Universal Resources Holdings, Inc. v EHM Energy Partners, Inc.
Filing
14
DECISION AND ORDER DENYING the parties' 1 - 2 , 9 Motions for Summary Judgment; REFERRING this case to alternative dispute resolution as specified and setting deadlines; SCHEDULING a Status Conference for 8/14/2019 at 9:00 AM. Signed by William M. Skretny, United States District Judge on 5/19/2019. (MEAL)
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF NEW YORK
UNIVERSAL RESOURCES HOLDINGS, INC.,
Plaintiff,
v.
DECISION AND ORDER
17-CV-423S
EHM ENERGY PARTNERS, INC.,
Defendant.
I. INTRODUCTION
In this action, Universal Resources Holdings, Inc. (“Universal”) seeks to enforce
two promissory notes against EHM Energy Partners, Inc. (“EHM”). Presently before this
Court are the parties’ cross motions for summary judgment. (Docket Nos. 1-2, 9.) For
the reasons that follow, both motions are denied.
II. BACKGROUND
A. Facts
In 2005, Universal and EHM began working together on oil and gas projects.
(Affidavit of John J. Nalbone, Jr. (“Nalbone Aff.”), Docket No. 13, ¶ 5; Affidavit of Thomas
B. Corby (“Corby Aff.”), Docket No. 9-3, ¶ 5.) Universal was represented by its president,
John J. Nalbone, Jr.; EHM was represented by its due diligence agent and corporate
secretary, Thomas Corby. (Nalbone Aff., ¶¶ 1, 7, 8; Corby Aff., ¶ 5.)
In late 2005, Nalbone and Corby met to discuss drilling oil and gas wells in New
York and Pennsylvania. (Nalbone Aff., ¶ 8; Corby Aff., ¶ 5.) Corby told Nalbone that
EHM was interested in retaining Universal to construct the oil and gas wells for EHM on
a “turnkey” basis—that is, for Universal to complete all steps necessary to make the oil
1
and gas well projects fully operable so that the only thing needed to run them would be
to “turn a key”—and for Universal to then operate the wells for EHM. (Nalbone Aff., ¶ 9;
Corby Aff., ¶ 5.) Corby further advised Nalbone that EHM would pay Universal the
majority of the total purchase price for each project in cash, and then treat the remaining
balance as a loan from Universal to EHM. (Nalbone Aff., ¶ 9.) Nalbone agreed to these
payment terms. (Id.)
The parties thereafter collaborated on well-drilling projects in New York and
Pennsylvania based on agreements reached in 2006 and 2007. (Nalbone Aff., ¶¶ 10,
25.) For the 2006 project, the parties agreed to collaborate on seven wells. (Nalbone
Aff., ¶ 10.) Universal agreed to construct and operate the wells in exchange for EHM
paying it $2,072,000, of which $1,781,920 was to be paid in cash and $290,080 was to
be treated as a loan from Universal to EHM. (Nalbone Aff., ¶ 10; Corby Aff., ¶ 5.) For
the 2007 project, the parties agreed to collaborate on five more wells under their turnkey
arrangement—four in New York, one in Pennsylvania.
(Nalbone Aff., ¶ 25.)
In
exchange for Universal constructing and operating the five wells, EHM agreed to pay
$1,600,000—$1,360,000 in cash and $240,000 as a loan from Universal to EHM.
(Nalbone Aff., ¶ 25; Corby Aff., ¶ 5.)
While the cash payments appear undisputed, the parties have differing views
concerning the terms of the loans from Universal to EHM.
For the 2006 project,
Universal maintains that EHM promised to pay it the $290,080 balance plus 4.6% interest
per year in monthly installments of principal and interest until the loan was fully paid or by
November 1, 2015, whichever was earlier. (Nalbone Aff., ¶ 17.) For the 2007 project,
2
Universal maintains that EHM promised to pay it the $240,000 interest-free balance in
monthly installments until the loan was fully paid or by November 1, 2016, whichever was
earlier. (Nalbone Aff., ¶ 32.)
In contrast, EHM maintains that Corby and Nalbone agreed that EHM would repay
both loans solely from a deduction by Universal of a fixed percentage of the net revenues
to be paid to EHM from the drilling projects. (Corby Aff., ¶¶ 6, 20-22.) For the 2006
project, Universal was to deduct 20% of the net revenue to be paid to EHM. (Corby Aff.,
¶ 6.) For the 2007 project, Universal was to deduct 35% of the net revenue to be paid
to EHM. (Id.) According to Corby, he and Nalbone never discussed or agreed that
Universal could recover from EHM under any promissory note independent of the fixed
percentage of net revenue due to EHM from the 2006 and 2007 projects. (Corby Aff.,
¶¶ 6, 23.)
