The Plumbing Supply, LLC v. ExxonMobil Oil Corporation et al
Filing
326
OPINION AND ORDER re: 271 MOTION to Amend/Correct 145 Amended Third Party Complaint, 169 Answer to Amended Complaint, Crossclaim Against Exxon Mobil Corp. filed by CPD NY Energy Corporation. Plaintiff's motion for reco nsideration is GRANTED as to the nuisance claim (Count Six) against CPD and CFI insofar as it seeks injunctive relief only, CPD's motion for leave to amend is GRANTED as to the claims against CFI and EMC, and DENIED as to the claims against G ES. By June 3, 2016, CPD shall file a Second Amended Third Party Complaint and First Amended Cross Claims in accordance with this Opinion and Order. The Clerk is directed to terminate the motions. (Docs. ##271, 275). (Signed by Judge Vincent L. Briccetti on 5/27/2016) (rj)
UNITED STATES DISTRICT COURT
SOUTHERN DISTRICT OF NEW YORK
---------------------------------------------------------------x
THE PLUMBING SUPPLY, LLC, d/b/a
:
FAUCET WORKS,
:
Plaintiff,
:
v.
:
:
EXXONMOBIL OIL CORP., EXXON
:
MOBIL CORP., CPD NY ENERGY
:
CORP., CUMBERLAND FARMS, INC.,
:
and JOHN DOES 1-10,
:
Defendants.
:
---------------------------------------------------------------x
CPD NY ENERGY CORP.,
:
Third-Party Plaintiff,
:
v.
:
:
CUMBERLAND FARMS, INC.,
:
GROUNDWATER & ENVIRONMENTAL
:
SERVICES, INC., and JOHN DOES 1-10,
:
Third-Party Defendants.
:
---------------------------------------------------------------x
OPINION AND ORDER
14 CV 3674 (VB)
Briccetti, J.:
By Opinion and Order dated March 28, 2016 (Doc. #268, hereinafter “Plumbing Supply
II”), the Court granted defendant CPD NY Energy Corp.’s (“CPD”) motion for judgment on the
pleadings (Doc. #175); granted defendant Cumberland Farms, Inc.’s (“CFI”) motion to dismiss
plaintiff’s Second Amended Complaint (“SAC”) (Doc. #147); and granted in part and denied in
part CFI’s motion to dismiss CPD’s First Amended Third Party Complaint (“FATPC”) (Doc.
#161).
Plaintiff moved for reconsideration of Plumbing Supply II under Local Civil Rule 6.3, or
alternatively for leave to amend the SAC. (Doc. #275). Before any defendant filed opposition,
the Court reserved ruling on whether it would reconsider the dismissal of plaintiff’s nuisance
claims against CPD and CFI insofar as they seek only injunctive relief. (Doc. #285, hereinafter
1
“Plumbing Supply III”). The Court denied plaintiff’s motion in all other respects. (Id.). CPD
and CFI oppose the motion for reconsideration.
Additionally, CPD moved for leave to amend the FATPC and its cross-claims against
defendant Exxon Mobil Corp. (“EMC”). (Doc. #271). CFI, EMC, and third-party defendant
Groundwater & Environmental Services, Inc. (“GES”) oppose the motion.
For the reasons set forth below, plaintiff’s motion for reconsideration, as it pertains to the
nuisance claim, is GRANTED. CPD’s motion for leave to amend is GRANTED as to the claims
against CFI and EMC, and DENIED as to the claims against GES.
The Court has subject matter jurisdiction pursuant to 28 U.S.C. § 1331 and § 1367(a).
DISCUSSION
Familiarity with Plumbing Supply II and Plumbing Supply III and the factual background
contained therein is presumed.
I.
