Ergon Asphalt & Emulsions, Inc. v. Capriati Constructions Corp, Inc. et al
Filing
65
ORDER that 41 Ergon's Motion for Summary Judgment is GRANTED as to Ergon's unjust enrichment claim and Ergons claim against bond.FURTHER ORDERED that 45 Ergon's Motion for Summary Judgment as to Defendants' Counterclaims i s GRANTED.FURTHER ORDERED that 46 Defendants' Motion for Summary Judgment is GRANTED as to Ergon's Claims for breach of contract and breach of the covenant of good faith and fair dealing.FURTHER ORDERED that 50 Defendant Capriati& #039;s Motion for Summary Judgment is DENIED. FURTHER ORDERED that judgment be entered in the amount of $224,901.91 in favor of Ergon and against Defendants Capriati, Zurich, and Fidelity, jointly and severally. The Clerk is instructed to close the case. Signed by Chief Judge Gloria M. Navarro on 4/29/15. (Copies have been distributed pursuant to the NEF - MMM)
1
UNITED STATES DISTRICT COURT
2
DISTRICT OF NEVADA
3
Ergon Asphalt and Emulsions, Inc.,
4
Plaintiff,
5
6
7
8
vs.
Capriati Construction Corp, Inc.; Zurich
American Insurance Company; Fidelity and
Deposit Company of Maryland,
Defendants.
9
)
)
)
)
)
)
)
)
)
)
)
Case No.: 2:13-cv-1683-GMN-NJK
ORDER
10
Pending before the Court are the Motions for Summary Judgment, (ECF Nos. 41, 45),
11
12
filed by Plaintiff Ergon Asphalt and Emulsions, Inc. (“Ergon”). Defendants Capriati
13
Construction Corp, Inc., Zurich American Insurance Company, and Fidelity and Deposit
14
Company of Maryland filed Responses in opposition, (ECF Nos. 53, 54), to which Ergon
15
replied, (ECF No. 56).
Also before the Court are Defendants’ Motions for Summary Judgment. (ECF Nos. 46,
16
17
50). Ergon filed a Response in opposition, (ECF No. 55), to which Defendants replied, (ECF
18
No. 58).
19
I.
20
21
22
BACKGROUND
This case arises out of a dispute over the payment of escalation costs for an asphalt
product sold by Ergon to Defendant Capriati in 2011 and 2012.
On July 9, 2010, Defendant Capriati entered into an agreement with the Nevada
23
Department of Transportation (“NDOT”) to furnish work, material, and equipment for the
24
completion of a highway improvement project (the “Project”). (NDOT Contract, ECF No. 23-
25
7). The Project was intended to improve a stretch of U.S. Highway 95 from Washington
Page 1 of 13
1
Avenue to Kyle Canyon Road in Las Vegas, and was originally anticipated to take 520 days to
2
complete. (Id.); (Final Balance Report at 30, ECF No. 41-7). The agreement between
3
Defendant Capriati and NDOT (the “NDOT Agreement”) specified that PG76-22NV, a
4
particular asphalt cement product, would be used in the Project. (NDOT Agreement p. 63, ECF
5
No. 23-7). The NDOT Agreement also included a price escalation provision which required
6
that NDOT increase its payments to Defendant Capriati if the market price of asphalt cement
7
increased while the Project was ongoing. (Id. at 69). The NDOT Agreement specifically noted
8
that the price escalation provision applied to “PG grades” of asphalt cement. (Id. at 214).
9
In October 2010, Ergon and Defendant Capriati began negotiating a deal in which Ergon
10
would supply asphalt for the Project. (Dep. of Golden Welch 23:21-24:4, ECF No. 47-5). On
11
October 26, 2010, David M. Rocchio, president of Defendant Capriati, executed a credit
12
application (the “Credit Application”) which, inter alia, set forth terms regarding the extension
13
of credit and timing of payments for anticipated future deliveries of asphalt. (Credit
14
Application, ECF No. 41-1).
