Hudson River-Black River Regulating District v. Erie Boulevard Hydropower, L. P.
Filing
34
DECISION AND ORDER granting Deft's 18 Motion to Dismiss. Complaint is dismissed. Signed by Judge David N. Hurd on 10/30/14. (sfp, )
UNITED STATES DISTRICT COURT
NORTHERN DISTRICT OF NEW YORK
-------------------------------HUDSON RIVER–BLACK RIVER
REGULATING DISTRICT,
Plaintiff,
-v-
6:14-CV-173
ERIE BOULEVARD HYDROPOWER, L. P.,
Defendant.
-------------------------------APPEARANCES:
OF COUNSEL:
HON. ERIC T. SCHNEIDERMAN
Attorney General for the State of New York
Attorneys for Plaintiff
The Capitol
Albany, NY 12224
C. HARRIS DAGUE, ESQ.
Ass't Attorney General
PATTERSON BELKNAP WEBB & TYLER LLP
Attorneys for Defendant
1133 Avenue of the Americas
New York, NY 10036
SARAH E. ZGLINIEC, ESQ.
STEPHEN P. YOUNGER, ESQ.
JASON R. VITULLO, ESQ.
DAVID N. HURD
United States District Judge
DECISION and ORDER
I. INTRODUCTION
Plaintiff Hudson River–Black River Regulating District ("plaintiff" or "the District")
initiated this action in New York State Supreme Court, Fulton County, on January 21, 2014,
seeking declaratory relief. Defendant Erie Boulevard Hydropower, L.P. ("defendant" or
"Erie") removed the action to federal court in the Northern District of New York on February
20, 2014.
Erie has now filed a motion to dismiss pursuant to Federal Rule of Civil Procedure
12(b)(1) and 12(b)(6). The District responded in opposition, Erie replied, and the District was
permitted to file a sur-reply. Oral argument was heard on October 29, 2014, in Utica, New
York. Decision was reserved.
II. BACKGROUND
The following factual and procedural background is not in dispute and has been
gleaned from the complaint and defendant's memorandum of law.1 The District is a public
authority that operates the Conklingville Dam ("the Dam") and its related body of water, the
Great Sacandaga Lake. Erie operates several hydropower facilities located downstream
from the Dam. During the relevant time period, and pursuant to New York state law, Erie
paid assessments to the District for "headwater benefits" or "downstream benefits" resulting
from the Dam.
In September 2002, the Federal Energy Regulatory Commission ("FERC") issued a
license to the District permitting the continued operation of the Dam pursuant to the Federal
Power Act, 16 U.S.C. §§ 791a–828c ("FPA"). Section 10(f) of the FPA recognizes headwater
benefits and allows public authorities, such as the District, to impose assessments on
downstream facilities, such as Erie, for such benefits. See 16 U.S.C. § 803(f). However, the
rates permitted under the FPA are significantly less than those allowed by New York law.
Erie initiated six separate Article 78 proceedings in state court between 2000 and
2006 challenging the amount of the assessments the District had imposed under New York
1
Plaintiff notes that defendant's memorandum of law "adequately summarize[s]" the relevant facts.
Pl.'s Mem. 2.
-2-
state law. In May 2006, the District and Erie entered into a Settlement Agreement resolving
these consolidated proceedings ("the 2006 Settlement Agreement"). As part of the
settlement, the District agreed to provide Erie with over $800,000 in credits to reduce future
assessments between July 2006 and June 2009, and Erie waived all claims related to the
assessments during that time period. The 2006 Settlement Agreement also indicates that
the parties "executed a document entitled 'Amendment to Reservoir Operating Agreement
and Letter Agreement' dated May 19, 2006 as part of the consideration for entering into this
Stipulation of Settlement and Order." Compl., Ex. B, ECF No. 1-1, ¶ 14. The agreement
also contains a severability clause.