Plaintiff’s Motion for Reconsideration
“To prevail on a motion for reconsideration, the movant must demonstrate ‘an
intervening change of controlling law, the availability of new evidence, or the need to correct a
clear error or prevent manifest injustice.’” Catskill Dev., L.L.C. v. Park Place Entm’t Corp., 154
F. Supp. 2d 696, 701 (S.D.N.Y. 2001) (quoting Doe v. N.Y.C. Dep’t of Soc. Servs., 709 F.2d
782, 789 (2d Cir. 1983)). Although the motion “may not advance new facts, issues, or
arguments not previously presented to the court,” Randell v. United States, 64 F.3d 101, 109 (2d
Cir. 1995) (internal citation omitted), nevertheless, “[r]econsideration of a previous order by the
court lies squarely within the court’s sound discretion.” Anwar v. Fairfield Greenwich Ltd., 745
F. Supp. 2d 379, 382 (S.D.N.Y. 2010).
2
The Court dismissed plaintiff’s nuisance claim against CFI and CPD (Count Six) as timebarred by N.Y. C.P.L.R. § 214-c(2). Plumbing Supply, LLC v. ExxonMobil Oil Corp., 2016 WL
1249611, at *9-10 (S.D.N.Y. Mar. 29, 2016). This statute’s three year limitations period applies
to plaintiff’s nuisance claim for monetary damages. Id. at *6; Hanna v. Motiva Enters., LLC,
839 F. Supp. 2d 654, 657, 663 (S.D.N.Y. 2012). However, it does not apply to claims for
injunctive relief. See N.Y. C.P.L.R. § 214-c(2) (referring to “the three year period within which
an action to recover damages for personal injury or injury to property caused by the latent effects
of exposure to any substance”) (emphasis added); Bano v. Union Carbide Corp., 361 F.3d 696,
709-10 (2d Cir. 2004) (“[T]he timeliness of a claim for injunctive relief is not governed by
[Section 214-c(2)].”).
Plaintiff argues, for the first time on motion for reconsideration, that the Court should not
have dismissed its nuisance claim because it timely seeks injunctive relief. Indeed, Count Six of
the SAC seeks both injunctive relief and damages. (SAC ¶ 278 (“Defendants are liable, jointly
and severally, to abate the nuisance at the Faucet Works Site, and for damages that the Plaintiff
has sustained, and continues to sustain[.]”)). Therefore, the Court erred by applying C.P.L.R. §
214-c(2) to a claim seeking injunctive relief.
Neither CPD nor CFI argue the Court correctly dismissed this claim. Instead, both
contend the Court should not reconsider its ruling because plaintiff did not argue this before.
(CFI’s Br. at 2-6; CPD’s Br. at 1-3). Additionally, CFI argues dismissing the nuisance claim
would not be manifestly unjust because “plaintiff has adequate relief available under” its
Resource Conservation and Recovery Act (“RCRA”) claim. (CFI’s Br. at 6). However, plaintiff
only asserts a RCRA claim against ExxonMobil Oil Corp and CPD—the past and present owners
3
of the Mobil station—not against EMC and CFI, the past and present owners of the Gulf station.
Without the nuisance claim, plaintiff would have no remaining claims against CFI.
CPD’s and CFI’s first point is well-taken—plaintiff should have raised this argument
when it opposed the original motions. Nevertheless, the Court exercises its discretion to reinstate
the nuisance claim for injunctive relief only.
Someone, not plaintiff, spilled petroleum that migrated onto plaintiff’s property. The
source of the petroleum is sharply in dispute. If the Court does not reinstate this timely,
adequately pleaded claim, plaintiff could be left without a remedy against the responsible party
or parties for no other reason than its own inartful motion practice. Local Civil Rule 6.3 does not
require this manifestly unjust result. See Anwar v. Fairfield Greenwich Ltd., 745 F. Supp. 2d at
383 (“[T]o the extent [plaintiff’s opposition] was not explicit enough regarding the negligence
claims, it would be unfair for [the] properly pled negligence claims to be dismissed because of
this technicality.”).
Accordingly, upon reconsideration, plaintiff’s claim for nuisance, insofar as it seeks only
injunctive relief, is not dismissed as time-barred.
II.
