Camino Properties, LLC v. Insurance Company of the West
Filing
60
ORDER Denying 33 , 40 , 41 , 44 , 56 , and 57 Motions. Signed by Judge Andrew P. Gordon on 5/12/2015. (Copies have been distributed pursuant to the NEF - DC)
1
UNITED STATES DISTRICT COURT
2
DISTRICT OF NEVADA
3
4
CAMINO PROPERTIES, LLC, a foreign
limited liability company,
5
Plaintiff,
6
v.
7
8
9
10
11
INSURANCE COMPANY OF THE WEST, a
California company, DOES INDIVIDUALS 1
through 100, inclusive; ROE ENTITIES 1
through 100, inclusive, BOE BONDING
COMPANIES 1 through 100, inclusive,
Case No. 2:13-cv-02262-APG-CWH
ORDER DENYING MOTIONS FOR
SUMMARY JUDGMENT AND MOTIONS TO
STRIKE
(Dkt. ##33, 40, 41, 44, 56, 57)
Defendants.
12
13
A developer agreed to make off-site improvements to public roads and other property in
14
15
16
exchange for the City of North Las Vegas (“City”) allowing the developer to build a new
residential community. The City also required the developer to purchase a bond to guarantee to
17
the City that the developer will complete the off-site improvements (the “Bond”). The Bond was
18
issued by defendant Insurance Company of the West (“ICW”)
19
20
The developer went bankrupt before it finished building the community or the off-site
improvements. Plaintiff Camino Properties, LLC purchased the half-built community and
21
endeavored to finish it. The City assigned its rights under the Bond to Camino, and Camino, in
22
23
24
turn, requested that ICW honor the Bond and pay for the off-site improvements. ICW refused.
Camino claims it finished the off-site improvements on its own and brought this lawsuit to
25
collect on the Bond from ICW. ICW moves for summary judgment, arguing that (1) Camino’s
26
claims on the Bond are barred by the statute of limitations; (2) only the City, not Camino, can
27
28
1
enforce the Bond; and (3) the Bond is discharged because of a failed condition precedent.
2
Camino also moves for partial summary judgment that ICW is liable to Camino under the Bond.1
3
I deny all motions. There are genuine disputes of fact about whether the statute of
4
limitations applies, whether Camino can enforce the Bond, and whether ICW is relieved of its
5
obligations. Summary judgment is thus not warranted.
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
I.
BACKGROUND
A.
Off-site improvements agreements and performance bonds generally
When a developer seeks to build a new residential community, Nevada law allows cities
to require that the developer make off-cite improvements to public property surrounding the new
homes, such as road improvements. Cities do this by requiring the developer to enter into an
“off-site improvement agreement” with the city. This agreement specifies the improvements the
developer must make. The city also may require that the developer buy a performance bond to
guarantee that the developer will finish the off-site improvements. If the developer fails to make
the improvements, the bond obligates the surety to either complete the improvements or pay for
someone else to complete them.
B.
Relevant facts in this case
In this case, a developer wished to build a residential community in North Las Vegas. In
2005, this original developer entered into an off-site improvement agreement with the City.2 That
agreement required the developer to make improvements to property surrounding its planned
community, such as renovating roadways. ICW provided the Bond guaranteeing that the original
developer would complete all the improvements in the off-site improvement agreement.3
23
24
25
26
27
28
1
ICW also filed two motions to strike and two motions for oral argument. I decline to order oral
argument in this case. I address ICW’s motions to strike below.
2
(Dkt. #34 at 25-29.)
3
(Id. at 31-32.)
Page 2 of 12
The original developer went bankrupt before it could finish the community and off-site
1
2
improvements. The City notified ICW of the developer’s default, and ICW endeavored to
3
complete the improvements itself (rather than pay out the Bond’s penal sum of roughly
4
$750,000).4 ICW and the City negotiated a final punch list of items to finish, and ICW alleges it
5
believed it had completed all of the improvements the City asked for.5 In 2010, ICW asked the
6
City to release the Bond, but the City refused.6 The off-site agreement states it will be in effect
7
until the City issues a written certificate of completion—which never occurred.7
8
The following year, Camino purchased the mostly-built residential community and began
9
finishing the project.8 Camino asked the City to compel ICW to finish the off-site improvements
10
or reimburse Camino for the improvements.9 Instead, the City assigned its rights under the Bond
11
to Camino.10 Camino completed the off-site improvements and sued ICW for reimbursement
12
under the Bond.
13
II.
