Netplanner Systems, Inc. v. GSC Construction, Inc., et al
Filing
37
ORDER denying 13 Motion for Summary Judgment. The matter is set for bench trial on 27 November 2017. Signed by Senior Judge W. Earl Britt on 8/21/2017. (Edwards, S.)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF NORTH CAROLINA
WESTERN DIVISION
NO: 5:17-CV-00154-BR
THE UNITED STATES OF AMERICA
for the use and benefit of
NETPLANNER SYSTEMS, INC.,
Plaintiff,
v.
GSC CONSTRUCTION, INC., and
LIBERTY MUTUAL INSURANCE
COMPANY,
Defendants.
)
)
)
)
)
)
)
)
)
)
)
)
ORDER
This matter is before the court on the 11 January 2017 motion for summary judgment
filed by plaintiff the United States of America for the use and benefit of NetPlanner Systems,
Inc., (“NetPlanner”). (DE # 13.) Defendants GSC Construction, Inc. (“GSC”) and Liberty
Mutual Insurance Company (“Liberty”) filed a response in opposition on 16 February 2017, (DE
# 27), to which NetPlanner replied on 27 February 2017, (DE # 29). The motion has been fully
briefed and is ripe for disposition.
I. BACKGROUND
This case involves a contractual dispute arising out of a government construction project
for the United States Army Corps of Engineers (the “Corps”). GSC was retained as a general
contractor by the Corps to construct the SOF Communications Training Facility at Fort Bragg,
North Carolina (the “Fort Bragg Project”). (Roberts Aff., DE # 13-3, ¶¶ 6, 14.) As required by
the Miller Act, 40 U.S.C. §§ 3131-34, GSC obtained performance and payment bonds for the
project from Liberty. (See Ex. 10, DE # 13-12.) On 16 November 2012, GSC entered into a
subcontract with NetPlanner to provide cabling and wiring services and materials on the Fort
Bragg Project. (Roberts Aff., DE # 13-3, ¶¶ 7, 14). The subcontract set NetPlanner’s
compensation at $296,074, subject to additions and deletions provided for under the subcontract.
(See Ex. 5, DE # 13-7.)
In addition to setting forth payment obligations, the subcontract set forth a time
requirement for when the work was to be substantially completed. Specifically, Article 9 of the
subcontract, which is entitled “Date of Commencement and Substantial Completion,” states in
pertinent part:
9.3
than
The Work of this Subcontract shall be substantially completed not later
Per Owner’s approved schedule
subject to adjustments of this Subcontract Time as provided in the Subcontract
Documents.
9.4
With respect to the obligations of both the Contractor and the
Subcontractor, time is of the essence of this Subcontract. *The approved project
schedule is available on site. Subcontractor is responsible for reviewing this
schedule periodically.
9.5
No extension of time will be valid without the Contractor’s written
consent after claim made by the Subcontractor in accordance with Paragraph 5.3.
(Ex. 5, DE # 13-7, at 9.) With respect to claims made by the subcontractor, Paragraph 5.3 states:
The Subcontractor shall make all claims promptly to the Contractor for additional
costs and extensions of time or other causes in accordance with the Subcontract
Documents. A claim which will affect or become part of a claim which the
Contractor is required to make under the Prime Contract within a specified time
period or in a specified manner shall be made in sufficient time to permit the
Contractor to satisfy the requirements of the Prime Contract. Such claims shall be
received by the Contractor not less than two working days preceding the time by
which the Contractor’s claim must be made. Failure of the Subcontractor to make
such a timely claim shall bind the Subcontractor to the same consequences as
those to which the Contractor is bound.
(Id. at 7.)
2
NetPlanner began work on the Fort Bragg Project in or around the first quarter of 2014,
and completed its contractual scope of work in or around May 2015. (Roberts Aff., DE # 13-3, ¶
15.) During the course of performance, GSC submitted two change orders for additional work in
the amount of $4,044.28. (Id. ¶¶ 16-17; see also Ex. 7, DE # 13-9.) This increased the total
price of the subcontract to $300,118.28. (Roberts Aff., DE # 13-3, ¶ 17.) GSC paid NetPlanner
a total amount of $259,391.33 for work performed on the Fort Bragg Project. (Id. ¶ 18.)
NetPlanner contends that it is still owed $40,719.95 for its work on the project. (Id. ¶¶ 22-23.)
