Bluegreen Vacations Unlimited, Inc. v. T. Park Central LLC et al
Filing
24
MEMORANDUM OPINION AND ORDER. The Petition must be and is DISMISSED. The Clerk of Court is directed to close this case. SO ORDERED. (Signed by Judge Jesse M. Furman on 1/28/25) (yv)
UNITED STATES DISTRICT COURT
SOUTHERN DISTRICT OF NEW YORK
---------------------------------------------------------------------- X
:
BLUEGREEN VACATIONS UNLIMITED, INC.,
:
:
Petitioner,
:
:
-v:
:
T. PARK CENTRAL LLC et al.,
:
:
Respondents.
:
:
---------------------------------------------------------------------- X
24-CV-8009 (JMF)
MEMORANDUM OPINION
AND ORDER
JESSE M. FURMAN, United States District Judge:
This case arises from a contractual dispute over a complex real estate transaction between
Petitioner Bluegreen Vacations Unlimited, Inc. (“Bluegreen” or “Petitioner”) and Respondents
T. Park Central LLC, O. Park Central LLC and New York Urban Ownership Management, LLC
(collectively, “Respondents”). Section 12.3 of the parties’ contract contains a mandatory
arbitration clause, providing that any disputes arising out of the agreement are to be resolved by
a three-member panel of arbitrators (the “Tribunal”). ECF No. 11-1 (“Interim Award”), at 1213. The provision further states that the Tribunal “shall have the authority to award only actual
damages” and that “[n]o Party shall be in default until ten (10) days after the determination of
such arbitration of the Dispute and such default shall be deemed cured if cured within such ten
(10) day period.” Id. In 2021, Respondents initiated arbitration proceedings, asserting two
contract claims and one claim for breach of the implied covenant of good faith and fair dealing.
Following extensive arbitration proceedings, including a twenty-day evidentiary hearing,
the Tribunal issued an eighty-one-page decision styled “Interim Award.” See id. The Tribunal
found in Respondents’ favor on the two contract claims (and denied the implied covenant claim
as duplicative). See id. at 79. But citing the cure provision in Section 12.3 of the parties’
agreement, the Tribunal expressly declined to reach the issue of remedy. See id. at 67-78 As the
Tribunal explained:
The decision whether to cure under § 12.3 is Bluegreen’s decision to make,
and Bluegreen’s alone. Only in the event that Bluegreen fails to cure, or the
Dispute is otherwise resolved by the Parties via a settlement, will it be necessary
for the Tribunal to proceed to the remedy stage of this Arbitration.
In the event that Bluegreen decides not to cure its breaches, the Tribunal will
need to determine whether and, if so, to what extent, TMC is entitled to recover
monetary damages for Bluegreen’s breaches. The Tribunal notes that the Parties
vigorously disagree about TMC’s entitlement to general monetary damages and
whether TMC has proven such damages.
Id. at 68; see also id. at 70 (“tak[ing] no position at this time” on the parties’ disputes “with
respect to whether [Respondents are] entitled to recover general monetary damages and, if so, the
amount of such damages”). The Tribunal “direct[ed] the Parties to meet and confer . . . to
determine whether and, if so, how Bluegreen will cure its breaches of the [contract], and to
report back to the Tribunal concerning those efforts.” Id. at 76-78. More specifically, the
Tribunal ordered the parties, following a meet-and-confer, to file letters addressing a handful of
issues and scheduled “a status conference . . . for the purpose of determining what further
proceedings, if any, are necessary before the Tribunal issues its Final Award.” Id. at 78.
Apparently without waiting for that process to run its course, however, Bluegreen filed a petition
in this Court (the “Petition”), seeking, pursuant to Section 10 of the Federal Arbitration Act
(“FAA”), 9 U.S.C. § 10, to vacate the Interim Award. ECF No. 13 (“Am. Pet.”). 1
Upon review of the parties’ submissions and the Interim Award itself, the Court
concludes that the Petition must be dismissed because the Court lacks authority to review the
1
The record is silent with respect to what, if anything, has happened in the arbitration
proceedings since the Tribunal’s ruling. The Court presumes that the proceedings have been
stayed pending adjudication of the Petition in this case.
