued Travelers and the prime 20 contractor. Meanwhile, Travelers settled a separate lawsuit with CCSD for the liquated damages 21 that resulted from the project delays. Travelers then counterclaimed against Fidelity in this case, 22 seeking reimbursement for the damages it paid to CCSD and its cost of completing the projects. 23 Fidelity and Travelers both move for partial summary judgment: Travelers seeks to establish Fidelity’s liability under the subcontracts, while Fidelity advances numerous defenses 1 to Travelers’s claims. I find that there is no genuine dispute of material fact that the original 2 subcontractor breached its subcontracts with the prime contractor. But on the record before me, I 3 cannot conclude that Fidelity separately breached these subcontracts after it took over 4 performance, so I grant in part and deny in part Travelers’s motion. And because I also conclude 5 that Fidelity’s defenses are without merit, I deny its two motions. 6 Background 7 In 2010, CCSD hired Big Town Mechanical as the prime contractor for the HVAC 8 modernization at the five schools at issue. Big Town and Travelers entered into a series of 9 performance bonds in which Travelers (the surety) promised CCSD (as obligee) that it would 10 complete the work on each school if Big Town (the principal) defaulted.1 Under a General 11 Indemnity Agreement (GAI) between Travelers and Big Town, a default would require Big 12 Town to assign its rights under the contracts and subcontracts to Travelers.2 13 Big Town hired subcontractor F.A.S.T. Systems—a non-party in this action—to complete 14 the low-voltage work for the five schools, which primarily included installing the HVAC 15 automation systems.3 In August 2010, the two companies formed subcontracts that set 16 completion dates for FAST’s work at each school.4 These dates ranged from October 2010 to 17 the end of December 2011. Big Town, like CCSD, also required FAST to acquire performance 18 bonds for each school. FAST bought its bonds from Fidelity, which promised Big Town that it 19 would complete FAST’s scope of work if the subcontractor defaulted. 20 21 1 22 2 ECF No. 47-2. 3 ECF No. 287 ¶ 2; see, e.g., ECF 288-1 at 36–40. 4 ECF Nos. 288-1, 288-2, 288-3, 289-1, 289-2. 23 ECF No. 319-1. Travelers issued performance bonds for each of the five schools, and each bond contains materially identical terms. Id. 2 1 This agreement was soon put to the test. By mid-November 2011, FAST was well past 2 the deadlines for four of the schools and had not completed their installations—or had at least 3 failed to provide functioning automated systems. Big Town therefore fired FAST from all five 4 schools5 and demanded that Fidelity step in as the surety under the performance bond for FAST. 5 As I’ve explained in my prior orders, a surety in Fidelity’s position has two options: pay for the 6 contract damages caused by the defaulting principal—in this case FAST—or hire its own 7 subcontractor to complete the work and thereby (ideally) minimize costs.6 Fidelity opted for the 8 latter avenue, hiring Perini as its subcontractor in December 2011. Perini then hired its own 9 subcontractors and got to work.7 The following month, Fidelity asserted to Big Town that it was 10 entitled to the remaining subcontract funds, but Big Town responded that it would not issue any 11 progress payments.8 Fidelity’s subcontractors nonetheless continued to work. 12 In May 2012, Perini informed Big Town that it had “substantially completed” all of 13 FAST’s work at the five schools and it therefore intended to leave the job sites in the next few 14 weeks.9 Shortly after, Perini also informed Big Town that it was commencing the one-year 15 warranty period for its work.10 Big Town did not object to either notice. That August, Perini 16 submitted invoices to Big Town, but Big Town never remitted payment or otherwise responded. 17 Fidelity consequently filed suit against Big Town and Travelers in early 2013.11 18 19 5 ECF No. 289-7. 6 E.g., Fid. & Deposit Co. of Maryland v. Big Town Mech., LLC, No. 2:13-CV-00380-JAD20 GWF, 2017 WL 1102725, at *1 (D. Nev. Mar. 23, 2017). 7 None of the subcontractors that Fidelity hired is a party to this action. 8 22 ECF No. 330-3 at 36–37; ECF 322-3 ¶ 8. 9 ECF No. 330-3 at 75. 23 10 ECF No. 330-2 at 83. 11 ECF No. 1. 21 3 1 Around the same time, Big Town was attempting to receive its final payment from 2 CCSD. In May 2013, CCSD rejected that payment application, summarily asserting that the 3 project was not yet complete.12 Big Town filed for bankruptcy two weeks later. On May 22, 4 CCSD notified Travelers that it considered Big Town in default under the prime contracts.13 5 CCSD also claimed that there were “significant defects and deficiencies in the work, including 6 roof leaks at several schools and a general failure of HVAC control systems.”14 In turn, CCSD 7 “demand[ed] that Travelers immediately take action” under the performance bonds between 8 Travelers and Big Town.15 The following month, CCSD filed suit against Travelers, alleging 9 that Travelers had “refuse[d] to proceed with [its] duties” and seeking to compel specific 10 performance.16 CCSD also sought to recover over $11 million in liquidated damages.17 11 While the suit was ongoing, Big Town put out a request in September 2013 for bids from 12 subcontractors to complete the HVAC projects.18 In December, CCSD and Travelers formed a 13 “takeover agreement,” in which Travelers agreed to complete the unfinished work under the 14 original contracts with Big Town.19 On the same day, Travelers hired Sletten Construction as its 15 contractor,20 and Sletten began working the following month.21 16 17 12 ECF No. 330-5 at 44. 13 Id. at 114. 14 Id. 15 Id. at 115. 16 Id. at 138, ¶¶ 41, 45–51. 17 Id. at 171. 18 22 ECF No. 330-6 at 11–13. 19 Id. at 18–26. 23 20 Id. at 28–55 21 Id. at 95–98. 18 19 20 21 4 1 In February 2014, Travelers wrote to Fidelity, asserting (without detail) that Fidelity had 2 failed to complete FAST’s work on each of the five schools.22 Travelers demanded that Fidelity 3 resume its work. This was the first notice that Fidelity received that its work was unsatisfactory 4 since its subcontractors left the job sites in June 2012. It is unclear if Fidelity ever responded. 5 Meanwhile, Travelers had also engaged the firm MEP Consulting to help evaluate why 6 the automation and control systems were not functioning. MEP issued a report critical of the 7 HVAC building controllers that FAST had installed23 and which CCSD had pre-approved. 