On 20 April 2016, NetPlanner filed a complaint in the Middle District of Georgia
alleging a Miller Act violation against both defendants, along with state-law claims for breach of
contract and quantum meruit against GSC. (DE # 1.) In the complaint, NetPlanner seeks to
recover payments due under the subcontract for its work on the Fort Bragg Project, as well as a
separate subcontract for a construction project in Fort Benning, Georgia (the “Fort Benning
Project”). The Middle District of Georgia subsequently determined venue was not proper there
for the claims arising from the Fort Bragg Project, and ordered those claims transferred to this
district. See NetPlanner Systems, Inc. v. GSC Construction, Inc., No. 4:16-CV-150 (CDL), DE
# 30 (M.D. GA. April 3, 2017).
II. ANALYSIS
In its motion for summary judgment, NetPlanner asks this court to enter judgment against
defendants, jointly and severally, in the amount of $40,719.95, plus interest, and attorneys’ fees.
(Pl.’s Supp. Mem., DE # 13-2, at 10.) NetPlanner also requests that the court disregard the
affidavit of GSC’s in-house counsel Kasey Bryan, (DE # 27-2), which was submitted by
defendants in response to the motion for summary judgment. (Pl.’s Reply, DE # 29, at 3-4.)
3
A. Request to Strike
The court first considers NetPlanner’s request to strike because Bryan’s affidavit is the
only evidence submitted by defendants in response to the motion for summary judgment.
NetPlanner asks that the court strike the entirety of Bryan’s affidavit on the ground that Bryan
does not have personal knowledge of the facts as required under Federal Rule of Civil Procedure
56(c)(4). (Pl.’s Reply, DE # 29, at 4-5.) Additionally, NetPlanner challenges certain portions of
the affidavit as containing inadmissible evidence. (Id. at 5-7.)
Rule 56(c)(4) states the criteria for affidavits and declarations to be used in regards to a
motion. The terms set by Rule 56(c)(4) are that “[a]n affidavit or declaration used to support or
oppose a motion must be made on personal knowledge, set out facts that would be admissible in
evidence, and show that the affiant or declarant is competent to testify on the matters stated.”
Therefore, an affidavit filed in opposition to a motion for summary judgment “cannot be
conclusory, . . . or based upon hearsay.” Evans v. Techs. Applications & Serv. Co., 80 F.3d 954,
962 (4th Cir. 1996) (citations omitted). Affidavits, or portions of affidavits, may be struck when
in violation of these requirements. See id. (upholding the district court’s decision to strike
portions of an affidavit deemed inadmissible or improper).
Here, Bryan’s affidavit states that it is based on her personal knowledge as in-house
counsel, who personally reviewed GSC’s files regarding the scope of and schedule of
NetPlanner’s work on the Fort Bragg Project. (Bryan Aff., DE # 26-1, ¶ 4.) NetPlanner
contends that the court should not consider the affidavit because Bryan’s review of GSC’s files
did not give her “personal knowledge” of the facts. (Pl.’s Reply, DE # 29, at 4.) However,
personal knowledge is not strictly limited to activities in which the affiant has personally
participated. See Londrigan v. FBI, 670 F.2d 1164, 1174-75 (D.C. Cir. 1981) (noting that FBI
4
agent who reviewed file had personal knowledge sufficient to support statements about the
conduct of an investigation in which he had not participated); Danone Asia Pte. v. Happy Dragon
Wholesale, Inc., No. CV-05-1611, 2006 WL 845573, at *4 n.3 (E.D.N.Y Mar. 29, 2006) (finding
that the affidavit of a witness who was general counsel of a parent company, as opposed to a
litigating attorney in the action, was admissible because he was an officer of the company and
made statements based upon his “personal knowledge and from review of the company’s
records, both of which are admissible”). An “affiant’s personal knowledge may be based on
review of files, if the testimony states facts reflected by the files and does not give inferences,
opinions, and surmises.” Howard Acquisitions, LLC v. Giannasca New Orleans, LLC, No.
WDQ-09-2651, 2010 WL 3834917, at *3 (D. Md. Sept. 28, 2010) (citations and internal
quotation marks omitted); see also Sutton v. Roth LLC, 361 F. App’x 543, 550 n.7 (4th Cir.
2010) (noting that an affidavit is of “questionable value” when the affiant’s knowledge is based
on a review of files and the affiant gives legal conclusions). The contents of Bryan’s affidavit do
not offer any opinions or legal conclusions. Therefore, as a result of her review of the records
and position with GSC, the court finds that Bryan had personal knowledge of the relevant facts
as required by Rule 56(c)(4).
NetPlanner further challenges Paragraphs 7-9 of Bryan’s affidavit as setting forth facts
which would not be admissible. NetPlanner asserts that Paragraph 7, which addresses the actual
and expected duration of work performed by NetPlanner on both projects, lacks foundation and
disregards the best evidence rule because it is not supported by attached documents. (Pl.’s
Reply, DE # 29, at 5-6.) Paragraph 7 states “The Government-approved schedules for the
projects show that the duration of Netplanner’s activities extended beyond the original expected
5
duration,” and provides the following table summarizing the periods of delay on the Fort Bragg
Project:
Netplanner Activity
Comm Rough In
Comm Devices
Pull Comm Wire
Original Duration
20 days
15 days
15 days
Actual Duration
336 days
91 days
121 days
(Bryan Aff., DE # 27-2, ¶ 7.)
