Enclos Corporation v. Dormitory Authority of the State of New York

Filing 15

MEMORANDUM-DECISION and ORDER - That DASNY's 10 Motion to Dismiss for Failure to State a Claim is DENIED. That DASNY shall file the appropriate responsive pleadings within the time allotted by the rules. That the parties notify Magistrate Judge Treece in order to schedule further proceedings in accorandance with this order. Signed by Chief Judge Gary L. Sharpe on 2/28/2013. (jel, )

Download PDF
UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK ________________________________ ENCLOS CORPORATION, Plaintiff, 1:12-cv-1760 (GLS/RFT) v. DORMITORY AUTHORITY OF THE STATE OF NEW YORK, Defendant. ________________________________ APPEARANCES: OF COUNSEL: FOR THE PLAINTIFF: Dorsey, Whitney Law Firm NY Office 51 West 52nd Street New York, NY 10019-6119 FOR THE DEFENDANT: Mazur, Carp Law Firm 1250 Broadway, Suite 3800 New York, NY 10001 DAVID C. SINGER, ESQ. ELIZABETH R. BAKSH, ESQ. ERIC A.O. RUZICKA, ESQ. GARY L. RUBIN, ESQ. FRANK L. WAGNER, ESQ. Gary L. Sharpe Chief Judge MEMORANDUM-DECISION AND ORDER I. Introduction Plaintiff Enclos Corporation commenced this action against defendant Dormitory Authority of the State of New York (DASNY), alleging several contractual and quasi-contractual claims. (See Compl., Dkt. No. 1.) Pending is DASNY’s motion to dismiss. (See Dkt. No. 10.) For the reasons that follow, the motion is denied. II. Background1 In March 2007, Enclos entered into a construction contract (“the Contract”) with DASNY, wherein it agreed to “perform certain curtain wall work and other exterior work at the John Jay College of Criminal Justice [. . . ] in exchange for compensation . . . in the sum of $40,550,300.00.” (Compl. ¶ 6.) As is relevant here, the Contract contains a provision entitled “Claims for Delay,”2 (Dkt. No. 10, Attach. 4 at 19), which is a so-called nodamages-for-delay clause, (see Dkt. No. 10, Attach. 7 at 6; Compl. ¶ 44). While Enclos implicitly acknowledges the effect of that clause, (see Compl. ¶¶ 44, 49), it nonetheless claims that DASNY’s redesign of the project, change of the construction schedule, and failure to mitigate delays, disrupted and delayed its performance of the contracted work. (See 1 Unless otherwise noted, the allegations are drawn from Enclos’ Complaint and presented in a light most favorable to it. To this end, the court, having discerned no disputes in the parties’ recitations of the background and allegations, incorporates them by reference here, and discusses only the allegations necessary to adjudicate the instant motion. (See Dkt. 10, Attach. 7 at 1-4; Dkt. No. 13 at 2-8.) 2 Because the Complaint incorporates by reference the Contract, (see, e.g., Compl. ¶¶ 6, 13), the court may consider it “in deciding the defendant’s motion to dismiss,” Int’l Audiotext Network, Inc. v. Am. Tel. and Tel. Co., 62 F.3d 69, 72 (2d Cir. 1995). 2 Compl. ¶¶ 22-39, 84-123.) Enclos further alleges that DASNY, as it did during a previous project, promised—but later refused—to compensate it for the disruptions and delays. (See id. ¶¶ 45-77, 145-54, 160-65.) Consequently, Enclos now alleges the following eight causes of action: (1) breach of contract for delaying the commencement of work, (see id. ¶¶ 8498); (2) breach of contract for delays during the project, (see id. ¶¶ 99-111); (3) breach of contract due to disruptions in its work, (see id. ¶¶ 112-23); (4) breach of contract based on DASNY’s promises to pay, (see id. ¶¶ 124-31); (5) breach of warranty, (see id. ¶¶ 132-40); (6) fraudulent inducement, (see id. ¶¶ 141-58); (7) promissory estoppel, (see id. ¶¶ 159-75); and (8) misrepresentation, (see id. ¶¶ 176-94). III. Standard of Review The standard of review under Fed. R. Civ. P. 12 is well established and will not be repeated here. For a full discussion of the standard, the court refers the parties to its decision in Ellis v. Cohen & Slamowitz, LLP, 701 F. Supp. 2d 215, 218 (N.D.N.Y. 2010). IV. Discussion DASNY argues that Enclos’ contractual claims are barred by the Contract, chiefly by the no-damages-for-delay clause. (See Dkt. No. 10, 3 Attach. 