Sequoia Electric Underground, LLC v. Capriati Construction Corp, Inc. et al

Filing 24

ORDER. IT IS ORDERED that appellant Sequoia Electric Underground, LLC's appeal is DISMISSED without prejudice to Sequoia attempting to obtain relief before the bankruptcy court. The clerk of court is instructed to close this case. Signed by Judge Andrew P. Gordon on 3/31/17. (Copies have been distributed pursuant to the NEF - cc: Bankruptcy Court - MR)

Download PDF
1 UNITED STATES DISTRICT COURT 2 DISTRICT OF NEVADA 3 *** 4 5 IN RE: CAPRIATI CONSTRUCTION CORP, INC., Debtor. 6 7 8 OPINION SEQUOIA ELECTRIC UNDERGROUND, LLC, Appellant, 9 v. 10 11 Case No. 2:16-cv-01560-APG CAPRIATI CONSTRUCTION CORP, INC., et al., 12 Appellants. 13 Sequoia Electric Underground, LLC appeals from the bankruptcy court’s order granting a 14 15 stipulation entered into among debtor Capriati Construction Corp, Inc.; the Nevada Department of 16 Taxation (NVTax); and the Nevada Department of Transportation (NDOT). ECF No. 1. That 17 stipulation resolved (1) proofs of claim NVTax and NDOT filed against Capriati’s estate and (2) 18 the distribution of funds NDOT owed to Capriati under a construction contract. In a nutshell, 19 Sequoia contends the stipulation improperly distributes funds that do not belong to Capriati’s 20 estate because Capriati breached the underlying contract and thus no longer was entitled to the 21 funds in NDOT’s possession. Capriati responds that Sequoia did not object to the stipulation before the bankruptcy court 22 23 and thus Sequoia cannot raise this issue for the first time on appeal. Capriati also contends the 24 bankruptcy court’s order was not final and appealable. Finally, Capriati, NVTax, and NDOT 25 respond that under Nevada law Capriati had an interest in the funds; thus, the funds properly were 26 treated as property of the estate that must be returned to Capriati. 27 //// 28 1 Sequoia did not raise any of its arguments before the bankruptcy court. A party cannot 2 raise issues for the first time on appeal absent various exceptions. None of those exceptions 3 applies in this case. I therefore dismiss this appeal, without prejudice to Sequoia attempting to 4 obtain relief before the bankruptcy court. 5 I. BACKGROUND 6 Capriati was a general contractor on the US 95 highway project under contract 3409 with 7 NDOT (Project 3409). ECF No. 16 at 8-9. Sequoia was a subcontractor to Capriati on Project 8 3409. ECF No. 9 at 40-61. Capriati obtained performance and payment bonds for the project 9 from Fidelity and Deposit Company of Maryland. Id. at 11-18; ECF No. 16 at 10-17; see also 10 Nev. Rev. Stat. § 408.357 (requiring bidders on highway projects to furnish performance and 11 payment bonds).1 12 On March 12, 2014, NDOT advised Capriati that NDOT had inspected Capriati’s work on 13 Project 3409 and “all items have been found to be satisfactorily completed in accordance with the 14 Construction Plans, Specifications and Special Provisions.” ECF No. 14 at 4. NDOT further 15 stated that the “contract was completed December 1, 2012, and is hereby accepted by the Nevada 16 Department of Transportation, as of March 7, 2014.” Id. As required by Nevada law, NDOT 17 published a notice to creditors in the newspaper “[p]ursuant to NRS 408.387” advising them that 18 the project was completed and any claims on the contract must be submitted to NDOT within 30 19 days. ECF No. 16 at 32-33; see also Nev. Rev. Stat. § 408.363(1) (requiring persons furnishing 20 materials or labor to the general contractor to make a claim on the contractor’s bond within 30 21 days from the date NDOT finally accepts the contract); id. § 408.387 (requiring NDOT to publish 22 a notice of the date of final acceptance). 23 Capriati did not pay Sequoia amounts due for Sequoia’s work on Project 3409, so Sequoia 24 sued in Nevada state court. ECF No. 9 at 62; see also Nev. Rev. Stat. § 408.363(2) (providing that 25 persons furnishing materials or labor to contractor may file suit against the surety six months after 26 27 28 1 Sequoia apparently disputes which chapter of the Nevada Revised Statutes applies. For purposes of providing a factual context to the dispute, I cite to Chapter 408. Page 2 of 7 1 they file a claim with NDOT). That litigation resulted in two partial summary judgments holding 2 that Capriati breached the subcontract and owed Sequoia $349,125.08 and $253,655.29, 3 respectively. ECF No. 9 at 62-81. Sequoia contends it is still due funds, including attorney’s fees 4 and amounts due under Change Order 15, which involved the resetting of high mast poles. ECF 5 No. 16 at 22-30. 6 Capriati filed for chapter 11 bankruptcy protection but did not identify Sequoia or the state 7 court litigation in its schedules. ECF Nos. 6 at 46-54; 7 at 4-80, 85-86. Fidelity filed a proof of a 8 secured claim based on payments it made on the payment bond, including the second Sequoia 9 partial summary judgment award. ECF No. 9 at 4-18, 27 (identifying $972,411.88 in losses 10 related to “US 95”), and 31 (identifying $270,804.51 for Sequoia and $7,946.07 in related 11 interest). Sequoia filed a proof of claim in the amount of $392,575.98. Id. at 34-39. 