Soroof Trading Development Company LTD. v. GE Fuel Cell Systems LLC. et al
Filing
110
MEMORANDUM OPINION AND ORDER: re: 45 MOTION for Judgment on the Pleadings Pursuant to F.R.C.P. 12(c). filed by GE Microgen Inc., 91 MOTION for Summary Judgment. filed by GE Microgen Inc., Plug Power Inc., 87 MOTION for Partial Summary Ju dgment. filed by Soroof Trading Development Company LTD., 74 MOTION for Sanctions against Defendants GE Microgen, Inc. and Plug Power, Inc.. filed by Soroof Trading Development Company LTD. For the foregoing reasons, Defendants' motion for judgment on the pleadings is granted as to Plaintiffs third, fourth, fifth and sixth causes of action. Plaintiffs first and second causes of action are dismissed without prejudice to repleading. Plaintiffs motion for sanctions and Defendants' ; application for attorneys' fees and costs are both denied. Plaintiffs motion for partial summary judgment is granted with regard to the piercing of the veil of GEFCS and is denied in all other respects. Defendants' motion for summary judg ment dismissing all claims against GEFCS is granted. Defendants' motion for summary judgment dismissing all claims against GE Microgen and Plug Power is denied. Any amended complaint repleading the first and second causes of action must be filed by February 10, 2012. Failure to file a timely amended pleading will result in the dismissal of Plaintiffs Complaint in its entirety, with prejudice and without further advance notice. If an amended complaint is timely filed, the parties must meet with Magistrate Judge Francis to discuss the possibility of settlement and any outstanding pretrial matters. This Memorandum Opinion and Order resolves docket entry numbers 45, 74, 87 and 91. (Signed by Judge Laura Taylor Swain on 1/24/2012) (jfe)
UNITED STATES DISTRICT COURT
SOUTHERN DISTRICT OF NEW YORK
-------------------------------------------------------x
SOROOF TRADING DEVELOPMENT
COMPANY LTD.,
No. 10 Civ. 1391 (LTS)(JCF)
Plaintiff,
-against
~y
,
~~
GE FUEL CELL SYSTEMS LLC,
GE MICROGEN, INC. and
PLUG POWER, INC.,
Defendants.
......-
,
..
ea.r ..
_~,..,..>"ot
J
.".
.1
!'
j
~~~~~r,.~~_~1~~~
MEMORANDUM OPINION AND ORDER
Plaintiff SoroofTrading Development Company Ltd. ("Plaintiff' or "Soroof')
brings this action against GE Fuel Cell Systems, LLC ("GEFCS"), GE Microgen, Inc., and Plug
Power, Inc. (collectively, "Defendants"), for breach of contract, misrepresentation, conversion,
constructive trust, unjust enrichment and an accounting under New York state law. The claims
arise from disputes regarding a contract that the parties entered into in 2000, under which Soroof
was to have exclusive distribution rights in Saudi Arabia for a fuel cell product (the "Contract").
Soroof commenced this action, seeking an estimated three million dollars in eompensatory
damages, after GEFCS failed to produce the fuel cells. The Court has diversity jurisdiction of
the action pursuant to 28 U.S.C. § 1332.
Defendants have moved for judgment on the pleadings, pursuant to Federal Rule
of Civil Procedure 12(c). The parties have cross-moved for summary judgment, and Soroofhas
moved for sanctions. The Court has considered carefully all of the parties' arguments and
VERSION 1/24112
_Mill"._
tJSDC :SlY\( Ct
t .DOCUt\iE!'i"'r
,
t E'"" ~/""""""ON·IC.';...~l I:;'T1-'-f.'l D
flo T "'~r
~ ·.:t~:<:.'-'..... £\.
L"-""-'.
i Dot; #:
" i
~.
-------------------------------------------------------x
SOROOF.GE. WPD
I
.....""---..'.......,-.~"'II~~
submissions. For the reasons that follow, Defendants' motion for judgment on the pleadings will
be granted and Plaintiff will be permitted to replead its claims for breach of contract and
misrepresentation. Plaintiffs motion for sanctions and Defendants' application for attorneys'
fees and costs will both be denied. Plaintiffs motion for partial summary judgment will be
granted as to the request to pierce the veil of GEFCS and denied in all other respects.
Defendants' summary judgment motion for dismissal of all claims will be granted with respect
to GEFCS and denied with respect to GE Microgen and Plug Power.
BACKGROUND
For the purposes of evaluating Defendants' motion for judgment on the pleadings,
all of the non-conclusory factual allegations of Plaintiffs Complaint are assumed to be true.
Soroofis a company organized under the laws of the Kingdom of Saudi Arabia. (Compl.
~
4.)
Defendant GEFCS was a limited liability company made up of two memhers: GE Microgen and
Plug Power. (ld.
~~
5-8.) GEFCS was dissolved in 2006. (Id.
~
6.) On June 6,2000, Soroof
and GEFCS entered into a contract whereby Soroofwas to distribute in Saudi Arabia GEFCS
produced Proton Exchange Membrane Fuel Cells, which were to meet specific contractual
standards. (Compl., Ex. 1("Contract") §§ 1-2.4.) Under the terms of the Contract, Soroofwas
required to pay GEFCS an up-front "non-refundable distributor fee" of one million U.S. dollars.
(Id. § 6.4.) Soroofwas also required to use its "best efforts to sell, advertise and promote" the
fuel cells in Saudi Arabia and to purchase a minimum number of fuel cells from GEFCS each
year, including 100 units in the first year that commercial units became available, 300 units the
second year and 500 units the third year. (Id. §§ 6.1,6.6.) GEFCS was not, however, obligated
to fulfill every Soroof order. Rather, the Contract obligated GEFCS to "use reasonable efforts to
supply" the fuel cells to Soroof and to satisfy any "firm purchase orders" that were "accepted by
SOROOF.GE. WPD
YERSIOr-;
1/24/12
2
GEFCS." (Id. §§ 5.1, 5.2.) GEFCS was also obligated to "share promptly [with Soroof] relevant
information, including but not limited to product performance, failure and liability issues." (rd.
§ 7.4.) The Contract specified further that GEFCS was not liable for any "incidental ... or
consequential damages" that Soroof incurred, even in the event of tortious conduct or breach of
contract and, also, that "[t]he total liability for GEFCS ... whether in contract, warranty,
indemnity, tort (including negligence), strict liability, or otherwise, arising out of or related to
this Agreement ... shall not exceed the amount that has been paid to GEFCS by [SoroofJ under
this Agreement." (Id. §§ 12.1 12.2.) In the Contract, both parties represented that they had the
"full authority and capacity to enter into and perform [their] obligations" under the Contract.
(Id. §§ 10.1.2.)
The Contract includes a merger clause, providing that the written document
"contains the entire and only agreement between [Soroot] and GEFCS . . .. Any representations
or terms and conditions relating to transactions within the scope of this Agreement which are not
incorporated or referenced herein shall not be binding upon either Party." (rd. § 22.1.) On
December 31, 2005, the Contract expired on its own terms. (rd. § 4.1.)