8 Sletten eventually replaced these controllers with a different brand24 and also replaced the wiring 9 that FAST had installed and which (as discussed in more detail below) was later determined to 10 be improper.25 Sletten completed work on the schools throughout 2014, and each school passed 11 the commissioning process that verified its HVAC system was functional and complied with 12 CCSD’s specifications. Travelers eventually settled CCSD’s suit against it for $5 million.26 Through its 13 14 counterclaim in this action, Travelers seeks reimbursement from Fidelity for this amount and the 15 over $1 million that it expended to complete the HVAC projects.27 16 Summary-judgment standard 17 Summary judgment is appropriate when the pleadings and admissible evidence “show 18 there is no genuine issue as to any material fact and that the movant is entitled to judgment as a 19 20 22 Id. at 111–21. 23 ECF No. 330-7 at 40–41. 24 22 Id. at 101–05. 25 ECF No. 261-1 at 14–15. 23 26 ECF No. 330-5 at 3. 27 ECF No. 319 ¶¶ 33–34. 21 5 1 matter of law.”28 When considering summary judgment, the court views all facts and draws all 2 inferences in the light most favorable to the nonmoving party.29 If reasonable minds could differ 3 on material facts, summary judgment is inappropriate because its purpose is to avoid unnecessary 4 trials when the facts are undisputed, and the case must then proceed to the trier of fact.30 5 If the moving party satisfies Rule 56 by demonstrating the absence of any genuine issue 6 of material fact, the burden shifts to the party resisting summary judgment to “set forth specific 7 facts showing that there is a genuine issue for trial.”31 The nonmoving party “must do more than 8 simply show that there is some metaphysical doubt as to the material facts”; it “must produce 9 specific evidence, through affidavits or admissible discovery material, to show that” there is a 10 sufficient evidentiary basis on which a reasonable fact finder could find in his favor.32 11 Discussion 12 Each of the three pending motions for partial summary judgment addresses only 13 Travelers’s counterclaims. Travelers’s motion seeks to establish that FAST and Fidelity— 14 through the actions taken while standing in FAST’s shoes—breached the subcontracts,33 and 15 Fidelity’s two motions raise defenses to liability. Fidelity first contends that Big Town 16 contributed to the delays in completing the HVAC work and that Travelers—standing in Big 17 18 19 20 28 See Celotex Corp. v. Catrett, 477 U.S. 317, 330 (1986) (citing FED. R. CIV. P. 56(c)). 29 Kaiser Cement Corp. v. Fishbach & Moore, Inc., 793 F.2d 1100, 1103 (9th Cir. 1986). 30 Warren v. City of Carlsbad, 58 F.3d 439, 441 (9th Cir. 1995); see also Nw. Motorcycle Ass’n 21 v. U.S. Dep’t of Agric., 18 F.3d 1468, 1471 (9th Cir. 1994). 22 31 Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 256 (1986); Celotex, 477 U.S. at 323. 32 Bank of Am. v. Orr, 285 F.3d 764, 783 (9th Cir. 2002) (internal citations omitted); Bhan v. 23 NME Hosps., Inc., 929 F.2d 1404, 1409 (9th Cir. 1991); Anderson, 477 U.S. at 248–49. 33 ECF No. 327. 6 1 Town’s shoes—therefore cannot establish that FAST caused the liquated damages to accrue.34 2 Fidelity then raises a hodgepodge of other defenses, including equity and the Spearin doctrine.35 3 I address breach before moving to Fidelity’s defenses. 4 I. 5 FAST breached the subcontracts by missing the project deadlines, but I cannot determine on summary judgment whether Fidelity also caused a subsequent breach. 6 Travelers moves for a variety of rulings supporting its counterclaims against Fidelity. As 7 a threshold matter, it seeks to establish that the subcontracts signed by FAST and Big Town 8 governed their relationship. Travelers then aims to establish that FAST and Fidelity breached 9 these subcontracts by (1) failing to complete the HVAC projects by their deadlines and (2) 10 leaving the projects before completing the commissioning process. Travelers also argues that the 11 purported failure to complete commissioning breached Fidelity’s performance bond and 12 prevented Perini’s warranties from coming into effect. I address these issues in turn. 13 A. The subcontracts signed on August 30, 2010, govern. 14 The parties dispute which agreements govern: the five subcontracts that FAST and Big 15 Town executed or a set of documents that are each titled “Addendum to Subcontract 16 Agreement.” Because both sets of agreements purport to be the complete and final contract 17 between the two contractors, the answer turns on which set was signed last. I therefore turn to 18 the sequence of events that Travelers proffers and will highlight where the dispute of fact arises. During the summer of 2010, Big Town sent FAST five proposed subcontracts—one per 19 20 school—after selecting FAST as its subcontractor under its prime contract with CCSD.36 The 21 22 34 ECF No. 287. 23 35 ECF No. 329. 36 See ECF No. 327 at 6. 7 1 subcontracts are materially identical but each sets a different completion date for its respective 2 school.37 The subcontracts explicitly incorporate the terms of the prime contract, including all of 3 its attachments, and state that the intent of the agreement was to “result in a complete and 4 functional system in full compliance with the Subcontract . . . .” 38 Each subcontract specifies 5 that “[t]ime is of the essence” and notifies FAST that it would be liable to Big Town for any 6 liquidated damages that CCSD assessed that were the result of FAST’s delays.39 The “Scope of 7 Work” section for each subcontract states that FAST’s work would “include but not be limited 8 to” the proposal that FAST submitted in its bid for each school.40 Each corresponding proposal 9 varied slightly but generally specified the hardware that FAST would install.41 All the 10 subcontracts also contain an integration clause specifying that the agreement “supersede[d] all 11 prior negotiations, representations, or agreements, whether written or oral . . . .”42 12 According to Travelers, FAST requested several changes to the proposed subcontracts 13 and, rather than executing them, submitted its own proposed agreements. Each document was 14 styled as an “addendum” but operated as a standalone agreement: “[Big Town] and FAST have 15 agreed that this document and the Prime Contract between CCSD and [Big Town], and the 16 Proposal submitted by FAST, and [Big Town’s] acceptance of the Proposal constitutes the 17 Parties’ Subcontract Agreement.”43 Thus, under the addendums, the subcontracts that Big Town 18 19 37 ECF Nos. 161-1–161-5. 38 E.g., ECF No. 161-2 at 3. 39 E.g., id. at 6. 40 22 E.g., id. at 13. 41 E.g., ECF No. 288-1 at 36–40. 23 42 E.g., ECF No. 161-2 at 11. 43 E.g., ECF No. 288-2 at 34. 20 21 8 1 drafted would not constitute any part of the agreement between itself and FAST. Big Town 2 initially agreed to FAST’s request and both parties signed the addendums, each of which had a 3 typed date of August 20, 2010.44 4 On August 25, however, Big Town sent FAST a letter “in response to [FAST’s] request 5 for changes to the subcontract between Big Town Mechanical and FAST Systems, Inc.”45 The 6 letter informed FAST that CCSD requires subcontractors for its projects to be bound to the prime 7 contract between CCSD and the prime contractor and that “[t]he contract between Big Town 8 Mechanical and FAST . . . is based entirely on the terms as detailed in the CCSD Master 9 Contract.”46 Big Town stated that it was therefore “unable to perform any changes to the 10 contract provisions and subsequently denies your request for sub-contract change.” The 11 following day, FAST’s CEO signed the original five subcontracts.47 Big Town then signed the 12 same subcontracts on August 30. 