ORDER Denying Petitioner's 3 Motion for a Temporary Injunction. The case is Dismissed without prejudice. Signed by Judge Andrew P. Gordon on 6/7/2017. (Copies have been distributed pursuant to the NEF - SLD)
1
UNITED STATES DISTRICT COURT
2
DISTRICT OF NEVADA
3
***
4
5
6
7
8
9
10
CORNELE A. OVERSTREET, Regional
Director of the Twenty-Eighth Region of the
National Labor Relations Board, for and on
behalf of the National Labor Relations Board,
Petitioner,
Case No. 2:17-cv-01436-APG-NJK
ORDER DENYING PETITION FOR
TEMPORARY INJUNCTION
(ECF Nos. 1, 3)
v.
IGT D/B/A/ INTERNATIONAL GAME
TECHNOLOGY,
Respondent.
11
12
Petitioner National Labor Relations Board Regional Director Cornele Overstreet requests
13
an order temporarily enjoining respondent IGT from using subcontractors or non-unit employees
14
for work normally undertaken by its technicians’ union without first bargaining with the union.
15
The Board also asks me to require IGT to furnish certain information about IGT’s use of
16
subcontractors and non-unit employees. IGT responds that the Board has not carried its burden
17
of establishing both a likelihood of success and irreparable harm, each of which must be shown
18
to support an injunction. I agree, and therefore deny the injunction.
19
To qualify for a preliminary injunction, the Board must demonstrate: (1) a likelihood of
20
success on the merits, (2) a likelihood of irreparable harm, (3) the balance of hardships favors the
21
plaintiff, and (4) an injunction is in the public interest. Winter v. Natural Res. Def. Council, Inc.,
22
555 U.S. 7, 20 (2008). Alternatively, the Board must demonstrate (1) serious questions on the
23
merits, (2) a likelihood of irreparable harm, (3) the balance of hardships tips sharply in the its
24
favor, and (4) an injunction is in the public interest. Alliance for the Wild Rockies v. Cottrell, 632
25
F.3d 1127, 1135 (9th Cir. 2011). A preliminary injunction is “an extraordinary and drastic
26
remedy, one that should not be granted unless the movant, by a clear showing, carries the burden
27
28
1
of persuasion.” Mazurek v. Armstrong, 520 U.S. 968, 972 (1997) (quotation and emphasis
2
omitted).
I do not repeat the facts here, as they are adequately laid out in the pleadings and mostly
3
4
agreed to by the parties. The merits of this case hinge on whether IGT is violating the August
5
31, 2016 Letter of Understanding (LOU) in which it agreed to an “interim” hiring procedure with
6
the union. The LOU reads, in part, as follows:
7
Notification of Vacancies. In the event that IGT is going to hire a
temporary or regular full-time or regular part-time bargaining unit
position in Southern Nevada, IGT may first fill the vacancy from
existing employees of IGT. In the event that IGT does not select an
existing employee for such vacancy, IGT shall secure applicants for
the position from the Union’s dispatch office. IGT will notify the
Union’s dispatch office of such vacancy and the nature of the
vacancy, and the dispatch office shall furnish to IGT the required
number of qualified and competent applicants. Applicants referred
to IGT by the Union dispatch office must submit their resumes and
be available to interview with IGT, according to IGT's schedule,
within 10 days after IGT provides the Notice to the dispatch office,
unless IGT specifies that applicants are needed within a shorter
period of time, in which case IGT will provide the timing of the need
with its notice to the Union. The dispatch office will only refer
applicants to IGT who meet the qualifications for employment as
stated in IGT’s notice.
8
9
10
11
12
13
14
15
16
17
Employer’s Discretion. IGT shall have sole discretion to determine
whether or not to hire any applicant. If IGT does not select an
applicant who was submitted by the Union’s dispatch office, IGT
may hire from any source.
18
19
20
ECF No. 1 at 17–18. This much of the LOU seems straightforward. IGT must give the union a
21
good faith opportunity to fill new positions before going to outside sources but retains discretion
22
on that choice. This procedure apparently was the union’s suggestion, to which IGT eventually
23
agreed.
24
25
26
27
The last provision of the agreement, however, is the problem. It reads:
Use of Contractors. Nothing in this Letter of Understanding shall
be construed as waiving IGT’s exclusive right to determine whether
or not to hire an employee or utilize a contractor, and nothing waives
28
2
the Union’s right to request bargaining over the same where such
obligation to bargain exists under the NLRA.
1
2
Id. at 18. The parties do not agree on what this clause means, and neither could clearly explain
3
to me how to reconcile it with the described process. The Board’s focus on the reservation of
4
bargaining rights seems to nullify IGT’s “sole discretion to . . . hire from any source” after
5
following the process. IGT’s interpretation seems to read out the union’s reservation of
6
bargaining rights.1 I conclude on review of the evidence that serious questions exist about what
7
the LOU means and whether IGT is violating it, but I do not find that the Board has carried its
8
burden at this point of showing a likelihood of success on the merits.
9
Under the Wild Rockies “serious questions” test, the petitioner must show a likelihood of
10
irreparable harm and that the balance of equities tips sharply in the petitioner’s favor. The Board
11
has not shown, however, that in the nine months since the LOU was signed, the bargaining unit
12
has been significantly harmed. One union member contends that morale in the unit is declining.
13
But actual membership numbers have stayed more or less the same in this period, and some new
14
technicians have been hired into the unit pursuant to the LOU process. I am not convinced that
15
awaiting the result of an administrative decision for a few additional months poses a likelihood
16
of irreparable harm. The Board also has not shown that the balance of the equities tips sharply
17
toward it. The union’s legitimate interest in maintaining whatever bargaining rights it is entitled
18
to under the LOU is tempered by IGT’s interest in being able to hire employees in a timely
19
fashion to meet its contractual duties to its clients. The Board’s suggestion that IGT could apply
20
to the Board for an “exigent circumstances” exception to the bargaining requirement does not
21
alleviate this potential harm because approval of that exception routinely takes one to two
22
months.2
23
24
25
The serious questions raised by this petition are best decided after careful evaluation by
an Administrative Law Judge with expertise in this area, a process that will begin with a hearing
1
26
The LOU also contains a clause allowing either party to terminate the agreement on written
notice. The fact that neither party has done so suggests that both still see benefit from the LOU.
27
2
Statement of Board attorney at June 5, 2017 hearing.
28
3
1
on June 13, 2017. I will deny the Board’s motion for an injunction and dismiss the petition
2
without prejudice, so that the Board may revive its petition if the factual situation changes
3
significantly while the administrative process is ongoing, especially with respect to irreparable
4
harm.
5
6
7
IT IS THEREFORE ORDERED that the petitioner’s application for a temporary
injunction (ECF Nos. 1, 3) is DENIED. The case is dismissed without prejudice.
DATED this 7th day of June, 2017.
8
9
ANDREW P. GORDON
UNITED STATES DISTRICT JUDGE
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
4
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?