LEGAL STANDARDS
14
A.
Summary Judgment
15
Summary judgment is appropriate when “the pleadings, depositions, answers to
16
interrogatories, and admissions on file, together with the affidavits, if any, show there is no
17
genuine issue as to any material fact and that the movant is entitled to judgment as a matter of
18
law.”11 For summary judgment purposes, the court views all facts and draws all inferences in the
19
light most favorable to the nonmoving party.12
20
4
(Dkt. #33-1 at 5.)
5
(Id.)
6
(Id.)
23
7
(Id.)
24
8
(Dkt. #35.)
9
(Id.)
21
22
25
10
(Id.)
26
11
Celotex Corp. v. Catrett, 477 U.S. 317, 330 (1986) (citing Fed. R. Civ. P. 56(c)).
27
12
Kaiser Cement Corp. v. Fishbach & Moore, Inc., 793 F.2d 1100, 1103 (9th Cir. 1986).
28
Page 3 of 12
If the moving party demonstrates the absence of any genuine issue of material fact, the
1
2
burden shifts to the nonmoving party to “set forth specific facts showing that there is a genuine
3
issue for trial.”13 The nonmoving party “must do more than simply show that there is some
4
metaphysical doubt as to the material facts.”14 It “must produce specific evidence, through
5
affidavits or admissible discovery material, to show” a sufficient evidentiary basis on which a
6
reasonable fact finder could find in its favor.15
A party must support or refute the assertion of a fact with admissible evidence.16 As the
7
8
summary judgment procedure is the pretrial functional equivalent of a directed-verdict motion, it
9
requires consideration of the same caliber of evidence that would be admitted at trial.17 Thus, it is
10
insufficient for a litigant to merely attach a document to a summary judgment motion or
11
opposition without affirmatively demonstrating its authenticity.
12
III.
DISCUSSION
13
ICW presents three theories for why it should not be liable to Camino on the performance
14
bond: (1) the statute of limitations period has passed, (2) the assignment to Camino is invalid, and
15
(3) the City’s failure to notify ICW of defects in their performance relieves ICW of its bond
16
obligations.
17
A.
18
The parties dispute both (1) which statute of limitations period applies to Camino’s claim
19
Whether the statute of limitations bars Camino’s suit
on the Bond and (2) the date the limitations period commences.
20
21
22
13
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 256 (1986); Celotex, 477 U.S. at 323.
23
14
Bank of Am. v. Orr, 285 F.3d 764, 783 (9th Cir. 2002) (internal citations omitted).
15
Bhan v. NME Hosps., Inc., 929 F.2d 1404, 1409 (9th Cir. 1991); Anderson, 477 U.S. at
24
25
26
248–49.
16
Fed. R. Civ. Proc. 56(c)(1); Orr, 285 F.3d at 773; Harris v. Graham Enterprises, Inc.,
2009 WL 648899, at *2 (D. Ariz. Mar. 10, 2009).
17
27
28
Anderson, 477 U.S. at 251 (citing Bill Johnson’s Restaurants, Inc. v. NLRB, 461 U.S.
731, 745 n.11 (1983)).
Page 4 of 12
1.
1
Applicable limitations period
2
ICW argues that Camino’s claim on the Bond is governed by the three-year limitations
3
period for claims arising from statutory liabilities. NRS §11.190(3)(a). Camino argues the six-
4
year contract limitations period applies because its claim on the Bond is contractual. NRS
5
§11.190(1)(b).
6
Generally, the nature of the principal’s liability (not the surety’s liability) defines the
7
applicable limitations period. For example, in Torrealba v. Kesmetis, the Nevada Supreme Court
8
held that the three-year limitations period applied to a claim on a notary’s performance bond. 18
9
The Nevada Supreme Court looked to the nature of the notary’s services, not to the terms of the
10
bond. The Court explained that a claim on a notary bond is an action upon a liability created by
11
statute because “the position, duties, and liability of a notary public” are created by statute.19
12
Because the notary’s liability is created by statute, the bond guaranteeing the notary’s compliance
13
with a statute was also treated as a statutory liability for purposes of the limitations period. In
14
Steel v. Nat'l Sur. Corp. of N.Y., a real estate broker’s bond was found to not be a statutory
15
liability because the bond guaranteed the broker would not defraud customers, a liability that
16
arose from common law duties rather than statutory ones.20
17
Here, there is no allegation that either the original developer or ICW violated a statute.