13 Travelers contends that, because the subcontracts contained integration clauses and were 14 the final documents signed, the addendums may not be used to interpret Big Town’s—and thus 15 Fidelity’s—scope of work under the subcontracts. Travelers relies on the parol-evidence rule, 16 which “generally bars extrinsic evidence regarding prior or contemporaneous agreements that 17 are contrary to the terms of an integrated contract.”48 Fidelity challenges the factual premise of 18 19 44 ECF No. 288-2 at 34; ECF No. 288-3 at 35; ECF No. 289-1 at 34; ECF No. 289-2 at 49. The th 20 year for one of the addendums was cut off and reads, “It is so agreed this 20 day of August, 201[.]” ECF No. 288-3 at 35. None of the parties, however, contends that any of the addendums 21 were signed after 2010. 45 E.g., ECF No. 288-2 at 33. 22 46 E.g., id. 23 47 E.g., id. at 2. 48 Khan v. Bakhsh, 306 P.3d 411, 413 (Nev. 2013) (emphasis added). 9 1 this argument, asserting that dates printed on the addendums (August 20, 2010) are typographical 2 errors and that the addendums were all signed at some point after the subcontracts were fully 3 executed on August 30.49 Accordingly, Fidelity is not relying on the addendums as extrinsic 4 evidence to interpret the subcontracts; rather, it is arguing that the addendums supersede the 5 subcontracts and are therefore the only agreements between FAST and Big Town. The parol6 evidence rule is therefore inapposite,50 and the order of execution must be determined. 7 Fidelity’s evidence that the date on the addendums is merely a typo consists almost 8 exclusively of the deposition testimony of Josh McConnico, FAST’s former CEO. Fidelity 9 argues that his testimony creates a genuine dispute of material fact about when the addendums 10 were signed. Travelers counters that, while McConnico initially stated that the addendums were 11 signed after the subcontracts,51 he later equivocated on this point: 12 15 [McConnico]. . . . I don’t know if this addendum was created on the 20th and signed on some other date, you know, beyond the 26th [of August 2010]. I would assume that it -- that would have been the case is that it would have been signed after the fact. Otherwise, why would [Big Town] sign it? I don’t -- I don’t know, sir. It’s my belief it was signed after the contract, not prior to the contract. 16 Q. And you base that belief based upon what, if you don’t know? 17 A. Just because I believe that we created it for a reason. And, yes, I signed the contract with the agreement that this is being signed, so I don’t believe that this was signed prior. I believe it was signed after. And I think that these -- that it’s either signed prior or on the same day. And you’re right. I probably went through, and I signed all that stuff and initialed it with the exceptence [sic] of this addendum. 13 14 18 19 20 21 22 49 ECF No. 333 at 18. 50 Khan, 306 P.3d at 413–14 (“Extrinsic or oral evidence, however, is admissible . . . to establish 23 a subsequent alteration of an agreement . . . .” (citation omitted)). 51 ECF No. 334 at 41. 10 1 Q. Do you have a specific recollection of doing that, sir, as you sit here today, or are you speculating based upon what you want to believe? 2 3 A. Well, I’m speculating based on, you know, what how we were going to move forward with these projects. And this was the way that we were going to be able to move forward with the projects.52 4 5 The only fact clear from this exchange is that McConnico did not recall when he signed the 6 addendums relative to the subcontracts. Indeed, he has never provided even an estimate of how 7 long after August 30, 2010, the addendums were purportedly executed. This is understandable 8 given that McConnico testified seven years after the fact, but his speculation and assumptions are 9 insufficient to raise a genuine dispute of material fact. 10 Nor am I persuaded by Fidelity’s attempts to draw inferences from the documents 11 exchanged between FAST and Big Town. Fidelity argues that it be would odd for the 12 addendums to be titled “Addendum to Subcontract Agreement” if they were not drafted to 13 modify the already-executed subcontracts. The word “addendum,” however, was a misnomer 14 regardless of when the two sets of agreements were signed; the term means “[s]omething to be 15 added . . . to a document,”53 but the addendums, if signed after the subcontracts, were replacing 16 them as the agreements between FAST and Big Town—not modifying them. Moreover, there is 17 no insight gained from the fact that Big Town did not explicitly reference the addendums in its 18 August 25 letters written “in response to [FAST’s] request for changes to the 19 20 52 Id. at 58–59. Travelers also argues that the testimony itself violates the parol-evidence rule because Fidelity proffers it to contradict the dates printed on the addendums: August 20, 2010. 21 This argument is wide of the mark because, “in an overwhelming number of jurisdictions, parol evidence is admissible to show that the actual date of execution of a contract is different from the 22 date stated on the contract face.” Fram Corp. v. Davis, 401 A.2d 1269, 1273 (R.I. 1979) (citing cases). And it is peculiar that Travelers attempts to apply the parol-evidence rule to the 23 addendums—agreements that it contends the subcontracts superseded. 53 Addendum, BLACK’S LAW DICTIONARY (10th ed. 2014). 11 1 subcontract[s] . . . .”54 Although it is possible that Big Town was not referring directly to the 2 addendums, Fidelity has failed to provide any alternate explanation. I therefore find that there is 3 no genuine dispute that the subcontracts were signed after the addendums and thus govern the 4 contractor-subcontractor relationship between Big Town and FAST. So, I next consider whether 5 FAST and Fidelity breached these subcontracts. 6 B. 7 There is no dispute that FAST failed to complete the HVAC projects by the deadlines FAST breached the subcontracts by missing the project-completion dates. 8 that the subcontracts set. Indeed, by the time Big Town terminated FAST in late 2011, four of 9 the schools were between five and fourteen months behind schedule.55 Travelers argues that 10 these completion dates were never modified because FAST also failed to seek extensions of 11 time, which were permitted under the subcontracts as FAST’s “exclusive remedy” in the event of 12 delay. 