The Pike Company, Inc. v. Tri-Krete Limited
Filing
51
DECISION AND ORDER granting in part and denying in part 43 Motion to Confirm Arbitration Award, to Enter Partial Final Judgment, and to Lift Stay; finding as moot 46 Motion to Stay Entry/Execution of Final Judgment. Signed by Hon. Elizabeth A. Wolford on 11/09/2021. (CDH)-CLERK TO FOLLOW UP-
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF NEW YORK
THE PIKE COMPANY, INC.,
Plaintiff,
DECISION AND ORDER
v.
6:18-CV-06311 EAW
TRI-KRETE LIMITED,
Defendant.
BACKGROUND
Plaintiff The Pike Company (“Pike”) commenced this action on April 20, 2018,
against Defendant Tri-Krete Limited (“Tri-Krete”) for breach of contract. (Dkt. 1). TriKrete thereafter asserted several counterclaims against Pike, including common law causes
of action for breach of contract and unjust enrichment, and violations of the New York
Prompt Payment Act, N.Y. Gen. Bus. Law §§ 756-758 (“PPA”). (Dkt. 5 at 4-7).
Contemporaneously with the filing of its Answer, Tri-Krete filed a motion to stay
this action and to compel arbitration based upon the alleged PPA violations. (Dkt. 7). Pike
opposed Tri-Krete’s motion. (Dkt. 9; Dkt. 22). On November 20, 2018, this Court entered
a Decision and Order granting Tri-Krete’s motion for arbitration and denying Pike’s
motions seeking to stay arbitration. (Dkt. 39) (the “November 2018 Decision”)1. More
specifically, the Court held that the “alleged PPA violations . . . encompassed by Tri
1
The factual and procedural background of this matter are set forth in detail in the
November 2018 Decision, familiarity with which is assumed for purposes of the instant
Decision and Order. The Court has summarized the relevant developments following entry
of the November 2018 Decision.
-1
Krete’s fourth counterclaim” were arbitrable. (Id. at 22). The Court further found that
Pike’s claim for breach of contract and Tri-Krete’s counterclaims for breach of contract,
unjust enrichment, and unpaid labor and materials were not arbitrable. (Id. at 22-23). The
Court explained that while Pike could “argue to the [arbitration] panel that Tri-Krete’s
purported breach of the Subcontract2 represent defenses to its obligations under the PPA,”
the arbitration panel would be “without jurisdiction to determine whether Pike has asserted
a meritorious common law cause of action for breach of contract.” (Id. at 23). The Court
stayed the remainder of this action pending arbitration of the PPA claims. (Id. at 28).
Following briefing and a hearing, on March 9, 2020, the arbitration panel issued a
final arbitration award (the “Arbitration Award”) finding that: (1) Pike violated the PPA
by not paying $262,689.36, plus interest, to Tri-Krete on Tri-Krete’s Payment Application
#12; (2) Tri-Krete is entitled to interest at 1% per month on that sum from August 17, 2017;
(3) Pike did not violate the PPA by not paying Tri-Krete’s Payment Application #13 or
Tri-Krete’s invoices 8880, 8893, 8894, 8915, and 8916; (4) there was insufficient proof to
establish that Pike acted in bad faith or unreasonably withheld payment from Tri-Krete; (5)
the administrative fees and expenses of arbitration ($18,975.00) and the compensation and
expenses of the arbitrators ($108,141.35) are to be borne equally, such that Pike is required
to pay Tri-Krete an amount of $9,487.50. (Dkt. 43-8 at 19).
2
As explained in the November 2018 Decision, the “Subcontract” refers to the Master
Subcontract Agreement and Work Order, dated October 2, 2015, and June 14, 2016,
respectively, that govern the relationship between the parties as relevant to the instant
action. (Dkt. 39 at 2).
-2
On November 16, 2020, Tri-Krete filed a motion for confirmation of the Final
Award pursuant to Section 9 of the Federal Arbitration Act (the “FAA”), 9 U.S.C. § 9.