NetPlanner argues that information contained in Paragraph 7 is inadmissible because the
“Government-approved schedules” were not attached to the affidavit. (Pl.’s Reply, DE # 29, at
5.) However, “[t]here is no requirement that all statements made on personal knowledge be
supported by independent documentation” when the affiant “states, under penalty of perjury, that
[her] declaration is based on personal knowledge of the contents of the file.” Washington Cent.
R. Co., Inc. v. Nat’l Mediation Bd., 830 F. Supp. 1343, 1355 (E.D. Wash 1993). Because
Bryan’s statements in Paragraph 7 concerning the expected and actual duration of work
performed by NetPlanner come from her review of the content of GSC’s files, this paragraph will
not be stricken and the court will consider it in ruling on NetPlanner’s motion for summary
judgment.
The court need not consider NetPlanner’s request to strike Paragraphs 8 and 9 because,
even if these paragraphs were stricken from Bryan’s affidavit, the remaining paragraphs of the
affidavit provide sufficient evidence to create a question of fact precluding summary judgment.
B. Motion for Summary Judgment
Summary judgment is proper if “the movant shows that there is no genuine dispute as to
any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P.
56(a). The party seeking summary judgment bears the initial burden of demonstrating the
absence of any genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 322-23
6
(1986). Once the moving party has met its burden, the nonmoving party then must affirmatively
demonstrate with specific evidence that there exists a genuine issue of material fact requiring
trial. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586-87 (1986). The
nonmoving party may not rest on the allegations or denials in its complaint or other pleadings,
but must come forward with affidavits or other verified evidence showing that there is a genuine
issue for trial. Celotex, 477 U.S. at 322; see also Williams v. Griffin, 952 F.2d 820, 823 (4th Cir.
1991). In determining whether an issue of fact exists, the court must view the evidence and
inferences drawn therefrom in the light most favorable to the nonmoving party. Shealy v.
Winston, 929 F.2d 1009, 1011 (4th Cir. 1991).
1. Breach of Contract Claim
To succeed on a breach of contract claim under North Carolina law, a plaintiff must
prove: (1) the existence of a valid contract, and (2) a breach of the terms of the contract. Poor v.
Hill, 530 S.E.2d 838, 843 (N.C. Ct. App. 2000). In this case, the evidence clearly shows the
existence of valid contract between the parties: the subcontract and change orders submitted by
NetPlanner indicate that GSC agreed to pay NetPlanner $300,118.28 for labor, materials,
equipment, and services in connection with the Fort Bragg Project. (See Ex. 5, DE # 13-7; Ex. 6,
DE # 13-8.) There is no dispute that GSC has in fact paid NetPlanner only $259,391.33 for work
performed on the Fort Bragg Project. The question at issue here is whether GSC breached the
terms of the subcontract by refusing to pay NetPlanner the remaining balance of $40,719.95 due
under the subcontract.
Pursuant to the terms of the subcontract, GSC agreed that “[f]inal payment, constituting
the entire unpaid balance of the Subcontract Sum, shall be made by the Contractor to the
Subcontractor when the Subcontractor’s Work is fully performed in accordance with the
7
requirements of the Contract Documents, . . .” (See Ex. 5, DE # 13-7, at 12.) Article 9 of the
subcontract specifically references the time frame for completion of the Fort Bragg Project,
stating “[t]he Work of this Subcontract shall be substantially completed not later than Per
Owner’s approved schedule.” (See id. at 9.) Relying on this provision, GSC contends that it
has a valid defense to non-payment because NetPlanner materially breached the subcontract by
failing to complete its work within the scope of the subcontract’s time for substantial completion
and final payment.
GSC has proffered evidence, through Bryan’s affidavit, that NetPlanner did not complete
its work on the Fort Bragg Project within the government-approved schedule. For example,
NetPlanner’s work on the “Comm Rough In” was not completed until 316 days after the
government-approved date. (Bryan Aff., DE # 27-2, ¶ 7.) NetPlanner was also 106 days behind
schedule in completing the Pull Comm Wire. (Id.) While NetPlanner may dispute the length of
the delays, NetPlanner does not dispute that its work on the project took longer than expected.
Moreover, there is no evidence that NetPlanner requested an extension of time for its work, or
that GSC issued written consent for an extension. Therefore, a genuine factual dispute exists as
to whether NetPlanner substantially completed the work under the subcontract in a timely
manner. Accordingly, summary judgment will be denied on NetPlanner’s breach of contract
claim against GSC.
2.