The parties also have differing views concerning which party would be financially
liable for plugging the wells. Nalbone maintains that, consistent with industry standards,
EHM agreed to pay for the eventual plugging of each well in both the 2006 and 2007
projects—$18,000 per well in New York; $23,000 per well in Pennsylvania. (Nalbone
Aff., ¶¶ 10, 25; Reply Affidavit of John J. Nalbone, Jr. (“Nalbone Reply Aff.”), Docket No.
10-1, ¶¶ 11, 12.) Corby represents that he and Nalbone never discussed or agreed that
EHM would be financially responsible for plugging the wells. (Corby Aff., ¶¶ 10, 11, 18.)
Universal contends that the parties memorialized their 2006 and 2007 agreements
in two Turnkey Drilling Agreements, dated December 2006 and December 2007 (“2006
TDA” and “2007 TDA”) and two promissory notes, dated December 2006 and December
3
2007 (“2006 Note” and “2007 Note”). (Nalbone Aff., ¶¶ 11, 26.) But none of these four
documents are executed. (Nalbone Aff., ¶¶ 13, 28; Corby Aff., ¶¶ 4, 12.) Nalbone
states that neither he nor Corby signed the documents because they considered
execution of the contracts an unnecessary formality. (Nalbone Aff., ¶¶ 13, 28.)
In contrast, Corby maintains that he and Nalbone reached only oral agreements.
(Corby Aff., ¶¶ 4, 6, 7, 8.) He claims that Nalbone never sent the 2006 or 2007 TDAs to
EHM for execution at the time he and Nalbone reached their oral agreements or at any
time thereafter. (Corby Aff., ¶¶ 7, 8, 16.) Corby asserts that neither the 2006 TDA nor
the 2007 TDA reflect his oral agreements with Nalbone, and in fact, he believes that
Nalbone falsified these two agreements and two promissory notes by backdating them in
an effort to support Universal’s present claims against EHM. (Corby Aff., ¶ 17.)
In response, Nalbone denies falsifying or backdating the relevant documents and
insists that he memorialized the agreements he reached with Corby in the 2006 and 2007
TDAs contemporaneous to those negotiations, including their agreement that EHM would
pay to plug the wells.
(Nalbone Reply Aff., ¶¶ 6, 7.)
Nalbone represents that he
executed some of the 2006 and 2007 documents and sent them to Corby to be
countersigned, but rather than countersigning, EHM simply began performing the
agreements. (Nalbone Reply Aff., ¶¶ 6, 7.)
Universal constructed and operated the twelve wells and performed all of its
obligations under the 2006 and 2007 TDAs and the 2006 and 2007 Notes. (Nalbone
Aff., ¶¶ 14-16, 29-31.) In exchange, EHM paid Universal $1,781,920 in cash for the 2006
project and $1,360,000 in cash for the 2007 project. (Nalbone Aff., ¶¶ 14, 29; Corby Aff.,
4
¶¶ 7, 8.) EHM also paid Universal $104,285.15 and some interest against the 2006 Note
and $149,892.94 against the 2007 Note. (Nalbone Aff., ¶¶ 22, 37.)
According to Universal though, EHM did not meet either the November 1, 2015
deadline for repayment of the 2006 Note or the November 1, 2016 deadline for repayment
of the 2007 Note.
(Nalbone Aff., ¶¶ 19, 34.)
Universal therefore maintains that
$280,484.85 remains due and owing on the 2006 Note, consisting of $185,794.85 in
outstanding principal and $94,690 in outstanding interest, and $90,107.06 remains due
and owing in principal on the 2007 Note. (Nalbone Aff., ¶¶ 19, 34.) Universal further
maintains that EHM is liable for $231,000 in plugging costs. (Nalbone Aff., ¶¶ 24, 39.)
EHM, on the other hand, contends that it paid all that was due under the 2006 and 2007
oral agreements (the two cash payments) and that nothing further, including plugging
costs, is due and owing. (Corby Aff., ¶ 9.)
B. Procedural History
Universal commenced this action in New York State Supreme Court, Chautauqua
County, on April 21, 2017, by way of a Motion for Summary Judgment in Lieu of
Complaint, under N.Y. C.P.L.R. § 3213. (Docket No. 1-2.) EHM removed the action on
May 16, 2017, under 28 U.S.C. §§ 1332 (a)(1), 1441, and 1446. (Docket No. 1.) It then
responded to Universal’s Motion for Summary Judgment in Lieu of Complaint and moved
for summary judgment in its own favor on August 17, 2017. (Docket No. 9.) Universal
filed a reply in further support of its motion and in opposition to EHM’s motion on August
31, 2017. 1 (Docket No. 10.) This Court thereafter took the motions under advisement
1 At this Court’s direction, Universal also filed a corrected affidavit on April 17, 2019. (Docket Nos. 12,
13.)