In July 2006, Albany Engineering Corporation, a FERC-licensed operator of a
downstream facility similar to Erie, filed an administrative complaint with FERC arguing the
District lacked authority to impose assessments greater than that permitted by section 10(f)
of the FPA. See Albany Eng'g Corp. v. F.E.R.C., 548 F.3d 1071, 1073 (D.C. Cir. 2008). The
case made its way to the D.C. Circuit, which noted "Congress's clear intent to limit the total
amount of charges imposed on downstream operators" and ultimately held that section 10(f)
of the FPA preempted "all state headwater benefits assessments." Id. at 1079. Thus, from
the time FERC issued its license to the District in 2002, "the District never had such authority
to exact any compensation from Albany for headwater benefits." Id. The Court remanded
the matter to FERC for consideration of an appropriate remedy. Id. at 1081.
Subsequent to the Albany Engineering Corp. decision, the District and the
downstream operators have attempted to resolve their disputes regarding alleged
overpayments. Citing a July 2012 FERC Order, Erie claims it overpaid the District
approximately $7.3 million in assessments between September 2002 and June 2009. Erie
-3-
and the District have been unable to amicably resolve their dispute and are currently
engaged in administrative proceedings before FERC. The District initiated this action after
the FERC proceedings began.
In its complaint, the District reports that Erie refuses to pay additional headwater
benefits assessments until the full amount of its $7.3 million overpayment has been offset.
The District claims the 2006 Settlement Agreement "expressly operates to extinguish any
claimed entitlement by Erie to any State law-based assessment that Erie paid the Regulating
District between 2002–2008." Compl. ¶ 23. In accordance with that conclusion, plaintiff
seeks a declaration that the 2006 Settlement Agreement "precludes Erie's claim for a refund
of assessments collected by the Regulating District for budget years encompassing July 1,
2000 through June 30, 2009." Id. ¶ 24.
III. DISCUSSION
Erie asserts the following arguments in support of its motion to dismiss: (1) The
District's request for declaratory relief, pursuant to the 2006 Settlement Agreement, is an
attempt to enforce the previous state law assessments and is thus preempted by the FPA, as
explained in the Albany Engineering Corp. decision; (2) the 2006 Settlement Agreement is
unenforceable because FERC never approved it; (3) the administrative proceedings before
FERC are ongoing and concern the exact same issues presented in this action; and,
alternatively, (4) the action should be stayed pending the outcome of the FERC proceeding.
Importantly, Erie also points out that it does not seek a refund of the $7.3 million. It instead
desires future credits.
In its response, the District addressed only Erie's first argument and "concedes that
the Settlement Agreement is wholly unenforceable as preempted by federal law, and
-4-
consents to entry of Judgment by the Court dismissing the Complaint on the specific ground
that the entire Settlement Agreement is unenforceable as preempted by the Federal Power
Act." Pl.'s Mem., ECF No. 20, 2.2 The District did not respond to Erie's remaining
arguments.
In its reply brief, Erie attempts to clarify its initial position. Specifically, Erie argues that
only the portion of the 2006 Settlement Agreement that deals with headwater benefits
assessments—not the entire document—is unenforceable. Therefore, despite the initial
concession to dismissal based on the unenforceability of the 2006 Settlement Agreement,
the parties do not agree on which parts of the 2006 Settlement Agreement, if any, remain
enforceable.
However, this issue need not be decided. The District seeks "[a] declaration that
Erie's claim for a refund of District assessments levied between July 1, 2000 and June 30,
2009 is precluded by Erie's waiver memorialized in the 2006 Stipulation of Settlement and
Order." Compl. 12 (emphasis provided). As the parties tacitly agreed during oral argument,
the court system is the appropriate forum for claims related to refunds of District
assessments. Therefore, the district court would have jurisdiction to decide what impact, if
any, the 2006 Settlement Agreement has on a claim by Erie for a refund of the approximately
$7.3 million in overpayments. However, as Erie has repeatedly noted before FERC and in its
motion papers here, it is not seeking a refund. It is instead seeking future credits to offset
the amount it owes the District.