During discussions prior to the execution of the Contract, GEFCS officials told
Soroofthat they "stood ready to deliver the Product to Soroofwithin six months." (Compi. ~ 9.)
However, no such delivery timetable was included in the Contract. In November of 2000,
GEFCS informed Soroofthat the fuel cells did not yet meet quality standards and thus were not
ready for distribution. (Id.,r 16.) Over the remaining years of the Contract, GEFCS continued to
tell Soroof that the product was not yet ready but would nevertheless be forthcoming. (Id.
~~
17-18.) As a result, Soroof did not place any firm orders for the duration of the Contract (id.
'(17), but maintained offices and employees and engaged in third-party negotiations in
SOROOFGE.wPD
VERSIO!'J 1I24!l2
preparation for eventually distributing the fuel cells, spending an estimated two million U.S.
dollars on these preparations (id.
'[~
20,26). In 2005, GEFCS informed Soroofthat it was unable
to make fuel cells meeting the Contract's specifications and, in 2006, GE Microgen and Plug
Power dissolved GEFCS. (Id. ~~ 6, 21, 27.)
On July 1, 2008, Soroof initiated arbitration proceedings against GEFCS, alleging
that GEFCS had breached the Contract and misrepresented its ability to bring the fuel cells to
market. (Pl.'s Mem. in Opp'n to Mot. for J. on the Pleadings 2.) Soroofmoved to compel GE
Microgen and Plug Power to join the arbitration. (Id.) GEFCS moved to dismiss Soroofs
claims, arguing that suit could not be brought against a dissolved LLC or its former member
companies, that the terms of the Contract barred Soroof from recovering the consequential
damages and one million dollar non-refundable payment, that GEFCS never breached the terms
ofthe Contract and that the claims were, in any event, barred by New York's six-year statute of
limitations. (Baker Decl., Exh. A (Mot. to Dismiss Claims.» On November 9,2009, the
American Arbitration Association Panel (the "Arbitration Panel") denied GEFCS's motion,
stating: "Respondent's motion to dismiss the claims in this arbitration is denied without
prejudice to the filing of a motion for summary disposition at the close of discovery on the issues
raised in the motion to dismiss and the merits of the arbitration claims." (Baker Decl., Exh. B
(Prehr'g Order No.2.»
Shortly thereafter, Soroof, GE Microgen and Plug Power entered into a Venue
Agreement, discontinuing the arbitration and agreeing to litigate the controversy in this Court.
(Baker Decl., Exh. C ("Venue Agreement"), Recitals ~ C.) In its sanctions motion, Soroof
alleges that GEFCS, GE Microgen and Plug Power breached certain terms of the Venue
Agreement, which included a provision limiting the statute of limitations-based arguments that
SOROOF.GE.wPD
VERSION 1124/12
4
Defendants could assert in this Court and further alleges that Defendants misled the Court by
failing to disclose the argument limitations and the existence of the Venue Agreement in their
Rule l2(c) motion filings.
DISCUSSION
Defendants' Rule 12(c) Motion for Judgment on the Pleadings
In considering a Federal Rule of Civil Procedure 12(c) motion for judgment on
the pleadings, the Court applies the same standards used for the determination of a motion to
dismiss a complaint pursuant to Federal Rule of Civil Procedure 12(b)(6) for failure to state a
claim. Cortes v. City of New York, 700 F. Supp. 2d 474,480-81 (S.D.N.Y. 2010); see also
LaFaro v. New York Cardiothoracic Group, PLLC, 570 F.3d 471,475-76 (2d Cif. 2009). Thus,
the Court accepts as true the non-conclusory factual allegations in the complaint and draws all
inferences in the Plaintiffs favor. Roth v. Jennings, 489 F.3d 499, 501 (2d Cif. 2007); see also
Ashcroft v. Iqbal, 556 U.S. 662, 129 S. Ct. 1937, 1949 (2009).
To survive a motion to dismiss, a complaint must plead "enough facts to state a
claim to relief that is plausible on its face." Bell Atlantic Corp. v. Twombly, 550 U.S. 544,570
(2007). Under this standard, a pleader is obliged "to amplify a claim with some factual
allegations in those contexts where such amplification is needed to render the claim plausible."
Boykin v. KeyCorp, 521 F.3d 202,213 (2d Cif. 2008) (internal quotation marks, citation and
emphasis omitted). The Supreme Court has explained that "[d]etermining whether a complaint
states a plausible claim for relief will ... be a context-specific task that requires the reviewing
court to draw on its judicial experience and common sense .... But where the well-pleaded
facts do not permit the court to infer more than a mere possibility of misconduct, the complaint
has alleged
SOROOF.GE. WPD
but it has not 'show[n]'
VERSION 1/241] 2
'that the pleader is entitled to relief.' Fed. R. Civ. P.
8(a)(2)." Iqbal, 129 S. Ct. at 1950 (some internal citations omitted).
"The complaint is deemed to include any written instrument attached to it as an
exhibit or any statements or documents incorporated in it by reference." O'Shea v. Board of
Educ. of Poughkeepsie City Sch. Dist., 521 F. Supp. 2d 284,288 (S.D.N.Y. 2007);
also Fed.
R. Civ. P. 10(c) ("A copy ofa written instrument thatis an exhibit to a pleading is part of the
pleading for all purposes."). "Because the interpretation of contracts generally is a question of
law to be determined by the Court, it may dismiss the complaint where contracts are
unambiguous and do not support the plaintiffs claim." FlightSafety In1'l, Inc. v. Flight Options,
LLC, 418 F. Supp. 2d 103, 107 (E.D.N.Y. 2005) (affd in part, vacated in part and remanded)
(citing Furniture Consultants, Inc. v. Datatel Minicomputer Co., 1986 WL 7792, at *2 (S.D.N.Y.
July 10, 1986)).
Breach of Contract (First Cause of Action)
New York has "long adhered to the 'sound rule in the construction of contracts
that where the language is clear, unequivocal and unambiguous, the contract is to be interpreted
by its own language." RlS Assoc. v. New York Job Dev. Auth., 98 N.Y.2d 29, 32 (2002).
"When parties set down their agreement in a clear, complete document, their writing should as a
rule be enforced according to its terms." Id. Thus, "parol evidence is not admissible to create an
ambiguity in a written agreement which is complete and clear and unambiguous upon its face."
Id. at 33 (quoting W.W.W. Assoc. v. Giancontieri, 77 N.Y.2d 157, 163 (1990). An agreement
is considered unambiguous on its face if its language "has a definite and precise meaning ...
concerning which there is no reasonable basis for a difference of opinion." FlightSafety In1'l,
Inc., 418 F. Supp. 2d at 107-08. In contrast, a contract is said to contain ambiguous language,
and thus to be subject in certain circumstances to clarification via parol or other extrinsic
SOROOF.GE.wPD
VERSION 1/24112
6
evidence, if its language is "capable of more than one meaning when viewed objectively by a
reasonably intelligent person who has examined the context of the entire integrated agreement
and who is cognizant of the customs, usages and terminology as generally understood in the
particular trade or business." Id. at 108 (quoting Seiden Assoc., Inc. v. ANC Holdings, Inc., 959
F.2d 425,428 (2d Cir. 1992)).