5
without oral argument.
III. DISCUSSION
Universal commenced this action in state court by way of a Motion for Summary
Judgment in Lieu of Complaint under N.Y. C.P.L.R. § 3213. That provision provides a
streamlined procedure to recover on an instrument for the payment of money under
certain circumstances, combining pleading and motion practice into a single step, before
issue is joined. See Dammers v. Wells Fargo Bank, N.A., 17-CV-2560 (NSR), 2018 WL
264519, at *1 (S.D.N.Y. Jan. 2, 2018) (citing Weissman v. Sinorm Deli, Inc., 88 N.Y.2d
437, 443, 646 N.Y.S.2d 308, 669 N.E.2d 242 (1996)). A motion for summary judgment
in lieu of complaint removed to federal court is converted to a motion for summary
judgment under Rule 56 of the Federal Rules of Civil Procedure. See Beaufort Capital
Partners LLC v. Oxysure Sys., Inc., 16-CV-5176 (JPO), 2017 WL 913791, at *2 (S.D.N.Y.
Mar. 7, 2017); Valley Nat'l Bank v. Oxygen Unlimited, LLC, No. 10 Civ. 5815, 2010 WL
5422508, at *2 (S.D.N.Y. Dec. 23, 2010) (“Plaintiff's motion for summary judgment in lieu
of complaint will be treated as a motion for summary judgment made under Rule 56 of
the Federal Rules and the papers already submitted to be a complaint and answer.”).
Here, Universal argues that it is entitled to summary judgment because EHM is in
default on the 2006 and 2007 TDAs and Notes, which it contends are valid instruments
for the payment of money only. EHM, on the other hand, contends that there exist no
valid instruments for the payment of money because the parties never executed any
written agreements. It further maintains that Universal’s claims are time-barred and
precluded by New York’s Statute of Frauds. EHM therefore seeks summary judgment
6
dismissing this action, or alternatively, maintains that issues of fact preclude summary
judgment in Universal’s favor. The parties’ arguments are further discussed below.
A.
Summary Judgment
Summary judgment is appropriate “if the movant shows that there is no genuine
dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
Fed. R. Civ. P. 56 (a). A fact is “material” if it “might affect the outcome of the suit under
the governing law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S. Ct. 2505,
91 L. Ed. 2d 202 (1986). An issue of material fact is “genuine” if “the evidence is such
that a reasonable jury could return a verdict for the nonmoving party.” Id.
In deciding a motion for summary judgment, the evidence and the inferences
drawn from the evidence must be "viewed in the light most favorable to the party opposing
the motion." Addickes v. S.H. Kress & Co., 398 U.S. 144, 158-59, 90 S. Ct.1598, 26 L.
Ed. 2d 142 (1970). "Only when reasonable minds could not differ as to the import of
evidence is summary judgment proper." Bryant v. Maffucci, 923 F.2d 979, 982 (2d Cir.
1991). Indeed, “[i]f, as to the issue on which summary judgment is sought, there is any
evidence in the record from which a reasonable inference could be drawn in favor of the
opposing party, summary judgment is improper.”
Sec. Ins. Co. of Hartford v. Old
Dominion Freight Line, Inc., 391 F.3d 77, 82–83 (2d Cir. 2004) (citations omitted).
But a “mere scintilla of evidence” in favor of the nonmoving party will not defeat
summary judgment. Anderson, 477 U.S. at 252. A nonmoving party must do more than
cast a “metaphysical doubt” as to the material facts, Matsushita Elec. Indus. Co. v. Zenith
Radio Corp., 475 U.S. 574, 586, 106 S. Ct. 1348, 89 L. Ed. 2d 538 (1986); it must “offer
7
some hard evidence showing that its version of the events is not wholly fanciful,”
D’Amico v. City of N.Y., 132 F.3d 145, 49 (2d Cir. 1998). That is, there must be evidence
from which the jury could reasonably find for the nonmoving party. Anderson, 477 U.S.
at 252.
In the end, the function of the court at the summary judgment stage is not “to weigh
the evidence and determine the truth of the matter but to determine whether there is a
genuine issue for trial." Id. at 249. “Assessments of credibility and choices between
conflicting versions of the events are matters for the jury, not for the court on summary
judgment.” Rule v. Brine, Inc., 85 F.3d 1002, 1011 (2d Cir. 1996).