CPD’s Motion for Leave to Amend
Rule 15(a)(2) allows a party to amend its complaint only with the opposing party’s
consent or leave of court. While leave to amend should be “freely give[n] . . . when justice so
requires,” Fed. R. Civ. P. 15(a)(2), “motions to amend should generally be denied in instances of
futility, undue delay, bad faith or dilatory motive . . . or undue prejudice to the non-moving
party.” Burch v. Pioneer Credit Recovery, Inc., 551 F.3d 122, 126 (2d Cir. 2008) (citing Foman
v. Davis, 371 U.S. 178, 182 (1962)).
4
CPD’s proposed Second Amended Third Party Complaint (Doc. # 272-1, hereinafter
“SATPC”) re-pleads claims against CFI and GES, and CPD’s proposed First Amended CrossClaims re-pleads claims against EMC. (Doc. #305-1, 1 hereinafter “ACC”). Because CPD’s
proposed amendments to its claims against CFI and EMC are substantially the same, the Court
discusses these together, and then turns to CPD’s proposed amendments to its claims against
GES.
A.
Claims against CFI and EMC
The Court dismissed CPD’s Navigation Law claim against CFI (Count Two) in the
FATPC as time-barred because CPD did not allege the New York Department of Environmental
Conservation (“DEC”) approved CPD’s “cleanup and removal costs.” Plumbing Supply, LLC v.
ExxonMobil Oil Corp., 2016 WL 1249611, at *9. CPD must plead this for a six-year limitations
period to apply, because without DEC approval, costs incurred do not fall within the statutory
definition of recoverable “cleanup and removal costs.” Id. at 13-14; In re Methyl Tertiary Butyl
Ether (“MBTE”) Prods. Liab. Litig., 2007 WL 1601491, at *18 (S.D.N.Y. June 4, 2007).
Now, CPD moves to amend both the FATPC and its cross-claims against EMC to allege
facts showing it did have DEC approval to incur cleanup and removal costs. In doing so, CPD
seeks to revive its Navigation Law claim against CFI and avoid dismissal of its similar claim
against EMC. 2 Specifically, CPD claims it contracted with GES to remediate plaintiff’s property
in accordance with work plans GES submitted to the DEC in 2007 and 2012. CPD claims the
1
CPD revised its proposed amended cross-claims to correct a typographical error in
response to EMC’s opposition. Therefore, the Court considers the revised version.
2
EMC intends to move for judgment on the pleadings or summary judgment on this claim
for substantially the same reasons as the Court dismissed it as to CFI. (Doc. #270).
5
2007 plan was “implicitly or explicitly approved” by the DEC in 2008 (SATPC ¶ 73; ACC ¶ 49),
and the 2012 plan was explicitly approved in 2012.
At this stage in the proceedings, CPD’s new allegations sufficiently allege it incurred
“cleanup and removal costs” as defined by the Navigation Law. Failure to plead DEC approval
was the only reason CPD’s Navigation Law claim for reimbursement of cleanup and removal
costs was time-barred. Plumbing Supply, LLC v. ExxonMobil Oil Corp., 2016 WL 1249611, at
*9. Therefore, CPD’s proposed amendment fixes the only pleading deficiency for this claim.
Because Fed. R. Civ. P. 15(a)(2) requires leave to amend to be “freely give[n] . . . when
justice so requires,” the Court grants CPD leave to amend its pleadings to rescue its Navigation
Law claims from dismissal. It would be unjust to deny CPD the opportunity to meet a technical
pleading requirement when it has otherwise stated a valid claim.
CFI and EMC raise several arguments in opposition to CPD’s motion. None has merit.
First, CFI argues the Court’s Individual Practice ¶ 2(D) requires CPD to show “special
circumstances” justifying amendment of the FATPC because CPD did not amend following
CFI’s motion to dismiss. (CFI’s Br. at 4-8, citing Individual Practices of Judge Briccetti ¶ 2(D)).
However, Individual Practice ¶ 2(D) does not apply here. Following CFI’s motion to dismiss,
the Court never issued “an order requiring [CPD], within ten days, to notify the Court and [CFI]
whether it intends to file an amended pleading, or will rely on the pleading being attacked.”