Soroof claims that GEFCS breached three provisions of the Contract: first,
GEFCS failed to supply fuel cells that met the specified contractual standards; second, GEFCS
failed to use "reasonable efforts to supply" the fuel cells to Soroof; and third, GEFCS did not
promptly share relevant information regarding the fuel cells with Soroof. (Compl.
~~
14, 22,
35.)1 The Court will address each of the three bases for Soroofs breach of contract claim in
tum.
Soroof contends that, under the terms of the Contract, GEFCS was obligated to
"make available for Soroof a sufficient quantity of Product to distribute throughout the Kingdom
of Saudi Arabia." (Id. '114). To support this contention, Soroof cites three provisions of the
Contract: first, under the heading of "GEFCS Responsibilities," the statement that "GEFCS
covenants and warrants that it shall ... [u]se reasonable efforts to supply" the fuel cells (jJ:l,
Contract § 5.2); second, under the heading "Representations and Warranties," the statement that
GEFCS had the "full authority and capacity to enter into and perform its obligations under the
Agreement" (id. § 10.1.2); and third, under the same heading, the statement that GEFCS had
"full legal right, power, and authority to enter into and perform this Agreement" (id. § 10.1.4).
Soroof concludes from these written terms that GEFCS was under an obligation to supply a
Soroof asserts that GE Microgen, Inc., and Plug Power, Inc., are also liable for
these contractual breaches as alter egos ofGEFCS. (Compl. ~ 37.)
SOROOF.GE.wPD
VERSION \124/12
7
"sufficient quantity" of fuel cells to distribute throughout Saudi Arabia and that it had warranted
its capacity to do so. However, the Contract's language does not support this conclusion.
By the plain language of the terms Soroof cites in its pleadings, GEFCS was to
make "reasonable efforts" to supply Soroofwith fuel cells matching the specifications of the
Contract. Whcn interpreting the meaning of a "reasonable efforts" clause, "New York courts use
the term 'reasonable efforts' interchangeably with 'best efforts' ... [and] a 'best efforts' clause
imposes an obligation to act with good faith in light of one's own capabilities." Monex Fin.
Servo Ltd. v. Nova Info. Sys., Inc., 657 F. Supp. 2d 447,454 (S.D.N.Y. 2009). GEFCS'
contractual obligation to use "reasonable efforts" thus required it to work in good faith and to the
extent of its capabilities to produce the fuel cells. The provision did not, as Soroof would have
it, obligate GEFCS to successfully supply the fuel cells. So long as GEFCS used reasonable
efforts in its attempt to manufacture the fuel cells, the best efforts clause imposed no obligation
to provide any cells, much less a quantity sufficient to distribute throughout Saudi Arabia. Put
differently, reasonable efforts to supply a product are not necessarily the same as actual success
in supplying a product. The authority and capacity provisions that Plaintiff cites do not impose
production or supply obligations.
The Court has, independently, reviewed the Contract - which was attached to the
Complaint and is therefore properly considered a part of the pleadings - and found no additional
written terms or conditions to support Soroor s interpretation of GEFCS' obligations. The only
language that obliges GEFCS to provide any quantity of fuel cells is the provision that "GEFCS
covenants and warrants that it shall ... [s]ell to [Soroof] a sufficient quantity of Product to
satisfy [Soroot]'s firm purchase orders accepted by GEFCS." (Contract § 5.1) (emphasis added).
As Soroof avers in its pleadings, it never placed any such order. (Id.
SOROOF.GE.wPD
VERSION 1/24/12
~~
17,24.) Soroof alleges
that it was never given the opportunity to place an order because, for the duration of the
Contract, GEFCS failed to bring the fuel cells to market. (Id.
~
24.) But, as already explained,
GEFCS was under no obligation to succeed in bringing the fuel cells to market. Further, even if
Soroofhad placed an order, a breach would only have occurred had GEFCS accepted the order
and then failed to deliver, neither of which occurred.
Soroof provides additional proffers, in the form of parol evidence, to support its
contention that GEFCS had an obligation to supply a sufficient quantity of fuel cells to distribute
throughout Saudi Arabia. Specifically, Soroof alleges that, prior to entering into the written
agreement, unnamed GEFCS officials told Soroof that the fuel cells would be ready for
distribution within six months. New York law is clear, however, that such parol evidence is
inadmissible to vary the terms of a fully integrated, clear and unambiguous contract. Morgan
Stanley High Yield Sec., Inc. v. Seven Circle Gaming Corp., 269 F. Supp. 2d 206,214 (S.D.N.Y.
2003); RlS Assoc. v. New York Job Dev. Auth., 98 N.Y.2d 29, 33 (2002). Explaining the
rationale for this rule, the New York Court of Appeals has stated that "[ t]he best evidence of
what parties to a written agreement intend is what they say in their writing." Slamow v. Del Col,
79 N.Y.2d 1016,1018 (1992).
In the case at hand, the language of the Contract obligates GEFCS to make
reasonable efforts to supply the fuel cells but makes no mention of a time period, whether six
months or otherwise, in which such reasonable efforts were to result in success. Had the parties
intended to include such a time frame in their agreement, they could have incorporated it into the
written document. Moreover, the Contract contains an explicit integration clause, providing that
"any terms and conditions relating to transactions within the scope of this Agreement which are
not incorporated or referenced herein shall not be binding upon either Party" and "this
SOROOF.GE.wPD
VERS10l' 1124/1 2
9
Agreement wholly cancels, terminates and supersedes any agreement heretofore entered into
between [Soroo£] and GEFCS with respect to the distribution and servicing of the Product."
(Contract §§ 22.1-.2.) Parol evidence is properly excluded where, as here, a contract is clear,
unambiguous, complete on its face and, moreover, contains an explicit integration clause. See
Morgan Stanley High Yield Sec., Inc., 269 F. Supp. 2d at 214-15. Accordingly, Soroors breach
of contract claim that is premised on a contractual obligation to supply fuel cells to Soroof in
sufficient quantity for distribution is unavailing, as the Complaint fails to allege facts sufficient
to support such a claim.
Soroors second basis for its breach of contract claim, that GEFCS failed to make
reasonable efforts to supply fuel cells, is similarly unavailing. As previously noted, when a party
agrees to use "reasonable efforts," it agrees to act '''in good faith and to the extent of its own
capabilities." Monex Fin. Servo Ltd., 657 F. Supp. 2d at 454. Soroof asserts that "GE Fuel Cell
breached its obligations under the Agreement by failing to ... use "reasonable efforts to supply"
this Product" (Compi.
~~
14, 22, 35), and that "GE MicroGen [sic] and Plug Power wrongfully
delayed performance [of the Contract by] waiting for the term of the Agreement to run" (id.
