JACKSON GEOTHERMAL HVAC & DRILLING, LLC v. WESTERN SURETY COMPANY et al
Filing
19
OPINION. Signed by Magistrate Judge Tonianne J. Bongiovanni on 3/14/2016. (km)
NOT FOR PUBLICATION
UNITED STATES DISTRICT COURT
DISTRICT OF NEW JERSEY
UNITED STATES OF AMERICA for the
use and benefit of JACKSON
GEOTHERMAL HVAC & DRILLING,
LLC,
Plaintiff,
Civil Action No. 14-7871 (FLW)
MEMORANDUM OPINION
v.
WESTERN SURETY COMPANY,
Defendant.
BONGIOVANNI, Magistrate Judge
Pending before the Court is proposed Intervenor/Defendant Ranco Construction, Inc.’s
(“Ranco”) motion to intervene through which Ranco seeks to become a defendant in this matter
and file a Third-Party Complaint asserting claims against B&S Sheet Metal, Inc. (“B&S”).
[Docket Entry No. 11]. Defendant Western Surety Company (“Western”) consents to Ranco’s
proposed intervention.
Plaintiff Jackson Geothermal HVAC & Drilling, LLC (“Jackson”)
opposes Ranco’s motion. B&S does as well. The Court has fully reviewed and considered all
arguments made in support of and in opposition to Ranco’s motion. The Court has considered
Ranco’s motion without oral argument pursuant to L.Civ.R. 78.1(b). For the reasons set forth
below, Ranco’s motion is GRANTED.
I. Factual & Procedural Background
This case arises out of work performed in relation to a governmental construction project
at the Joint Military Base: McGuire-Dix-Lakehurst (“McGuire-Dix”). Specifically, the United
States of America engaged Ranco to be the general contractor on a project to construct a 120
person dormitory at McGuire-Dix (the “Project”). [Docket Entry No. 1; Pl. Cmplt ¶ 8]. Given
the scope of the Project, Ranco was required under the Miller Act, 40 U.S.C. § 3131, et seq., to
post a bond for payment. Ranco obtained the payment bond from Western. [Id. ¶ 9].
On or about June 2012, Ranco entered into a subcontractor agreement with B&S to
provide HVAC, geothermal services, plumbing and sprinklers on the Project. [Id. ¶ 10]. In
turn, on or about August 2012, B&S entered into a subcontractor agreement with Jackson to
provide certain geothermal services on the Project. [Id. ¶ 11].
Jackson alleges that it began work on the Project in August 2012 and completed its work
on the Project on December 18, 2013. [Id. ¶¶ 12-13]. Jackson further alleges that its work on
the Project was accepted with a final invoice related to same being submitted thereafter. [Id. ¶
13].
Jackson claims that by correspondence dated March 14, 2014, it put Ranco on notice that
there remained a balance of $300,105.66 due and owing for the geothermal services it performed
and equipment/materials it provided on the Project. [Id. ¶ 14]. Ranco did not make payment on
said balance upon receiving notice of same, nor has it done so since. [Id. ¶ 18].
Western has acknowledged receipt of notice of the claim made by Jackson regarding the
Project. Jackson contends that it has satisfied all conditions precedent to obtain recovery under
the payment bond obtained by Ranco from Western. [Id. ¶ 17]. As a result, Jackson filed the
instant litigation against Western seeking a judgment in the amount of $300,105.66, together
with interest and attorney fees and costs, under the Miller Act.
Ranco now seeks to intervene in Jackson’s suit against Western as a party defendant.
Ranco seeks to assert additional affirmative defenses against Jackson then those raised by
2
Western, and to assert a Counterclaim for negligence. Ranco also requests permission to file a
Third-Party Complaint against B&S for negligence and breach of contract. Ranco argues that it
has a right to intervene in this matter pursuant to FED.R.CIV.P. (“Rule”) 24(a), but that should the
Court find otherwise, it should be permitted to intervene pursuant to Rule 24(b).
II. Analysis
A.
Intervention of Right
Rule 24(a) governs requests made to intervene as of right in federal litigation. According
to Rule 24(a):
On timely motion, the court must permit anyone to intervene who:
(1)
is given an unconditional right to intervene by a
federal statute; or
(2)
claims an interest relating to the property or
transaction that is the subject of the action, and is so
situated that disposing of the action may as a
practical matter impair or impede the movant’s
ability to protect its interest, unless existing parties
adequately represent that interest.