56 In order to obtain an extension, FAST had to submit written “change requests” to Big 13 Town.57 The subcontracts specify that FAST’s “failure to timely request an extension shall act 14 as a waiver of that claim.”58 15 Fidelity responds that its subcontractor, Perini, did request extensions but that Big Town 16 rejected them.59 It similarly contends that Big Town’s project manager instructed Fidelity’s and 17 18 54 E.g., ECF No. 288-2 at 33. 19 55 23 58 Id. at 7 (capitalization omitted). 59 ECF No. 333 at 30. Compare ECF No. 327 at 5 (listing the project completion dates), with ECF No. 289-7 (listing the termination dates). Fidelity argues that CCSD extended the contract-completion dates to 20 October 14, 2011. ECF No. 333 at 29 n.146. Travelers disagrees with this conclusion, but because FAST also failed to complete the projects by the alleged extension date, this dispute is 21 irrelevant to the question of breach. 56 See, e.g., ECF No. 288-2 at 7. 22 57 Id. at 8–9. 12 1 Perini’s representatives to stop submitting the change requests.60 But as Travelers correctly 2 highlights, Perini, not FAST, made these requests and did so after FAST had already missed the 3 project deadlines.61 These requests are therefore irrelevant to that particular breach of the 4 subcontracts. 5 Fidelity also contends that Big Town failed to maintain a project schedule and, in turn, 6 made it impossible for FAST and Fidelity to complete the projects on time. Fidelity cites to a 7 statement by Big Town’s project manager that the project schedules were “dead” since August 8 2011 and its manager’s refusal to provide Perini past project schedules.62 But this evidence 9 reflects only the fact that FAST was well behind schedule by late 2011; it provides no indication 10 that Big Town contributed to FAST’s delay. And whether Big Town was willing to provide the 11 outdated schedules to Perini says nothing about FAST’s missed deadlines. 12 Accordingly, the undisputed evidence establishes that FAST breached the five 13 subcontracts by missing the project deadlines. And because these subcontracts specified that 14 time was of the essence, this breach was material.63 15 C. 16 I cannot conclude that Fidelity breached its duties under the subcontracts or performance bonds in relation to the commissioning process. Travelers’s remaining arguments all pertain to its assertion that Fidelity and its 17 18 subcontractors failed to finish FAST’s scope of work because they left the projects without 19 20 60 21 61 See ECF No. 323-1 at 73–119. 62 ECF No. 286-3 at 7, 14. 22 23 ECF No. 323-1 at 122 (“I suggest everyone stop the delay nonsense, finish the work and get off the job. I can’t get anymore blunt or clearer than that.”). 63 Johnson v. Alexander, 134 Cal. Rptr. 101, 105 (Cal. Ct. App. 1976) (“Delay in performance is a material failure only if [t]ime is of the essence, i.e., if prompt performance is, by the express language of the contract or by its very nature, a vital matter.”). 13 1 completing the commissioning process. Although it is evident from the parties’ arguments that 2 “commissioning” refers to testing the HVAC systems to ensure that they function correctly, 3 neither side has elaborated on what this process entails. Travelers argues that the subcontracts 4 “included commissioning work,” but it provides block quotations of the subcontracts that make 5 no explicit reference to the term or to any form of testing.64 Travelers also cursorily cites to 6 documents called “Section 25 00 00 (Integrated Automation),” and “Section 25 08 00 7 (Commissioning of Integrated Automation).”65 The latter document enumerates “contractor 8 responsibilities,” including “[d]emonstrate system operation” and “[m]anipulate systems and 9 equipment to facilitate testing.”66 10 Although Section 25 08 00 sheds some light on the commissioning process, Travelers has 11 failed to explain what this document is and how it relates to the subcontracts. Travelers refers to 12 this section as a “specification,” which indicates that it is part of CCSD’s project specifications. 13 Indeed, a portion of the subcontracts that Travelers quotes refers to FAST furnishing its work in 14 accordance with the “Manufacturer Specifications . . . .”67 It therefore appears that the 15 subcontract may incorporate these specifications by reference. Nonetheless, it improper to make 16 multiple logical leaps in favor of the moving party at summary judgment. On this record, I 17 cannot find as a matter of law that Fidelity was bound to the requirements of Section 25 08 00.68 18 64 19 E.g., ECF No. 327 at 5–6. 65 ECF No. 328-7 at 6–37. 20 66 ECF No. 328-7 at 29. 67 ECF No. 327 at 5. Travelers also asserts that the term “‘Subcontract Documents’ was defined in the Subcontracts as including the Prime Contract and specifications,” ECF No. 327 at 6, but the provision Travelers appears to be referencing makes no direct reference to any form of 22 specifications. ECF No. 327 at 4. 21 23 68 Travelers contends that McConnico, FAST’s former CEO, acknowledged during his deposition that FAST’s scope of work included commissioning. But his testimony is unclear. McConnico testified that commissioning was part of FAST’s process “[a]s long as we’re on the 14 1 But even if Travelers did establish the link between the subcontracts and 2 Section 25 08 00, it has failed to provide sufficient facts to demonstrate that Fidelity breached its 3 obligations. Travelers merely cites to the fact that Fidelity’s team of subcontractors left the job 4 sites without completing the commissioning process after Perini issued its notice of substantial 5 completion in May 2012. It is unclear what steps Travelers expected Fidelity to take at that 6 point. Indeed, other subcontractors were working on different aspects of the projects, and 7 Travelers has argued that FAST (and thereby Fidelity) was only “responsible for the 8 commissioning process associated with FAST’s own work.”69 But was Travelers therefore 9 required to maintain a holding pattern until all work by all subcontractors was completed at the 10 five schools? Travelers’s bare-bones arguments on this point provide no insight, and I therefore 11 cannot conclude as a matter of law that Fidelity breached its duties under the subcontracts or 12 performance bonds in relation to the commissioning process. 13 Accordingly, I grant Travelers’s motion in part as to FAST’s failure to meet the project 14 deadlines, but I deny the motion as to Fidelity’s alleged failure to complete the commissioning 15 process. I therefore need not—and do not—address the performance-bond and warranty arguments 16 related to commissioning. 17 18 19 20 21 job to do it.” ECF No. 328-7 at 4. He also answered affirmatively the question of whether he testified earlier that Section 25 00 00 was “a portion of the specification that related to FAST’s 22 scope of work on” one of the five elementary schools. Id. (emphasis added). His use of the term “related” is ambiguous, especially given that Travelers did not provide an excerpt of the earlier 23 deposition testimony referenced. 69 ECF No. 346 at 14. 