~
28). Soroof provides no facts
such as specific instances of delay, facts regarding what efforts
were lacking, or even allegations concerning GEFCS's capabilities and its failure to live up to
them
to support these conclusory statements. Soroofrelies instead on GEFCS's lack of
success in manufacturing the fuel cells. GEFCS's failure to manufacture and supply the cells,
however, does not, in and of itself, provide a plausible basis for inferring that GEFCS acted in
bad faith or at a level below its capacities, as would be required to state a plausible claim for
breach of a reasonable efforts covenant. Soroofhas failed to allege facts sufficient to "permit the
court to infer more than a mere possibility of misconduct," Iqbal, 129 S. Ct. at 1950, and thus
SOROOF.GE.wPD
VERSION 1/24112
10
has failed to state a breach of contract claim premised on GEFCS's failure to use reasonable
efforts to produce fuel cells.
As its third basis for the breach of contract claim, Soroof asserts that "GE Fuel
Cell breached its obligations under the Agreement by failing to ... share promptly relevant
information, including but not limited to product performance, failure and liability issues."
(CompI.
'I~
14,22, 35.) In its Complaint, Soroof fails to amplify this conclusory allegation with
any specific facts to render the claim plausible. While Soroof identifies instances in which
GEFCS notified Soroof of delays in producing the fuel cells, the Complaint provides no basis for
the inference that GEFCS withheld material information about the ultimate viability of the cells
on any of these occasions, or that the notifications were not made on a timely basis. As the
Supreme Court made clear in Iqbal, "a pleading that offers labels and conclusions or a formulaic
recitation of the elements of a cause of action will not do. Nor does a complaint suffice if it
tenders nakcd assertion[ s] devoid of further factual enhancement." 129 S. Ct. at 1949 (internal
citations and quotations omitted). Because Soroofs pleading does no more than make naked
assertions without any factual enhancements to support them, this aspect of the breach of
contract claim is not viable as currently pleaded.
Although the Complaint is insufficient to support a claim that GEFCS breached
the Contract by failing to use reasonable efforts to produce fuel cells or by failing to share
promptly relevant information, Soroofhas proffered evidence in connection with the instant
motion practice that suggests those claims might be meritorious. Courts "should freely give
leave to amend when justice so requires," Fed. R. Civ. P. 15(a)(2), and the United States Court
of Appeals for the Second Circuit has stated that courts should be "hesitant to preclude the
prosecution of a possibly meritorious claim because of defects in the pleadings." Ross v. A.H.
SOROOF.GE.wPD
VERSION 1/24112
II
Robins Co., 607 F.2d 545, 547 (2d Cir. 1979). In its moving papers, Soroofproffers the
deposition of one Frank Scovello, the former President of GEFCS, during which he testified that
Defendants began to realize as early as "the 2001 time frame" that "they could not build a
product even close to what [they] had originally contemplated." (Dep. of Frank Scovello 12-13,
102.) Soroof, however, did not learn until 2005 that the product could not be built according to
the contractual specifications. These facts suggest that Soroof may have a meritorious claim that
Defendants breached the provision of the contract that required them to "share promptly relevant
information, including but not limited to product performance" and breached the best efforts
covenant by failing to work in good faith to bring the fuel cells to market during the life of the
Contract. These aspects of the breach of contract claim will be dismissed without prejudice to
repleading them in a manner that incorporates relevant facts that support the claim. In all other
respects, Soroofs first cause of action for breach of contract will be dismissed with prejudice.
Misrepresentation (Second Cause of Action)
Claims for fraud must satisfy the heightened pleading standard of Federal Rule of
Civil Procedure 9(b), which requires that "all averments of fraud" be "stated with particularity."
Fed. R. Civ. P. 9(b). To satisfy this heightened pleading standard when asserting a claim of
fraudulent misrepresentation, a plaintiff must identify: (I) specific statements that plaintiff
contends were fraudulent; (2) the speaker; (3) where and when the statements were made; and
(4) why the statements were fraudulent. Novak v. Kasaks, 216 F.3d 300, 306 (2d Cir. 2000); see
also Manhattan Motorcars, Inc. v. Automobili Lamborghini, S.P.A., 244 F.R.D. 204, 213
(S.D.N.Y. 2007). "In the case of fraudulent concealment or omission, where the plaintiff is
unable to specify the time and place because no act occurred, 'the complaint must still allege: (1)
what the omissions were; (2) the person responsible for the failure to disclose; (3) the context of
SOROOF.GE.wPD
VERSIO'l 1i24/12
J2
the omissions and the manner in which they misled the plaintiff; and (4) what the defendant
obtained through fraud.'" Manhattan Motorcars, Inc., 244 F.R.D. at 213 (quoting Odyssey Re
(London) Ltd. v. Stirling Cooke Brown Holdings Ltd., 85 F. Supp. 2d 282,293 (S.D.N.Y.
2000)).
Soroof identifies two specific instances in which GEFCS made allegedly
fraudulent statements: GEFCS's pre-contractual assurance that the fuel cells would be ready
within six months and its assurance in November 2000 that the fuel cells would be ready in
2001. (Compi.
'I~
9, 17.) Plaintiffs proffers merely paraphrase these alleged statements and
provide no direct quotes. Moreover, Soroof attributes the alleged statements to unnamed "GE
officials" and gives no specific dates for the comments, failing to provide even a specific month
for the alleged pre-contractual statement that the fuel cells would be ready within six months.
Plaintiff thus fails to adequately plead at least three of the four elements necessary to state a
claim of fraudulent misrepresentation.
Plaintiff further alleges that GEFCS made "repeated representations" about the
viability ofthe fuel cells that were fraudulent, as well as multiple omissions of material facts,
upon which Plaintiff relied when spending an estimated total of three million dollars. (Id.
'[~
13,
18,20,41,45.) These allegations -lacking proffers as to who, when, how or even what was
misstated or omitted
similarly fail to satisfy the heightened pleading standard of 9(b).
However, as noted in the discussion of the claim for breach of contract, Soroof
has proffered evidence in connection with the instant motion that suggests Soroof may have a
meritorious claim. Therefore, Soroofs misrepresentation claim will be dismissed for failure to
satisfy the requirements of Federal Rule of Civil Procedure 9(b) without prejUdice to repleading
in a manner consistent with the requirements of Rule 9(b).
SOROOF.GE.wPD
VERSION 1/24/12
13
Conversion (Third Cause of Action)
Under New York law, "conversion is the unauthorized assumption and exercise of
the right of ownership over goods belonging to another to the exclusion of the owner's rights."
Thyroffv. Nationwide Mut. Ins. Co., 460 F.3d 400, 403-04 (2d CiL 2006) (quoting Vigilant Ins.
Co. of Am. v. Hous. Auth., 87 N.Y.2d 36, 44 (1995». "To state a claim of conversion, the
plaintiff must allege that (1) the party charged has acted without authorization, and (2) exercised
dominion or a right of ownership over property belonging to another[,] (3) the rightful owner
makes a demand for the property, and (4) the demand for the return is refused." Lefkowitz v.
