Buesing Corporation, an Arizona corporation v. Helix Electric of Nevada LLC

Filing 56

ORDER Granting Buesing's 51 Motion for Reconsideration. The court's 50 Order is Vacated. Signed by Judge James C. Mahan on 3/20/2019. (Copies have been distributed pursuant to the NEF - SLD)

Download PDF
1 2 3 4 UNITED STATES DISTRICT COURT 5 DISTRICT OF NEVADA 6 *** 7 BUESING CORPORATION, 8 Plaintiff(s), 9 10 Case No. 2:16-CV-1439 JCM (NJK) ORDER v. HELIX ELECTRIC OF NEVADA, LLC, 11 Defendant(s). 12 13 Presently before the court is plaintiff Buesing Corporation’s (“Buesing”) motion for 14 reconsideration. (ECF No. 51). Defendant Helix Electric of Nevada, LLC (“Helix”) filed a 15 response (ECF No. 54), to which Buesing replied (ECF No. 55). 16 I. Facts 17 On August 7, 2015, Helix entered into a contract with Buesing for the performance of 18 certain pile driving construction work at a project in Henderson, Nevada (the “solar project”). 19 (ECF No. 33-3). The contract required Buesing to install 7,898 piles at a total cost of $313,296.00 20 in accordance with certain project documents, including the SNWA Ninyo & Moore pile test (“the 21 pile test report”). (ECF Nos. 1, 33, 33-3). The pile test report detailed soil and site conditions. 22 (ECF No. 41-3). Based on the information in the report, Buesing anticipated that it would install 23 approximately 527 piles per day. (ECF No. 41-6). 24 On August 31, 2015, Buesing began working on the solar project. (ECF No. 41). Buesing 25 almost immediately encountered soil conditions that were different than those disclosed in the pile 26 test report. (ECF No. 41-6). After four days of work, Buesing had installed only 500 piles, many 27 of which were damaged and required removal. Id. 28 James C. Mahan U.S. District Judge 1 On September 11, 2015, Buesing informed Helix that it encountered differing soil 2 conditions. (ECF No. 41-9). On September 24, 2015, Helix and Buesing modified the contract in 3 the amount of $130,000.00 for “pulling and drilling for remediation of piles.” (ECF No. 41-6). 4 Despite the modification, Buesing encountered ongoing difficulties and, on October 2, 2015, the 5 parties agreed to temporarily stop installing piles. Id. 6 On October 9, 2015, Buesing informed Helix that it “can no longer continue the pile work” 7 due to the differing soil conditions. (ECF No. 41-15). On October 12, 2015, Helix sent Buesing 8 a written notice of default for Buesing’s abandonment of the solar project. (ECF No. 41-16). The 9 next day, Buesing notified Helix that it would be on the site the following day “to work through 10 the issues involved in completing the remediation work.” (ECF No. 41-17). Buesing allegedly 11 did not cure its default but instead “demobilized its equipment, tapered down, stopped work, and 12 performed only a minimal amount of sub survey work[.]” (ECF No. 33). 13 On October 16, 2015, Helix terminated the contract for Buesing’s “failure to perform and 14 job abandonment.” (ECF No. 41-19). On that same day, Buesing sent a letter to Helix, in which 15 Buesing stated that it had not abandoned the solar project but that it could not complete 16 performance without further modification of the contract. (ECF No. 41-18). Thereafter, Helix 17 contracted with another company to compete the pile driving work. (ECF No. 33). 18 On June 21, 2016, Buesing filed a complaint, asserting three causes of action: (1) 19 declaratory judgment; (2) breach of contract; and (3) breach of the implied covenant of good faith 20 and fair dealing. (ECF No. 1). On July 8, 2016, Helix filed an answer and counterclaim, asserting 21 three causes of action: (1) declaratory judgment; (2) breach of contract; and (3) breach of the 22 implied covenant of good faith and fair dealing. (ECF No. 8). 23 On November 27, 2017, Helix moved for summary judgment on (1) Buesing’s breach of 24 contract claim; (2) Buesing’s good faith claim; (3) Helix’s breach of contract claim; and (4) Helix’s 25 good faith claim. (ECF No. 33). On January 8, 2018, Buesing filed a cross-motion for summary 26 judgment requesting that the court deny Helix’s motion. (ECF No. 41). 27 28 James C. Mahan U.S. District Judge -2- 1 On July 13, 2018, the court issued an order holding that Buesing breached the contract by 2 failing to install piles in compliance with the contract. (ECF No. 50). Now, Buesing moves for 3 reconsideration. (ECF No. 51). 4 II. Legal Standard 5 A motion for reconsideration “should not be granted, absent highly unusual 6 circumstances.” Marlyn Nutraceuticals, Inc. v. Mucos Pharma GmbH & Co., 571 F.3d 873, 880 7 (9th Cir. 2009). “Reconsideration is appropriate if the district court (1) is presented with newly 8 discovered evidence, (2) committed clear error or the initial decision was manifestly unjust, or (3) 9 if there is an intervening change in controlling law.” School Dist. No. 1J v. ACandS, Inc., 5 F.3d 10 1255, 1263 (9th Cir. 1993). 