15 1 II. 2 Even if the project delays attributable to FAST ran concurrent to Big Town’s own delays, Travelers may still seek reimbursement for the resulting damages because FAST failed to request time extensions under the subcontracts. 3 Travelers’s reimbursement claim is largely premised on its contention that the liquidated 4 damages that CCSD assessed—and that Travelers paid in settlement—resulted from FAST’s 5 delays during the HVAC projects.70 In support, Travelers obtained a report from Jeff Ottesen, a 6 schedule-delay expert who opined that over $2.7 million in delay damages were attributable to 7 FAST.71 Fidelity moves for a determination that Travelers cannot establish that FAST caused 8 any of these damages. It asserts that the delays cited in the Ottesen report ran concurrent to 9 delays that Big Town caused, and therefore, FAST was not the “but for” cause of the liquidated 10 damages.72 Travelers counters with its own expert, Philip Spinelli,73 who criticizes the Ottesen 11 report’s methodology and concludes that Ottesen’s own findings reveal concurrent delays.74 12 This battle of the experts alone precludes summary judgment,75 and I would normally conclude 13 14 15 70 ECF No. 318 ¶ 34. 71 ECF No. 291-1 at 1, 11. 72 ECF No. 287 at 9–13; see also R.P. Wallace, Inc. v. United States, 63 Fed. Cl. 402, 410 (2004); Morrison Knudsen Corp. v. Fireman’s Fund Ins. Co., 175 F.3d 1221, 1232–33 (10th Cir. 17 1999) (explaining Critical Path Methodology); 5 Philip L. Bruner & Patrick J. O’Connor, Jr., Bruner & O’Connor on Construction Law § 15:67 (2018) (“Because the party seeking damages 18 for delay must prove that delay to the critical path would not have occurred ‘but for’ an event within the ‘control’ of the other party, proof of a concurrent cause of delay outside of the other 19 party’s ‘control’ precludes recovery of damages.”). 73 Travelers argues that Spinelli is not qualified to opine on Ottesen’s methodology because he 20 lacks certain certifications. ECF No. 314 at 16. But Travelers has not moved to exclude Spinelli’s report and proposed testimony under Daubert v. Merrell Dow Pharmaceuticals, Inc., 21 509 U.S. 579 (1993), or its progeny. 16 22 74 ECF No. 291-3. 75 Likely recognizing this defect in its own motion, Fidelity argues that Ottesen confirmed the 23 existence of concurrent delays during his deposition. Ottesen did testify that there were concurrent delays—a factor that he contends he compensated for in his analysis—but he does not appear to conclude that all the delays were concurrent. ECF No. 291-2 at 7–8. Because it 16 1 my analysis at this point. But Travelers contends that FAST’s failure to comply with the 2 subcontracts’ time-extension provisions bars Fidelity from relying on a concurrent-delay 3 defense. So, in the interest of paring down the issues remaining for trial, I will address this 4 argument.76 5 Travelers asserts that, “[w]here a subcontractor fails to comply with mandatory 6 subcontract procedures pertaining to requesting an extension of the subcontract time, the 7 subcontractor is responsible for all delay damages and loses the right to assert that others caused 8 the delay.”77 In support, Travelers primarily cites to the California Court of Appeal’s decision in 9 Greg Opinski Construction, Inc. v. City of Oakdale.78 There, the contractor was more than seven 10 months late on a project and failed to seek an extension under its contract with the city 11 government. 79 The contract allowed for written requests for extensions of time if the delay was 12 caused by forces “beyond the control of the Contractor,” including “acts of neglect by Owner,” 13 i.e., the city.80 The contractor was found liable at trial for liquated damages and argued on 14 appeal that such damages were precluded for “any portion of the delay that” the city had 15 16 remains possible that some (or even most) of the delays are solely attributable to FAST, Ottesen’s ambiguous concession does not resolve the material dispute of fact. 17 76 Travelers raises several evidentiary objections to Fidelity’s motion that are without merit. 18 ECF No. 314 at 8–12. For instance, it objects to the Spinelli report as hearsay. But at summary judgment, it is the admissibility of the evidence’s content rather than its form that is important. 19 Fraser v. Goodale, 342 F.3d 1032, 1036 (9th Cir. 2003). The purpose of an expert report is to provide the opposing party notice of what the expert would testify to at trial, along with the facts 20 and data relied upon. See FED. R. CIV. PRO. 26(a)(2)(B). Further, Travelers’s objections to Fidelity’s copies of the subcontracts largely overlap with the substantive question of which 21 agreements (the subcontracts or addendums) govern. 77 22 ECF No. 314 at 19. 78 Greg Opinski Constr., Inc. v. City of Oakdale, 132 Cal. Rptr. 3d 170 (Cal. Ct. App. 2011). 23 79 Id. at 172. 80 Id. at 173–74. 17 1 caused.81 The court held that, because the contractor failed to comply with the time-extension 2 provision, it made “no difference whether [the contractor’s] timely performance was possible or 3 impossible . . . .”82 It reasoned that the purpose of these provisions “is to allocate to the 4 contractor the risk of delay costs—even for delays beyond the contractor’s control—unless the 5 contractor follows the required procedures for notifying the owner of its intent to claim a right to 6 an extension.”83 7 Fidelity offers no contrary authorities in response. It merely argues that, unlike in 8 Opinski, which involved an owner-contractor relationship, Travelers’s claim stems from a 9 contractor-subcontractor relationship, in which “multiple subcontractors could be responsible for 10 the delay.”84 But given that Fidelity has attributed FAST’s delays only to Big Town, this is a 11 distinction without a difference. Indeed, the subcontracts here allowed FAST to seek an 12 extension for delays that CCSD or Big Town caused.85 And as discussed above, the subcontracts 13 emphasized that seeking an extension was FAST’s “exclusive remedy” in the event of such a 14 delay and that a failure to request one would “act as a waiver of that claim.”86 As in Opinski, this 15 provision was clearly intended to allocate the risk of delay costs. I thus agree that a defaulting 16 party’s failure to request an extension of time through the procedures specified in these 17 18 19 81 Id. at 176. 82 Id. at 178. 83 21 Id. 84 ECF No. 323 at 15. 22 85 20 E.g., ECF No. 288-2 at 6. The subcontracts refer to “higher-tiered” parties, which they elsewhere define as “the Owner, the Tenant, the Prime Contractor and any higher-tiered 23 subcontractor . . . .” Id. at 3. 86 Id. at 7. 18 1 subcontracts precludes that party from asserting that a delay caused by the owner or prime 2 contractor prevented it from rendering timely performance. 