18
ICW’s liability, if any, arises from the Bond and from the original developer’s breach of the off-
19
site improvement agreement. These are contractual claims subject to the contractual limitations
20
period of six years.
21
ICW argues that Camino’s Bond claim is a statutory liability claim because a statute
22
required the developer to buy the Bond. But, as explained above, whether the bond is required by
23
statute is irrelevant; the proper inquiry is whether the principal’s liability arose from statute. ICW
24
25
18
26
124 Nev. 95, 103-04 (2008).
19
Id.
27
20
74 Ariz. 193, 196 (1952).
28
Page 5 of 12
1
primarily relies on Torrealba v. Kesmetis, and Sonoma County v. Hall21 for its argument. But
2
neither of these cases supports its position. In both cases the court applied a statutory liability
3
period to a bond claim because the bond guaranteed performance of statutory duties. In
4
Torrealba, the Nevada Supreme Court applied the statutory liability period to a claim on a notary
5
bond because the bond guaranteed that a notary would comply with statutory duties. Similarly, in
6
Sonoma, the California Supreme Court held that a bond guaranteeing a county recorder’s services
7
was a statutory liability because the bond guaranteed performance of the recorder’s statutory
8
duties.
9
Unlike in Torrealba and Sonoma, the Bond here guarantees compliance with a contract,
10
not a statute. The terms of the off-site agreement are not prescribed by statute. NRS §278.380
11
merely allowed the City to require the developer to enter into the off-site agreement and procure a
12
bond. The developer, and ICW, are liable only if the off-site agreement was breached. There is
13
no claim that either violated a statute.
ICW cannot be right that liabilities arising from a contract, where the contract is required
14
15
by statute, is a “liability by statute.” Indeed, drivers in this state are required to enter into a
16
contract for insurance.22 Even though insurance contracts exist because a statute requires drivers
17
to buy them, claims for breaches of the insurance policy are governed by the six-year limitations
18
period for contracts.23 Statutes require people to enter into contracts in many situations, but this
19
does not convert an action on the contract into a statutory claim.
The principal’s and ICW’s liability are thus contractual liabilities with a six-year
20
21
limitations period.
22
////
23
////
24
25
21
26
132 Cal. 589 (1900)
22
Nev. Rev. Stat. § 485.185.
27
23
See State Farm Mut. Auto. Ins. Co. v. Fitts, 120 Nev. 707, 710 (2004).
28
Page 6 of 12
2.
1
Accrual date
The general rule in Nevada is that a cause of action accrues on the date a lawsuit could
2
3
first be brought.24 A surety’s liability usually accrues at the same time as the principal.25 But if a
4
contract term says otherwise, a surety’s liability may accrue at a later time. The “discharge of the
5
principal by the running of the statute of limitations” does not necessarily “exonerate [the
6
surety’s] obligation on the bond.”26
ICW argues it could have been sued on the Bond the day the principal was obligated to
7
8
complete the off-site improvements, which is March 17, 2007. It argues that March 17, 2007 is
9
the date Camino’s bond action accrued. But as ICW notes in other places during its briefing, the
10
Bond specifically gave ICW the option of completing the improvements itself in lieu of paying
11
out the Bond’s penal sum. By the terms of the Bond, the City could not have sued ICW until
12
ICW failed to complete the improvements.
13
The relevant date for the statute of limitations calculation is December of 2007, six years
14
before Camino brought this case. In other words, the statute of limitations bars Camino’s claims
15
only if the City could have brought its claim before December of 2007. But ICW has submitted
16
no evidence the City knew of ICW’s alleged failure to complete the improvements before
17
December of 2007. Indeed, ICW admits it continued working on the improvements long after
18
then.
ICW elected to conduct the improvements to the property rather than paying out the penal
19
20
sum. ICW cannot now claim the City sat on its rights by allowing ICW the opportunity to finish
21
the project. ICW’s motion for summary judgment based on the statute of limitations is denied.
22
////
23
////
24
25
26
27
28
24
Clark v. Robison, 113 Nev. 949, 951 (1997).
25
Bloom v. Bender, 48 Cal. 2d 793, 799, 313 P.2d 568, 572 (1957); Royal Thrift & Loan Co. v.
Cnty. Escrow, Inc., 123 Cal. App. 4th 24, 43 (2004).
26
Cnty. of Los Angeles v. Sec. Ins. Co., 52 Cal. App. 3d 808 (Ct. App. 1975).
Page 7 of 12
1
B.