(Dkt. 43 at 1). Tri-Krete further asks the Court to enter a judgment against Pike in the
amount of $262,689.36 plus interest at 1% per month from August 17, 2017, until the date
of payment, and to award Tri-Krete “the costs and disbursements associated with this
proceeding including attorneys’ fees[.]” (Id.). Finally, Tri-Krete asks the Court to lift the
stay in this matter. (Id.).
On December 11, 2020, Pike filed an opposing motion asking the Court to stay “the
entry/execution of a judgment against The Pike Company, Inc. in the amount of
$262,689.36 plus interest at 1% per month from August 17, 2017 until the final resolution
of The Pike Company, Inc’s claims against Tri-Krete, Ltd.” (Dkt. 46 at 1). Pike does not
oppose the request that the stay of this matter be lifted.
Tri-Krete filed a reply in further support of its motion and a response in opposition
to Pike’s motion on January 8, 2021. (Dkt. 49). Pike filed a reply in further support of its
motion on January 15, 2021. (Dkt 50-3).
DISCUSSION
“The FAA provides a ‘streamlined’ process for a party seeking a ‘judicial decree
confirming an award, an order vacating it, or an order modifying or correcting it.’” Seneca
Nation of Indians v. New York, 988 F.3d 618, 625 (2d Cir. 2021) (quoting Hall St. Assocs.,
L.L.C. v. Mattel, Inc., 552 U.S. 576, 582 (2008)). “Normally, confirmation of an arbitration
award is a summary proceeding that merely makes what is already a final arbitration award
a judgment of the court, and the court must grant the award unless the award is vacated,
-3
modified, or corrected.” D.H. Blair & Co. v. Gottdiener, 462 F.3d 95, 110 (2d Cir. 2006)
(quotations and citations omitted).
“Courts . . . play only a limited role when asked to review the decision of an
arbitrator, and only a very narrow set of circumstances delineated by statute and case law
permit vacatur.” Porzig v. Dresdner, Kleinwort, Benson, N. Am. LLC, 497 F.3d 133, 138
(2d Cir. 2007) (quotations and citations omitted). Pike does not argue that any such
circumstances are present here, and indeed “does not oppose the confirmation of the Final
Award to the extent it is properly read and understood.” (Dkt. 46-1). However, Pike asks
the Court to stay entry and/or execution of a final judgment entered upon the Final Award.
In support of this request, Pike argues that: (1) “[t]he language contained in the . . . Final
Award does not direct that Pike, at the conclusion of the Arbitration, was required to pay
Tri-Krete $262,689.36 plus interest from August 17, 2017 until paid,” and Tri-Krete is thus
“not currently entitled to an immediately payable/enforceable judgment”; and (2) the Court
should stay entry and/or enforcement of judgment as a matter of discretion because of
Pike’s potential set-off rights and unresolved claims. (Dkt. 46-1 at 3-13).
Tri-Krete has not responded to Pike’s first argument regarding the language of the
Final Award. However, the Court does not find this argument persuasive. Pike notes that
the arbitrators expressly said “The Pike Company has to pay Tri-Kete Ltd., an amount of
$9,487.50” in connection with the portion of the Final Award dealing with administrative
fees and expenses, but did not include similar language in the portion of the Final Award
concluding that Pike violated the PPA by not paying $262,689.36 on Pay Application #12
and that Tri-Krete is entitled to that sum plus interest in the amount of 1% per month from
-4
August 17, 2017. According to Pike, this difference in language indicates the arbitrators’
“awareness of the pending litigation and remaining issues” and reflects the arbitrators’
intention to leave open the possibility that the Pike should not be obliged to pay Tri-Krete
until this action is finally resolved. (Dkt. 46-1 at 4).