Bank of New York, 676 F. Supp. 2d 229,251 (S.D.N.Y. 2009) (internal quotations omitted).
Soroof contends that GEFCS "wrongfully and without authority" exercised dominion over the
one million dollars it paid upon signing the Contract, thereby committing conversion. (CompI.
~
48.) The Contract, however, expressly characterizes the payment as a non-refundable fee, and
Soroof knowingly authorized GEFCS to receive it by both signing the Contract and paying the
one million dollars. (Id.
~
11.) Under these circumstances, the Court finds no factual basis for a
determination that GEFCS acted without authorization or that the property in question belonged
to Soroof. Judgment on the pleadings will therefore be granted as to Plaintiffs conversion
claim.
Constructive Trust and Unjust Enrichment (Fourth and Fifth Causes of Action)
A finding of unjust enrichment is required for a finding of a constructive trust. In
re First Central Fin. Corp., 377 F.3d 209,212 (2d CiL 2004). "[U]njust enrichment is a quasi
contractual remedy, so that such a claim is ordinarily unavailable when a valid and enforceable
contract governing the same subject matter exists." Mina Inv. Holdings Ltd. v. Lefkowitz, 16 F.
Supp. 2d 355,361 (S.D.N.Y. 1998); see also In re First Central Fin. Corp., 377 F.3d at 212;
SOROOF.GE.wPD
VERSION 1I24i12
14
Clark-Fitzpatrick, Inc. v. Long Island R.R. Co., 70 N.Y.2d 382, 388 (1987). Indeed, the Second
Circuit has held that the "existence of a written agreement precludes a finding of unjust
enrichment ... [and] constructive trust." In re First Central Fin. Corp., 377 FJd at 213
(emphasis added). In the case at hand, Soroof and GEFCS' s relationship was, at all relevant
times, governed by a contract. It is under this very contract that Soroof seeks relief on its other
claims. As such, Plaintiff has no basis for relief under quasi-contractual remedies such as
constructive trust and unjust enrichment. Accordingly, judgment on the pleadings in
Defendants' favor will be granted as to Plaintiffs fourth and fifth causes of action.
Demand for an Accounting (Sixth Cause of Action)
"A party seeking an accounting must first establish four conditions: (1) relations
of a mutual and confidential nature; (2) money or property entrusted to the defendant imposing
upon him a burden of accounting; (3) that there is no adequate legal remedy; and (4) in some
cases, a demand for an accounting and a refusal." IMG Fragrance Brands LLC v. Houbigant,
Inc., 679 F. Supp. 2d 395, 411 (S.D.N.Y. 2009) (quoting Pressman v. Estate of Steinvorth, 860
F. Supp. 171, 179 (S.D.N.Y. 1994)). Though the pleadings are not specific, Plaintiff presumably
bases its demand for accounting on the one million dollar non-refundable fee, on the theory that
this money was entrusted to GEFCS. As already explained, the fee was clearly labeled in the
Contract as a non-refundable payment and Soroofhad no right to reclaim it once it was paid.
Soroof cannot demand an accounting for monies that it gave, via contract, to GEFCS under the
explicit understanding that they were non-refundable. Nor does Soroof allege that it entrusted
any other monies or property to GEFCS upon which the demand for accounting could be based.
Defendants will be granted judgment on the pleadings as to Plaintiffs sixth cause
of action.
SOROOF.GE. WPD
VERSION 1/24/12
15
Contractual Limitation on Liability
Defendants assert that Soroofs claims must be dismissed because the claims are
barred by the Contract's express limitations on liability and because the claims are untimely,
having been asserted after the applicable statutes oflimitations had run. The Court addresses
Defendants' limitation on liability argument and statute of limitations argument only insofar as
they relate to the two claims that Soroof will be permitted to replead and only to determine
whether these arguments provide clear bases for denying leave to replead on the grounds that
amendment of the pleadings would be futile. For the following reasons, the Court finds that
Defendants' arguments do not provide a proper basis for denying Plaintiff an opportunity to
replead some of its claims.
With regard to Defendants' limitation on liability argument, the Contract
provides, in pertinent part, as follows:
In no event, whether as a result of breach of contract, indemnity, warranty, tort
(including negligence), strict liability or otherwise, shall GEFCS or its officers,
directors or employees be liable to [Soroot] ... for loss of profit or revenues,
downtime costs, cost of capital, cost of facilities or services, or any other costs or
damages which may be categorized as indirect, incidental, exemplary or
consequential damages.
(Contract § 12.2.) The Contract provides further that:
Neither GEFCS nor [Soroot] shall be liable to the other by reason of termination,
expiration, or non-renewal of this Agreement for compensation, reimbursement or
damages on account of loss of present or prospective profits on sales or
anticipated sales or on account of expenditures, investments, leases or
commitments in connection with the business or good will ofGEFCS or [Soroot]
or on account of any other cause or thing whatsoever ....
(Contract § 15.4.)
"An entrepreneur may provide protection against its own fault," and contract
provisions that limit liability are "perfectly common and acceptable." Kalisch-larcho v. City of
SOROOF.GE.wPD
VERSION
1/24/12
16
New York, 58 N.Y.2d 377,384-85 (1983). However, "an exculpatory agreement, no matter how
flat and unqualified its terms, will not exonerate a party from liability under all circumstances.
Under announced public policy, it will not apply to exemption of willful or grossly negligent
acts." rd. at 384.
Based on the evidentiary proffers that Soroof has made in connection with the
instant motion practice, Soroofmight have a good faith basis for alleging in its amended
pleadings that GEFCS willfully and/or with gross negligence breached the contract and/or
misrepresented material facts. The evidence proffered in connection with the instant motion
practice suggests that GEFCS knew as early as 2001 that it could not build a product that would
meet the contractual specifications and that GEFCS withheld this infoffilation from Soroof until
2005 and that GEFCS affirmatively deceived Plaintiff by indicating repeatedly that a
contractually adequate product would soon be ready for distribution. As Soroofmay have a
good faith basis for asserting willful misconduct or gross negligence on the part of GEFCS,
Defendants' argument that the contract provisions limiting liability preclude Plaintiffs claims is,
at this stage of the proceeding, unavailing.
The foregoing analysis applies as well to Soroofs request for an award of the one
million dollar distribution fee insofar as it is premised on a claim that Soroofs inability to reap
the benefit of the distribution arrangement was the product of willful misconduct or gross
negligence on the part ofGEFCS. Defendants assert that the fee's characterization as non
refundable limits Defendants' liability by precluding a particular category of damages, just as
section 12.2 of the Contract limits liability by precluding damages "for loss of profit or revenues,
downtime costs, cost of capital," and section 15.4 precludes damages for "loss of present or
prospective profits on sales or anticipated sales." Because the fee's non-refundable status
SOROOF.GE. WPD
VERSION
1/24/12
17
functions in the same manner as the other contractual limitations on liability, the fee's non
refundable status is subject to the same public policy considerations that justify disregarding
limitations on liability in the event of willful misconduct or gross negligence. Furthermore, the
non-refundable fee was paid by Soroof not as a gift but as one element in a bargained for
exchange and, in that context, "the word non-refundable cannot be construed as a license to
provide little or no consideration and to still retain an advance payment." Iwon, Inc. v.