2
Interim Award. “By its terms, the FAA gives courts the power to confirm only a final ‘award’ of
an arbitral panel.” Major League Baseball Players Ass’n v. Arroyo, No. 24-CV-3029 (LJL),
2024 WL 3539575, at *3 (S.D.N.Y. July 24, 2024) (citing 9 U.S.C. § 9). “In order to be ‘final,’”
the Second Circuit has explained, “an arbitration award must be intended by the arbitrators to be
their complete determination of all claims submitted to them. Generally, in order for a claim to
be completely determined, the arbitrators must have decided not only the issue of liability of a
party on the claim, but also the issue of damages.” Michaels v. Mariforum Shipping, S. A., 624
F.2d 411, 413-14 (2d Cir. 1980) (citation and footnote omitted). Put differently, “an arbitration
award, to be final, must resolve all the issues submitted to arbitration, and . . . it must resolve
them definitively enough so that the rights and obligations of the two parties, with respect to the
issues submitted, do not stand in need of further adjudication.” Rocket Jewelry Box, Inc. v.
Noble Gift Packaging, Inc., 157 F.3d 174, 176 (2d Cir. 1998) (emphasis omitted); accord KerrMcGee Refin. Corp. v. M/T Triumph, 924 F.2d 467, 471 (2d Cir. 1991).
The Second Circuit’s decision in Michaels is especially instructive here. It arose from a
two-year time charter party between a charterer and ship owner that was terminated early by the
charterer, prompting arbitration proceedings. Michaels, 624 F.2d at 412. The arbitration panel
issued an interim award resolving liability, but not damages, on five of the owner’s six
counterclaims and deferring decision on the charterer’s six claims. Id. at 412-13. The charterer
sought to vacate the interim award in federal court. The district court denied the petition on the
merits, but on appeal, the Second Circuit held that the district court had erred in doing so because
the award was not final and, thus, the court lacked power under the FAA, to review it. Indeed,
the court of appeals did not even consider the issue to be a close one. “Since the interim award
here did not decide any of Charterer’s claims,” the court explained, “it obviously was not a final
3
determination of all issues submitted.” Id. at 414 (emphasis added); see also Metallgesellschaft
A.G. v. M/V Capitan Constante, 790 F.2d 280, 283 (2d Cir. 1986) (“Clearly, the arbitrators’
award in [Michaels] was not intended to be, and was not, a final award.”). “Moreover,” the
Michaels court continued, “with the exception of the one Owner counterclaim decided in
Charterer’s favor, which Charterer obviously does not attack, the award did not finally dispose of
any of the claims submitted, since it left open the question of damages on the four counterclaims
of Owner that it sustained and reserved decision on the fifth.” Michaels, 624 F.2d at 414.
Applying these standards here, the Court is compelled to conclude that the Interim Award
is not final because, like the interim award in Michaels, it “did not finally dispose of any of the
claims submitted, since it left open the question of damages.” Id. Moreover, it is plain from the
Interim Award’s terms that the Tribunal did not “intend[]” the ruling “to be their complete
determination of all claims submitted to them.” Id. at 413. Not only did the Tribunal style its
ruling “Interim Award,” but it “[took] no position at this time with respect to” the parties’
arguments with respect to whether and how much Respondents were entitled to in damages,
Interim Award 70 (emphasis added); it stated that, “unless and until Bluegreen fails to cure its
breaches, a determination of whether [Respondents are] entitled to the monetary damages that
[they] seek[] . . . is premature,” id.; it expressly rejected Respondents’ contention that it “should
prepare a Final Award,” id. at 71; it directed the parties to “meet and confer” and “to report back
to the Tribunal” regarding various issues, id. at 76-78; it deferred consideration of fees and costs
to “its Final Award,” id. at 80; and it scheduled “a status conference” for the express “purpose of
determining what further proceedings, if any, are necessary before the Tribunal issues its Final
Award in this Arbitration,” id. at 78 (emphases added). If anything, therefore, the interim nature
of the Interim Award here is even more “obvious[]” than it was in Michaels.
4
Bluegreen’s counterarguments are unpersuasive. First, relying on the Second Circuit’s
decision in Zeiler v. Deitch, 500 F.3d 157 (2d Cir. 2007), and cases holding that “jurisdiction
exists when the parties have agreed to bifurcation,” Bluegreen argues that the Interim Award is
final because the Tribunal found it “liable and compelled [it] to remain in an ongoing business
relationship with Claimants under the pain of potentially staggering damages in the context of a
potential series of arbitral decisions.” ECF No. 22 (“Pet.’s Reply”), at 2-3 & n.2 (citing Trade &
Transp., Inc. v. Nat. Petroleum Charterers Inc., 931 F. 2d 191 (2d Cir. 1991)). Zeiler, however,
is no help to Bluegreen. There, the decisions at issue “require[d] specific action and [did] not
serve as a preparation or a basis for further decisions by the arbitrators.” 500 F.3d at 169
(emphasis added). Further, the decisions arose from a “unique” agreement between the parties,
which asked the arbitrators to issue a series of “specific and final” orders directing parties “to
take various actions, including conducting accountings and providing documents.” Id. at 168-69.