Individual Practices of Judge Briccetti ¶ 2(D). 3
3
CFI and EMC also rely on State Trading Corp. of India v. Assuranceforeningen Skuld,
921 F.2d 409, 418 (2d Cir. 1990) (“When the moving party has had an opportunity to assert the
amendment earlier, but has waited until after judgment before requesting leave, a court may
exercise its discretion more exactingly.”). Unlike this case, State Trading Corp. of India
concerned amendment following a grant of summary judgment, which ended the entire case. In
any event, the Court declines to “exercise its discretion more exactingly” here. Id.
6
Second, CFI and EMC argue CPD has known about the information it seeks to include in
the amended pleadings for a long time. This may be true, but under the circumstances, the Court
cannot find CPD omitted this information from the FATPC in “bad faith” or with a “dilatory
motive.” Burch v. Pioneer Credit Recovery, Inc., 551 F.3d at 126. At worst, CPD failed to
predict the Court would require it to plead DEC approval. This does not warrant the dismissal of
a claim it can plead adequately when given another chance.
Third, CFI argues granting CPD leave to amend would cause CFI undue delay and
prejudice by “requiring [CFI] to file another response to CPD’s pleadings.” (CFI’s Br. at 8).
If CFI is concerned about briefing another motion to dismiss, that fear is unfounded. As
discussed below, the Court finds amendment here is not futile. Amendment is not futile when
the amended claim would withstand a motion to dismiss. Lucente v. Int’l Bus. Machs. Corp.,
310 F.3d 243, 258 (2d Cir. 2002). Accordingly, by allowing this amendment, the Court has
decided CPD’s Navigation Law claim, as amended, states a claim under Rule 12(b)(6). If CFI
moved to dismiss CPD’s Navigation Law claim as time-barred, the Court would deny the motion
for the reasons set forth in this Opinion and Order. Therefore, motions to dismiss this claim will
not cause further delay. 4 Nor will the de minimis burden on CFI to file a new answer.
Moreover, CFI will suffer little prejudice. Discovery began before Plumbing Supply II
was decided, and is ongoing. Because CPD still has indemnification and contribution claims
against CFI, CFI has always known it should take discovery on whether it is responsible for
contaminating plaintiff’s property. Therefore, reinstating CPD’s Navigation Law claim less than
two months after it was dismissed will not greatly expand or change CFI’s goals in discovery.
4
Additionally, because CFI’s only ground to dismiss CPD’s Navigation Law claim was
statute of limitations (Doc. #162 at 6-9), it cannot move to dismiss again on any other grounds.
7
Finally, CFI and EMC argue amendment is futile. According to the proposed
amendments, CPD incurred cleanup and removal costs pursuant to the 2007 and 2012 plans,
which were made in response to Spill Report 89-13000. CFI and EMC claim this shows two
things: (i) CPD was at least partially at fault for the spill and therefore cannot recover under N.Y.
Nav. L. § 181; 5 and (ii) the costs were incurred more than six years before CPD filed suit in
2015, outside the limitations period. Furthermore, CFI and EMC argue the costs associated with
CPD’s 2012 Indoor Air Quality Assessment Work Plan are not adequately pleaded as “cleanup
and removal costs” and therefore cannot be recovered under the Navigation Law.
None of these arguments about futility is persuasive.
First, CPD maintains even if it did spill petroleum onto its own property, it caused no part
of the spill on plaintiff’s property, because the petroleum on plaintiff’s property came solely
from the Gulf station. This is an issue of fact that cannot be resolved on the pleadings.
Second, CPD alleges it incurred costs in and after 2011 based on remediation work GES
performed pursuant to the 2007 plan. These costs would have been incurred within the
limitations period, even if the plan was approved earlier.
As for the work undertaken pursuant to the 2012 plan, “cleanup and removal” is defined
broadly under the Navigation Law, and includes the “taking of reasonable measures to prevent or
mitigate damages to the public health, safety, or welfare, including . . . private property.” N.Y.