Ourhouse, Inc., 744 N.Y.S.2d 791,794 (N.Y. Sup. Ct. 2001). Accordingly, Plaintiff will be
permitted to replead its breach of contract and misrepresentation claims, including the claims'
prayer for recovery of the one million dollar distribution fee, notwithstanding the contract's
characterization of the fee as non-refundable.
The Court notes that the parties have not briefed, and the Court does not address
here, whether loss of the distribution fee was the result of the particular misconduct that Plaintiff
has been given leave to replead in its amended complaint such that the fee should be included in
an award of damages. The Court has addressed only Defendants' argument that the non
refundable characterization of the fee provides a complete bar to recovery of the fee.
Statute of Limitations for Plaintiffs Breach of Contract and Misrepresentation
Defendants assert that Plaintiffs claims for breach of contract and
misrepresentation are barred by the applicable statutes of limitations. Specifically, Defendants
assert that (i) Plaintiffs claims accrued as early as November 2000 when, according to Soroof,
GEFCS was required, but failed, to deliver fuel cells to Soroof; (ii) a four-year statute of
limitations applies to the breach of contract claim pursuant to N ew York's Uniform Commercial
Code because the Contract provided expressly that the relationship of GEFCS and Soroof was
that of buyer and seller and a two-year statute of limitations applies to the misrepresentation
SOROOF.GE.wPD
VERSION 112411 2
18
claim pursuant to New York's Civil Practice Law and Rules; and (iii) Soroofs claims are
untimely because Soroof did not initiate arbitration until July of 2008.2 Soroof responds that its
claims are timely, as the claims did not accrue until 2005 or, alternatively, the statute of
limitations was tolled until 2005 or later. Soroof also asserts that a six-year statute of limitations
applies pursuant to § 213 of New York's Civil Practice Law and Rules because Soroofs
relationship to GEFCS was primarily that of a distributor and not a buyer.
"Generally, any Statute of Limitations begins to run when a cause of action
accrues. In New York, a breach of contract cause of action accrues at the time of breach." ElyCruikshank v. Bank of Montreal, 81 N.Y.2d 399, 402 (1993). For a misrepresentation cause of
action, the statute oflimitations runs "from the date the cause of action accrued" for six years or
"from the time the plaintiff ... discovered the fraud, or could with reasonable diligence have
discovered it," for two years. N.Y. C.P.L.R. 213(8) (McKinney Supp. 2011). "[U]nder the
equitable tolling doctrine, a statute of limitations does not run against a plaintiff who was
justifiably ignorant of his cause of action," and "the doctrine of equitable estoppel may toll a
statute of limitations where defendant's misconduct caused him to delay bringing suit." Access
Northern Sec. Com. v. Linear Com., 97 Civ. 2937,1998 WL 566815, *5 (S.D.N.Y. Sept. 4,
1998) (citations and some internal punctuation omitted).
Based on the evidence proffered in connection with the instant motion practice,
Soroof might have a good faith basis for alleging that Soroof was justifiably ignorant of its
2
SOROOF.GE.wPD
"Defendants' position is that the filing of the arbitration did not toll the statute of
limitations [but] for the purposes of this motion, Defendants assume that the July
2008 arbitration filing did toll the statute." (Defs.' Reply Mem. ofL. in Support
of Mot. for J. on the Pleadings 2.)
VERSIO'lli24iI2
19
claims or was caused by Defendants' misconduct to delay bringing its claims until 2005 or some
time thereafter, on account of Defendants , repeated representations that a viable product would
be available imminently and Defendants' failure to disclose that GEFCS knew it would be
unable produce a viable product. The statute of limitations thus might have begun to run in 2005
or later so that the commencement of arbitration in July of 2008 would have been within the
limitations period, whether a 4-year or 6-year limitations period applies. Even if a 2-year
limitations period applies to the misrepresentation claim, the claim could be timely depending on
when Soroof discovered or could have discovered that Defendants' representations were
fraudulent. Accordingly, Defendant has not show that giving Soroof the opportunity to replead
would be futile, and Plaintiff will be given the opportunity to amend its breach of contract and
misrepresentation claims.
Plaintiff's Motions for Sanctions
"Rule II(c) of the Federal Rules of Civil Procedure[] al10ws the court to sanction
a party, if the court determines that the party has violated Rule 11 (b) by making false,
misleading, improper, or frivolous representations to the court." Williamson v. Recovery Ltd.
Partnership, 542 F.3d 43,51 (2d Cir. 2008); Fed. R. Civ. P. II. Plaintiff contends that
Defendants' Rule 12(c) motion filings are misleading and, as such, warrant sanctions.
Specifically, Plaintiff contends that Defendants failed to disclose three key facts in their Rule
12(c) motion filings, that the omissions misled the Court, and that Defendants' Rule 12(c)
motion should thus be denied and Defendants should be sanctioned. Plaintiff's contentions are
unavailing for the reasons discussed below.
First, according to Plaintiff, the Arbitration Panel's denial of Defendants' motion
to dismiss the arbitration conclusively resolved the issues that Defendants raise in their present
SOROOF.GE. WPD
VERSION \/24112
20
Rule 12(c) motion, establishing law of the case precluding relitigation of those issues. Plaintiff
argues that Defendants misled the Court by allegedly failing to disclose the prior proceedings
and their allegedly preclusive effect on the present motion. However, contrary to Plaintiff's
assertion, Defendants did not hide either the existence of the prior arbitration or the Arbitration
Panel's decision denying Defendants's motion to dismiss the arbitration proceeding. See Docket
Nos. 31-32. Furthennore, there is no basis for Plaintiff's contention that the Panel's action on
the motion precludes Defendants' arguments here. The Arbitration Panel denied Defendants'
motion to dismiss without prejudice, with an explicit allowance for Defendants to re-assert the
same arguments after discovery, and without any discussion of or conclusions regarding the
merits of the legal arguments advanced by Defendants.
Second, Plaintiff alleges that Defendants raised only a six-year statute of
limitations in the context of the arbitration proceeding and thus are judicially estopped from
relying on a four-year statute of limitations in their Rule 12(c) motion filings. This assertion is
baseless. Defendants were under no obligation, by reason ofjudicial estoppel or otherwise, to
limit themselves to the six -year statute of limitations in the present action. Judicial estoppel is
inapposite where, as here, no final judgment was reached in the prior proceeding, the disputed
representation was one of law rather than fact, and the court (or arbitration panel) never adopted
the disputed representation in its decision-making process. See, e.g., Republic of Ecuador v.