15
On October 27, 2010, Ergon sent a one-page confidential price quote (the “Price Quote”)
16
to Defendant Capriati, which laid out prices for four different asphalt products, specified that
17
taxes and environmental fees were not included in the listed prices, and contained the phrase
18
“index escalator specifics NDOT.” (Price Quote, ECF No. 41-2). One of the quoted prices was
19
for PG76-22NV. (Id.). The Price Quote also included provisions regarding the timing of
20
orders, the location and duration of the Project, shipping methods, and freight costs. (Id.). The
21
Price Quote did not contain any signature lines or text indicating that a signature was required
22
to give effect to its terms. (Id.).
23
On January 10, 2011, Defendant Capriati sent a six-page draft of a purchase agreement
24
(the “Draft Agreement”) to Ergon. (ECF No. 41-3). The Draft Agreement included detailed
25
terms regarding the scope of the work to be completed by Ergon, termination of the agreement,
Page 2 of 13
1
indemnification, and other aspects of the supply arrangement between Ergon and Defendant
2
Capriati. (Id.). The Draft Agreement did not specify the price of any goods, but instead
3
provided that “[Defendant Capriati] agrees to pay [Ergon] in the payment quantities and
4
schedules as is more fully described in Exhibit ‘A’: Supplier’s Scope of Work.” (Id. at § 3.1).
5
The Draft Agreement also stated that all applicable taxes had been included in the agreed-upon
6
prices. (Id. at § 5.1). The Draft Agreement also incorporated the terms of the Price Quote,
7
stating:
8
9
10
11
12
The [Draft] Agreement and [Ergon]’s quote, providing said quote is
not contrary to this Agreement or all Contract Documents as
provided in Section One, comprises the entire Agreement between
the parties relating to [Ergon’s] furnished materials, and no other
agreements, representations, terms, provisions or understandings
concerning the Supplier furnished materials have been made.
Unlike the Price Quote, the Draft Agreement did not address whether the prices would
13
be subject to an escalation index. The last page of the Draft Agreement contained two
14
signature blocks, one designated for Ergon, and the other designated for Defendant Capriati.
15
(Id. at p. 5). Directly above the signature blocks, the Draft Agreement stated, “The parties
16
hereto have executed this Purchase Agreement for themselves, their heirs, executors,
17
successors, administrators, and assignees on the day and year first above written.” (Id.).
18
On January 12, 2011, after reviewing the Draft Agreement, Ergon’s sales manager,
19
Gregory Hunt, sent an email to Defendant Capriati’s contract administrator, Golden Welch,
20
stating that Ergon typically charged a $0.4424/ton environmental fee for PG76-22NV, and
21
indicated that this term should be incorporated into the Draft Agreement. (Gregory Hunt Email,
22
ECF No. 48-4). Over the next day, Mr. Hunt and Mr. Welch exchanged several emails
23
regarding proposed changes to the Draft Agreement. (Hunt-Welch Email Thread, ECF No. 48-
24
5). On January 18, 2011, Mr. Welch sent an email to Mr. Hunt asking, “Is Ergon going to sign
25
our Purchase Agreement?” (Id.). Mr. Hunt responded the same day, stating “Yes, I will get it
Page 3 of 13
1
to you tomorrow.” (Id.). However, there is no evidence on the record demonstrating that any
2
agent of Ergon or Defendant Capriati ever signed the Draft Agreement.
3
In the midst of these negotiations, Ergon began delivering PG76-22NV, which was
4
accepted by Defendant Capriati. The records of both of these parties reflect that Ergon sold
5
40.73 tons of the product to Defendant Capriati on January 13, five days before Mr. Welch’s
6
email inquiring as to whether Ergon would sign the revised Draft Agreement. (Capriati
7
Account Summary p. 94, ECF No. 23-3); (Ergon Account Summary p. 695, ECF No. 23-4).
8
Ergon continued to make deliveries of PG76-22NV until the Project concluded in November
9
2012. (Capriati Account Summary p. 104).