Here, by contrast, the parties agreed to a “regular” arbitration culminating in “a conclusive
resolution of the entire case.” Id. at 169. And the Interim Award is, by its terms, “preparation
. . . for further decisions” by the Tribunal. Id.; cf. Daum Glob. Holdings Corp. v. Ybrant Digit.
Ltd., No. 13-CV-3135 (AJN), 2014 WL 896716, at *2 (S.D.N.Y. Feb. 20, 2014) (Nathan, J.)
(deeming an award final where it “required specific action — payment of $250,000 — and was
not intended to serve as preparation for further decisions”). And caselaw involving bifurcated
proceedings is plainly of no help to Bluegreen either. As Bluegreen acknowledges, it expressly
objected to bifurcation of liability and damages. See Pet.’s Reply 3 n.2.
Second, Bluegreen asserts that the Interim Award is “final” because it “did far more”
than “serve[] as the basis for future decisions by the” Tribunal. Pet.’s Reply 3. But that
assertion falls flat. Although the Interim Award does ask the parties to take certain next steps —
5
namely, to meet and confer and then inform the Tribunal about Bluegreen’s decision to cure its
breaches — these are necessary steps only in furtherance of the arbitration proceedings. They
are nothing like the specific actions that courts have found to render an arbitration award final
and appealable, such as ordering the payment of funds, Ecopetrol S.A. v. Offshore Expl. & Prod.
LLC, 46 F. Supp. 3d 327, 338 (S.D.N.Y. 2014), or placing funds in escrow, Sperry Int'l Trade,
Inc. v. Gov't of Israel, 532 F. Supp. 901, 909 (S.D.N.Y.), aff'd, 689 F.2d 301 (2d Cir. 1982). See
also Brit. Ins. Co. of Cayman v. Water St. Ins. Co., 93 F. Supp. 2d 506, 513 (S.D.N.Y. 2000)
(“[A]n award of temporary equitable relief such as a security award, separable from the merits of
the arbitration, is subject to federal review.” (collecting cases)). And, of course, Bluegreen is (or
was) free to take no action to cure its breaches, in which case the Tribunal would proceed to
resolve the parties’ remaining disputes and enter a Final Award, at which point Bluegreen could
seek relief in federal court. See e.g., SH Tankers Ltd. v. Koch Shipping Inc., No. 12-CV-375
(AJN), 2012 WL 2357314, at *5 (S.D.N.Y. June 19, 2012) (Nathan, J.) (rejecting the petitioner’s
argument that an interim award was final because, “as [a] practical matter,” it could not do what
the arbitrators had directed on the ground that that was the petitioner’s choice).
Finally, in its initial memorandum of law, Bluegreen floats one additional argument: that
deeming the Interim Award to be non-final would run afoul of the principle “that ‘parties seeking
to enforce arbitration awards through federal court confirmation’” — and, as here, seeking to
vacate arbitration awards — “‘may not divest the courts of their statutory and common-law
authority to review the substance of the awards and the arbitral process for compliance with
§ 10(a) and the manifest disregard standard.’” ECF No. 10 (“Pet.’s Mem.”), at 4 n.2 (quoting
Zurich Am. Ins. Co. v. Team Tankers A.S., 811 F. 3d 584, 591 (2d Cir. 2016)). But Bluegreen
does not press that argument in its reply and, thus, the Court deems the argument to be
6
abandoned. See, e.g., Doe v. Indyke, 465 F. Supp. 3d 452, 466 (S.D.N.Y. 2020) (“Defendants do
not respond to this argument in reply, and the Court deems them to have abandoned the
argument.”). And in any event, the principle upon which Bluegreen relies has no purchase here,
as the parties’ contract poses no bar to Bluegreen’s right and ability to seek judicial review over
a final arbitration award (or, correspondingly, Respondents right and ability to seek confirmation
of a final arbitration award).
In short, the Interim Award is plainly “‘“interim” in the sense of being an “intermediate”
step toward a further end.’” Offshore Expl. & Prod., LLC v. Morgan Stanley Priv. Bank, N.A.,
626 F. App’x 303, 307 (2d Cir. 2015) (summary order) (quoting S. Seas Navigation Ltd. of
Monrovia v. Petroleos Mexicanos of Mex. City, 606 F. Supp. 692, 694 (S.D.N.Y. 1985)
(Weinfeld, J.)). It follows that the Court is “without authority to review” the Tribunal’s ruling.
Michaels, 624 F.2d at 414. Accordingly, the Petition must be and is DISMISSED.
The Clerk of Court is directed to close this case.
SO ORDERED.
Dated: January 28, 2025
New York, New York
__________________________________
JESSE M. FURMAN
United States District Judge
7
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?