Nav. L. § 172(4); see also State v. Neill, 17 A.D.3d 802, 803-04 (3d Dep’t 2005) (noting the
“broad definition” of “cleanup and removal”). CPD’s and GES’s plan to assess and remediate
the air quality inside plaintiff’s property, though not pleaded in detail, falls within this broad
definition because it seeks to mitigate petroleum-related damages to plaintiff’s property.
5
Parties who are partially at fault for discharging petroleum cannot recover under Section
181. Niagara Mohawk Power Corp. v. Chevron U.S.A. Inc., 596 F.3d 112, 137 (2d Cir. 2010).
8
Therefore, leave to amend is warranted.
B.
Claims against GES
CPD also seeks “to remove and combine its various claims in the [FATPC] against GES
to be consistent with the Court’s prior rulings and CPD’s prior acknowledgment that certain
claims were duplicative.” (CPD’s Br. at 3). GES opposes the motion. CPD represents it “does
not seek to add any claims against GES” in the proposed SATPC. (Id. at 6). The proposed
SATPC also does not add factual content in support of these claims. Rather, it drops some
claims and reorganizes the allegations contained in others. In particular, CPD seeks to re-plead
parts of the FATPC’s claims for “Breach of [the] Duty of Implied Covenant Of Good Faith and
Fair Dealing” (Count Eleven), “Performance of Work in An Unworkmanlike Manner” (Count
Twelve), and Negligence (Count Fourteen) not as distinct, stand-alone claims but as legal
theories supporting its claim against GES for breach of contract (Count Three).
GES has moved to dismiss the FATPC twice. The Court denied the first motion without
prejudice on March 16, 2016, because GES and CPD went to arbitration and obtained a decision
after the first motion was filed. This development required re-briefing the motion. (Doc. #265).
By order dated March 30, 2016, almost two weeks before CPD filed its motion for leave
to amend, the Court set a briefing schedule for GES’s second motion to dismiss, as well as
CPD’s cross-motion for summary judgment based on the arbitration decision. (Doc. #269). In
accordance with the schedule, GES filed its motion on April 20, 2016 (Doc. #281), and CPD
cross-moved on May 4, 2016. (Doc. #308). The motions should be fully submitted by June 8,
2016.
The Court denies GES’s motion to amend its claims against GES. Because the proposed
SATPC does not add claims against GES, or factual content pertaining to these claims,
9
amendment at this moment would serve no purpose. Additionally, the briefing on GES’s motion
to dismiss is nearly finished, and amendment of these claims may require this motion to be
briefed a third time. Under the circumstances, this constitutes undue delay.
Instead, the Court will rule on GES’s and CPD’s cross-motions in due course. If, as CPD
contends, some claims ought to be dismissed consistent with the Court’s prior rulings, CPD
should not oppose the motion as to these claims. If factual allegations or legal theories in Counts
Eleven, Twelve, and Fourteen (or anywhere else) support CPD’s contract claim, the Court will
give them due consideration in ruling on GES’s motion to dismiss.
Because CPD will be filing a SATPC to amend its claims against CFI, GES’s motion to
dismiss the FATPC will be converted into a motion to dismiss the SATPC. However, in
accordance with this Opinion and Order, the SATPC’s claims against GES, and the underlying
factual allegations, shall be identical to those in the FATPC. Therefore, no re-briefing will be
necessary or allowed.
10
CONCLUSION
Plaintiff’s motion for reconsideration is GRANTED as to the nuisance claim (Count Six)
against CPD and CFI insofar as it seeks injunctive relief only.
CPD’s motion for leave to amend is GRANTED as to the claims against CFI and EMC,
and DENIED as to the claims against GES.
By June 3, 2016, CPD shall file a Second Amended Third Party Complaint and First
Amended Cross Claims in accordance with this Opinion and Order.
The Clerk is directed to terminate the motions. (Docs. ##271, 275).
Dated: May 27, 2016
White Plains, NY
SO ORDERED:
____________________________
Vincent L. Briccetti
United States District Judge