10
On May 2, 2012, Mr. Hunt sent Mr. Welch an email stating, in full, “Here is a revised
11
escalator increase. I have also included our contract for you to view. Let me know what
12
questions you might have. Thank you!” (Gregory Hunt Email, ECF No. 41-5). Attached to the
13
email was a revised version of the Price Quote, which, with the exception of a single line that
14
stated “Escalator passed to Ergon,” was identical to the original. (Revised Price Quote, ECF
15
No. 41-6). There is no evidence on the record indicating that Defendant Capriati objected to
16
the characterization of the Price Quote as the “contract” or to the additional text in the Revised
17
Price Quote at that time.
18
Between June 2012 and November 2012, Ergon submitted five invoices to Defendant
19
Capriati requesting escalation payments, calculated pursuant to NDOT’s formula, in the total
20
amount of $288,406.92. (Ergon Invoices, ECF Nos. 41-8, 41-11). Defendant Capriati paid the
21
first of these, in the amount of $63,505.01, on October 12, 2012. The other four invoices were
22
initialed and stamped as approved by Defendant Capriati on December 28, 2012, but Defendant
23
Capriati subsequently refused to issue the corresponding payments, (Approved Invoices, ECF
24
No. 41-10), asserting that the Draft Agreement did not require payments for escalation.
25
However, it is undisputed that Defendant Capriati received $401,041 from NDOT during the
Page 4 of 13
1
course of the Project as compensation for “asphalt escalation.” (NDOT Balance Report p. 23,
2
ECF No. 41-7).
3
Seeking to recover the unpaid asphalt escalation balance, Ergon filed its Complaint on
4
September 13, 2013, setting forth claims against Defendant Capriati for: (1) breach of contract;
5
(2) breach of the covenant of good faith and fair dealing; and (3) unjust enrichment. (Compl.,
6
ECF No. 1). Ergon also asserted a claim against Defendants Zurich and Fidelity as sureties of
7
Defendant Capriati’s labor and material bond. (Id.).
8
9
10
In response, Defendant Capriati asserted counterclaims against Ergon for: (1) breach of
contract; (2) breach of the covenant of good faith and fair dealing; (3) unjust enrichment; and
(4) deceptive trade practices. (Answer, ECF No. 14).
11
In its Motions, Ergon requests that summary judgment be entered in its favor as to all
12
pending claims. Defendants, in their Motions, request the entry of summary judgment as to all
13
claims except Defendant Capriati’s claim for deceptive trade practices.
14
II.
15
LEGAL STANDARD
The Federal Rules of Civil Procedure provide for summary adjudication when the
16
pleadings, depositions, answers to interrogatories, and admissions on file, together with the
17
affidavits, if any, show that “there is no genuine dispute as to any material fact and the movant
18
is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). Material facts are those that
19
may affect the outcome of the case. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248
20
(1986). A dispute as to a material fact is genuine if there is sufficient evidence for a reasonable
21
jury to return a verdict for the nonmoving party. See id. “Summary judgment is inappropriate if
22
reasonable jurors, drawing all inferences in favor of the nonmoving party, could return a verdict
23
in the nonmoving party’s favor.” Diaz v. Eagle Produce Ltd. P’ship, 521 F.3d 1201, 1207 (9th
24
Cir. 2008) (citing United States v. Shumway, 199 F.3d 1093, 1103-04 (9th Cir. 1999)). A
25
principal purpose of summary judgment is “to isolate and dispose of factually unsupported
Page 5 of 13
1
claims.” Celotex Corp. v. Catrett, 477 U.S. 317, 323-24 (1986).
2
In determining summary judgment, a court applies a burden-shifting analysis. “When
3
the party moving for summary judgment would bear the burden of proof at trial, it must come
4
forward with evidence which would entitle it to a directed verdict if the evidence went
5
uncontroverted at trial. In such a case, the moving party has the initial burden of establishing
6
the absence of a genuine issue of fact on each issue material to its case.” C.A.R. Transp.
7
Brokerage Co. v. Darden Rests., Inc., 213 F.3d 474, 480 (9th Cir. 2000) (citations omitted).