Chevron Corp., 638 F.3d 384, 397 (2d Cir. 2011); In re Adelphia Recovery Trust, 634 F.3d 678,
695-97 (2d Cir. 2011).
Third, Plaintiff alleges that Defendants misled the Court by failing to disclose the
existence of and details of the Venue Agreement that the parties reached at the close of the
arbitration. Plaintiff also asserts that Defendants breached the Venue Agreement by making
SOROOF.GE.wPD
VERSIO'.l1/24112
21
statute of limitations arguments premised on the filing date of this action. Defendants'
limitations arguments cite the 2010 filing date of this action but also assert that the action is
untimely in relation to any assertions of the claims by Plaintiffs, so the argument that defendants
misled the Court in violation of Rule 11 is unavailing. Furthermore, Defendants acknowledged
those aspects of the Venue Agreement that were, conceivably, material to their Rule 12(c)
motion
namely, the argument that the statute of limitations should be tolled from the date that
arbitration was initiated - within the motion itself. (Mem. of Law in Supp. of Defs.' Mot. for J.
on the Pleadings, 12 n.3.) The other details of the agreement were inapplicable to the Rule 12(c)
motion and Defendants had no obligation to disclose them in their papers.
For these reasons, Plaintiffs motion for sanctions against Defendants and their
counsel is denied.
Defendants' Application for Attorneys' Fees and Costs
Defendants seek an award of attorneys' fees and costs in connection with
Plaintiffs sanctions motion, arguing that Plaintitrs sanctions motion is frivolous and vexatious.
Financial sanctions, such as an order to pay an award of attorneys' fees and costs to the opposing
party, may be imposed pursuant to Federal Rule of Civil Procedure 11 when a party makes
"false, misleading, improper, or frivolous representations to the court." Williamson, 542 F.3d at
51. A claim is considered frivolous when "the legal position has no chance of success." Fishoff
v. Coty Inc., 634 F.3d 647, 655 (2d Cir. 2011) (internal quotations omitted). However, "[t]he
fact that a legal theory is a long-shot does not necessarily mean it is sanctionable." Id. Also, 28
U.S.C. § 1927 authorizes a court to impose financial sanctions on an attorney "who ...
multiplies the proceedings in any case unreasonably and vexatiously." 28 U.S.C.A § 1927 (West
2006). However, "[t]he Second Circuit has made clear that such sanctions are only 'proper when
SOROOF.GE.WPD
VERSION 1124/12
22
the attorney's actions are so completely without merit as to require the conclusion that they must
have been undertaken for some improper purpose such as delay.'" Fagan v. Republic of Austria,
No. 08 Civ 6715,2011 WL 1197677, at *20 (S.D.N.Y. Mar. 25,2011) (quoting Oliveri v.
Thompson, 803 F.2d 1265, 1272 (2d Cir. 1986». The Second Circuit has further explained that
there must be "clear evidence that the challenged actions are entirely without color, and [are
taken] for reasons of harassment or delay or for other improper purposes." Revson v. Cinque &
Cinque, P.e., 221 F.3d 71, 78 (2d Cir. 2000) (emphasis added).
Plaintiffs motion for sanctions, though not meritorious, was not patently
frivolous, as would be required to support the imposition of sanctions pursuant to Rule 11. The
motion did not cross the line from being a "long shot" to having "no chance of success." Nor
does the Court agree that Plaintiffs motion for sanctions was so un-meritorious as to compel the
conclusion that it was filed for an improper purpose, as is necessary to impose sanctions
pursuant to Section 1927. Defendants allege that Plaintiff filed the motion for sanctions to
improperly delay and interfere with the case, but their only evidence is that the motion was filed
during a particularly busy time in the proceedings. Their circumstantial argument falls far short
of the "clear evidence" necessary to justify sanctions under Section 1927.
Defendants' application for an award ofattomeys' fees will be denied.
Parties' Cross-motions for Summary Judgment
Plaintiff has moved for partial summary judgment, seeking nullification of
GEFCS's certificate of cancellation and the piercing of the veil ofGEFCS. Defendants have
cross-moved for summary judgment, arguing that GEFCS's certificate of cancellation should not
be nullified and, thus, all claims against GEFCS must be dismissed, and that all claims against
GEFCS's members should be dismissed because Plaintiff has not proffered facts adequate to
SOROOF.GE. WPD
VERS10N JI24il2
23
warrant the piercing of GEFCS' s corporate veil.
Summary judgment is to be granted in favor of a moving party if "the movant
shows that there is no genuine dispute as to any material fact and the movant is entitled to
judgment as a matter oflaw." Fed. R. Civ. P. 56(a); see also Anderson v. Liberty Lobby, Inc.,
477 U.S. 242,256 (1986) (the moving party bears the burden of establishing that there is no
genuine issue of material fact). A fact is considered material "if it might affect the outcome of
the suit under the governing law," and an issue of fact is a genuine one where "the evidence is
such that a reasonable jury could return a verdict for the nonmoving party." Holtz v. Rockefeller
& Co. Inc., 258 F.3d 62, 69 (2d Cir. 2001) (quoting Anderson, 477 U.S. at 248). The Second
Circuit has explained, however, that "[ t]he party against whom summary judgment is sought ...
'must do more than simply show that there is some metaphysical doubt as to the material facts
. . .. [T]he nonmoving party must come forward with specific facts showing that there is a
genuine issue for triaL'" Caldarola v. Calabrese, 298 F.3d 156, 160 (2d Cir. 2002) (quoting
Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586-87 (1986»). Similarly,
"mere conclusory allegations, speculation or conjecture" will not suffice to defeat summary
judgment. Cifarelli v. Vill. of Babylon, 93 F.3d 47, 51 (2d Cir. 1996); see also Fed. R. Civ. P.
56(e). When cross-motions for summary judgment are filed, "the standard is the same as that for
individual motions for summary judgment." Natural Res. Def. Council v. Evans, 254 F. Supp.
2d 434,438 (S.D.N.Y. 2003). "The court must consider each motion independently of the other
and, when evaluating each, the court must consider the facts in the light most favorable to the
non-moving party." Id. (citing Morales v. Quintel Entrn't, Inc., 249 F.3d 115, 121 (2d Cir.
2001)).
SOROOF.GE.wPD
-_._._--
-------......
_---
VERSION 1/24112
24
Plaintiffs Motion for Partial Summary Judgment Nullifying GEFCS's Certificate
of Cancellation and Defendants' Motion for Summary Judgment Dismissing Claims
A limited liability company cannot be sued under Delaware law once the
company's certificate of cancellation has been filed unless the plaintiff successfully seeks to
have the company's certificate of cancellation nullified on the ground that the company was not
"wound up" in compliance with Delaware law. Metro Commc'n Corp. BVI v. Advanced
Mobilecomm Tech., 854 A.2d 121, 138-39 (Del. Ch. 2004) (citing In re CC&F Fox Hill Assoc.
