ORDER Granting 16 Motion for Summary Judgment. The Clerk of Court is instructed to enter judgment in favor of Plaintiffs and close this case. Signed by Judge Richard F. Boulware, II on 7/13/2016. (Copies have been distributed pursuant to the NEF - DL)

Download PDF
1 2 3 4 UNITED STATES DISTRICT COURT 5 DISTRICT OF NEVADA 6 *** 7 9 TRUSTEES OF THE BRICKLAYERS & ALLIED CRAFTWORKERS LOCAL 13 DEFINED CONTRIBUTION PENSION TRUST FOR SOUTHERN NEVADA, et al., 10 Plaintiffs, 8 11 12 Case No. 2:14-cv-01448-RFB-NJK ORDER v. G.G. CONSTRUCTION, INC., et al., 13 Defendants. 14 15 I. INTRODUCTION 16 This is an action brought under the Employee Retirement Income Security Act of 1974 17 (“ERISA”), 29 U.S.C. § 1001 et seq. Plaintiffs are various trusts seeking to collect unpaid 18 contributions allegedly owed to them under a collective bargaining agreement and related trust 19 agreements under which Defendant G.G. Construction is obligated to make regular payments for 20 the benefit of its employees. Plaintiffs now move for summary judgment. For the reasons stated 21 below, the Court grants summary judgment in favor of Plaintiffs. 22 23 24 II. BACKGROUND A. Procedural History 25 Plaintiffs filed their Complaint on September 8, 2014. ECF No. 1. Plaintiffs assert three 26 causes of action in their Complaint: (1) Breach of Written Collective Bargaining Agreements and 27 Related Trust Agreements, (2) Breach of Fiduciary Duty, and (3) Misappropriation of Trust Assets. 28 Defendants G.G. Construction, Inc., Kevin V. Green, and Chris S. Green filed an Answer 1 on October 15, 2014. ECF No. 6. On November 6 and November 17, 2014, the Court issued two 2 separate Orders to Show Cause why Defendants should not be sanctioned and/or have default 3 judgment entered against them for failure to file a certificate of interested parties. ECF No. 8, 9. 4 On December 5, 2014, following Defendants’ filing of a certificate of interested parties, the Court 5 discharged its Order to Show Cause, but cautioned Defendants and their counsel that future non- 6 compliance with Court orders or rules of court will result in significant monetary sanctions and/or 7 case-dispositive sanctions. ECF No. 13. 8 On December 23, 2014, Defendants filed a Notice of Bankruptcy on the Record as to 9 Defendants Kevin V. Green and Christine S. Green. ECF No. 14. On June 19, 2015, Plaintiffs filed 10 a Notice of Voluntary Dismissal against Kevin and Christine Green. ECF No. 15. The docket does 11 not reflect that these Defendants were ever dismissed from the case. The Court finds that dismissal 12 is appropriate under Fed. R. Civ. P. 41(a)(1)(A), and Kevin V. Green and Chris S. Green are 13 therefore dismissed from this action. Accordingly, G.G. Construction is the only remaining 14 Defendant in this action. 15 On September 15, 2015, Plaintiffs filed a Motion for Summary Judgment against G.G. 16 Construction. ECF No. 16. G.G. Construction failed to respond to the motion. On October 16, 17 2015, Plaintiffs filed a Notice of Non-Opposition and a Proposed Findings of Fact and Order. ECF 18 No. 17. The Court held a hearing on the motion on July 7, 2016, at which G.G. Construction failed 19 to appear. B. Effect of G.G. Construction’s Failure to Respond 20 21 In its Notice of Non-Opposition, Plaintiffs request that the Court grant summary judgment 22 in their favor based on G.G. Construction’s failure to respond to Plaintiffs’ Motion for Summary 23 Judgment. Plaintiffs cite Local Rule of Practice 7-2(d), which at the time of the filing of the motion 24 stated that “[t]he failure of an opposing party to file points and authorities in response to any 25 motion shall constitute a consent to the granting of the motion.” 1 26 27 28 1 The Local Rules of Practice for the District of Nevada were revised effective May 1, 2016. The new version of Local Rule 7-2(d) excludes motions under Fed. R. Civ. P. 56 and motions for attorney’s fees, which is consistent with the Court’s analysis here. -2- 1 The Court finds, however, that the local rules in this district do not permit the automatic 2 granting of an unopposed motion for summary judgment. “[A] nonmoving party’s failure to 3 comply with local rules does not excuse the moving party’s affirmative duty under Rule 56 to 4 demonstrate its entitlement to judgment as a matter of law. Short of that, we turn the summary 5 judgment rule into a mere sanction for noncompliance with local rules.” Martinez v. Stanford, 323 6 F.3d 1178, 1182 (9th Cir. 2003) (citing Fed. R. Civ. P. 56); see also Henry v. Gill Indus., Inc., 983 7 F.2d 943, 950 (9th Cir. 1993) (“A local rule that requires the entry of summary judgment simply 8 because no papers opposing the motion are filed or served, and without regard to whether genuine 9 issues of material fact exist, would be inconsistent with Rule 56, hence impermissible under Rule 10 83.”). 