8
9
In contrast, when the nonmoving party bears the burden of proving the claim or defense,
the moving party can meet its burden in two ways: (1) by presenting evidence to negate an
10
essential element of the nonmoving party’s case; or (2) by demonstrating that the nonmoving
11
party failed to make a showing sufficient to establish an element essential to that party’s case
12
on which that party will bear the burden of proof at trial. See Celotex Corp., 477 U.S. at 323-
13
24. If the moving party fails to meet its initial burden, summary judgment must be denied and
14
the court need not consider the nonmoving party’s evidence. See Adickes v. S.H. Kress & Co.,
15
398 U.S. 144, 159-60 (1970).
16
If the moving party satisfies its initial burden, the burden then shifts to the opposing
17
party to establish that a genuine issue of material fact exists. See Matsushita Elec. Indus. Co. v.
18
Zenith Radio Corp., 475 U.S. 574, 586 (1986). To establish the existence of a factual dispute,
19
the opposing party need not establish a material issue of fact conclusively in its favor. It is
20
sufficient that “the claimed factual dispute be shown to require a jury or judge to resolve the
21
parties’ differing versions of the truth at trial.” T.W. Elec. Serv., Inc. v. Pac. Elec. Contractors
22
Ass’n, 809 F.2d 626, 631 (9th Cir. 1987). In other words, the nonmoving party cannot avoid
23
summary judgment by relying solely on conclusory allegations that are unsupported by factual
24
data. See Taylor v. List, 880 F.2d 1040, 1045 (9th Cir. 1989). Instead, the opposition must go
25
beyond the assertions and allegations of the pleadings and set forth specific facts by producing
Page 6 of 13
1
competent evidence that shows a genuine issue for trial. See Celotex Corp., 477 U.S. at 324.
2
At summary judgment, a court’s function is not to weigh the evidence and determine the
3
truth but to determine whether there is a genuine issue for trial. See Anderson, 477 U.S. at 249.
4
The evidence of the nonmovant is “to be believed, and all justifiable inferences are to be drawn
5
in his favor.” Id. at 255. But if the evidence of the nonmoving party is merely colorable or is
6
not significantly probative, summary judgment may be granted. See id. at 249-50.
7
III.
8
9
DISCUSSION
This dispute centers upon whether a valid contract existed between Ergon and Defendant
Capriati, and, if so, whether that contract required escalation payments. Defendants argue that
10
the Draft Agreement constitutes a binding contract which does not provide for escalation
11
payments. Ergon asserts that the Credit Application and Price Quote together constitute a
12
legally binding agreement requiring that Defendant Capriati make escalation payments.
13
Alternatively, Ergon argues that Defendant Capriati was unjustly enriched by receiving
14
escalation payments from NDOT without actually bearing the risk of a rise in asphalt prices.
15
In considering the instant Motions, the Court will first address whether parties are bound
16
by the Draft Agreement. The Court will then assess whether the Credit Application and Price
17
Quote collectively constitute a binding contract. Finally, the Court will analyze the merits of
18
the parties’ claims for unjust enrichment.
19
A.
The Draft Agreement
20
Pursuant to Nevada law, a valid contract requires: (1) an offer and acceptance, (2) a
21
meeting of the minds, and (3) consideration. See, e.g., May v. Anderson, 119 P.3d 1254, 1257
22
(Nev. 2005). In regard to the first criterion, a party may accept an offer by “any reasonable
23
manner” unless specific language or conduct indicates that a particular manner of acceptance is
24
required. Jim L. Shetakis Distrib. Co. v. Centel Commc’ns Co., 756 P.2d 1186, 1188 (Nev.
25
1988). Indeed, “where the circumstances indicate that a particular manner of contract
Page 7 of 13
1
formation is contemplated by the parties, a binding contract is not formed in the absence of
2
compliance with the contemplated procedure.” Id. (citing Widett v. Bond Estate, Inc., 382 P.2d
3
212 (Nev. 1963).