Whether the assignment to Camino was invalid
2
ICW next argues the City’s assignment of the Bond to Camino was invalid and that
3
Camino therefore cannot enforce the Bond. ICW’s sole argument against the assignment is that
4
some courts in other states have held that municipalities may not assign their rights under
5
performance bonds.27 ICW mainly relies on a California case from the 1950’s: Morro Palisades
6
Co. v. Hartford Acc. & Indem. Co.28 In Morro, the California Supreme Court held that only
7
municipalities can enforce performance bonds in favor of the public.
8
But nearly every case after Morro has narrowed its holding. Courts appear to now
9
generally agree that municipalities may assign their rights under a performance bond if the
10
assignment is made for the purpose of completing the improvements in question. These courts
11
reason that a surety like ICW should not “be exonerated . . . simply because the bargained-for
12
improvements were completed by an assignee of the claim by agreement with the municipality.
13
The purpose of the bond, to provide the means by which a municipality may insure completion of
14
a bargained for performance, will be fulfilled” by allowing assignment.29 For example, in
15
Transdulles Ctr. Ltd. P'ship v. USX Corp., the Court held that a private assignee of a performance
16
bond could enforce the bond because there was evidence the assignee had completed some of the
17
off-site improvements in question.30
18
19
In its reply, ICW appears to now agree the City could assign its right under the Bond if the
assignment was for the purpose of completing the improvements. But ICW argues that the City
20
21
22
23
24
25
26
27
28
27
The parties agree that Nevada courts have not yet addressed whether municipalities can assign
rights under performance bonds.
28
52 Cal. 2d 397 (1959).
29
Clearwater Associates, Inc. v. F. H. Bridge & Son, Contractors, 144 N.J. Super. 223, 228-29
(App. Div. 1976); see also Transdulles Ctr. Ltd. P'ship v. USX Corp., 761 F. Supp. 430, 436 (E.D. Va.
1991) (holding that Morro has been “repeatedly” narrowed to situations where an assignment is made for
the sole benefit of a private party and there is no evidence the improvements have been made); Bd. of
Sup'rs of Fairfax Cnty. v. Ecology One, Inc., 219 Va. 29, 33 (1978); Clearwater Associates, Inc. v. F. H.
Bridge & Son, Contractors, 144 N.J. Super. 223, 229 (App. Div. 1976); Will Cnty. v. Woodhill
Enterprises, Inc., 4 Ill. App. 3d 68, 75 (1971).
30
Transdulles, 761 F. Supp. at 436.
Page 8 of 12
1
did not assign its rights for the purpose of completing the improvements. Instead, ICW argues,
2
the City assigned its rights “for Plaintiff’s sole financial benefit.”
3
Camino has provided evidence raising a genuine dispute about whether the City assigned
4
its rights under the Bond, at least in part, to facilitate completion of the off-site improvements.31
5
Indeed, the assignment’s language indicates the assignment was made to facilitate the off-site
6
improvements. It states the assignee “intends to complete” the improvements and that it is in the
7
“best interests of the Parties to complete” the improvements.32
8
9
Even if Nevada would adopt the assignment rule ICW raises, it has not established it
applies here.
10
C.
Whether Camino’s claims are barred by the City’s failure to notify ICW
11
A party’s contractual obligations may be excused if another party has not satisfied a
12
condition precedent to the obligations. But, contractual promises are not generally interpreted to
13
be conditions to another party’s performance “unless it is clear that this is what the parties
14
intended.”33 “Conditions precedent are not favored,” and a contract is strictly construed against a
15
party asserting a condition precedent.34
16
ICW argues that its obligations on the bond are “conditioned” on the City notifying ICW
17
before finishing the off-site improvements. ICW points to the Bond which states that “in case of
18
default by Principal, [ICW] may assume and complete or procure completion of the obligations of
19
Principal.” Although the City originally informed ICW of the default and allowed ICW to work
20
31
21
22
(Dkt. #34.) ICW suggests that Mr. Walters has no personal knowledge of this fact, but he avers
that he directly participated in the discussions with the City’s attorney.
32
Id. at 39
33
23
24
25
26
Unihan Corp. v. Max Grp. Corp., 2011 WL 6814044, at *11 (C.D. Cal. Dec. 28, 2011); see also
Alpha Beta Food Markets v. Retail Clerks Union Local 770, 45 Cal.2d 764, 771, 291 P.2d 433 (1956)
(“[I]t is the general rule in contract interpretation that stipulations in an agreement are not to be construed
as conditions precedent unless such construction is required by clear, unambiguous language.”); Pacific
Allied v. Century Steel Products, Inc., 162 Cal.App.2d 70, 79–80, 327 P.2d 547 (1958) (“Conditions
precedent are not favored in the law and the provisions of a contract will not be construed as conditions
precedent in the absence of language plainly requiring such construction.”).