Pike has cited no case law that supports this argument, nor has the Court discovered
in its own research a factually analogous circumstance wherein a court determined that,
despite a clear finding in the arbitration award of the amount owed by one party to another
on a particular claim, there was an implicit stay of the payment obligation. This is
unsurprising, inasmuch as the Court interprets an arbitration award according to its plain
language. See Daum Glob. Holdings Corp. v. Ybrant Digital Ltd., No. 13-CV-3135 AJN,
2015 WL 5853783, at *3 (S.D.N.Y. Oct. 6, 2015). The Court does not search for hidden
meanings or attempt to divine the arbitrators’ intentions. To the contrary, if an arbitration
award is “ambiguous or incomplete,” the proper course is remand to the arbitrators.
Folkways Music Publishers, Inc. v. Weiss, 989 F.2d 108, 112 (2d Cir. 1993).
Here, the arbitrators unambiguously concluded that Tri-Krete is entitled to
$262,689.36 plus interest in the amount of 1% per month from August 17, 2017 for the
PPA violation. The arbitrators did not indicate that there were any pre-conditions that had
to be satisfied or open questions regarding that liability. Further, as Pike acknowledges,
“when the question was raised whether any award should be stayed pending the conclusion
of the federal litigation, the [arbitrators] specifically concluded that the determination of
that question was outside the scope assigned to [them] by this Court.” (Dkt. 46-1 at 4).
-5
The Court thus rejects Pike’s argument that the language of the Final Award necessarily
conditions Tri-Krete’s payment obligation on resolution of the other claims in this action.
Turning to Pike’s second argument, it is well-established that a “District Court has
broad discretion to stay proceedings as an incident to its power to control its own docket.”
Clinton v. Jones, 520 U.S. 681, 706 (1997); see also WorldCrisa Corp. v. Armstrong, 129
F.3d 71, 76 (2d Cir. 1997) (recognizing “the power inherent in every court to control the
disposition of the causes on its docket with economy of time and effort for itself, for
counsel, and for litigants” (citation omitted)). Although the Second Circuit has not
addressed the issue, the First Circuit has held that a district court is empowered to defer
entering judgment on a final arbitration award “for prudential reasons.” Hewlett-Packard
Co. v. Berg, 61 F.3d 101, 105 (1st Cir. 1995); cf. DeMartini v. Johns, 693 F. App’x 534,
538 (9th Cir. 2017) (reviewing for abuse of discretion district court’s denial of
“Defendants’ request to stay ruling on Plaintiffs’ motion to confirm the arbitration award”).
But see Belize Soc. Dev. Ltd. v. Gov’t of Belize, 668 F.3d 724, 733 (D.C. Cir. 2012) (finding
that district court’s order staying confirmation of arbitration award pending resolution of
other litigation, “exceeded the bounds of any inherent authority the district court may have
had to stay proceedings in the interest of judicial economy”).
At least one court in this Circuit has relied on the First Circuit’s decision in HewlettPackard to grant a motion to stay enforcement of a confirmed arbitration award pending
resolution of a final accounting. Companhia De Navegacao Maritima Netumar v. Armada
Parcel Serv., Ltd., No. 96 CIV. 6441 (PKL), 1997 WL 16663, at *7 (S.D.N.Y. Jan. 17,
1997); see also Katz v. Feinberg, No. 99 CIV. 11705 (CSH), 2001 WL 1132018, at *4
-6
(S.D.N.Y. Sept. 24, 2001) (granting motion to stay enforcement of judgment pending
resolution of arbitration regarding related set-off claim).
Before assessing the merits of Pike’s request, the Court must clarify a procedural
point. Although courts are not always precise in the language they use in this context, there
is a distinction between confirmation of an arbitration award and the subsequent entry of
final judgment thereon. As the First Circuit explained in Hewlett-Packard, “the order
confirming the award is not itself a judgment that can be collected through court processes
until it is entered on the docket as a judgment.” 61 F.3d at 101 (citing 9 U.S.C. § 13)3.