7 at 6-20.) It further asserts that the quasi-contractual claims fail as a matter of law because there is a contract between the parties that governs the subject-matter in question. (See id. at 21-22.) In response, Enclos contends that DASNY’s conduct falls within one of the recognized exceptions to the no-damages-for-delay clause, and thus it is entitled to sue under the contract. (See Dkt. No. 13 at 8-19.) And, with respect to its quasi-contract claims, Enclos avers that these are plead in the alternative in the event that DASNY’s promises did not constitute an enforceable contract. (See id. at 24.) The court is presently unpersuaded by DASNY’s arguments. While it is possible that the no-damages-for-delay clause could preclude Enclos’ contractual claims, see, e.g., Travelers Cas. & Sur. Co. v. Dormitory Auth.-N.Y., 735 F. Supp. 2d 42, 58-59 (S.D.N.Y. 2010); Corinno Civetta Constr. Corp. v. City of N.Y., 67 N.Y.2d 297, 309 (1986), it is equally so, as Enclos seeks to prove, (see Dkt. No. 13 at 9-17), that one of the general exceptions to that clause exists, which would entitle Enclos to recover damages, see Travelers, 735 F. Supp 2d at 58-59. Thus, it is simply premature—given the limited scope of review, see McCarthy v. Dun & Bradstreet Corp., 482 F.3d 184, 191 (2d Cir. 2007), and the way in which 4 the burden shifts in this type of case3—to determine whether the nodamages-for-delay clause controls, and assuming it does, if Enclos has proven that an exception applies. And though skeptical of the viability of Enclos’ quasi-contract claims, the court, in light of its decision with respect to the contractual claims, deems it appropriate to allow Enclos additional time to demonstrate, inter alia, how the contract does not govern DASNY’s alleged misconduct. See Clark-Fitzpatrick, Inc. v. Long Island R.R. Co., 70 N.Y.2d 382, 388 (1987) (“The existence of a valid and enforceable written contract governing a particular subject matter ordinarily precludes recovery in quasi contract for events arising out of the same subject matter.”). As such, DASNY’s motion to dismiss is denied. V. Conclusion 3 As Judge Cote explained in Travelers, where DASNY prevailed on summary judgment under the same no-damages-for-delay clause: The defendant bears the prima facie burden of establishing that the damages sought by the plaintiff are barred by the no-damage-for-delay exculpatory clause of the parties’ contract. Part of the defendant’s required showing is demonstrating prima facie that none of the exceptions to the damages for delay clause are present. Once that prima facie burden has been met, the burden shifts to the plaintiff to raise a triable issue of fact as the applicability of any of the [Corinno] exceptions to the contractual bar. In proving that one of the Corinno exceptions applies, the plaintiff bears a heavy burden. 735 F. Supp. 2d at 57-59, 69 (internal quotation marks and citations omitted). 5 WHEREFORE, for the foregoing reasons, it is hereby ORDERED that DASNY’s motion to dismiss (Dkt. No. 10) is DENIED; and it is further ORDERED that DASNY shall file the appropriate responsive pleadings within the time allotted by the rules; and it is further ORDERED that the parties notify Magistrate Judge Treece in order to schedule further proceedings in accordance with this order; and it is further ORDERED that the Clerk provide a copy of this MemorandumDecision and Order to the parties. IT IS SO ORDERED. February 28, 2013 Albany, New York 6

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?