4
Numerous courts have held that if a written agreement indicates that a signature is
5
required for acceptance, its terms are not binding unless the offeree actually provides a
6
signature. Leodori v. CIGNA Corp., 814 A.2d 1098, 1107 (N.J. 2003) (“Defendant’s own
7
documents contemplated plaintiff’s signature as a concrete manifestation of his assent. . . . Our
8
contract law does not permit defendant to contemplate or require plaintiff’s signature on an
9
agreement and then successfully to assert that the omission of that signature is irrelevant to the
10
agreement’s validity.”); Open Solutions Inc. v. Granite Credit Union, No. 3:12-CV-1353-RNC,
11
2013 WL 5435105, at *2 (D. Conn. Sept. 29, 2013) (“On the last page of the Agreement, it
12
states, “ACCEPTED AND AGREED TO BY OPEN SOLUTIONS, INC.,” above a blank space
13
for OSI’s signature. Had it been the intent of the parties to not require OSI’s signature, this
14
section likely would not have been included.” (internal citation omitted)); Pacific Photocopy,
15
Inc. v. Canon U. S. A., Inc., 646 P.2d 647, 649-50 (Or. Ct. App. 1982) (“The document was
16
written and contained a signature line for approval by defendant. Even though paragraph 23
17
does not specifically require a signature of defendant’s authorized agent, it appears from the
18
character and form of the document that the parties contemplated signatures by both parties to
19
complete the agreement.”)
20
In this case, it is apparent both from the Draft Agreement’s text and from Defendant
21
Capriati’s conduct that Ergon’s signature was required for acceptance. The last page of the
22
Draft Agreement contains signature blocks for Ergon and Defendant Capriati, preceded by the
23
statement, “The parties hereto have executed this Purchase Agreement for themselves, their
24
heirs, executors, successors, administrators, and assignees on the day and year first above
25
///
Page 8 of 13
1
written.” 1 (Draft Agreement p. 15, ECF No. 41-3). Furthermore, following several days of
2
negotiations regarding the Draft Agreement, Defendant Capriati’s agent, Golden Welch,
3
specifically asked, “Is Ergon going to sign our purchase agreement?” (Hunt-Welch Email
4
Thread, ECF No. 48-5) (emphasis added). Therefore, both the text and Defendant Capriati’s
5
related communications clearly illustrate that Defendant Capriati contemplated that a signature
6
was required for Ergon to accept the terms of the Draft Agreement. As it is undisputed that
7
Ergon never signed the document, the Court finds that the Draft Agreement does not constitute
8
a binding contract.
9
Alternatively, Defendant Capriati argues that the terms of the Draft Agreement should
10
be given effect pursuant to the doctrine of promissory estoppel. However, promissory estoppel
11
may only be applied as a substitute for consideration or as an exception to the statute of frauds,
12
and cannot not act as a substitute for an actual agreement. See, e.g., Bartello v. CitiMortgage,
13
Inc., No. 2:13-CV-1891-GMN-VCF, 2014 WL 1514174, at *5 (D. Nev. Apr. 16, 2014).
14
Defendant Capriati ignores this limitation, arguing that promissory estoppel could be applied to
15
nullify the Draft Agreement’s signature requirement. However, as Defendant Capriati fails to
16
cite any prior case in which the doctrine of promissory estoppel was applied to nullify a
17
specific manner of acceptance contemplated within an agreement, and the Court is unable to
18
identify any such authority, the Court finds Defendant Capriati’s argument unavailing.2
19
B.
The Credit Application and Price Quote
20
Ergon argues that the Credit Application and Price Quote constitute a binding
21
22
23
24
25
As relevant here, Black’s Law Dictionary defines “execute” as “[t]o make (a legal document) valid by signing;
to bring (a legal document) into its final, legally enforceable form.” EXECUTE, Black’s Law Dictionary (10th
ed. 2014).
1
2
Nevertheless, even if the requirement of a specific manner of acceptance could be nullified through promissory
estoppel, Defendant Capriati has failed to show that it was harmed as a result of reasonable reliance upon
Ergon’s conduct. The fact that Defendant Capriati began accepting deliveries of PG76-22NV five days before
Mr. Hunt indicated that he would sign the Draft Agreement belies the assertion that Defendant Capriati relied on
the statement in conducting its business with Ergon.
Page 9 of 13
1
agreement. It is undisputed that Mr. Rocchio, Defendant Capriati’s president, executed the
2
Credit Application on October 26, 2010. (Credit Application, ECF No. 41-1). However, the
3
Credit Agreement does not address asphalt products or prices, nor does it contain any
4
provisions regarding escalation. Furthermore, Ergon does not allege that Defendant Capriati
5
violated any terms of the Credit Agreement. Therefore, while it appears that the Credit
6
Agreement constitutes a valid contract between Ergon and Defendant Capriati, this agreement
7
bears no relevance to the instant dispute.