3 Fidelity nonetheless raises several reasons why this rule should not apply to the 4 circumstances of this case. It first argues that it is not bound by the time-extension provisions 5 because they are part of the Big Town-FAST subcontracts, which Fidelity contends do not apply 6 to itself or its team of subcontractors.87 But this position ignores the fact that Fidelity took over 7 performance from FAST once it defaulted on these subcontracts and thus stands in FAST’s 8 shoes.88 9 Fidelity similarly contends that compliance with the extension provisions was impossible 10 because, once CCSD declared Big Town in default as the prime contractor, the subcontracts were 11 terminated.89 But even if I accept this legal premise, it does account for the fact that Big Town’s 12 default occurred approximately a year-and-a-half after Big Town had fired FAST and a year after 13 Fidelity’s team declared their work complete. Big Town’s default may have contributed to the 14 overall project delay, but this fact does not speak to FAST’s delays or any delays that Fidelity’s 15 16 17 87 ECF No. 323 at 6. Fidelity also asserts that the addendums—which do not contain the same time-extension provisions—govern the Big Town-FAST relationship. Fidelity proffers the same 18 evidence it does in opposition to Travelers’s motion on breach, and I reject this argument for the 19 same reasons. 88 Emp’rs Mut. Cas. Co. v. United Fire & Cas. Co., 682 N.W.2d 452, 457 (Iowa Ct. App. 2004); 20 Caron v. Andrew, 284 P.2d 544, 549 (Cal. 1955); see also ECF No. 310 ¶ 56 (Fidelity alleging in its complaint that it “completed the FAST subcontracts and is therefore also ‘in the shoes’ of 21 FAST in making its bond claim”). 89 ECF No. 323 at 13; see also C. C. Smith Co. v. Frankini Const. Co., 135 N.E.2d 924, 927 (Mass. 1956) (stating that a subcontractor’s “right to work on the project was derived from its subcontract with [the owner] and when the general contract was terminated it had no standing to 23 perform further, in the absence of a new contract between it and [the owner]”); 2 Philip L. Bruner & Patrick J. O’Connor, Jr., Bruner & O’Connor on Construction Law § 5:265 (2018). 22 19 1 team caused or exacerbated. And Fidelity overlooks the fact that Big Town’s default resulted in 2 an assignment of its rights to Travelers under the GAI. 3 Finally, Fidelity makes several related arguments that it also raised in opposition to 4 Travelers’s motion: (1) that Perini did comply with the time-extension provisions until Big Town 5 purportedly instructed it to stop submitting such requests; (2) that Big Town failed to keep a 6 project schedule—as evidenced by its statement that the schedule was “dead” since August 2011; 7 and (3) that Big Town refused to provide Fidelity and Perini the past project schedules. These 8 arguments suffer from the same infirmities discussed above. Accordingly, I deny Fidelity’s 9 motion and decline to find that Travelers is barred from seeking delay damages. 10 III. Fidelity’s remaining defenses are without merit. 11 Fidelity’s “final motion for partial summary judgment” raises three defenses to 12 Travelers’s counterclaims. First, Fidelity argues that Travelers engaged in various forms of 13 misconduct once Fidelity and its team took over performance and that the balance of equities 14 thus prevents Travelers from pursuing its equitable-subrogation and assignment claims. Fidelity 15 separately contends that Travelers cannot maintain its claim for breach of the performance bond 16 because Travelers was the first to breach Fidelity’s bond. Finally, Fidelity invokes the Spearin 17 doctrine, contending that the HVAC-controller specifications that Fidelity was required to follow 18 were defective and thus preclude Fidelity’s liability. Many of these arguments implicate a 19 question central to this litigation: what went wrong with the HVAC automation systems that so 20 many contractors and subcontractors attempted to install? I will first address the parties’ 21 evidence on this point and then turn to Fidelity’s arguments. 22 23 20 1 A. 2 3 Improper controllers and wiring prevented the HVAC automation systems from functioning correctly. The first report describing the technical problems plaguing the HVAC systems appears to 4 be the MEP report issued by the consulting firm that Travelers engaged after taking over for Big 5 Town.90 The report is short and comprised primarily of technical jargon and references to the 6 project specifications. What is clear is that report blamed the HVAC issues, at least in part, on 7 the “building controllers” installed at the five schools. Fidelity explains that “controllers are 8 mini computers that essentially control air heating and cooling” and fall into the categories of 9 Variable Air Volume (VAV) controllers and Roof Top Unit (RTU) controllers.91 Specification 10 Section 25 00 00 for the projects listed six pre-approved controller brands, along with approved 11 installers.92 FAST was approved as the installer for Honeywell-brand controllers, which it 12 installed as the VAV controllers at all five schools and as the RTU controllers at two of these 13 schools.93 Another subcontractor installed Johnson-brand RTU controllers at the three remaining 14 schools.94 15 The MEP report was specifically critical of the Honeywell and Johnson RTU 16 controllers.95 It opined that these controllers had “programming limitations” that caused a 17 component referred to as the “JACE” to “lock[] up,” which causes the “entire system to go[] 18 19 20 90 See ECF No. 330-7. 91 ECF No. 329 at 3–4. 92 22 E.g., ECF No. 333 at 82. 93 ECF No. 330 at 82; ECF No. 333 at 6. 23 94 ECF No. 333 at 7. 95 ECF No. 330-7 at 41. 21 21 1 down.”96 Although this report is often a focal point of the parties’ arguments, it provides little 2 insight to the HVAC layperson. Fortunately, Travelers commissioned a separate expert report 3 (the Hammond report) that fills in many of the gaps.97 4 The Hammond report explains that one of the project specifications required the 5 controllers to include a stand-alone capability.98 This means that, if a controller does not receive 6 instructions from an external device, it will default to a preset heating and cooling mode 7 designed for a school building filled with students and staff.99 This is a redundancy feature that 8 ensures that buildings will be heated or cooled appropriately even if CCSD’s remote servers or 9 the onsite “supervisory devices” lose power or become inoperative.100 One of these supervisory 10 devices is the aforementioned JACE, which communicates with CCSD’s servers and the local 11 controllers at each school.101 According to the Hammond report, Travelers’s contractor Sletten 12 discovered that some of the Honeywell controllers that FAST installed did not have stand-alone 13 capacity.102 Consequently, if the JACE became overburdened and failed, the controllers were 14 incapable of operating autonomously and the HVAC systems would not function.103 15 Beyond the problem with the controllers themselves, the Hammond report also concludes 16 that FAST used “sub-standard” wiring when installing the controllers.104 This wiring did not 17 18 19 20 96 Id. 97 See ECF No. 261-1. 