11 Nevertheless, an opposing party’s failure to respond does permit the Court to consider the 12 moving party’s assertions of fact as undisputed for purposes of the motion, and to “grant summary 13 judgment if the motion and supporting materials—including the facts considered undisputed— 14 show that the movant is entitled to it.” Fed. R. Civ. P. 56(e)(2)-(3); see also Heineman v. 15 Satterberg, 731 F.3d 914, 916-17 (9th Cir. 2013) (discussing the consequences of failing to respond 16 to facts presented in a motion for summary judgment). The Court will therefore treat the facts 17 presented by Plaintiffs, provided they are properly supported with admissible evidence, as 18 undisputed for purposes of this motion. 19 C. Undisputed Facts 20 After reviewing the admissible evidence in the record, the Court finds the following facts 21 to be undisputed. Plaintiffs are trustees of numerous express trusts and one union. The trustees are 22 the Trustees of the Bricklayers & Allied Craftworkers Local 13 Defined Contribution Pension 23 Trust for Southern Nevada, the Trustees of the Bricklayers & Allied Craftworkers Local 134 24 Health Benefits Fund, the Trustees of the Bricklayers & Allied Craftworkers Local 13 Vacation 25 Fund, the Trustees of the Bricklayers & Trowel Trades International Pension Fund, the Trustees 26 of the Bricklayers & Trowel Trades International Health Fund, and the Trustees of the International 27 Masonry Institute (collectively, the “Trust Plaintiffs”). The remaining Plaintiff is the Bricklayers 28 & Allied Craftworks Local 13 Nevada (“Local 13”). The Trust Plaintiffs are trustees of express -3- 1 trusts created pursuant to formal written Trust Agreements between Local 13 and the Nevada 2 Masonry Employers and the Nevada Tile, Marble, Stone, and Terrazzo Contractors Association. 3 G.G. Construction entered into a collective bargaining agreement (the “Labor Agreement”) 4 with Local 13 on approximately June 15, 2006 as a signatory employer. The trust agreements 5 establishing the trusts represented by the Trust Plaintiffs (the “Trust Agreements”) are 6 incorporated into the Labor Agreement. By signing the Labor Agreement, G.G. Construction also 7 accepted the Trust Agreements and became obligated to the terms and provisions of both sets of 8 agreements. Under the Labor Agreement, G.G. Construction is required to submit regular 9 contribution reports and make monthly fringe benefit contributions to Plaintiffs. The Labor 10 Agreement allows Plaintiffs to conduct an audit of G.G. Construction’s payroll and other records 11 to ensure compliance with the Labor Agreement and ERISA. The Trust Agreements require 12 payment of interest at a rate of 14% on all unpaid contributions until paid, liquidated damages of 13 20% of the unpaid contribution amount, and payment of the Trust Plaintiffs’ attorney’s fees and 14 costs incurred in enforcing payment. 15 In January 2014, Plaintiffs’ auditor completed an audit of G.G. Construction’s records from 16 May 1, 2010 through September 30, 2013. The audit report stated that G.G. Construction failed to 17 make all required fringe benefit payments to Plaintiffs during this period. G.G. Construction 18 disputed the initial audit results and provided supporting documentation to refute certain amounts 19 claimed as being owed. After reviewing these documents, the auditor revised the audit claim. 20 Plaintiffs’ counsel sent a final demand letter to G.G. Construction on August 18, 2014, requesting 21 payment of amounts due as stated in the revised audit. To date, G.G. Construction has not paid the 22 amounts due as stated in the revised audit, although two third parties (the Whiting-Turner 23 Contracting Company and CNA Surety) have paid their portions of the audit claim. The total 24 amount of unpaid contributions owed by G.G. Construction is $7,845.25. 25 26 III. LEGAL STANDARD 27 Summary judgment is appropriate when the pleadings, depositions, answers to 28 interrogatories, and admissions on file, together with the affidavits, if any, show “that there is no -4- 1 genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” 2 Fed. R. Civ. P. 56(a); Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). In considering whether 3 to grant summary judgment, the court views all facts and draws all inferences in the light most 4 favorable to the nonmoving party. Johnson v. Poway Unified Sch. Dist., 658 F.3d 954, 960 (9th 5 Cir. 2011). “When the moving party also bears the burden of persuasion at trial, to prevail on 6 summary judgment it must show that the evidence is so powerful that no reasonable jury would be 7 free to disbelieve it.” Shakur v. Schriro, 514 F.3d 878, 890 (9th Cir. 2008). 