Indeed, FERC explained this critical distinction in a May 2009 order:
2
In its sur-reply, the District reveals its motivation for conceding the 2006 Settlement Agreement is
entirely unenforceable; to wit, such may allow the parties to renegotiate the six-year Reservoir Operating
Agreement in light of the Albany Engineering Corp. decision.
-5-
We continue to believe, as we concluded in our prior orders, that we do not
have the authority to order refunds of charges collected by the District without
authority, although we may be able, at the conclusion of a headwater benefits
investigation, to permit [a downstream operator] to offset amounts it owes by
the amounts it has paid to the District. If [the downstream operator] wishes to
pursue immediate refunds, it would have to do so through the court system.
Younger Decl., Ex. 4, ECF No. 18-7, ¶ 19 (footnote omitted); see also Albany Eng'g Corp. v.
Hudson River–Black River Regulating Dist., 110 A.D.3d 1220, 1221–22 (N.Y. App. Div. 3d
Dep't 2013) (noting FERC has concluded that, although "it would consider applying the
improper assessments as a credit in determining the assessments owed by plaintiff in the
future[,] . . . plaintiff was free to seek a refund in state court"). Erie has elected to seek an
offset of the amount it has allegedly overpaid to the District. Therefore, FERC is the proper
forum, and the District's requested declaratory relief regarding a refund is moot.3
Moreover, the parties are currently working with FERC to address the issue of an
appropriate remedy. Part of that administrative proceeding relates to what impact, if any, the
2006 Settlement Agreement has on the remedy. See ECF No. 1-3 (outlining the District's
opposition to Erie's submissions to FERC and asserting that the 2006 Settlement Agreement
"clearly limits the amount which Erie can claim as a credit"); ECF No. 1-4 (detailing Erie's
reply to the District's argument regarding the impact of the 2006 Settlement Agreement).
Therefore, the very issue for which the District seeks declaratory relief in this action is
squarely, and more appropriately, before FERC in the pending administrative proceeding.4
3
At oral argument, counsel for the District attempted to expand its request for declaratory relief to
include the credits/offset issue. This is unpersuasive given the specific language used in the complaint.
Also, such an argument smacks of hypocrisy in light of the District's attempt to hold Erie to the specific
language put forth in its original motion papers.
4
Erie reports that "FERC is presently considering this very issue" and claims the administrative
proceeding "is now nearly complete." Def.'s Mem., ECF No. 18-1, 16, 23. Further, the fact that this exact
issue was pending before FERC when the District initiated this lawsuit suggests it did so with an improper
(continued...)
-6-
Accordingly, even if the issue were not moot, it is proper to abstain from deciding this
matter before the administrative process is complete. See Wilton v. Seven Falls Co., 515
U.S. 277, 286 (1995) (noting that the Declaratory Judgment Act confers upon federal courts
"substantial discretion in deciding whether to declare the rights of litigants"); Dow Jones &
Co., 346 F.3d at 359–60. Additionally, assuming FERC's ultimate decision is made pursuant
to its authority under the FPA, such is only reviewable in the United States Court of Appeals.
16 U.S.C. § 825l(b); In re NRG Energy, Inc., No. 03 Civ. 3754, 2003 WL 21507685, at *4
(S.D.N.Y. June 30, 2003) ("In sum, under the elaborate statutory scheme created by the
FPA, only a federal court of appeals may exercise jurisdiction to review a FERC decision.").
Therefore, it is
ORDERED that
1. Defendant Erie Boulevard Hydropower, L.P.'s motion to dismiss is GRANTED; and
2. The complaint is DISMISSED in its entirety.
IT IS SO ORDERED.
The Clerk of the Court is directed to close the case.
Dated: October 30, 2014
Utica, New York.
(...continued)
motive; to wit, forum shopping or a "race to res judicata." See Dow Jones & Co. v. Harrods Ltd., 346 F.3d
357, 359 (2d Cir. 2003) (per curiam) (internal quotation marks omitted).
-7-