Here, Ranco seeks to intervene as of right pursuant to Rule 24(a)(2). The Third Circuit
has held that intervention under Rule 24(a)(2) is only appropriate if:
(1) the application for intervention is timely; (2) the applicant has a
sufficient interest in the litigation; (3) the interest may be affected
or impaired, as a practical matter by the disposition of the action;
and (4) the interest is not adequately represented by an existing
party in the litigation.
Mountain Top Condo. Ass’n v. Dave Stabbert Master Builder, Inc., 72 F.3d 361, 366 (3d Cir.
1995) (quoting Harris v. Pernsley, 820 F.2d 592, 596 (3d Cir. 1987)). Each requirement must
be met in order for an applicant to intervene as of right. Id.
3
In its opposition to Ranco’s motion, Jackson essentially concedes that Ranco has met the
first three factors, focusing its opposition solely on Ranco’s alleged failure to establish that its
interest is not adequately represented by Western in this litigation. The Court agrees with
Jackson’s tacit acknowledgement and finds that:
(1)
Ranco’s motion, which comes less than 9 months after Jackson’s
Complaint was filed, less than 4 months after Western filed its Answer and
just 2 months after the Court conducted the Initial Pretrial Conference, is
timely;
(2)
Ranco, the principal of the payment bond, clearly has a sufficient interest
in this litigation because if a judgment is entered against Western, Western
will likely seek indemnification from Ranco under the terms of their surety
agreement (see U.S. ex rel. Frank M. Sheesley Co. v. St. Paul Fire and
Marine Ins. Co., 239 F.R.D. 404, 412 (M.D. Pa. 2006) (citing Mountain
Top Condo, 72 F.3d at 366) (holding that bonds issued by sureties is the
kind of specific fund that can ground legitimate interests for purposes of
Rule 24(a)(2), especially where agreements exists under which the
principal on bond may be responsible for indemnifying sureties)); and
(3)
Ranco’s interest in the litigation may, as a practical matter, be impaired by
the disposition of Jackson’s claim against Western because if Ranco is not
allowed to intervene, it could nonetheless be forced to indemnify Western
for the debt claimed by Jackson without having the opportunity to legally
dispute its liability (Harris, 820 F.2d at 601 (finding that legal interest is
4
impaired when in assessing “the practical consequences of the litigation”
there is “a tangible threat” to proposed intervenor’s legal interest)).
Thus, the only question that remains is whether Ranco’s interests are adequately
represented by Western. “The burden of establishing inadequacy of representation by existing
parties varies with each case.” Kleissler v. United States Forest Serv., 157 F.3d 964, 972 (3d
Cir. 1998). The burden rests with “the applicant for intervention” who must “show that his
interests are not adequately represented by the existing parties.” Brody v. Spang, 957 F.2d 1108,
1123 (3d Cir. 1992) (quoting Hoots v. Pennsylvania, 672 F.2d 1133, 1135 (3d cir. 1982) (internal
quotation marks omitted)).
However, the Supreme Court has stated that, “[t]he requirement of
the Rule is satisfied if the applicant shows that representation of his interest ‘may be’ inadequate;
and the burden of making that showing should be treated as minimal.” Trbovich v. United Mine
Workers, 404 U.S. 528, 538 n. 10, 92 S.Ct. 630, 30 L.Ed. 2d 686 (1972) (citation omitted).
Nevertheless, where the applicant and the existing party have the same ultimate objective,
intervention as of right may not be appropriate as a presumption arises that the applicant’s
interests are adequately represented.
In re Cmty. Bank of N. Va. Guar. Nat’l Bank of
Tallahassee Second Mortgage Loan Litig., 418 F.3d 277, 315 (3d Cir. 2005) (citing Virginia v.
Westinghouse Elec. Corp., 542 F.2d 214, 216 (4th Cir. 1976)). “To overcome the presumption
of adequate representation, the proposed intervenor must ordinarily demonstrate adversity of
interest, collusion, or nonfeasance on the part of a party to the suit.” Id.