8 9 IV. DISCUSSION 10 In its motion, Plaintiffs contend that G.G. Construction was bound by a collective 11 bargaining agreement it entered into with Local 13 that obligated it to make monthly fringe benefit 12 contributions to Plaintiffs and that G.G. Construction failed to make these contributions. Plaintiffs 13 attached evidence supporting the amount of unpaid contributions owed, the interest that has 14 accrued on those unpaid contributions, the costs incurred by the auditor, and the attorney’s fees 15 and costs Plaintiffs accrued in litigating this action. 16 Based upon its review of the evidence submitted, the Court concludes G.G. Construction 17 was required to make fringe benefit contributions to Plaintiffs, that it failed to do so, and that 18 Plaintiffs are entitled to recover those unpaid contributions as well as interest, attorney’s fees and 19 costs, and audit costs. The Court finds this amount to be $38,893.31, plus the interest that continues 20 to accrue from September 14, 2015 onward. 21 A. Applicable Law 22 “ERISA was enacted to protect, inter alia, the interests of participants in employee benefit 23 plans and their beneficiaries. ERISA applies to any employee benefit plan if it is established or 24 maintained . . . by any employer . . . or . . . by any employee organization . . . or by both.” 25 Daniels-Hall v. Nat’l Educ. Ass’n, 629 F.3d 992, 999 (9th Cir. 2010) (quoting 29 U.S.C. §§ 26 1001(b), 1003(a)(1)-(3)). Under ERISA, eligible “employee benefit plans” are classified into two 27 types: employee welfare benefit plans and employee pension benefit plans. 29 U.S.C. § 1002(3). 28 A plan qualifies as an employee welfare benefit plan under ERISA if it provides medical, -5- 1 disability, or vacation benefits, or any benefits “other than pensions on retirement or death, and 2 insurance to provide such pensions.” Id. § 1002(1). Employee pension benefit plans provide 3 retirement income to employees or defer income until retirement. Id. § 1002(2). 4 ERISA provides that “[e]very employer who is obligated to make contributions to a 5 multiemployer plan under the terms of the plan or under the terms of a collectively bargained 6 agreement shall, to the extent not inconsistent with law, make such contributions in accordance 7 with the terms and conditions of such plan or such agreement.” Id. § 1145. A fiduciary of an ERISA 8 plan is authorized to bring a civil action to obtain equitable relief to redress violations of the Act 9 or “to enforce any provisions of this subchapter or the terms of the plan.” Id. § 1132(a)(3). If 10 successful in a Section 1145 enforcement action, the fiduciary may recover damages as follows: 11 19 In any action under this subchapter by a fiduciary for or on behalf of a plan to enforce section 1145 of this title in which a judgment in favor of the plan is awarded, the court shall award the plan— (A) the unpaid contributions, (B) interest on the unpaid contributions, (C) an amount equal to the greater of— (i) interest on the unpaid contributions, or (ii) liquidated damages provided for under the plan in an amount not in excess of 20 percent (or such higher percentage as may be permitted under Federal or State law) of the amount determined by the court under subparagraph (A), (D) reasonable attorney's fees and costs of the action, to be paid by the defendant, and (E) such other legal or equitable relief as the court deems appropriate. 20 29 U.S.C. § 1132(g)(2); see also Idaho Plumbers & Pipefitters Health & Welfare Fund v. United 21 Mech. Contractors, Inc., 875 F.2d 212, 215 (9th Cir. 1989) (ERISA, as amended after 1980, 22 “provide[s] a statutory remedy for a trust fund fiduciary suing to collect unpaid plan 23 contributions.”). 12 13 14 15 16 17 18 24 25 B. Summary Judgment Is Granted in Favor of Plaintiffs for Their First Cause of Action 26 Based on the evidence presented, the Court finds that the Labor Agreement, which 27 incorporates the Trust Agreements establishing the trusts represented by the Trust Plaintiffs, is a 28 qualifying plan under ERISA. The Court further finds that G.G. Construction was obligated to -6- 1 make contributions under the terms of the Labor Agreement and related Trust Agreements and that 2 it failed to make such contributions. The Court therefore grants summary judgment in favor of 3 Plaintiffs on their first cause of action for breach of the collective bargaining agreement and related 4 trust agreements. The Court will now assess the damages owed to Plaintiffs. 