Quantum Meruit Claim
NetPlanner’s motion for summary judgment does not specifically address its alternative
state-law claim for quantum meruit, rather plaintiff argues that GSC “failed to pay it what it is
owed for its work.” (Pl.’s Supp. Mem., DE # 13-2, at 2.) “Quantum meruit serves as an
equitable remedy to prevent unjust enrichment when there is no express contract.” Neighbors
8
Law Firm, P.C. v. Highland Capital Mgmt., L.P., No. 5:09-CV-352-F, 2010 WL 3767126, at *4
(E.D.N.C. Sept. 24, 2010) (citing Whitfield v. Gilchrist, 497 S.E.2d 412, 414-15 (N.C. 1998)).
When there is an actual agreement between the parties, quantum meruit is not an appropriate
remedy “because an express contract precludes an implied contract with reference to the same
matter.” Ron Medlin Const. v. Harris, 704 S.E.2d 486, 489 (N.C. 2010) (internal quotation
marks and citation omitted). The facts here establish the existence of an express contract
between the parties regarding the work to be performed on the Fort Bragg Project. (See Ex. 5,
DE # 13-7, at 2.) Consequently, NetPlanner cannot recover on a theory of unjust enrichment for
services rendered under its subcontract with GSC. See TSC Research, LLC v. Bayer Chems.
Corp., 552 F. Supp. 2d 534, 540 (M.D.N.C. 2008) (noting that a quantum meruit claim can only
prevail “in the absence of an enforceable, express contract”).
3. Miller Act Claim
Finally, NetPlanner moves for summary judgment seeking to recover from defendants
under the Miller Act for the remaining balance it claims it is owed under the subcontract.
According to NetPlanner, Liberty, as obligor under the bond, is jointly and severally obligated to
pay NetPlanner for the materials and work for which GSC has failed to make payment. (Pl.’s
Supp. Mem., DE # 13-2, at 11.)
The Miller Act provides financial protection to subcontractors for government
construction projects. 40 U.S.C. §§ 3131-34. Before any contract of more than $100,000 may
be awarded for a federal construction project, the Miller Act requires that a contractor post a
payment bond “with a surety satisfactory to the officer for the protection of all persons supplying
labor and material in carrying out the work provided for in the contract.” Id. The Miller Act
also allows an unpaid subcontractor to file suit seeking payment from a surety on a payment
9
bond when the subcontractor has not been paid by the general contractor within 90 days of
completing the subcontractor’s work. Id. A plaintiff must prove four elements to collect under
the Miller Act: (1) labor or materials were supplied for work in the contract; (2) the supplier of
that labor or materials is unpaid; (3) the supplier had a good faith belief that the labor or
materials were for the specified work; and (4) jurisdictional requisites are met. United States ex
rel. ProBuild Co., LLC v. Scarborough, No. 2:11CV451, 2012 WL 1571500, at *5 (E.D. Va.
Apr. 11, 2012) (quoting 40 U.S.C. § 3133(b)(1)), adopted, 2012 WL 1571493 (E.D. Va. May 3,
2012).
Defendants argue that NetPlanner cannot recover payment under the Miller Act bond for
work that was not timely performed and that violated terms of the subcontract. (Defs.’ Resp.,
DE # 27, at 4.) “Whether a subcontractor has been paid in full for providing labor and materials
must be determined by reference to the underlying subcontract as it relates to the scope of the
work and the payment terms.” United States ex rel. Acoustical Concepts, Inc. v. Travelers Cas.
and Sur. Co. of Am., 635 F. Supp. 2d 434, 438 (E.D. Va. 2009). Pursuant to the terms of the
subcontract, NetPlanner agreed to complete its work within the government-approved schedule.
(Ex. 5, DE # 13-7, at 9.) The subcontract also states that “[f]inal payment, constituting the
entire unpaid balance of the Subcontract Sum,” shall be made when “the Subcontractor’s Work
is fully performed in accordance with the requirements of the Contract Documents.” (Id. at 12.)
As noted previously, a genuine factual dispute exists as to whether NetPlanner substantially
completed the work under the subcontract in a timely manner. See Empire Enters. JKB, Inc. v.
Union City Contractors, Inc., 660 F. Supp. 2d 492 (W.D.N.Y. 2009) (noting that a successful
Miller Act “plaintiff must show that it complied with its contractual obligations under the
10
subcontract”). Therefore, NetPlanner has not carried its burden of showing there are no disputed
issues of material facts which would entitle it to judgment as a matter of law as to this claim.
III. CONCLUSION
For the foregoing reasons, NetPlanner’s motion for summary judgment, (DE # 13), is
DENIED. The matter is set for bench trial on 27 November 2017.
This 21 August 2017.
__________________________________
W. Earl Britt
Senior U.S. District Judge
11
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?