12 NVTax filed proof of claim 19 in the amount of $47,854.85. ECF Nos. 8 at 31; 16 at 34- 13 35. NDOT filed several separate proofs of claim. NDOT filed claim 44 for $5,500 for taxes or 14 penalties owed based on a final decision by the Nevada State Labor Commissioner. ECF No. 16 15 at 36-52. NDOT indicated this claim was subject to a right of setoff based on “[r]etainage under 16 NDOT Contract No. 3409.” Id. at 37. NDOT also filed claims 73 through 78 for back wages and 17 related penalties. Id. at 54-130. Like claim 44, each of these claims stated that they may be 18 subject to setoff by “retainage” under the Project 3409 contract. Id. at 55, 66, 77, 94, 111, 122. 19 The “retainage” arises from Nevada law, which requires NDOT to make progress 20 payments for no more than ninety-five percent of the entire contract price. Nev. Rev. Stat. 21 § 408.383(1). “The remaining 5 percent, but not more than $50,000, must be retained until the 22 entire contract is completed satisfactorily and accepted by the Director.” Id. 23 On June 10, 2016, Capriati entered into a stipulation with NDOT and NVTax to accept 24 unpaid funds NDOT owed to Capriati on Project 3409, including the $50,000 retainage, and apply 25 them to claims 19, 44, and 73 through 78. ECF Nos. 6 at 25; 8 at 92-95. That stipulation states 26 that “NDOT currently holds a retention under Contract No. 3409 in the sum of $50,000.00 and 27 the sum of $182,746.30 for quantities not yet paid to date under Contract No. 3409 for a total 28 Page 3 of 7 1 amount retained of $232,746.30.” ECF No. 8 at 92. The stipulation provides that the funds will 2 be applied as follows: (1) $15,777.46 of the retention fund to be held in trust by NDOT pending a 3 final decision by the Labor Commissioner; (2) $36,014.18 of the retention fund to be held by 4 NDOT to be paid to NVTax on its priority claim upon plan confirmation, with NVTax’s 5 unsecured claim to be treated under the plan; (3) $5,500 of the retention fund to be paid to NDOT 6 upon plan confirmation; and (4) all remaining amounts remitted to Capriati upon confirmation. Id. 7 at 94-95. The bankruptcy court approved the stipulation four days later. ECF Nos. 6 at 25-26; 8 8 at 97-98. 9 Sequoia did not object to the stipulation, but now appeals the bankruptcy court’s approval 10 of it. Sequoia argues that the amounts in the retention fund and the remaining $182,746.30 were 11 not property of the estate, and thus the parties could not stipulate to the distribution of those funds 12 through Capriati’s bankruptcy proceeding. Sequoia contends Capriati had no interest in those 13 funds because it had breached the general contract by not paying its subcontractors. Sequoia thus 14 reasons that NDOT had no obligation to pay Capriati those funds, so the funds never became 15 estate property. Rather, Sequoia argues, because Fidelity paid out on its payment bond, Fidelity 16 was entitled to the funds remaining on the Project 3409 contract. Alternatively, Sequoia argues 17 that because the remaining unpaid funds represent Sequoia’s work on Change Order 15, the funds 18 belong to Sequoia. Sequoia also objects to the balance of any remaining funds being distributed 19 to Capriati without any protection of the surety, Fidelity. 20 Capriati responds that Sequoia’s appeal is barred because it failed to object to the 21 stipulation. Capriati also contends that the bankruptcy court’s order granting the stipulation is an 22 interlocutory order for which Sequoia did not obtain leave to appeal. On the merits, Capriati 23 argues that NDOT has never found Capriati in breach of the contract and Sequoia has no standing 24 to assert a breach of a contract to which it is not a party. Capriati also argues that under Nevada 25 law, a subcontractor on a highway project does not have an equitable lien on monies held by 26 NDOT. Rather, Capriati contends, the subcontractor’s only remedy is to make a claim on the 27 28 Page 4 of 7 1 payment bond. Finally, Capriati claims that Sequoia’s appeal is frivolous and therefore the court 2 should award Capriati its fees and costs for having to respond. 3 NVTax and NDOT separately respond that under Nevada law and the applicable contract, 4 the balance owed on the contract and the retention must be released to the contractor, not to 5 subcontractors or the contractor’s surety. They thus contend that Capriati had at least an 6 equitable interest in the funds at the time it filed for bankruptcy, so the funds are property of the 7 estate. NVTax and NDOT also contend Sequoia lacks standing to argue that Fidelity ought to 8 have an equitable lien on the retainage and unpaid contract amounts. 