5
The Third Circuit has stated that:
The most important factor in determining adequacy of
representation is how the interest of the absentee compares with the
interest of the present parties. If the interest of the absentee is not
represented at all, or if all existing parties are adverse to him, then
he is not adequately represented. If his interest is identical to that
of one of the present parties, or if there is a party charged by law
with representing his interest, then a compelling showing should be
required to demonstrate why this representation is not adequate.
Mountain Top Condo, 72 F.3d at 368-69 (quoting Wright & Miller, § 1909 at 318-19). The
Court therefore focuses its inquiry on whether Western’s interests diverge from those of Ranco.
Here, both Western and Ranco have the same ultimate objective: they both seek to
avoid liability on the payment bond. They are also represented by the same counsel, which does
engender a certain degree of “skepticism that the interest of one will somehow be marginalized in
favor of the other.” U.S. ex rel. Frank M. Sheesley Co., 239 F.R.D. at 413. Further, Western
and Ranco’s defense against Jackson’s claim is also strikingly similar with Ranco asserting
essentially every affirmative defense raised by Western. 1 (Compare Western’s Answer and
Affirmative Defenses, Docket Entry No. 7 with Ranco’s Proposed Answer, Counterclaim and
Third-Party Cmplt., Docket Entry No. 11-3).
Nevertheless, Ranco does seek to assert 5 affirmative defenses, and a Counterclaim for
negligence against Jackson that Western did not raise. Under the “minimal” burden established
by the Supreme Court, this would appear to establish that Ranco’s interests may be inadequately
represented by Western in this litigation, thereby making intervention as of right appropriate.
All of Western’s affirmative defenses are alleged by Ranco in its proposed Answer; though Ranco’s proposed
Twelfth Affirmative Defense, which corresponds to Western’s Thirteenth Affirmative Defense, refers to “Plaintiff”
not being the intended beneficiary under the terms of the payment bond, instead of “the defendant” (presumably
because Western’s reference to “the defendant” represents a typographical error; much like Ranco’s proposed
6
1
The Court, however, need not conclusively decide the issue because even if Western was found
to adequately represent Ranco’s interests and even if intervention as of right would not be
warranted under Rule 24(a)(2), as explained below, the Court finds that permissive intervention
is appropriate under Rule 24(b).
B.
Permissive Intervention
Permissive intervention is governed by Rule 24(b). According to Rule 24(b)(1)(B),
“[o]n timely motion, the court may permit anyone to intervene who: has a claim or defense that
shares with the main action a common question of law or fact.” Rule 24(b)(3) further advises
that “[i]n exercising its discretion, the court must consider whether the intervention will unduly
delay or prejudice the adjudication of the original parties’ rights.” Here, there is no doubt that
Ranco’s proposed defenses and claims share common questions of both law and fact with
Jackson’s suit against Western: did Jackson complete its work on the Project to the satisfaction
of its subcontract agreement with B&S, is Jackson still owed money according to that agreement,
etc. Therefore, the only question for the Court is whether Ranco’s intervention in this matter
will unduly delay or prejudice the adjudication of Jackson’s rights.
In opposing permissive intervention, Jackson relies almost exclusively on Union Switch
& Signal, Inc. v. St. Paul Fire and Marine Ins. Co., 226 F.R.D. 485 (S.D.N.Y. 2005) in arguing
that it would be unfair and prejudicial to Jackson if Ranco is allowed to intervene in this matter.
Union Switch & Signal is an out of district case in which a “sub-subcontractor brought statutory
claims against [a] surety under a surety bond for unpaid invoices for construction work
performed at the PATH station damaged by the September 11, 2001, terrorist attacks” and a
Fifteenth Affirmative Defense and Western’s Fourteenth Affirmative Defense also appear to contain typos).
7
“general contractor sought to intervene as of right and permissively under Fed.R.Civ.P. 24 in the
action to assert its affirmative claims against the subcontractor.” (Jackson’s Opp. Br. at 4 (citing
Union Switch & Signal, 226 F.R.D. at 486)).
While Jackson argues that “[t]he similarity
between Union Switch & Signal, Inc. and the instant matter is non-discernable[,]” the Court
disagrees.