Ltd. P'ship, 1997 WL 349236, at *4 (Del. Ch. June l3, 1997)). Plaintiff moves for partial
summary judgment nullifying GEFCS' s certificate of cancellation, asserting that GEFCS was
wound up in contravention of Delaware law when GEFCS failed to make provision sufficient to
provide compensation to Soroof for claims likely to arise at the time of dissolution. Defendants
cross-move for summary judgment dismissing all claims against GEFCS, asserting that GEFCS
had no obligation to make provision for Plaintiffs claims because GEFCS had no available
assets at the time of dissolution. The applicable section of the Delaware LLC Act provides that:
If there are sufficient assets, such claims and obligations [against an LLC] shall
be paid in full and any such provision for payment made shall be made in full. If
there are insufficient assets, such claims and obligations shall be paid or provided
for according to their priority and, among claims of equal priority, ratably to the
extent of assets available therefor (emphasis added).
LLC Act § 18-804(b). It is undisputed that GEFCS had no assets available to pay potential
claims at the time of dissolution. (See Scovello Dep. ("GEFCS really had no cash assets. The
only items that existed within the physical plant were the [computer] server ... and a phone
switch.")) Because an LLC is obligated to make provision for claims only "to the extent of
assets available therefor," GEFCS was not wound up in contravention of Delaware law when,
lacking any real assets, it did not make adequate provision for Soroofs claims. Therefore,
SOROOF.GE.IVPD
VERSION
1/24/12
25
Plaintiff s motion for partial summary judgment nullifying GEFCS' s certificate of cancellation
will be denied, and Defendants' motion for summary judgment dismissing all claims against
GEFCS will be granted.
Plaintiff argues that GEFCS' s lack of assets was the result of Defendants'
intentional and improper undercapitalization of GEFCS as the mere alter ego of the Defendants,
and that GEFCS should not be permitted to avoid liability on that basis. Although the question
of whether GEFCS was the Defendants' alter ego is clearly relevant to a determination of
whether claims may proceed against GE Microgen and Plug Power, Soroof has cited no legal
authority for the proposition that an LLC's certificate of cancellation should be nullified because
the LLC was the alter ego of its owners. Furthermore, as a practical matter, permitting Soroof to
proceed with its claims against GEFCS will not augment Soroofs prospects of actual recovery
should it successfully litigate this suit, as all parties agree that GEFCS no longer exists, lacks any
assets, and lacked any significant assets at the time of dissolution. Plaintiff has failed to raise a
genuine issue of material fact as to the propriety of GEFCS' s dissolution and has not shown that
it is entitled as a matter of law to nullification of the certificate of cancellation. Plaintiffs
motion for partial summary judgment nullifying GEFCS's certificate of cancellation will be
denied, and Defendants' motion for summary jUdgment dismissing all claims against GEFCS
will be granted.
Plaintiffs Motion to Pierce the Veil ofGEFCS
Plaintiff moves for partial summary judgment to pierce the veil of GEFCS,
thereby enabling Plaintiff to pursue its claims against GE Microgen and Plug Power. Defendants
argue in their cross-motion that Plaintiff has not proffered facts adequate to pierce the veil of
GEFCS and that, therefore, all claims should be dismissed as against GE Microgen and Plug
SOROOF,GE, WPD
VERSION 1124112
26
Power. "Delaware law permits a court to pierce the corporate veil where there is fraud or where
[the corporation] is in fact a mere instrumentality or alter ego of its owner." NetJets Aviation,
Inc. v. LHC Commc'ns LLC, 537 F.3d 168, 177 (2d Cir. 2008) (citations and internal quotation
marks omitted). "To prevail under the alter-ego theory of piercing the veil, a plaintiff need not
prove that there was actual fraud but must show a mingling of the operations of the entity and its
owner plus an overall element of injustice or unfairness." ld. (citation and internal quotation
marks omitted). The factors that a court must consider when evaluating an alter-ego argument
for veil piercing include:
whether the corporation was adequately capitalized for the corporate undertaking;
whether the corporation was solvent; whether dividends were paid, corporate
records kept, officers and directors functioned properly, and other corporate
fOlUlalities were observed; whether the dominant shareholder siphoned corporate
funds; and whether, in general, the corporation simply functioned as a facade for
the dominant shareholder.
Id. at 176-77. "These principles are generally applicable as well where one of the entities in
question is an LLC rather than a corporation," except that "somewhat less emphasis is placed on
whether the LLC observed internal fOlUlalities because fewer such fOlUlalities are legally
required." Id. at 178. Overall, "no single factor can justify a decision to disregard the corporate
entity, but ... some combination of them is required, and ... an overall element of injustice or
unfairness must always be present, as well." Id. at 177.
Plaintiff has proffered evidence that GEFCS had no cash assets at the time of
dissolution; that GEFCS had no employees and that the individuals working at GEFCS were
actually employees of Plug Power, Microgen or GE; and that GEFCS did not lease its office
space but, instead, GE Microgen leased the office space from Plug Power. The office space did
not have a plaque or other sign indicating the presence of GEFCS; instead, the space "was
SOROOf.GE. WPD
VERSION 1124112
27
identified as GE Microgen." (Conway Dep. 22:l3-22.) Plaintiffs uncontroverted proffers
demonstrate an extensive "mingling of the operations" of GEFCS and its owners, such that
GEFCS was a mere instrumentality or alter ego of GE Microgen and Plug Power, as well as an
overall element of unfairness to Soroof. Defendants's proffers have not created a genuine issue
of material fact such that a rational jury could find that piercing GEFCS' s corporate veil is not
warranted.
Plaintiffs motion for partial summary judgment piercing the veil of GEFCS will
be granted so that Soroof may proceed with its claims against GE Microgen and Plug Power.
Defendants' motion for summary judgment dismissing all claims against GE Microgen and Plug
Power will be denied.
CONCLUSTON
For the foregoing reasons, Defendants' motion for judgment on the pleadings is
granted as to Plaintiffs third, fourth, fifth and sixth causes of action. Plaintiffs first and second
causes of action are dismissed without prejudice to repleading. Plaintiffs motion for sanctions
and Defendants' application for attorneys' fees and costs are both denied. Plaintiffs motion for
partial summary judgment is granted with regard to the piercing of the veil of GEFCS and is
denied in all other respects. Defendants' motion for summary judgment dismissing all claims
against GEFCS is granted. Defendants' motion for summary judgment dismissing all claims
against GE Microgen and Plug Power is denied.
Any amended complaint repleading the first and second causes of action must be
filed by February 10, 2012. Failure to file a timely amended pleading will result in the dismissal
of Plaintiffs Complaint in its entirety, with prejudice and without further advance notice.
If an amended comp laint is timely filed, the parties must meet with Magistrate
SOROOF.GE.\\'PD
VERSION
1/24112
28
Judge Francis to discuss the possibility of settlement and any outstanding pretrial matters.
This Memorandum Opinion and Order resolves docket entry numbers 45, 74, 87
and 91.
SO ORDERED.
Dated: New York, New York
January 24,2011
~SWAIN
United States District Judge
SOROOF.GE.wPD
VERSIO!'-J 1/24112
29