ORDER granting ECF No. 166 Stipulation : Defendant-Intervenor/Cross-Claimant Carlin/Hecla's Opposition to Cross-Motion for Summary Judgement (ECF No. 143 ) and Reply in Support of Motion for Summary Judgment (ECF No. 140 ) are due February 15, 2023 and Federal Defendants' Reply in Support of Cross Motion for Summary Judgment (ECF No. 143 ) is due March 7, 2023. Signed by Judge Larry R. Hicks on 12/14/2022. (Copies have been distributed pursuant to the NEF - DRM)
Case 3:16-cv-00268-LRH-CSD Document 167 Filed 12/14/22 Page 1 of 2
1
2
3
4
UNITED STATES DISTRICT COURT
5
DISTRICT OF NEVADA
6
***
7
8
BATTLE MOUNTAIN BAND of the TEMOAK TRIBE OF WESTERN SHOSHONE
INDIANS,
9
10
11
12
13
ORDER GRANTING DEFENDANTS’
JOINT MOTION FOR EXTENSION OF
TIME (FOURTEENTH REQUEST)
Plaintiff,
v.
U.S. BUREAU OF LAND MANAGEMENT,
and JILL SILVEY, in her official capacity as
Bureau of Land Management Elko District
Manager,
Defendant, and
14
15
Case No. 3:16-cv-00268-LRH-CSD
CARLIN RESOURCES, LLC,
Defendant-Intervenor and
Cross-Claimant.
16
17
18
Before the Court is Defendants’ Joint Motion for Extension of Time (Fourteenth Request).
19
ECF No. 166. In its Motion, Defendants request leave until February 15, 2023, for Defendant-
20
Intervenor/Cross-Claimant Carlin/Hecla (“Hecla”) to file its Opposition to Cross-Motion for
21
Summary Judgement and Reply in Support of Motion for Summary Judgment, and until March 7,
22
2023, for Federal Defendants to file their Reply in Support of Cross Motion for Summary
23
Judgment. Id.
24
Defendant Hecla filed its Motion for Summary Judgment on September 29, 2020. ECF No.
25
140. Federal Defendants filed their Motion for Summary Judgment and Opposition to Hecla’s
26
(formerly known as Carlin) Motion for Summary Judgment on December 11, 2020. ECF No. 143.
27
In the interim, the Defendants have filed nine joint motions for extension of time to file their
28
corresponding oppositions and replies, not including the one currently before the Court. See ECF
1
Case 3:16-cv-00268-LRH-CSD Document 167 Filed 12/14/22 Page 2 of 2
1
Nos. 144, 146, 148, 150, 152, 156, 160, 162, and 164. The Court has granted all of them. See ECF
2
Nos. 145, 147, 149, 151, 153, 157, 161, 163, and 165. Each contain the same language justifying
3
the request for an extension, but the delay has reached a point of questionable delay and merit.
4
The Motion will be granted in the interest of not jeopardizing settlement potential and any
5
party’s status. However, no further continuances will be considered without personal appearance
6
of counsel and sufficient cause having been shown.
7
8
IT IS THEREFORE ORDERED that Defendants’ Joint Motion for Extension of Time
(Fourteenth Request) (ECF No. 166) is GRANTED.
9
Defendant-Intervenor/Cross-Claimant Carlin/Hecla’s Opposition to Cross-Motion for
10
Summary Judgement and Reply in Support of Motion for Summary Judgment are due February
11
15, 2023 and Federal Defendants’ Reply in Support of Cross Motion for Summary Judgment is
12
due March 7, 2023.
13
IT IS SO ORDERED.
14
DATED this 14th day of December, 2022.
15
16
LARRY R. HICKS
UNITED STATES DISTRICT JUDGE