Obviously, there are some prevalent factual similarities between the instant litigation and
Union Switch & Signal: both involve Miller Act claims asserted by sub-subcontractors for work
performed for which they were allegedly not fully paid. There are, however also significant
differences. The court in Union Switch & Signal denied the request for permissive intervention
finding that:
Permitting the Joint Venture to intervene would result in highly
complex litigation if Daidone acts as would be expected and
asserts a panoply of third-party counterclaims against the Joint
Venture and potentially other parties, including U.S. & S., related
to the PATH reconstruction effort. Where the dispute now centers
around U.S. & S.’s performance of a single subcontract,
post-intervention litigation may require far more extensive
discovery and require a lengthier trial to adjudicate not only U.S. &
S.’s relatively simple contract claim, but also Daidone’s potential
RICO counterclaims and assorted other counterclaims and
cross-claims.
Union Switch & Signal, 226 F.R.D. at 492.
The same simply is not true here. While Ranco, if permitted to intervene, does seek to
assert two third-party claims against B&S (one for negligence and the second for breach of
contract), there is no expectation that B&S will allege numerous counterclaims against Ranco,
nor is there any expectation that B&S will allege complicated RICO counterclaims against
8
Ranco. There is an expectation that B&S will move to dismiss any claims asserted by Ranco
against it. (See Cert. of William Jackson ¶ 4; Docket Entry No. 13-1).
Under these circumstances, the Court finds no reason to believe that permitting Ranco to
intervene in this matter will unduly delay these proceedings or unfairly prejudice the adjudication
of Jackson’s rights. While Ranco could pursue its state law claims against B&S and Jackson in
state court, “notions of judicial economy suggest aggregating them in a single proceeding […]
rather than have different tribunals examine these issues at different times.” U.S. ex. Rel. Frank
M. Sheesley Co., 239 F.R.D. at 415. Indeed, as the Third Circuit has noted, the court’s policy
preference, i.e., “judicial economy, favors intervention over subsequent collateral attacks.”
Brody, 957 F.2d at 1123. As a result, the Court finds that intervention will protect all of the
parties from having to revisit the main issues being litigated here in separate proceedings. Thus,
the Court shall permit Ranco to intervene in this matter.
C.
Third-Party Complaint
In its motion to intervene, Ranco also seeks permission to file a Third-Party Complaint
against B&S. Ranco’s motion was made within the deadline set by the Court for motions to
amend the pleadings and/or to join parties. (See Scheduling Order of 7/10/2015 ¶¶ 3 & 4;
Docket Entry No. 10).
Rule 14 governs third-party practice. According to Rule 14(a)(1),
“[a] defending party may, as third-party plaintiff, serve a summons and complaint
on a nonparty who is or may be liable to it for all or part of the claim against it.
But the third-party plaintiff must, by motion, obtain the court’s leave if it files the
third-party complaint more than 14 days after serving tis original answer.”
9
Ranco is just now being given permission to intervene in this matter. It has yet to serve
its original Answer. As a result, Ranco need not obtain the Court’s permission to file its
third-party claims against B&S. Instead, it can file its Third-Party Complaint as of right when it
files its Answer.
Moreover, even if permission were needed, the Court would exercise its discretion to
allow Ranco to file its proposed Third-Party Complaint against B&S. In determining whether to
permit impleader under Rule 14(a), the Court considers the following factors:
“(1) the
timeliness of the motion; (2) the probability of trial delay; (3) the potential for complication of
issues at trial; and (4) prejudice to the original plaintiff.” Spencer v. Canon Equip. Co., Civil
No. 07-2437 (JBS), 2009 WL 1883929, *2 (D.N.J. June 29, 2009) (quoting Ronson v. Talesnick,
33 F.Supp. 2d 347, 356 (D.N.J. 1999) (internal quotation marks and citation omitted)). The
Court essentially considered those factors in determining that permissive intervention was
appropriate in this case. For the same reasons, the Court shall permit Ranco to pursue its
third-party claims against B&S.
III. Conclusion
For the reasons stated above, Ranco’s motion to intervene is GRANTED.
appropriate Order follows.
Dated: March 15, 2016
s/ Tonianne J. Bongiovanni
TONIANNE J. BONGIOVANNI
UNITED STATES MAGISTRATE JUDGE
10
An
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?