11 Rule 54(b) permits a district court to revise an order that does not terminate the action at 12 any time before the entry of judgment. Fed. R. Civ. P. 54(b); see also Los Angeles v. Santa Monica 13 Baykeeper, 254 F.3d 882, 887 (9th Cir. 2001). However, reconsideration is “an extraordinary 14 remedy, to be used sparingly in the interests of finality and conservation of judicial resources.” 15 Carroll v. Nakatani, 342 F.3d 934, 945 (9th Cir. 2003) (internal quotations omitted). A motion 16 for reconsideration is also an improper vehicle “to raise arguments or present evidence for the first 17 time when they could reasonably have been raised earlier in litigation.” Marlyn Nutraceuticals, 18 571 F.3d at 880. 19 III. 20 21 22 Discussion Good cause appearing, the court reconsiders the parties’ cross-motions for summary judgment. See School Dist. No. 1J v. ACandS, Inc., 5 F.3d 1255, 1263 (9th Cir. 1993). a. Breach of contract 23 Helix argues that Beusing breached the contract when it failed to install piles. (ECF No. 24 33). Buesing argues that its deficient performance was excusable in light of the differing soil 25 condition and that Helix breached the contract when it improperly terminated the agreement. (ECF 26 No. 41). 27 To prevail on a claim for breach of contract, a plaintiff must demonstrate (1) the existence 28 of a valid contract; (2) that plaintiff performed or was excused from performance; (3) that the James C. Mahan U.S. District Judge -3- 1 defendant breached the contract; and (4) that the plaintiff sustained damages. Calloway v. City of 2 Reno, 993 P.2d 1259, 1263 (Nev. 2001); see also Sierra Dev. Co. v Chartwell Advisory Group, 3 Ltd., 223 F. Supp. 3d 1098, 1103 (D. Nev. 2016). 4 The contract at issue provides separate provisions for termination without cause and 5 termination for cause. (ECF No. 33-3). Helix terminated the contract due to Buesing’s alleged 6 “failure to perform and job abandonment.” (ECF No. 41-19). Thus, Helix terminated the contract 7 for cause. 8 Helix’s termination constitutes a breach of contract only if Buesing’s deficient performance 9 was not a material breach. On the other hand, if Buesing was in breach, then Helix’s termination 10 was proper. See Young Elec. Sign Co. v. Fohrman, 466 P.2d 846, 847 (Nev. 1970) (holding that a 11 material breach excuses further performance by the non-breaching party). 12 Buesing has provided evidence showing that it did not abandon the solar project and that 13 its deficient performance was not a material breach in light of the differing soil conditions. (ECF 14 Nos. 41, 41-6, 41-9, 41-16, 41-19). Helix has also provided evidence showing the contrary, that 15 the pile test report disclosed substantially accurate soil conditions. (ECF No. 33-11, 41-13). This 16 conflicting evidence creates a genuine dispute of material fact and precludes summary judgment 17 on the parties’ breach of contract claims. See T.W. Elec. Service, Inc. v. Pacific Elec. Contractors 18 Ass’n, 809 F.2d 626, 630 (9th Cir. 1987) (holding that at summary judgment courts do not “make 19 credibility determinations or weigh conflicting evidence.”). 20 b. Breach of the implied covenant of good faith and fair dealing 21 A contractual breach of the implied covenants of good faith and fair dealing occurs 22 “[w]here the terms of a contract are literally complied with but one party to the contract 23 deliberately countervenes the intention and spirit of the contract.” Hilton Hotels Corp. v Butch 24 Lewis Prods., Inc., 808 P.2d 919, 922–23 (Nev. 1991); see Shaw v. CitiMortgage, Inc., 201 F. 25 Supp. 2d 1222, 1252 (D. Nev. 2016). Although the evidence before the court does not establish 26 which party is in breach, it does establish that one of the parties did not comply with the terms of 27 contract. Accordingly, the court will summarily deny both parties’ claims for breach of the implied 28 covenant of good faith and fair dealing. See Hilton Hotels Corp., 808 P.2d at 922-23. James C. Mahan U.S. District Judge -4- c. Declaratory judgment 1 2 “[A] ‘claim’ for declaratory relief is not a substantive cause of action at all; it is merely a 3 prayer for a remedy.” Pettit v. Fed. Nat’l Mortg. Ass’n, no. 2:11-cv-00149-JAD-PAL, 2014 WL 4 584876 (D. Nev. Feb. 11, 2014); see Wells Fargo Bank, N.A. v. SFR Invs. Pool 1, LLC, no. 2:15- 5 cv-02257-JCM-CWH, 2017 WL 1902158, at *4 (D. Nev. May 9, 2017) (citing Stock West, Inc. v. 6 Confederated Tribes of the Colville Reservation, 873 F.2d 1221, 1225 (9th Cir. 1989)). As Helix 7 requests a remedy of declaratory relief, the court will dismiss the claim to the extent it purports to 8 create a cause of action. See Wells Fargo, 2017 WL 1902158, at *4. 9 IV. Conclusion 10 Accordingly, 11 IT IS HEREBY ORDERED, ADJUDGED, and DECREED that Buesing’s motion for 12 reconsideration (ECF No. 51) be, and the same hereby is, GRANTED, consistent with the 13 foregoing. 14 IT IS FURTHER ORDERED that the court’s order filed on July 13, 2018, (ECF No. 50) 15 be, and the same hereby is, VACATED. 16 DATED March 20, 2019. 17 18 __________________________________________ UNITED STATES DISTRICT JUDGE 19 20 21 22 23 24 25 26 27 28 James C. Mahan U.S. District Judge -5-

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?