98 Id. at 7; see also ECF No. 330-7 at 41. 99 ECF No. 261-1 at 5–7. 100 Id. at 7–9. 101 22 Id. at 8. 102 Id. at 12–13. 23 103 Id. at 10–11. 104 Id. at 14–16. 21 22 1 satisfy the project specifications and affected the controllers’ warranty. 105 The report further 2 explains that the wiring issue distorts the HVAC automation system’s communications “and 3 leads to system malfunction.”106 Citing to findings from a commissioning agency that tested one 4 of the school’s systems, the report stated that this improper wiring was “a critical reason the 5 JACE was locking up” and that “the system would never function properly” unless the entire 6 school was re-wired.107 7 Based on these issues, Sletten and its subcontractor ultimately replaced the controllers at 8 all five schools with a different brand.108 And “irrespective of the controllers utilized, the Sletten 9 team had to re-wire all” the controllers at the five schools.109 10 B. 11 Travelers’s counterclaim for reimbursement is premised on its contention that FAST and I cannot conclude on summary judgment that equity tilts in Fidelity’s favor. 12 Fidelity breached the subcontracts and Fidelty’s performance bonds.110 But because Travelers 13 was not a party to either set of agreements, it relies on two legal principles that could allow it to 14 obtain relief against Fidelity: equitable subrogation, and the assignment under the GAI of Big 15 Town’s contractual rights. “Equitable subrogation permits a party who has been required to 16 satisfy the loss created by a party’s wrongful act to ‘stand in the shoes’ of the injured party and 17 105 18 19 Id. at 15. 106 Id. at 14. 107 Id. 108 See ECF No. 329 at 18. The parties dispute whether the evidence demonstrates that Travelers and Sletten decided to replace the controllers based solely on the MEP report or after considering 21 several factors, including the wiring issues. ECF No. 335 at 14–15; ECF No. 344 at 5–7. But even if Travelers made the initial decision to replace the controllers without being aware of the 22 wiring issues, it is undisputed that Travelers eventually determined that rewiring the schools was critical to ensuring that the HVAC systems functioned correctly. 20 23 109 ECF No. 261-2 at 16. 110 ECF No. 335 at 17. 23 1 pursue the wrongdoer.”111 In the construction context, a surety that steps in and performs a 2 contractor’s obligations is subrogated “to the position of the contractor-principal” and “may 3 pursue the principal’s claims and defenses” against subcontractors, the obligee, or other 4 parties.112 5 Fidelity argues that Travelers engaged in several misdeeds after Fidelity’s team took over 6 for FAST and that equity therefore precludes Travelers from standing in Big Town’s shoes under 7 subrogation or assignment. It similarly claims that Travelers unreasonably delayed in acting on 8 its assignment after Big Town’s default and that the equitable defense of laches therefore applies. 9 But there’s a foundational problem with Fidelity’s argument. Fidelity has not established 10 that a breach-of-contract claim premised on a contractual assignment is subject to equitable 11 defenses.113 Although subrogation and assignment operate similarly from the surety’s 12 perspective, the former is an equitable remedy (and thus subject to equitable defenses),114 while 13 the latter sounds in contract.115 Because Fidelity carries the burden of establishing that it is 14 15 111 16 Gulf Ins. Co. v. TIG Ins. Co., 103 Cal. Rptr. 2d 305, 312 (Cal. Ct. App. 2001). 112 4A Philip L. Bruner & Patrick J. O’Connor, Jr., Bruner & O’Connor on Construction Law 17 § 12:100 (2018). 113 Fidelity cites only to a federal district-court decision from Kentucky addressing a surety’s suit 18 against a subcontractor under equitable subrogration and assignment. Nat’l Sur. Corp. v. AllenCodell Co., 70 F. Supp. 189, 191 (E.D. Ky. 1947). Without further elaboration, the court 19 vagugely stated “[t]he fact that the [surety] took from . . . the principal contractor[] an assignment of his rights under his subcontract with the [subcontractor] seems to add nothing to 20 the [equitable-subrogation] rights here asserted.” Id. This vague conclusion is insufficent to assume a bridge between law and equity under Nevada law. 21 114 Am. Sterling Bank v. Johnny Mgmt. LV, Inc., 245 P.3d 535, 538 (Nev. 2010); Nat’l Sur. Corp., 70 F. Supp. at 192–93. 22 115 4A Philip L. Bruner & Patrick J. O’Connor, Jr., Bruner & O’Connor on Construction Law 23 § 12:100 (2018) (“Although the right of subrogation sometimes has been described as an ‘equitable assignment’ or ‘assignment by operation of law,’ the equitable right of subrogation is clearly distinct from contractual assignment . . . .”); see also Wyler Summit P’ship v. Turner 24 1 entitled to summary judgment and to any equitable defense, this deficiency defeats its 2 assignment argument. I will therefore address only equitable subrogation.116 3 A subrogation claim requires courts “to balance the equities based on the facts and 4 circumstances of each particular case.”117 A surety claiming the remedy must “establish that its 5 equitable position is superior to the position of the party to be charged.”118 In arguing that equity 6 tilts against Travelers, Fidelity asserts the following: (1) once Perini took over for FAST, Big 7 Town provided it “disorganized, incomplete records or failed to give records altogether”; (2) Big 8 Town breached the subcontracts by refusing to pay Perini for its work; and (3) after CCSD 9 declared Big Town in default, Travelers waited nine months before informing Fidelity that it 10 believed that Fidelity’s team had failed to complete their work.119 But these arguments reveal 11 that summary judgment is improper on this defense. Whether Big Town breached the 12 subcontracts through nonpayment is a question key to Fidelity’s primary claim against Travelers 13 and has yet to be resolved in this litigation. And, as discussed in more detail below, Fidelity has 14 not demonstrated that it was entitled to notice that its team of subcontractors failed to complete 15 the HVAC projects. 16 17 18 Broad. Sys., Inc., 235 F.3d 1184, 1193 (9th Cir. 2000) (distinguishing between claims at law and equity). 19 116 Because Fidelity’s laches defense was tied only to its assignment argument, I will not address this issue. 20 117 Am. Sterling Bank, 245 P.3d at 538. Citing to Federal Insurance Co. v. Toiyabe Supply Co., Travelers contends that the Nevada Supreme Court has “disapprove[d] of the ‘weighing of the 21 equities’ doctrine . . . .” 409 P.2d 623, 627 (Nev. 1966). But this assertion appears limited to the 22 peculiar facts of this hoary case, especially given that Nevada’s high court has approved of the doctrine in a far more recent and comparable case. See Am. Sterling Bank, 245 P.3d at 538. 23 118 Dobbas v. Vitas, 119 Cal. Rptr. 3d 798, 800 (Cal. Ct. App. 2011). 