5 1. Unpaid Contributions 6 The first category of damages recoverable by Plaintiffs is unpaid contributions. The 7 declaration and audit report from Plaintiffs’ auditor demonstrate that G.G. Construction owes 8 $7,845.25 in unpaid contributions to Plaintiffs. 9 2. Interest on Unpaid Contributions 10 In addition to unpaid contributions, Plaintiffs are entitled to recover “interest on the unpaid 11 contributions.” 29 U.S.C. § 1132(g)(2)(B). Plaintiffs have submitted copies of the applicable 12 agreements demonstrating that interest accrued at a rate of 14% per annum for G.G. Construction’s 13 delinquent contributions. Plaintiffs’ evidence shows that G.G. Construction owed $2,939.25 in 14 interest as of September 14, 2015 and that this interest continues to accrue. 15 3. The Greater of Interest or Liquidated Damages 16 Plaintiffs are also entitled to recover an amount equal to the greater of the interest on unpaid 17 contributions or the “liquidated damages provided for under the plan in an amount not in excess 18 of 20 percent . . . of the [unpaid contributions] determined by the court.” 29 U.S.C. § 19 1132(g)(2)(C). The liquidated damages provision applies “when (1) the fiduciary obtains a 20 judgment in favor of the plan, (2) unpaid contributions exist at the time of suit, and (3) the plan 21 provides for liquidated damages.” Idaho Plumbers, 875 F.2d at 215. Once the liquidated damages 22 provision applies, “liquidated damages are mandatory.” Id. 23 Here, Plaintiffs’ evidence shows that G.G. Construction was subject to a plan that provided 24 for liquidated damages of 20% of unpaid contributions. Given that the Court has determined that 25 the unpaid contributions total $7,845.25, the amount of liquidated damages is 20% of that amount, 26 or $1,569.05. Where the interest on the unpaid contributions exceeds any liquidated damages 27 award, however, ERISA requires that the court award an amount equal to the interest on the unpaid 28 contributions. 29 U.S.C. § 1132(g)(2)(C). The Court thus awards an amount equal to the interest -7- 1 on the unpaid contributions as of September 14, 2015, or $2,939.25—an amount that will continue 2 to rise as additional interest accrues. 4. Attorney’s Fees and Costs 3 4 In addition, Plaintiffs are entitled to recover reasonable attorney’s fees and costs of the 5 action against G.G. Construction. 29 U.S.C. § 1132(g)(2)(D). After reviewing Plaintiffs’ counsel’s 6 declaration and supporting documentation, the Court finds the claimed amount of attorney’s fees 7 and costs to be reasonable. Attorney’s fees and costs are awarded in the amount of $12,229.36 8 ($11,528.50 in fees and $700.86 in costs). 5. Audit Costs 9 10 Finally, Plaintiffs seek to recover the costs of performing audits of G.G. Construction’s 11 financial records. Audit costs are recoverable under ERISA as a type of “other legal or equitable 12 relief.” Operating Eng’rs Pension Trust v. A-C Co., 859 F.2d 1336, 1343 (9th Cir. 1988); 29 U.S.C. 13 § 1132(g)(2)(E) (where a judgment in favor of the plan is awarded, the court shall award “such 14 other legal or equitable relief as the court deems appropriate” to the plan). Plaintiffs’ evidence 15 shows that they incurred audit costs of $12,940.20 in connection with this action. The Court 16 therefore awards this amount under subsection (g)(2)(E). 17 18 V. CONCLUSION 19 For the reasons stated on the record at this hearing, 20 IT IS ORDERED that [16] Motion for Summary Judgment is GRANTED. Summary 21 judgment is granted in favor of Plaintiffs in the amount of $38,893.31, which is comprised of the 22 following amounts: 23 • $7,845.25 in unpaid contributions; 24 • $2,939.25 in interest on unpaid contributions as of September 14, 2015, on which additional interest will continue to accrue until paid; 25 26 • $2,939.25 as an amount equal to the greater of the interest on unpaid contributions 27 or liquidated damages provided for under the plan, on which additional interest will 28 continue to accrue until paid; -8- 1 • $11,528.50 in fees and $700.86 in costs; and 2 3 4 5 $12,229.36 in reasonable attorney’s fees and costs of the action, consisting of • $12,940.20 in audit costs. The Clerk of Court is instructed to enter judgment in favor of Plaintiffs for the above amount and close this case. 6 7 DATED: July 13, 2016. ____________________________ RICHARD F. BOULWARE, II United States District Judge 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 -9-

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?