Further, under Federal Rule of Civil Procedure 54:
When an action presents more than one claim for relief—whether as a claim,
counterclaim, crossclaim, or third-party claim—or when multiple parties are
involved, the court may direct entry of a final judgment as to one or more,
but fewer than all, claims or parties only if the court expressly determines
that there is no just reason for delay. Otherwise, any order or other decision,
however designated, that adjudicates fewer than all the claims or the rights
and liabilities of fewer than all the parties does not end the action as to any
of the claims or parties and may be revised at any time before the entry of a
judgment adjudicating all the claims and all the parties’ rights and liabilities.
Fed. R. Civ. P. 54(b).
In all of the cases cited by the parties wherein a court considered a motion to stay
either confirmation of the arbitration award or entry/execution of the judgment on the
confirmation order, there was a separate arbitration or a separate ongoing lawsuit. See
3
Notwithstanding the fact that it is not itself a final judgment, an order confirming an
arbitration award is immediately appealable pursuant to 9 U.S.C. § 16(a)(1)(D). See Thule
AB v. Advanced Accessory Holdings Corp., No. 09 CIV. 00091 (PKC), 2010 WL 2287012,
at *2 (S.D.N.Y. June 1, 2010) (“The text of the FAA does not require that an order be
reduced to final judgment to be appealable.”).
-7
Hewlett-Packard, 61 F.3d at 103 (second arbitration); Injazat Tech. Fund, B.S.C. v. Najafi,
No. C 11-4133 PJH, 2012 WL 1535125, at *2 (N.D. Cal. May 1, 2012) (second arbitration);
Brice Bldg. Co., Inc. v. Lee, No. CV-10-BE-0091-S, 2010 WL 11561713, at *2 (N.D. Ala.
Sept. 30, 2010) (state court lawsuit); Katz, 2001 WL 1132018, at *1 (second arbitration);
Companhia, 1997 WL 16663, at *7 (second arbitration). In other words, these were not
cases in which the outstanding claims that purportedly justified the requested stay were
pending in the same action.
However, in its own research, the Court discovered another case in which the
additional claims were pending in the same action—Middleby Corp. v. Hussmann Corp.,
No. 90 C 2744, 1991 WL 119123, at *3 (N.D. Ill. June 26, 1991). In Middleby, as in the
instant case, the plaintiff, which had lost in arbitration, “concede[d] the validity of the
arbitration award and [did] not object to confirmation of the award.” Id. at *3. The court
accordingly granted the petition to confirm the arbitration award under the FAA. Id.
The Middleby court then assessed the plaintiff’s “object[ion] to enforcement of the
award pending the outcome of its other claims against [the defendant] regarding the
[relevant] transaction” under the rubric of Rule 54(b). Id. The court explained that “[t]he
factual overlap between the arbitration proceeding and the pending litigation convince this
court that entry of final judgment on the arbitration award is not warranted until the entire
case is resolved.” Id.
Courts within this Circuit have also applied Rule 54(b) to orders confirming
arbitration awards, albeit not in the context of a request for a stay. See, e.g., 1999/Seiu
United Healthcare Workers E. v. Far Rockaway Nursing Home, No. 14 CIV. 5033 (BMC),
-8
2015 WL 13650033, at *1 (E.D.N.Y. Jan. 30, 2015) (“The court also finds, pursuant to
Federal Rule of Civil Procedure Rule 54(b), that there is no just reason for delay in entering
judgment in favor of plaintiff based on the Court’s confirmation of the arbitration award.
Defendant . . . has sought contribution by impleader of the estates of other general partners.