This same standard applies to cross motions for summary judgment.
See
Morales v. Quintel Entm’t, Inc., 249 F.3d 115, 121 (2d Cir. 2001). “[W]hen both parties
move for summary judgment, asserting the absence of any genuine issues of material
fact, a court need not enter judgment for either party. Rather, each party’s motion must
be examined on its own merits, and in each case all reasonable inferences must be drawn
against the party whose motion is under consideration.” Id. (citing Heublein, Inc. v.
United States, 996 F.2d 1455, 1461 (2d Cir. 1993); Schwabenbauer v. Bd. of Educ., 667
F.2d 305, 314 (2d Cir. 1981)).
B. New York Law
New York C.P.L.R. § 3213 permits expedited treatment of actions “based upon an
instrument for the payment of money only or upon any judgment.” The instrument for
the payment of money need not necessarily be a negotiable instrument, see Channel
Excavators v. Amato Trucking Corp., 48 Misc.2d 429, 430 (Sup. Ct. Nassau Cty. 1965),
8
but “it must be clear from the instrument that there exists an unconditional obligation to
make payment of the nature that ‘a prima facie case would be made out by the instrument
and a failure to make the payments called for by its terms,’” Dammers, 2018 WL 264519,
at *1 (quoting Interman Indus. Prods., Ltd. v. R.S.M. Electron Power, Inc., 37 N.Y.2d 151,
154, 371 N.Y.S.2d 675, 332 N.Ed.2d 859 (1975)). If proof outside of the document or
instrument is needed, other than simple proof of nonpayment or other de minimis proof,
the document or instrument does not qualify for enforcement under C.P.L.R. § 3213.
See Weissman, 88 N.Y.2d at 444. Most cases applying § 3213 involve commercial
paper where the party charged has formally and explicitly acknowledged the
indebtedness, though, again, a negotiable instrument per se is not required under the
statute. 2 See Slade v. Newman, 32 Misc.3d 1244(A), at *2 (Sup. Ct. N.Y. Cty. 2011).
Here, Universal seeks to enforce the 2006 and 2007 TDAs and promissory notes.
If it is determined that these documents are valid and contain unambiguous and
unconditional promises to pay specified sums on specified dates, they may be enforced
under § 3213. See DH Cattle Holdings Co. v. Kuntz, 165 A.D.2d 568, 570-71, 568
N.Y.S.2d 229 (3d Dep’t 1991) (finding that a promissory note containing a “clear,
unambiguous and unconditional promise to pay a specified sum on a specified date” was
“clearly an instrument for the payment of money only within the meaning of C.P.L.R.
3213”); Coneco Corp. v. Atl. Energy Serv. Inc., 270 A.D.2d 691, 692, 704 N.Y.S.2d 732
2 In New York, a written negotiable instrument is created where “(1) the instrument is signed by
the maker; (2) it contains an unconditional promise or order to pay a sum certain; (3) it is payable on demand
or at a definite [time]; and (4) it is payable to order or to bearer.” Dammers, 2018 WL 264519, at *2 (citing
N.Y. U.C.C. § 3-104 (1)(a)-(d)). Payment must be determinable from the instrument itself without reference
to any outside source. See id. (citing N.Y. U.C.C. § 3-106, Comment 1).
9
(3d Dep’t 2000) (same for written agreement).
“A promissory note is a type of instrument containing an unequivocal and
unconditional obligation to repay the lender, executed by the Defendant.” Dammers,
2018 WL 264519, at *2 (citing Lugli v. Johnston, 78 A.D.3d 1133, 1135, 912 N.Y.S.2d
108 (2d Dep’t 2010)). “To establish prima facie entitlement to judgment as a matter of
law on the issue of liability with respect to a promissory note, a plaintiff must show the
existence of a promissory note executed by the defendant and the failure of the defendant
to pay in accordance with the note’s terms.” Nunez v. Channel Grocery & Deli Corp.,
124 A.D.3d 734, 734-35, 998 N.Y.S.2d 663 (2d Dep’t 2015). Summary judgment is
warranted when there are no genuine issues of fact as to these material requirements.
See Torin Assocs., Inc. v. Perez, No. 15 Civ. 8043 (NSR), 2016 WL 6662271, at *4
(S.D.N.Y. Nov. 10, 2016) (citing Inland Mortg. Capital Corp. v. Realty Equities N.M., LLC,
71 A.D.3d 1089, 1090, 900 N.Y.S.2d 79 (2d Dep’t 2010)). If the plaintiff sufficiently
establishes these elements, the burden shifts to the defendant to establish by admissible
evidence that triable issues of fact exist with respect to a bona fide defense. See Jin
Sheng He v. Sing Huei Chang, 83 A.D.3d 788, 789, 921 N.Y.S.2d 128 (2d Dep’t 2011).
