ORDER: The Court has reviewed Plaintiff's submissions for default judgment and inquest. Plaintiff has not provided sufficient information to conduct the inquest. Accordingly, by March 19, 2025, Plaintiff shall file, with an authenticating decl aration: 1. Exhibit H to the Weiss Declaration (Dkt. 20) referenced at Paragraph 9 thereof; 2. Any demand letters directed to Defendants for payments due; 3. Any responses from Defendants to Plaintiff's demand letters; 4. A schedule of amount s paid and amounts due by Defendant; 5. Justification for using March 27, 2024 as the start date for interest; 6. Identification of Plaintiff's and Defendant' Caldwell & Walsh Building Construction, Inc.'s states of incorporation; and 7. The state in which Defendant Ferrone is domiciled (residence is not the same as domicile, and domicile determines the state of which an individual is a citizen). SO ORDERED. Copies transmitted this date to all counsel of record. (Signed by Magistrate Judge Robert W. Lehrburger on 3/10/2025) (mml)
UNITED STATES DISTRICT COURT
SOUTHERN DISTRICT OF NEW YORK
---------------------------------------------------------------X
M&J MECHANICAL CORP.,
:
:
Plaintiff,
:
:
- against :
:
CALDWELL & WALSH BUILDING
:
CONSTRUCTION, INC. and MICHAEL
:
FERRONE,
:
:
Defendants.
:
---------------------------------------------------------------X
24-CV-3336 (MMG) (RWL)
ORDER
ROBERT W. LEHRBURGER, United States Magistrate Judge.
The Court has reviewed Plaintiff’s submissions for default judgment and
inquest.
Plaintiff
has
not
provided
sufficient
information
to
conduct
the
inquest. Accordingly, by March 19, 2025, Plaintiff shall file, with an authenticating
declaration:
1.
Exhibit H to the Weiss Declaration (Dkt. 20) referenced at Paragraph 9
thereof;
2.
Any demand letters directed to Defendants for payments due;
3.
Any responses from Defendants to Plaintiff’s demand letters;
4.
A schedule of amounts paid and amounts due by Defendant;
5.
Justification for using March 27, 2024 as the start date for interest;
6.
Identification of Plaintiff’s and Defendant’ Caldwell & Walsh Building
Construction, Inc.’s states of incorporation; and
7.
The state in which Defendant Ferrone is domiciled (residence is not the
same as domicile, and domicile determines the state of which an individual is a citizen).
1
SO ORDERED.
_________________________________
ROBERT W. LEHRBURGER
UNITED STATES MAGISTRATE JUDGE
Dated: March 10, 2025
New York, New York
Copies transmitted this date to all counsel of record.