34
27
28
Chevron U.S.A. Inc. v. Sheikhpour, 469 F. App'x 593, 596 (9th Cir. 2012); see also Helzel v.
Superior Court, 123 Cal.App.3d 652 (1981).
Page 9 of 12
1
on the off-site improvements, ICW argues the City should have also informed ICW that the off-
2
site work had not been properly completed before having a third party finish it.
3
ICW provides no legal authority or analysis to suggest that the City’s failure to notify
4
ICW should be read as a “condition precedent” rendering the Bond unenforceable. The City
5
notified ICW of the principal’s default as the Bond required. The City gave ICW the opportunity
6
to finish the improvements, as the Bond required. There is no clear language in the Bond
7
suggesting that once ICW had failed to properly finish the project the City again had to notify
8
ICW before finishing it itself. Even if the Bond did require notice, there is no indication the
9
parties intended notification to be a condition precedent to ICW’s obligations.
10
ICW has not provided sufficient evidence or authority for me to find the parties intended
11
notification to be a condition precedent to ICW’s obligation. ICW’s motion for summary
12
judgment is therefore denied.
13
D.
Whether Camino is entitled to summary judgment on ICW’s liability
14
Camino asks for partial summary judgment that the Bond was validly assigned and that
15
ICW is liable under the Bond. Camino first argues there is no genuine dispute about whether the
16
City assigned the bond for the purposes of completing the off-site improvements.35 But ICW has
17
submitted evidence indicating there is a genuine dispute about the real purpose of the assignment.
18
For example, ICW points to language in letter agreements between Camino and the City that
19
indicate Camino had assumed the obligation to finish the off-site improvements before the City
20
transferred its Bond rights.36 Camino is thus not entitled to summary judgment that the Bond was
21
validly assigned.
22
Camino also seeks partial summary judgment that ICW is liable for breach of the Bond.
23
As explained above, Camino has not established a lack of genuine dispute about whether the
24
assignment was valid—so it is not entitled to summary judgment on ICW’s liability. Regardless,
25
26
35
(Dkt #44 at 23.)
27
36
(Dkt. #33-1.)
28
Page 10 of 12
1
there are genuine disputes about ICW’s liability on the Bond. For example, ICW has submitted
2
evidence from which a reasonable jury could find that the City, and therefore its assignee
3
Camino, agreed to relieve ICW of its obligations under the Bond by negotiating and signing off
4
on the improvements ICW completed.37
I therefore deny Camino’s request for partial summary judgment on whether its
5
6
assignment is valid and whether ICW is liable for a breach.
7
E.
8
ICW moves to strike portions of two affidavits Camino relies on, arguing the affiants have
9
Motions to Strike
no personal knowledge of the statements they make. In ruling on the parties’ motions for
10
summary judgment, I have not relied on most of these disputed statements. The one statement I
11
have considered in ruling on defendants’ motion for summary judgment appears to be supported
12
by personal knowledge. I considered Mr. Walter’s statement about whether the City assigned the
13
Bond for the purposes of completing the improvements. But Mr. Walters avers that he directly
14
participated in the assignment discussions with the City, and ICW provides no evidence
15
indicating Mr. Walters lacks personal knowledge of these events. I thus deny ICW’s motions to
16
strike.
17
IV.
IT IS THEREFORE ORDERED that defendant’s motion for summary judgment (Dkt.
18
19
#33) is DENIED.
IT IS FURTHER ORDERED that plaintiff’s motion for summary judgment (Dkt. #44) is
20
21
CONCLUSION
DENIED.
IT IS FURTHER ORDERED that defendant’s motions to strike (Dkt. ##40, 41) are
22
23
DENIED.
24
////
25
////
26
27
28
37
(See, e.g., Dkt. #33-1, at ¶¶18-21; Dkt. #33-11 (Ex. 9); Dkt. 33-12 (Ex. 10); Dkt. #33-1, at ¶23.)
Page 11 of 12
1
2
3
IT IS FURTHER ORDERED that defendant’s motions for oral argument (Dkt. ##56, 57)
are DENIED.
DATED this 12th day of May, 2015.
4
5
ANDREW P. GORDON
UNITED STATES DISTRICT JUDGE
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Page 12 of 12
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?