8
Though the parties are likely bound by the Credit Agreement, the same cannot be said of
9
the Price Quote. It is a thoroughly established principle of contract law that “a counteroffer that
10
deviates from the terms of an offer ordinarily operates as a rejection of the offer so as to
11
terminate the offer immediately.” Martinez v. Brownco Const. Co., 301 P.3d 1167, 1170 (Cal.
12
2013). There is no evidence in the record to suggest that Defendant Capriati unconditionally
13
accepted the terms of the Price Quote after it was transmitted on October 27, 2010. Quite the
14
contrary, instead of accepting the terms of the Price Quote, Defendant Capriati counteroffered
15
by sending the Draft Agreement to Ergon on January 10, 2011. Thus, even if the Price Quote
16
constituted an offer, that offer was terminated at the moment Defendant Capriati sent the Draft
17
Agreement.
18
As the parties have failed to show that either the Draft Agreement or the Price Quote
19
constitute a binding contract, the Court finds that both Ergon’s and Defendant Capriati’s claims
20
for breach of contract fail as a matter of law. Concordantly, as both parties’ claims for breach
21
of the covenant of good faith and fair dealing presuppose the existence of a valid contract, these
22
claims also fail.
23
C.
24
“In Nevada, the elements of an unjust enrichment claim or ‘quasi contract’ are: (1) a
25
Unjust Enrichment
benefit conferred on the defendant by the plaintiff; (2) appreciation of the benefit by the
Page 10 of 13
1
defendant; and (3) acceptance and retention of the benefit by the defendant (4) in circumstances
2
where it would be inequitable to retain the benefit without payment.” WMCV Phase 3, LLC v.
3
Shushok & McCoy, Inc., 750 F. Supp. 2d 1180, 1196 (D. Nev. 2010) (citing Leasepartners
4
Corp., Inc. v. Robert L. Brooks Trust, 942 P.2d 182, 187 (Nev. 1997)). However, a plaintiff
5
need not have directly conferred the benefit upon the defendant to recover under a claim of
6
unjust enrichment, so long as the benefit was conferred as a result of the plaintiff’s actions. Id.
7
(citing Topaz Mut. Co., Inc. v. Marsh, 839 P.2d 606, 613 (Nev. 1992)).
8
The undisputed facts in this case clearly demonstrate that the first three elements are
9
satisfied as to Ergon’s unjust enrichment claim.3 The parties do not dispute that, due to the
10
increase of PG76-22NV’s price during the course of the Project, Defendant Capriati received
11
over $224,901.91 in escalation payments from NDOT that were not passed on to Ergon.
12
(NDOT Balance Report p. 23, ECF No. 41-7). Nor does Defendant Capriati deny that it has
13
retained and appreciated these payments. However, Defendant Capriati does argue that it
14
would not be inequitable for the Court to allow it to continue to retain the escalation payments.
15
Defendant Capriati cites Korea Life Insurance Company v. Morgan Guaranty Trust
16
Company of New York, 269 F. Supp. 2d 424 (S.D.N.Y. 2003), in support of its assertion that
17
principles of equity weigh in its favor. In Morgan, the court held that, under New York law, no
18
liability may exist under a theory of unjust enrichment when a party incurs an additional cost
19
due to a risk that was known at the time a contract was formed. 269 F. Supp. 2d at 447.
20
However, this holding is inapplicable to the instant case because, as discussed supra, Ergon and
21
Defendant Capriati never entered a binding agreement governing the sale of PG76-22NV.
22
23
24
25
3
Citing Las Vegas Fetish & Fantasy Halloween Ball, Inc. v. Ahern Rentals, Inc., 182 P.3d 764 (Nev. 2008),
Defendant Capriati argues that Mr. Hunt’s ultimately incorrect representations that Ergon would sign the Draft
Agreement amount to “unclean hands” which prohibit Ergon from recovering under a theory of unjust
enrichment. However, Defendant Capriati fails to provide any evidence showing that these representations were
made in bad faith, and it is clear from the record that Ergon was not obligated to sign the Draft Agreement.