The liabilities of the defendant’s general partners inter se do not bear on plaintiff’s
entitlement to relief.”); Krantz & Berman, LLP v. Dalal, No. 09 CIV. 9339 DLC, 2011 WL
2923938, at *1 (S.D.N.Y. July 20, 2011) (“On February 3, 2011, the arbitrator issued an
award (the ‘Award’) against [the defendant] in the amount of $470,937.17 plus $9,600 in
arbitration fees. . . . The Court confirmed the Award by Opinion of May 12. Pursuant to
Rule 54(b), Fed.R.Civ.P., the Court granted partial judgment in favor of [the plaintiff] in
the total amount of $480,537.17 by Order of May 18” (citation omitted)); MCT Shipping
Corp. v. Sabet, 497 F. Supp. 1078, 1083 (S.D.N.Y. 1980) (directing entry of final judgment
on order confirming arbitration award under Rule 54(b)).
Here, the Final Award plainly resolves “fewer than all” of the claims in this action.
As a general rule, the Court’s issuance of an order resolving only Tri-Krete’s fourth
counterclaim (which is the practical effect of confirmation of the Final Award) would not
result in the entry of final judgment. Accordingly, although the parties have briefed the
matter with reference to the Court’s inherent authority to stay proceedings, the Court views
the relevant inquiry as whether entry of a partial final judgment is warranted under Rule
54(b). For the reasons that follow, the Court concludes that it is not.
In assessing whether a partial final judgment should be entered under Rule 54(b),
“[a] district court must first determine that it is dealing with a ‘final judgment.’ It must be
-9
a ‘judgment’ in the sense that it is a decision upon a cognizable claim for relief, and it must
be ‘final’ in the sense that it is ‘an ultimate disposition of an individual claim entered in
the course of a multiple claims action.’ Once having found finality, the district court must
go on to determine whether there is any just reason for delay.” Curtiss-Wright Corp. v.
Gen. Elec. Co., 446 U.S. 1, 7-8 (1980). In determining whether there is any just reason for
delay, “the court must balance the judicial administrative interests and relevant equitable
concerns.” Dayton Superior Corp. v. Spa Steel Prod., Inc., No. 1:08-CV-1312 FJS RFT,
2010 WL 3825619, at *5 (N.D.N.Y. Sept. 24, 2010).
“The relevant equitable
considerations include the possibility of setoff, the financial solvency of the parties, the
ability of a party to collect a judgment, the length of the delay if judgment is not entered
immediately, and the size of the appeal bond required if judgment is entered immediately.”
Id. The “determination of whether to grant Rule 54(b) certification is committed to the
discretion of the district court.” Harriscom Svenska AB v. Harris Corp., 947 F.2d 627, 629
(2d Cir. 1991).
Here, the Court finds that the first prong of the Rule 54(b) analysis is satisfied. The
Final Award disposes of Tri-Krete’s claim that Pike violated the PPA in its entirety. See
Cambridge Valley Machining, Inc. v. Hudson MFG LLC, No. 1:18-CV-1022, 2020 WL
6059787, at *4 (N.D.N.Y. Oct. 14, 2020).
However, the Court finds that there is just reason for delay in entering final
judgment with respect to the Final Award/fourth counterclaim. Specifically, as Pike notes
in its papers, Section 2.9 of the Subcontract expressly permits Pike to withhold “any
payment or payments due or to become due” to Tri-Krete in the event of certain breaches
- 10
of contract by Tri-Krete. (Dkt. 10 at 45). The fact that “the claims and counterclaims in
this case . . . arise out of the same underlying set of facts, and require an interpretation of
the duties and obligations of the parties pursuant . . . [to their] business relationship,” RIJ
Pharm. Corp. v. Ivax Pharms., Inc., 322 F. Supp. 2d 406, 417 (S.D.N.Y. 2004), counsels
against entry of partial final judgment under Rule 54(b). Moreover, Pike “allege[s] a
potential offset near or greater than the amount of damages [Tri-Krete] is entitled to” on its
PPA claims. Cambridge Valley, 2020 WL 6059787, at *4; see also Dayton, 2010 WL
3825619, at *5.