119 ECF No. 239 at 23–25. 25 1 Turning to Fidelity’s side of the scale, it argues that it acted in good faith and believed 2 that its subcontractors had completed their work when Perini issued the notice of substantial 3 competition in May 2012. The undisputed evidence reveals, however, that Perini, by April 2012, 4 was aware that FAST had used improper wiring.120 Perini never redressed this issue, and neither 5 it nor Fidelity informed Big Town or Travelers of the substandard wiring. On this record, I 6 cannot conclude that Travelers holds an equitable position inferior or even equal to Fidelity. 7 One final note on equity. Throughout its motions, Fidelity has argued that Travelers is 8 estopped from asserting that Fidelity’s team did not complete FAST’s scope of work.121 Fidelity 9 highlights the fact that Big Town never objected after Perini issued the notice of substantial 10 completion. Fidelity also advances evidence that a Big Town representative stated at the time 11 that Perini (and thus Fidelity) had completed work on the five schools.122 But to warrant 12 equitable estoppel, Fidelity must establish, among other things, that it was “ignorant of the true 13 state of facts . . . .”123 Because it undisputed that Fidelity’s subcontractor knew that the HVAC 14 systems were improperly wired, I find that Fidelity is not entitled to this estoppel defense. 15 C. 16 Travelers’s delay in notifying Fidelity that its work was incomplete did not breach Fidelity’s performance bond. Fidelity argues that “an obligee to a performance bond materially breaches the 17 18 performance bond if the obligee takes an action that deprives the surety of its ability to protect 19 itself or control costs under the performance bond, regardless of whether any actual prejudice is 20 21 120 22 121 ECF No. 329 at 22–23; ECF No. 333 at 27–28. 23 122 ECF No. 333 at 15. 123 Cheqer, Inc. v. Painters & Decorators Joint Comm., Inc., 655 P.2d 996, 999 (Nev. 1982). ECF No. 335 9–10 (citing ECF No. 331-10); see also ECF No. 261-1 at 16. Fidelity never addresses Travelers’s assertions or evidence on this point, which I interpret as a tacit concession. 26 1 caused to the surety.”124 In support, Fidelity relies primarily on Dragon, Inc. v. Parkway Bank & 2 Trust, where the Illinois Appellate Court determined that an obligee breached the performance 3 bond by failing to give the surety notice before firing the bonded contractor and hiring a 4 replacement.125 The bond required the obligee to provide seven-day written notice before doing 5 so in order to “allow [the surety] to exercise its right under the performance bond to participate 6 in the selection of a successor contractor.”126 Because the obligee acted unilaterally, the surety 7 “was stripped of its contractual right to minimize its liability under the performance bond by 8 ensuring that the lowest responsible bidder was selected to complete the job.”127 9 These facts bear little resemblance to this case. Big Town immediately notified Fidelity 10 that it had fired FAST and did not prevent the surety from attempting to complete FAST’s work 11 (and minimize costs) by hiring its own subcontractors. Dragon does not support the proposition 12 that Travelers was obligated to notify Fidelity that it had failed to remedy the HVAC problems 13 and to give Fidelity a second bite of the apple. Nor can Fidelity point to a provision in the bond 14 that would grant it this right. Accordingly, Travelers’s decision to hire its own contractor rather 15 than immediately contact Fidelity did not breach the performance bond. 16 17 18 19 20 21 124 22 ECF No. 329 at 28. 125 Dragon., Inc. v. Parkway Bank & Tr., 678 N.E.2d 55, 58 (Ill. App. Ct. 1997). 23 126 Id. 127 Id. 27 1 D. 2 Because FAST failed to properly wire the HVAC controllers, Fidelity cannot rely on the Spearin doctrine. The Spearin doctrine recognizes the owner’s implied warranty of the adequacy of a 3 4 project’s plans and specifications.128 Although the doctrine originated in federal contract law,129 5 most jurisdictions, including Nevada, have adopted the rule that where a contractor has followed the plans and specifications furnished by the owner and his architect, he will not be responsible to the owner, at least after the work is completed, for any loss or damage [that] results solely from the defects or insufficient plans or specifications, in the absence of any negligence on the part of the contractor or any express warranty by him as to their being sufficient or free from defects.130 6 7 8 9 10 Fidelity argues that it is undisputed that the Honeywell HVAC controllers were the reason the 11 HVAC automation systems failed to function correctly. And because the project specifications 12 required FAST to install these specific controllers, Fidelity contends that it cannot be held liable 13 for the resulting delay damages. But as discussed above, the undisputed evidence also 14 establishes that FAST used improper wiring and thus failed to install the controllers properly. 15 This mistake was not trivial, but rather was “a critical reason” the system was malfunctioning.131 16 Fidelity therefore cannot demonstrate that the controllers were the sole cause of the system 17 problems and resulting damages. Accordingly, the Spearin doctrine does not shield Fidelity 18 from liability. 19 20 128 3 Philip L. Bruner & Patrick J. O’Connor, Jr., Bruner & O’Connor on Construction Law 21 § 9:81 (2018). 22 129 United States v. Spearin, 248 U.S. 132 (1918). 130 Home Furniture, Inc. v. Brunzell Const. Co., 440 P.2d 398, 401 (Nev. 1968) (emphasis 23 added); see also Halcrow, Inc. v. Eighth Jud. Dist. Ct., 302 P.3d 1148, 1154 n.3 (Nev. 2013). 131 ECF No. 261-1 at 14. 28 1 2 Conclusion IT IS THEREFORE ORDERED that Travelers’s motion for partial summary judgment 3 [ECF No. 327] is GRANTED in part and DENIED in part. Summary judgment is granted on 4 the narrow issues that the subcontracts signed on August 30, 2010, govern, and FAST breached 5 these subcontracts by missing the project-completion dates. But summary judgment is denied as 6 to Travelers’s claim that Fidelity subsequently breached the subcontracts and performance bonds 7 by not completing the commissioning process. 8 IT IS FURTHER ORDERED that Fidelity’s motion for partial summary judgment on 9 reimbursement-related damages [ECF No. 287] is DENIED. 10 IT IS FURTHER ORDERED that Fidelity’s final motion for partial summary judgment 11 [ECF No. 329] is DENIED. 12 IT IS FURTHER ORDERED that this case is REFERRED to a magistrate judge for a 13 MANDATORY SETTLEMENT CONFERENCE. The parties’ obligation to file their joint 14 pretrial order is STAYED until 10 days after that settlement conference. 15 Dated: September 21, 2018 16 _______________________________ ____________________ _ ______ __ _ 17 U.S. District Judge Jennifer A. Dorsey S Jen Jennifer 18 19 20 21 22 23 29

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?