Therefore, the facts of this case do not warrant a finding that Ergon should be prohibited from recovering as a
result of “unclean hands.”
Page 11 of 13
1
Instead, the Court finds Asphalt Products Corporation v. All Star Ready Mix, Inc., 898
2
P.2d 699 (Nev. 1995), particularly relevant to the case at bar. All Star involved a dispute
3
between a concrete mixing company and an equipment seller. 898 P.2d at 700. Though the
4
parties never executed a written agreement, the mixing company issued a letter communicating
5
its intent to purchase a tractor from the seller once it obtained financing, to which the seller
6
responded by delivering the tractor to the mixing company. Id. The mixing company used the
7
tractor for ten weeks, but was ultimately unable to obtain financing. Id. As a result, the seller
8
repossessed the tractor. Id. In regard to the seller’s unjust enrichment claim, the Nevada
9
Supreme Court held that the mixing company was liable for the fair cost of renting the tractor
10
for ten weeks, because it had obtained a benefit from its use of the tractor without
11
compensating the seller. Id. at 702.
12
In the instant case, just as in All Star, there is no written agreement governing the
13
transaction between the parties. Just as the mixing company in All Star benefitted from the use
14
of the ultimately repossessed tractor, Defendant Capriati received significant compensation
15
from NDOT for market risks that were actually borne by Ergon. Concordantly, just as the
16
seller in All Star was entitled to compensation for the mixing company’s use of the tractor,
17
Ergon is entitled to the funds obtained by NDOT based on the increase in asphalt prices that
18
occurred while the Project was ongoing. Therefore, the Court will grant summary judgment in
19
favor of Ergon as to the unjust enrichment claims.4 As the parties do not dispute Ergon’s
20
calculation of escalation prices pursuant to NDOT’s formula, the Court will enter judgment in
21
favor of Ergon in the amount of $224,901.91.
22
Furthermore, because it is undisputed that Defendants Zurich and Fidelity should be held
23
24
25
4
Because the Court finds that it would be inequitable for Defendant Capriati to retain the escalation payments,
Defendant Capriati’s unjust enrichment claim, which seeks recovery for the $63,505.01 already paid for
escalation, fails as a matter of law. Similarly, Defendant Capriati’s deceptive trade practices claim also fails, as
it is premised upon the assertion that Ergon was not entitled to escalation payments.
Page 12 of 13
1
liable as sureties based on Defendant Capriati’s failure to pay for labor and materials related to
2
the Project, see (Labor and Material Bond, ECF No. 7), the Court will grant summary judgment
3
in favor of Ergon as to the claim against bond. Accordingly, Defendants Zurich and Fidelity
4
will be held jointly and severally liable pursuant to the judgment against Defendant Capriati.
5
IV.
6
CONCLUSION
IT IS HEREBY ORDERED that Ergon’s Motion for Summary Judgment, (ECF No.
7
41), is GRANTED as to Ergon’s unjust enrichment claim and Ergon’s claim against bond.
8
IT IS FURTHER ORDERED that Ergon’s Motion for Summary Judgment as to
9
10
Defendants’ Counterclaims, (ECF No. 45), is GRANTED.
IT IS FURTHER ORDERED that Defendants’ Motion for Summary Judgment, (ECF
11
No. 46), is GRANTED as to Ergon’s Claims for breach of contract and breach of the
12
covenant of good faith and fair dealing.
13
14
15
IT IS FURTHER ORDERED that Defendant Capriati’s Motion for Summary
Judgment as to its Counterclaims, (ECF No. 50), is DENIED.
IT IS FURTHER ORDERED that judgment be entered in the amount of $224,901.91
16
in favor of Ergon and against Defendants Capriati, Zurich, and Fidelity, jointly and severally.
17
The Clerk is instructed to close the case.
18
DATED this 29th day of April, 2015.
19
20
21
___________________________________
Gloria M. Navarro, Chief Judge
United States District Court
22
23
24
25
Page 13 of 13