Tri-Krete’s argument that Pike’s claim for an offset is subsumed in the Final Award
(see Dkt. 49-1 at 10-11) is unpersuasive. As the Court explained in the November 2018
Decision, “[a]n arbitration decision may effect collateral estoppel in a later litigation or
arbitration if the proponent can show with clarity and certainty that the same issues were
resolved.” (Dkt. 39 at 23 (quoting Bear, Stearns & Co. Inc. v. 1109580 Ontario, Inc., 409
F.3d 87, 91 (2d Cir. 2005) (internal quotation marks omitted))). Here, the Court does not
have before it a sufficient record to reach a determination regarding the collateral estoppel
effect of the Final Award. Further, the Court took great pains to establish in the November
2018 Decision that the arbitrators were “without jurisdiction” to assess the merits of Pike’s
breach of contract claim. (Id.). While Tri-Krete can certainly argue the collateral estoppel
effect of the Final Award in subsequent phases of this litigation, the Court cannot say at
this stage of the proceedings that the Final Award precludes the possibility that Pike will
ultimately prevail on its breach of contract claim.
- 11
The Court is further unpersuaded by Tri-Krete’s contention that failing to enter
immediate judgment on the PPA claim would frustrate the purposes of the PPA. As TriKrete acknowledges, the “Remedies” section of the PPA “does not explicitly direct
payment of amounts owed” (Dkt. 49-1 at 13 (citing N.Y. Gen. Bus. L. § 756-b(1)(b)), but
instead provides for the payment of interest on amounts withheld in violation of the PPA.
The PPA thus does not, on its own terms, require immediate payment notwithstanding the
existing of a potentially offsetting claim by Pike. Further, the Final Award expressly
requires the ongoing accumulation of interest in favor of Tri-Kete, thereby satisfying the
purposes of the PPA while also protecting against any potential prejudice.
Under the circumstances of this case, and in its discretion, the Court finds that the
“no just reason for delay” requirement of Rule 54(b) has not been satisfied. Accordingly,
while the Court, by this Decision and Order, confirms the Final Award entered by the
arbitrators, it does not find that partial final judgment should be entered at this time. In
light of this finding, the Court denies Pike’s request to stay entry and/or execution of said
final judgment as moot.
Finally, the Court turns to the other two requests for relief set forth in Tri-Krete’s
motion—a request for an award of “the costs and disbursements associated with this
proceeding including attorneys’ fees” and a request to lift the stay in this matter. (Dkt. 43
at 1). As to the request for costs and disbursements, including attorneys’ fees, Tri-Krete
has made no substantive argument whatsoever as to its entitlement to such relief, nor has
it submitted to the Court any evidentiary proof regarding the amount of any such costs and
disbursements. Accordingly, this request is denied without prejudice.
- 12
Tri-Krete’s request to lift the stay is granted. The conclusion of the arbitration
eliminates the basis for the stay, and the remaining claims in this matter are now ready to
proceed. Pike has not opposed this request by Tri-Krete.
CONCLUSION
For the foregoing reasons, the Court grants in part and denies in part Tri-Krete’s
motion to confirm the Final Award. (Dkt. 43). Specifically, the Court confirms “the Final
Award rendered by the panel in an arbitration held before International Centre for Dispute
Resolution, International Arbitration Tribunal entitled Tri-Krete Ltd., Claimant, v. The
Pike Company, Respondent, ICDR Case No. 02-17-0006-0053.” (Id. at 1). The Court
further grants Tri-Krete’s request that the stay of this matter be lifted. The Court will, by
separate order, refer the matter to a magistrate judge to conduct a pretrial conference and
set a schedule pursuant to Federal Rule of Civil Procedure 16.
The Court denies Tri-Krete’s request for entry of final judgment and request for
costs and disbursements, including attorney’s fees. The Court further denies as moot Pike’s
motion to stay entry and/or execution of judgment. (Dkt. 46).
SO ORDERED.
____________________________
ELIZABETH A. WOLFORD
Chief Judge
United States District Court
Dated:
November 9, 2021
Rochester, New York
- 13
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?