9 Sequoia replies that requiring it to object to a proposed stipulation within four days (but 10 only two business days) is unreasonable, and therefore its appeal should not be dismissed on the 11 basis that it failed to object below. Sequoia also contends that the order is not interlocutory 12 because it finally determines Capriati’s right to the retention fund and the unpaid balance on the 13 contract. On the merits, Sequoia argues that because Capriati breached the general contract by 14 failing to pay its subcontractors, Fidelity had to step in and pay and, as a result, Capriati no longer 15 has a claim to the funds. Instead, Sequoia argues, the bankruptcy court should have ordered those 16 funds be paid to Fidelity or placed into escrow. Sequoia also contends that the bankruptcy court 17 lacked the factual detail that is being provided here, and thus it had no evidentiary basis to make 18 its ruling. 19 II. ANALYSIS 20 “As a general rule, issues ‘not presented to the trial court cannot generally be raised for 21 the first time on appeal.’” In re Enewally, 368 F.3d 1165, 1173 (9th Cir. 2004) (quoting United 22 States v. Flores-Payon, 942 F.2d 556, 558 (9th Cir. 1991)). This rule applies to situations where 23 a party fails to raise issues before the bankruptcy court. Id. There are several exceptions to this 24 general rule: “(1) there are exceptional circumstances, (2) the new issue arises while the appeal is 25 pending because of a change in the law, . . . (3) the issue presented is purely one of law and the 26 opposing party will suffer no prejudice as a result of the failure to raise the issue below,” and (4) 27 “the trial court’s decision was plain error and injustice would otherwise result.” Id. 28 Page 5 of 7 1 Here, the bankruptcy court granted the stipulation within four days of the parties 2 submitting it. Sequoia did not object before the court granted the stipulation, but that is hardly 3 surprising given how quickly the court acted. However, Sequoia thereafter did not file with the 4 bankruptcy court a motion for reconsideration or some other relief advising that Sequoia objected 5 to the stipulation and the grounds for its objection. Instead, Sequoia filed this appeal. Because 6 Sequoia did not first raise these issues before the bankruptcy court, it cannot do so for the first 7 time in this appeal. 8 No exception warrants departure from the general rule that issues cannot be raised for the 9 first time on appeal. Sequoia argues there are exceptional circumstances because there was 10 insufficient time to respond to the stipulation before it was approved. But nothing prevented 11 Sequoia from filing a motion with the bankruptcy court after the stipulation was granted. 12 The issues on appeal are not purely questions of law—the surrounding factual context is 13 both disputed and not fully developed. Indeed, Sequoia admits in its reply brief that “[c]ontrary 14 to NDOT and NVTAX’s claims, this matter is far from fully briefed to the Court” and that many 15 pertinent facts were never provided to the bankruptcy court. ECF No. 23 at 12. Nor has Sequoia 16 shown that the opposing parties will suffer no prejudice by its failure to first present these issues 17 to the bankruptcy court, which could consider the parties’ arguments on a full factual record and 18 in the context of the overall bankruptcy proceeding. 19 20 21 Finally, the parties’ appellate briefs do not show plain error. Nor does Sequoia show an injustice because it could and should have first raised these issues before the bankruptcy court. I dismiss Sequoia’s appeal because it raises numerous issues that were never presented to 22 the bankruptcy court. I do so without prejudice to Sequoia attempting to obtain relief in the 23 bankruptcy court. I deny Capriati’s request for attorney’s fees and costs because there was no 24 request by separate motion. Fed. R. Bankr. P. 8020(a) (“If the district court or BAP determines 25 that an appeal is frivolous, it may, after a separately filed motion or notice from the court and 26 reasonable opportunity to respond, award just damages and single or double costs to the 27 appellee.”); In re Kyle, 317 B.R. 390, 395 (B.A.P. 9th Cir. 2004) (“To the extent Federal Rule of 28 Page 6 of 7 1 Bankruptcy Procedure 8020 applies, the requests are rejected as not being in ‘a separately filed 2 motion’ as required by that rule.”). 3 III. CONCLUSION 4 IT IS THEREFORE ORDERED that appellant Sequoia Electric Underground, LLC’s 5 appeal is DISMISSED without prejudice to Sequoia attempting to obtain relief before the 6 bankruptcy court. The clerk of court is instructed to close this case. 7 DATED this 31st day of March, 2017. 8 9 10 ANDREW P. GORDON UNITED STATES DISTRICT JUDGE 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Page 7 of 7

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?