C. Analysis
It is apparent that the parties agreed to collaborate on oil and gas drilling projects
because Universal constructed and operated twelve wells and EHM remitted significant
payment for them. But as the statement of facts above reveals, disputed issues of
material fact abound concerning the terms of the agreements. For example, Universal
contends that the parties had a written agreement; EHM contends that they had an oral
10
agreement. Universal contends that the 2006 and 2007 TDAs accurately memorialize
the parties’ agreements; EHM contends that the TDAs are inaccurate and fabricated.
Universal contends that EHM agreed to pay plugging costs; EHM contends that it never
made such an agreement.
Universal contends that the 2006 and 2007 Notes are
recourse notes; EHM contends that they are non-recourse notes. These material issues
of disputed fact preclude summary judgment for either side.
Universal’s motion for summary judgment must be denied because material issues
of fact exist concerning whether there even exists a written instrument requiring payment,
let alone one that contains an unambiguous and unconditional obligation to make sumcertain payments. Dammers, 2018 WL 264519, at *2. EHM challenges the documents
as unexecuted and inaccurate, and worse, as fabrications. Universal counters that an
executed instrument is not necessarily required if there is objective evidence of an intent
to be bound or a party performs under the agreement. But at this stage, the evidence
must be viewed in EHM’s favor.
Through that lens, EHM’s cash payments, other
performance, and subsequent letters must be viewed as consistent with the oral
agreement that it alleges the parties reached, rather than as partial performance or
acknowledgement of Universal’s alleged written agreements. 3 So too, Corby’s sworn
affidavit disclaiming the accuracy of the terms in the written documents and challenging
them as fabricated raises triable issues of material fact. For these reasons, summary
judgment in Universal’s favor is precluded.
3 EHM’s contention that the parties actually reached a similar alternate oral agreement factually
distinguishes this case from those Universal relies on— Torin Assocs., 2016 WL 6662271; Commonwealth
Land Title Ins. Co. v. Mattera, 208 A.D.2d 490, 491 (2d Dep’t 1994); Bank Hapoalim B.M. v. Madison Carpet
Corp., 103 Misc. 2d 522 (Sup. Ct. N.Y. Cnty., Mar. 17, 1980).
11
And for similar reasons, EHM is not entitled to summary judgment dismissing this
case either.
It first argues that the oral agreements between the parties are not
enforceable under § 3213 and barred by the New York Statute of Frauds. But viewing
the evidence in the light most favorable to Universal, a factfinder could credit its evidence
that the parties memorialized their oral agreement in the tendered written documents, and
EHM then performed under those written agreements. In other words, a factfinder could
find the existence of a written agreement to pay and a breach of that agreement. And
contrary to EHM’s argument, such a claim would be timely because the alleged breaches
occurred in 2015 and 2016, well within six years of the filing date of this action in 2017.
See N.Y. C.P.L.R. § 213 (2) (setting 6-year statute of limitations for breach-of-contract
claims). Consequently, summary judgment in EHM’s favor is also precluded.
IV. CONCLUSION
For the reasons stated above, the parties’ cross motions for summary judgment
are each denied. Before proceeding to trial, the parties are directed to engage in goodfaith mediation efforts to determine whether a pretrial resolution of this matter can be
reached.
V. ORDERS
IT HEREBY IS ORDERED, that the parties’ motions for summary judgment
(Docket Nos. 1-2, 9) are DENIED.
FURTHER, that this case is REFERRED for alternative dispute resolution under
Section 2.1.B of the Plan for Alternative Dispute Resolution in the United States District
Court for the Western District of New York (“the ADR Plan”).
12
FURTHER, that the parties shall confer and file a stipulation selecting a mediator
by May 31, 2019.
FURTHER, that the initial mediation session shall be held no later than July 2,
2019.
FURTHER, that within 10 days of each mediation session, the mediator shall file
a Mediation Certification setting forth the progress of mediation.
FURTHER, that the mediation process shall be completed by August 2, 2019.
FURTHER, that the parties shall timely comply with all relevant requirements of
the ADR Plan, which is available at http://www.nywd.uscourts.gov.
FURTHER, that the parties shall appear before this Court on August 14, 2019, at
9:00 a.m. to report on the status of this case if it is not sooner resolved through mediation.
SO ORDERED.
Dated: May 20, 2019
Buffalo, New York
/s/William M. Skretny
WILLIAM M. SKRETNY
United States District Judge
13
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?