Buffalo Laborers Welfare Fund et al v. Sanders Construction, Inc. et al
Filing
19
DECISION AND ORDER granting 13 Motion for Default Judgment. Plaintiffs are entitled to judgment against Timothy Sanders for breach of the settlement agreement in the amount of $257,189.30. All remaining claims against Defendants are DISMISSED WITHOUT PREJUDICE. The Clerk of Court shall enter judgment and close the case. so ordered. Signed by Hon. Frank P. Geraci, Jr. on 8/5/2020. copies of order and nef sent to defendants. (MFM)-CLERK TO FOLLOW UP-
Case 1:16-cv-01036-FPG Document 19 Filed 08/05/20 Page 1 of 3
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF NEW YORK
BUFFALO LABORERS WELFARE FUND, et al.,
Plaintiffs,
Case # 16-CV-1036-FPG
v.
DECISION AND ORDER
SANDERS CONSTRUCTION, INC., et al.,
Defendants.
In March 2016, Plaintiffs and Defendants—Sanders Construction, Inc. and Timothy
Sanders—entered into a settlement agreement to structure a judgment Plaintiffs obtained against
Sanders Construction in prior litigation. See ECF No. 1-1. In December 2016, Plaintiffs filed the
present action, alleging that Defendants failed to pay Plaintiffs and thereby breached the settlement
agreement. ECF No. 1. The Clerk of Court filed an entry of default against Timothy Sanders after
he failed to appear, ECF No. 12, and Plaintiffs moved for default judgment against him. ECF No.
13. For the reasons that follow, Plaintiffs’ motion is GRANTED.
Federal Rule of Civil Procedure 55 sets forth the procedure for obtaining a default
judgment. First, the plaintiff must have secured an entry of default from the clerk, which requires
a showing, “by affidavit or otherwise,” that the defendant “has failed to plead or otherwise defend”
itself in the action. Fed. R Civ. P. 55(a). Once the plaintiff has obtained an entry of default, and
if his claim against the defendant is not “for a sum certain,” the plaintiff “must apply to the court
for a default judgment.” Fed. R. Civ. P. 55(b)(1)-(2).
The clerk’s entry of default does not mean that default judgment is automatically
warranted. See Bricklayers & Allied Craftworkers Local 2, Albany, N.Y. Pension Fund v. Moulton
1
Case 1:16-cv-01036-FPG Document 19 Filed 08/05/20 Page 2 of 3
Masonry & Constr., LLC, 779 F.3d 182, 187 (2d Cir. 2015) (per curiam). Instead, “the court may,
on [the plaintiff’s] motion, enter a default judgment if liability is established as a matter of law
when the factual allegations of the complaint are taken as true.” Id. If liability is established, the
Court must then determine the proper amount of damages, which requires evidentiary support. See
id. at 189 (“[A] party’s default . . . is not considered an admission of damages.” (quotation
omitted)).
Plaintiffs move for default judgment on their claim that Sanders violated the settlement
agreement and is therefore liable for the unpaid judgment, attorney’s fees, and interest. See ECF
No. 1 at 14-15. They request $257,189.30 in damages, which is the sum of the unpaid judgment
($247,729.29), attorney’s fees ($6,757.50), and post-judgment interest ($2,702.51). ECF No. 14
at 6-7.
Based on the allegations in the complaint, Sanders’s liability is established as a matter of
law. “Under New York law, a breach of contract claim requires proof of (1) an agreement, (2)
adequate performance by the plaintiff, (3) breach by the defendant, and (4) damages.” Queens
Ballpark Co., LLC v. Vysk Comm’ns, 226 F. Supp. 3d 254, 258 (S.D.N.Y. 2016). Here, Plaintiffs
allege that Defendants agreed to make payments under the settlement agreement and that
Defendants failed to make such payments. ECF No. 1 at 5-6, 14-15. Furthermore, Sanders
personally guaranteed that, “in the event of [a] breach of the Agreement,” he would pay for “the
entire Unpaid Judgment plus all accrued post-judgment interest and the [] reasonable attorney’s
fees incurred in collecting the Unpaid Judgment.” ECF No. 14-5 at 2. Therefore, liability as to
Sanders is established.
The damages are also readily established. Plaintiffs aver that the outstanding balance on
the judgment is $247,729.29, ECF No. 14 at 4, 6, that they have incurred attorney’s fees in the
2
Case 1:16-cv-01036-FPG Document 19 Filed 08/05/20 Page 3 of 3
amount of $6,757.50, ECF No. 14-7, and that they are entitled to $2,702.51 for post-judgment
interest. The Court has reviewed Plaintiffs’ documentation and considers the amounts requested
reasonable and well-supported. Plaintiffs are entitled to relief.
The Court must address one final matter. Plaintiffs’ motion has been pending for over
three years. In that time, Plaintiffs have taken no action against the other defendant, Sanders
Construction, Inc.
Although it appears that the corporation was involved in a bankruptcy
proceeding for some time, see ECF No. 17 at 1, that proceeding ended in January 2019.
Furthermore, while Plaintiffs have requested money damages for Sanders’s alleged breach of the
settlement agreement, they do not press their remaining claims against him for other equitable and
monetary relief. See ECF No. 1 at 15-17. Given the lack of prosecution and the nature of the
requested relief, the Court construes Plaintiffs’ motion as one withdrawing and/or abandoning
those claims not addressed in the motion for default judgment.
CONCLUSION
For the reasons discussed above, Plaintiffs’ motion for default judgment as to Timothy
Sanders for breach of the settlement agreement (ECF No. 13) is GRANTED. Plaintiffs are entitled
to judgment against Timothy Sanders in the amount of $257,189.30. All remaining claims against
Defendants are DISMISSED WITHOUT PREJUDICE. The Clerk of Court shall enter judgment
and close the case.
IT IS SO ORDERED.
Dated: August 5, 2020
Rochester, New York
______________________________________
HON. FRANK P. GERACI, JR.
Chief Judge
United States District Court
3
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.